Beruflich Dokumente
Kultur Dokumente
_ __
__ RA|
I N D __| 1/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
UNIT 00
_ __
__ RA|
I N D __| 2/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
Contents
1 INTRODUCTION ................................................................................................................................... 5
2 DEFINITIONS ........................................................................................................................................ 5
2.1 Operating Pressure and Temperature ............................................................................................... 5
2.2 Maximum Operating Pressure............................................................................................................ 5
2.3 Maximum Operating Temperature ..................................................................................................... 5
2.4 Minimum Operating Temperature ...................................................................................................... 5
2.5 Design Internal Pressure .................................................................................................................... 6
2.6 Design External Pressure ................................................................................................................... 6
2.7 Design Temperature ............................................................................................................................ 6
2.8 Short Term Piping Design Condition................................................................................................. 6
3 DESIGN PRESSURE ............................................................................................................................ 7
3.1 Design Internal Pressure: General..................................................................................................... 7
3.2 Design External Pressure ................................................................................................................... 7
3.3 Steam-out Condition ........................................................................................................................... 8
3.4 Pump Suction Line .............................................................................................................................. 8
3.5 Centrifugal Pump Discharge Circuit.................................................................................................. 8
3.6 Positive Displacement Type Pump Discharge.................................................................................. 8
3.7 Compressor Suction ........................................................................................................................... 9
3.8 Centrifugal Compressor Discharge ................................................................................................... 9
3.9 Reciprocating Compressor Discharge.............................................................................................. 9
3.10 Reactor Recycle Gas Loop ................................................................................................................. 9
3.11 Shell and Tube Heat Exchanger ......................................................................................................... 9
3.12 Piping at Low Operating Pressure................................................................................................... 10
3.13 Atmospheric Storage Tank ............................................................................................................... 10
4 DESIGN TEMPERATURE .................................................................................................................. 10
4.1 Design Maximum Temperature ........................................................................................................ 10
4.2 Design Minimum Temperature ..........................................................................................................11
4.3 Pressure Relief Valve and Its Tail Pipe .............................................................................................11
4.4 Flare Header ........................................................................................................................................11
__ RA|
I N D __| 3/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
_ __
__ RA|
I N D __| 4/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
1 INTRODUCTION
This document covers the general design criteria for the determination of mechanical design
conditions for the equipment in RPLC Deep Conversion Project.
This document summarizes the Owner’s requirements stipulated in following specifications:
(1) 3006-5001-BG14001 Basic Engineering Design Guideline
(2) MDP-01-DP-01 Process Design Manual, Design Criteria, Temperature and Pressure Design
(3) 3006-5001-BM11504 Basis of Design: Pressure Vessels
(4) 3006-5001-BM11511 Basis of Design: Piping
It is noted that any details not covered in this procedure should refer the relevant part of the PDVSA
Standard MDP-01-DP-01.
2 DEFINITIONS
2.1 Operating Pressure and Temperature
The operating pressure and temperature is the one which exists during any modes in normal
operation.
The operating temperature should incorporate the normal operation fluctuation, such as reactor
start-of-run and end-of-run operation, change on heat recovery in different mode of operation, etc.
The highest normal operating temperature is used to evaluate the corrosion rate for material
selection.
_ __
__ RA|
I N D __| 5/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
_ __
__ RA|
I N D __| 6/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
3 DESIGN PRESSURE
It is noted that the statements below is general philosophy and unit specific requirement should be
examined individually.
Any deviations from general philosophy which may need to be considered for specific equipment
item should be consulted with the Owner.
The margin shown above may be increased if the process design anticipates higher pressure
surges.
The criteria above might not be applicable for the equipment located in HDH/SHP reactor loop.
Licensor’s design philosophy would be applied instead.
The design pressure should, in principle, be rounded up by every 5 psi.
The minimum design internal pressure for a pressure vessel should be 50 psig, or the flare design
pressure if the vessel is connected to flare, whichever is greater. The minimum design internal
pressure is standardized to be 50 psig, and the use of 51 psig should be avoided for the minimum
design pressure.
If the vessel is open to atmosphere, a vessel should be designed for atmospheric pressure, and is
not necessary to be designed at 50 psig. For the vessels which are not subject to 50 psig minimum
design pressure, but operates considerably higher than atmospheric pressure, the design pressure
should be the highest value of the operating pressure plus 10% or plus 15 psi.
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
_ __ The pressure relief valve is normally set at 110 % of the rated discharge pressure, or 25 psi higher
I N D __| 8/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
_ __ or between the section of first (closest) valve upstream/downstream of the exchanger when blocking
__ RA|
I N D __| 9/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
devices are provided around the exchanger [Case B]. In either case, pressure built-up due to the
passing fluid through rupture should be evaluated and the justification should be made for installing
additional pressure relief valve or increasing pressure rating of associated piping.
For the design of high-pressure exchangers, a maximum differential pressure of 725 psi should be
considered except where otherwise recommended by Licensor/Designer or approved by Owner.
[Case A] [Case B]
4 DESIGN TEMPERATURE
It is noted that the statements below is general philosophy and unit specific requirement should be
examined individually.
Any deviations from general philosophy which may need to be considered for specific equipment
item should be consulted with the Owner.
_ __
__ RA|
I N D __| 10/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
The design maximum temperature should, in principle, be rounded up by every 5 degrees, unless it
affects the material selection.
The design maximum temperature at downstream of coolers should be set equal to the normal
maximum operating temperature at upstream of coolers considering the coolant failure.
If the operating temperature exceeds 750 oF, economic alternatives may need to be studied to
reduce the margin required on the operating temperature.
_ __
__ RA|
I N D __| 11/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
piping design temperature should be set equal to the steam saturation temperature at maximum
supply pressure.
_ __ with the maximum operating temperature. Full vacuum design is due to the elevation difference
__ RA| between the process areas and the cooling water supply system.
I N D __| 12/13
||___
18-SE
P-200
7
REFINING MAJOR PROJECTS GENERAL MANAGEMENT
PROJECT: RPLC DEEP CONVERSION PDVSA DOC. NO.
SUBPROJECT: GENERAL 3006-5001-BP11601
UNIT: GENERAL (U-00) CONFEED DOC. NO.
PHASE: BASIC ENGINEERING S-000-1222-0021
DISCIPLINE: PROCESS REV. A
DATE
TITLE: DETERMINATION OF MECHANICAL DESIGN CONDITIONS
PDVSA PROJECT NO.: 3006; CONFEED JOB CODE: 0-4675-20-0000 05 09 07
(10) Caustic
Design Pressure / Temperature: later / 200 oF
(Design temperature is same with PDVSA VALCOR project.)
_ __
__ RA|
I N D __| 13/13
||___
18-SE
P-200
7