NCR STATUS (Package 1 & II)

Upto February-2020
PACKAGE - I
Responsible
Date of Issue Responsible person / NCR Status (Open/ Date of Closure of Deatails of closure of NCR
S.No. NCR No. NCR issued vide Letter No. Details of NCR person (IE
of NCR closed by Closed) NCR (mention Letter No.)
Representative)
Reinforcement Steel of Box Culvert in
deep water since last one month which
Structure Engineer-Mr. C.Venkateswara ABL/NHAI/TOT-01/PKG-
1 STR/01 AA/TL/TOT/SGTPL/19-20/126 9/14/2019 results in rusting of steel and Closed 9/23/2019
Ravi Teja Rao 1/PL/2019-20/1195
deterioration -Box Culvert @Ch.
986+090 BHS

RCC Drain wall concrete was bulged.


Wall is not in line, level and concrete Structure Engineer-Mr. ABL/NHAI/TOT-01/PKG-
2 HW/02 AA/TL/TOT/SGTPL/19-20/130 9/17/2019 HM cum RE Closed 9/23/2019
surface also not satisfactory -Ch From Ravi Teja 1/PL/2019-20/1196
968+130 to 968+200 RHS

Earthwork shoulder filling work carried Asst.Project Manager


ABL/NHAI/TOT-01/PKG-
3 HWY/04 AA/TL/TOT/STPL/19-20/202 11/26/2019 out with milling material from Ch. P.Satyanarayana HM cum RE Closed 1/6/2020
1/PL/2019-20/1580
963+590 to Ch. 963+740 LHS

Structure Engineer-Mr.
4 ATMS/06 AA/TL/TOT/SGTPL/19-20/281 2/14/2020 VMS- Full Gantry Works HM cum RE, TL Open
Ravi Teja
PACKAGE - II
VMS Full Gantry Works
1. Honey Combing Concrete Surface
observed on VMS Foundation Column
1st Lift due to improper vibration of
Structure Engineer-Mr.
5 ATMS-03 AA/TL/TOT/DSTPL/19-20/181 11/6/2019 concrete HM & RE Open
Ravi Teja
2. Slurry leakage observed on
shuttering joints
3. Concrete corner edge joints are not
satisfactory

Earthen Shoulder filling work carried


Asst.Project Manager ABL/NHAI/TOT-01/PKG-
6 HWY-05 AA/TL/TOT/STPL/19-20/203 11/26/2019 out with milling material from Ch. HM cum RE Closed 1/7/2020
P. Satyanarayana 2/PL/2019-20/1589
912+100 to Ch. 913+000.
Asst.ATM
VMS & VAS Gantry Foundation Structure Engineer-Mr.
7 ATMS/07 AA/TL/TOT/DSTPL/19-20/282 2/14/2020 Engineer, HM Open
Backfilling works Ravi Teja
cum RE
Asst.ATM
Structure Engineer-Mr.
8 ATMS/08 AA/TL/TOT/DSTPL/19-20/286 2/17/2020 VMS Compact Foundation works Engineer, HM Open
Ravi Teja
cum RE
Asst.Project Manager
9 HWY/09 AA/TL/TOT/DSTPL/19-20/300 2/28/2020 Preperation of Earthen Shoulder HM Cum RE Open
P. Satyanarayana
Asst.Project Manager
10 HWY/10 AA/TL/TOT/DSTPL/19-20/301 2/28/2020 Laying of Kerb HM Cum RE Open
P. Satyanarayana