Rebar (Building Structural 11F to 20F) L&T, E kg. 4.50 10.00 Cutting, Bending, Tying, Welding, Coupling, etc.
FORMWORKS
Formworks - Footings, Columns sq.m 220.00 250.00 Scaffolding, Shoring, Formworks
Formworks - Tie Beams, Beam on Grade, Slab sq.m 220.00 250.00 Scaffolding, Shoring, Formworks
on Grade
Formworks - Suspended Beams sq.m 220.00 250.00 Scaffolding, Shoring, Formworks
Formworks - Stairs & Landing sq.m 220.00 250.00 Scaffolding, Shoring, Formworks
CONCRETING - JOBMIX
Job Mix - Lean Concrete cu.m Mixing, Pouring, Vibrating, Surface Finishing
Job Mix - RC Pouring - Footing, Tie Beam, cu.m Mixing, Pouring, Vibrating, Surface Finishing
Beam on Grade, Slab on Grade
Job Mix - RC Pouring - Column, Suspended cu.m Mixing, Pouring, Vibrating, Surface Finishing
Slabs, Girders, Beams, Walls
CONCRETE POURING - READYMIX
Ready Mix - Lean Concrete Pouring & Road cu.m Pouring, Vibrating, Surface Finishing
Concreting
Ready Mix - RC Pouring - Footing, Tie Beam, cu.m Pouring, Vibrating, Surface Finishing
Beam on Grade, Slab on Grade
PumpCrete - RC Pouring - Column, Suspended cu.m Pouring, Vibrating, Surface Finishing
Slabs, Girders, Beams, Walls
MASONRY WORKS
CHB Laying 4" L&T, E sq.m 100.00 125.00
Page 1 of 36
ITEM SCOPE UNIT BASELINE MIN. SELLING WORKS INCLUDED REMARKS
(M, L&T, E) BUYING COST COST (EX-VAT) CHB Laying, Mortar, Rebar
CHB Laying 6" L&T, E sq.m (EX-VAT)
150.00 175.00
TRUSSES
Steel Trusses (Single, 2"x2" Angle Bar) L&T, E sq.m 200.00 720.00 Trusses & Purlins Installation + Primer
Steel Trusses (Double, 2"x2" Angle Bar) L&T, E sq.m 300.00 960.00 Trusses & Purlins Installation + Primer
Steel Trusses (G.I. Pipe) L&T, E sq.m Trusses & Purlins (Pipe Bending is Excluded)
ROOF
Metal Roofing (on Steel Frames) - ALL IN L&T, E sq.m 70.00 100.00 Roof Installation, Ridge Roll, Gutter, Flashing,
Sealant
Metal Roofing (on Steel Frames) L&T, E sq.m 40.00 70.00 Roof Installation
Gutters, Ridge Rolls & Flashing L&T, E l.m Fabrication, Installation, Rivets, Downspout, Sealing
FLOOR FINISH
Plain Cement sq.m
Granulithic sq.m
Page 2 of 36
ITEM SCOPE UNIT BASELINE MIN. SELLING WORKS INCLUDED REMARKS
(M, L&T, E) BUYING COST COST (EX-VAT)
Vinyl sq.m (EX-VAT)
Unglazed sq.m
Asphalt sq.m
CEILING
Plywood Ceiling on Wooden Frame sq.m Framing & Ceiling Installation
Acoustic Tile with Plywood Backing sq.m Framing & Ceiling Installation
Concealed Acoustic Tile with Aluminum T- sq.m Framing & Ceiling Installation
Runners
Spandrel sq.m
Page 3 of 36
ITEM SCOPE UNIT BASELINE MIN. SELLING WORKS INCLUDED REMARKS
(M, L&T, E) BUYING COST COST (EX-VAT)
(EX-VAT) DRY WALL
Ficem Drywall on Metal Frame sq.m Framing & Wall Face Installation
Gypsum Drywall on Metal Frame sq.m Framing & Wall Face Installation
Single Wall Plywood on Wooden Frame sq.m Framing & Wall Face Installation
Double Wall Plywood on Wooden Frame sq.m Framing & Wall Face Installation
Installation: Door (Wooden, Plastic, Steel) pc Installation of Jamb, Hinge, Door, Knob, Lock,
Stopper, Wall Repair, Cleaning
PAINT
Fence Painting M, L&T, E sq.m 80.00 150.00 Surface Preparation, Painting, Cleaning Per Square Meter of Face Area to be Painted.
Building Paint - ALL IN M, L&T, E sq.m 150.00 300.00 Surface Preparation, Painting, Cleaning Per Square Meter of Face Area to be Painted.
Floor Rubberized
ELECTRICAL
Lighting & Power Outlet L&T, E hole 200.00 Roughing-ins, Wires, Junctions, Intallations, etc. Per Lighiting & Power Outlet (Switches are not
counted)
Service Entrance L&T, E unit 3,500.00 Installation & Commisioning Service Entrance + 1 Free Panel Board (MDP)
Extra Panel Board (LPB, etc.) - Small Panels L&T, E set 1,000.00 Installation & Commisioning
Only
PLUMBING
Plumbing Lot pc Computed as the total fitting + plumbing fixtures
(Switches are not counted)
Page 4 of 36
ITEM SCOPE UNIT BASELINE MIN. SELLING WORKS INCLUDED REMARKS
(M, L&T, E) BUYING COST COST (EX-VAT)
Water Closet set (EX-VAT) Surface Preparation & Leveling, Application of Tile Computed according to the Total Face Area to be
Adhesives, Placement of Tiles, Grouting, Cleaning Tiled.
Lavatory set before
Surfaceturn-over.
Preparation & Leveling, Application of Tile Computed according to the Total Face Area to be
Adhesives, Placement of Tiles, Grouting, Cleaning Tiled.
before turn-over.
Page 5 of 36
ITEM SCOPE UNIT BASELINE MIN. SELLING THEORETICAL RECENT WORKS INCLUDED
(M, L&T, E) BUYING COST COST (EX-VAT) REFERENCE REFERENCE
(EX-VAT) DEMOLITION
Deconstruction sq.m -
TEMPORARY FACILITY
Temporary Fence: Blue Sack l.m -
EARTHWORKS
Excavation (Manual) cu.m 383.33
ROAD PCCP
Page 6 of 36
REMARKS
Page 7 of 36
ITEM SCOPE UNIT BASELINE MIN. SELLING WORKS INCLUDED REMARKS
(M, L&T, E) BUYING COST COST (EX-VAT)
(EX-VAT) TEMPORARY FACILITY
Temporary Fence: Blue Sack l.m
Page 8 of 36
Skilled Labor TOTAL
ITEM (m-hrs/unit) (m-hrs/unit) (m-hrs/unit)
Demolition
Deconstruction -
Demolition - RC Flooring (Manual) 26.67 26.67 53.33
Temporary Facility
Temporary Fence: Blue Sack -
Temporary Fence: Tin Sheets -
Site Development
Excavation (Manual) - 5.93 5.93
Backfill (Manual) - 2.07 2.07
Gravel Bedding (Manual) - 2.77 2.77
Compaction (Tamper) - - -
Riprap 4.00 4.00 8.00
Rebars
Rebar Installation - 0.08 0.08
Formworks
Formworks - Footings, Columns 1.25 1.25 2.50
Formworks - Tie Beams, Beam on Grade, Slab on Grade 1.40 1.40 2.80
Formworks - Suspended Beams 1.67 1.67 3.34
Formworks - Suspended Slab 1.55 1.55 3.10
Formworks - Retaining/Continuous Wall 1.20 1.20 2.40
Formworks - Stairs & Landing 1.24 1.24 2.48
Concreting - Jobmix
Job Mix - Lean Concrete Pouring & Road Concreting 6.67 6.67 13.33
Job Mix - RC Pouring - Footing, Tie Beam, Beam on Grade, Slab on G 9.52 9.52 19.05
Job Mix - RC Pouring - Column, Suspended Slabs, Girders, Beams, Wa 16.00 16.00 32.00
Concreting -Readymix
Ready Mix - Lean Concrete Pouring & Road Concreting 0.80 0.80 1.60
Ready Mix - RC Pouring - Footing, Tie Beam, Beam on Grade, Slab o 3.01 3.01 6.02
PumpCrete - RC Pouring - Column, Suspended Slabs, Girders, Beams, 1.78 1.78 3.56
Masonry Works
CHB Laying 4" 1.00 1.00 2.00
CHB Laying 5" 1.11 1.11 2.22
CHB Laying 6" 1.25 1.25 2.50
CHB Plastering - Joints Only 0.24 0.24 0.48
CHB Plastering - Rough Finish 1.00 1.00 2.00
CHB Plastering - Smooth Finish 1.20 1.20 2.40
Trusses
-
Roof
Metal Roofing on Steel Frames 0.48 0.48 0.97
Non Metal Roofing 0.54 0.54 1.08
Gutters, Ridge Rolls & Flashing 1.97 1.97 3.94
Floor Finishes
Plain Cement 0.67 0.67 1.33
Colored Cement 0.70 0.70 1.40
Pebble Washout 1.43 1.43 2.86
Granulithic 1.43 1.43 2.86
Marble Tile 1.43 1.43 2.86
Vinyl 2.34 2.34 4.67
Unglazed 2.00 2.00 4.00
Asphalt 0.84 0.84 1.67
Tiles & Cladding
Floor Tiles 10cm x 10cm (4"x4") 8.00 8.00 16.00
Floor Tiles 15cm x 15cm (6"x6") 4.94 4.94 9.88
Floor Tiles 30cm x 30cm (12"x12") 3.09 3.09 6.17
Floor Tiles 40cm x 40cm (16"x16") 1.93 1.93 3.86
Floor Tiles 60cm x 60cm (24"x24") 1.21 1.21 2.41
Wall Tiles -
Wall Cladding -
Column Cladding -
Stair Tiles -
Ceiling
Plywood Ceiling on Wooden Frame 0.92 0.92 1.84
Fiber-Cement Board Ceiling 0.92 0.92 1.84
Acoustic Tile with Plywood Backing 1.54 1.54 3.08
Concealed Acoustic Tile with Aluminum T-Runners 1.54 1.54 3.08
Spandrel -
PVC Ceiling -
Dry Wall
Ficem Drywall on Metal Frame -
Gypsum Drywall on Metal Frame -
Single Wall Plywood on Wooden Frame 1.24 1.24 2.48
Double Wall Plywood on Wooden Frame 1.69 1.69 3.38
Wooden Louver 1.69 1.69 3.38
Cyclone Wire Partition 0.13 0.13 0.25
Glass & Aluminum
Labor & Materials: Glass & Aluminum -
Doors & Windows
Fabrication: Wooden Flush Door 8.00 8.00 16.00
Installation: Door (Wooden, Plastic, Steel) 5.33 5.33 10.67
Paint
Labor & Materials: Paint Lot
Wall Smooth
Ceiling Smooth
Ceiling -
Floor Rubberized
Electrical
Electrical Lot -
Plumbing
Plumbing Lot -
Water Closet 16.00 16.00 32.00
Lavatory 12.00 12.00 24.00
UNIT COST UNIT
- sq.m
3,833.33 cu.m
- l.m
- l.m
383.33 cu.m
133.72 cu.m
179.18 cu.m
35.00 cu.m
575.00 cu.m
5.18 kg.
179.69 sq.m
201.25 sq.m
240.06 sq.m
222.81 sq.m
172.50 sq.m
178.25 sq.m
958.33 cu.m
1,369.05 cu.m
2,300.00 cu.m
115.00 cu.m
432.33 cu.m
255.56 cu.m
143.75 sq.m
159.72 sq.m
179.69 sq.m
34.23 sq.m
143.75 sq.m
172.50 sq.m
69.63 sq.m
77.37 sq.m
282.97 l.m
95.59 sq.m
100.63 sq.m
205.56 sq.m
205.56 sq.m
205.56 sq.m
335.66 sq.m
287.50 sq.m
120.03 sq.m
1,150.00 sq.m
709.88 sq.m
443.67 sq.m
277.30 sq.m
173.31 sq.m
- sq.m
- sq.m
- sq.m
- sq.m
132.30 sq.m
132.30 sq.m
221.27 sq.m
221.27 sq.m
- sq.m
- sq.m
- sq.m
- sq.m
177.94 sq.m
242.93 sq.m
242.93 sq.m
18.26 sq.m
- sq.m
1,150.00 pc
766.67 pc
80.00 sq.m
150.00 pc
pc
2,300.00 set
1,725.00 set
WORKS INCLUDED
Placement of Lean Concrete, Placement of Boulders, Mixing & Application of Concrete Grouting.
Fabrication to Installation
Installation of Jamb, Hinge, Door, Knob, Lock, Stopper, Wall Repair, Cleaning
Surface Preparation & Leveling, Application of Tile Adhesives, Placement of Tiles, Grouting, Cleaning before turn-over.
Surface Preparation & Leveling, Application of Tile Adhesives, Placement of Tiles, Grouting, Cleaning before turn-over.
REMARKS
Computed as the total outlet + lighting fixture (Switches are not counted)
Computed as the total fitting + plumbing fixtures (Switches are not counted)
Computed according to the Total Face Area to be Tiled.
Computed according to the Total Face Area to be Tiled.
DIRECT LABOR CONTACTOR'S
OCM
& EQUIPMENT PROFIT
ITEM
A = as per DUPA B = 12% of (A) C = 8% of (A)
DEMOLITION
- -
EARTHWORKS
Excavation - Pipe Culvert & Drain (Common Soil) 260.28 31.23 20.82
Subgrade Preparation
16.09 1.93 1.29
(Correction & Compaction)
Subbase Preparation
96.51 11.58 7.72
(Installation, Correction, Compaction)
CONCRETING - JOBMIX
REINFORCING STEEL
BOX CULVERT
PAINT
- - -
Labor, Tools & Equipment (jack hammer), Heavy Equipment (backhoe, breaker, dump truck), Fees &
Consumables (tipping fee, passway, fuel, electricity, etc),
Labor, Tools & Equipment (cutting outfit, grinder, jack hammer), Heavy Equipment (backhoe, breaker, dump
truck), Fees & Consumables (tipping fee, passway, oxy-acetelene, cutting disks, fuel, electricity, etc),
Labor, Tools & Equipment, Heavy Equipment (backhoe, dump truck), Fees & Consumables (tipping fee, passway,
fuel, electricity, etc),
Structure Excavation
Foundation Fill
Embankment
Subgrade Preparation
Agreagate Sub-base
(Volume is computed in bank)
Weight is computed as per plan
ITEM UNIT COST UNIT
STRUCTURAL
Rebar works 4.40 kg
MASONRY WORKS
CHB Laying 170.00 sq.m
ARCHITECTURAL
CHB Plastering (Interior Walls) - Smooth Finish 140.00 sq.m
OTHER NOTES
vatable, (verify thickness), 2.8m wall height, includes hauling from alemac/elevator, barracks to be paid by subcon - P35/man/day
vatable, 2.8m wall height, includes hauling from alemac/elevator, barracks to be paid by subcon - P35/man/day
SOURCE
Mark-up 15%
TERMS & CONDITIONS
TERMS & CONDITIONS
Subcontractors must be evaluated and accredited according to their specialty.
Sub-Contracts with an estimated amount exceeding P300,000 must have quotations from at least three specialty subcontracto
Labor-only-Sub-Contracts must have a maximum down payment of P40,000 or 5% of subcontract price only, whichever is lowe
Labor&Material-Sub-Contracts must have a maximum down payment of P40,000 or 5% of the labor price of the subcontract p
All materials to be used on Labor&Material-Sub-Contracts must be supplied by Teravera Corporation. The cost of materials su
Tools & Light Equipment to be used on all Sub-Contracts must be supplied by the sub-contractor. However, the sub-contracto
Sub-Contracts shall have a weekly progress bill scheme, with an amount payable of no greater than the amount of accomplish
Safety
Performance Bond
Retention
Warranty Bond
Includes all Labor, Tools & Equipment, Heavy Equipment, Consumables , Utilities
Measurements are computed as per plan
The cost of lease shall be deducted to the amount payable per progress bill.
Other notes
plastering - P140 per square meter - smooth finish, 2.8m height - interior wall - vatable, mandaluyong
barracks P35/head per day
including hauling from alimac