PROJECT NAME: Al Qana Project Location : DELIVER TO: Date Wanted: 21/4/2020
PURPOSE: Tools for Scaffolding Dept & Materials Required for Alumnium Cladding Task Covering the Bridges Page : 1-1
STOCK
S/NO DESCRIPTION ( Be as specific as possible) SPECIFIC DETAILS UNIT QTY REMARKS
AVAILABLE
Steel Ladder Beam Thk. 4.0 mm, 1 Sets for Bridges No.
5 OD=48.3 mm, THK.=4.0 mm NOS 4
Dim. =0.45 X 5.0 m 4,3
for Low Deck
Aluminum Lattice/Unit Beam Thk. 4.0 mm,
6 OD=48.3 mm, THK.=4.0 mm NOS 2 jobs&inclined parts
Dim.=0.78 X 8.0 m
Bridge No.4
9 Joint Box (Box Pin) Scaff. Tube Connection NOS 30 For 1 Bridge 1 set
Special Instruction: for procurement to inform the choosen supplier to start fabrication for the Beams mentioned above ASAP as
per management to prevent delays.