Document Reference

FREY-FIL CORPORATION FFC


Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
1 of 11
Alignment B. M17-CIV-007-ABP-005

Construction of Abusag Bridge Location


San Jose, Baggao, Cagayan

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


Contract ID: 18B00053
Contract Name: 001 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM
BRIDGE -REPLACEMENT OF PERMANENT WEAK BRIDGES ABUSAG
BRIDGE (B04258LZ) & APPROACHES Along Baybayog - Baggao - Dalin -
Sta. Margarita Road Baggao, Cagayan
Location of the Contract: Baggao - Dalin - Sta. Margarita Road Baggao, Cagayan
----------------------------------------------------------------------------------------------------------------------------------

Method Statement for


Alignment - B Sub-base course laying.

Revision and Approval Block


Re Prepared By Verified By Approved By Noted By
Issue
v Description Details Marcelo
Date PM
No Tenio Jr.
Sign
Date
Sign
Date
Sign
Date
Print Date: 05/Jun/2020
Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
2 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Contents

1. Purpose......................................................................................................................................2

2. Scope of Work...........................................................................................................................2

3. Responsibilities.........................................................................................................................3

4. Work Methodology....................................................................................................................3

5. Resources..................................................................................................................................4

5.1 Manpower................................................................................................................................4

5.2 Safety Equipment...................................................................................................................4

5.3 Equipment...............................................................................................................................4

6. Safety Precautions
--------------------------------------------------------------------------------------------------5

7. ENVIRONMENTAL PROTECTIONMEASURES----------------------------------------------------------5
8. Annexes................................................................................................................................6-10

1. Purpose
 .The main load bearing layer of the pavement.

2. Scope of Work
This Item shall consist of furnishing, placing and compacting Sub-Base course materials on a
prepared sub-grade layers. Lines, grades, thickness and typical cross-sections shown on the
Plans and with accordance with the DPWH Standard Specifications for Highways, Bridges and
Airports and in conformity to lines, grades and dimensions shown on the plans or established
by the Employer’s Representative.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
3 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

3. Responsibilities
Project Manager/Deputy Project Manager shall be Responsible to deliver the project safely, on
time, adherent to project quality requirements,and within budget.Responsible for formulation of
construction methodologies and procedures.Coordinates work activities with logistics, commercial
and other site personnel and home base groups.
Field Engineer/Site Engineer shall be responsible for the execution of Sub-base course laying.
Quality Control Engineer will ensure the strict implementation of the Quality Plan and from
time to time provide such other personnel and resources as maybe required to ensure effective
operation of the quality assurance system. Responsible for all quality test requirements.Conducts
orientation on project quality objectives and programs to Construction Group and Subcontractors
prior to start of project and/or work packages.Accountable for ensuring the quality programs
formulated to meet the contract requirements.
Surveyor shall be responsible for establishing boundaries, limits, elevations and extend of
Sub-base course laying.
Safety officer shall ensures that the safety of the workers ha taken into consideration at all
times. He makes sure that the stake, poles and barricades with warning tapes on it shall be
in placed whenever required as the roadway embankment progresses. Warning lights shall
likewise be introduced if found necessary.

4. Work Methodology

 Secure necessary permits prior to any construction activities.


 Layout and Staking for center line and limits of sub-base course with its elevation.
 Laying of approved sub-base course materials using dump truck.
- The aggregate Sub-base course material shall be placed at a uniform mixture on a prepared sub-
grade in a quantity which will provide the required compacted thickness. When more than one layer is
required, each layer shall be compacted and tested before the succeeding layer is placed.
The placing of material shall begin at the point designated by the by the Employer’s Representative.
Placing shall be from vehicles especially equipped to distribute the material in a continuous uniform
layer or windrow. The layer or windrow shall be of such size that when spread and compacted the
finished layer be in reasonably close conformity to the nominal thickness shown on the Plans.
When hauling is done over previously placed material, hauling equipment shall be dispersed uniformly
over the entire surface of the previously constructed layer, to minimize rutting or uneven compaction.
 Grading and leveling of sub-base materials using Motor Grader.
- When uniformly mixed, the mixture shall be spread to the plan thickness, for compaction.
Where the required thickness is 200 mm or less, the material may be spread and compacted in one
layer. Where the required thickness is more than 200 mm, the aggregate Sub-base course shall be
spread and compacted in one layer of the required thickness, and the maximum compacted thickness
of any layer shall not exceed 200 mm. All subsequent layers shall be spread and compacted in a similar
manner.
The moisture content of Sub-base course material shall, if necessary, be adjusted prior to compaction
by watering with approved sprinklers mounted on trucks or by drying out, as required in order to obtain
the required compaction.

Immediately following final spreading and smoothening, each layer shall be compacted to the full width
by means of approved compaction equipment.
Rolling shall progress gradually from the sides to the center, parallel to the center line of the road and
shall continue until the whole surface has been rolled. Any irregularities or depressions that develop
shall be corrected by loosening the material at these places and adding or removing material until
surface is smooth and uniform. Along curbs, headers, and walls, and at all places not accessible to the
roller, the sub-base material shall be compacted thoroughly with approved tampers or compactors.
Compaction of each layer shall continue until a field density of at least 100 percent of the maximum dry

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
4 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

density determined in accordance with AASHTO T180, Method D has been achieved. In-place density
determination shall be made in accordance with AASHTO T 191.
 The finished sub-base surface shall be firm and uniform, true to grade and cross-section, and shall be approved by
the Consultant before placing subsequent material thereon. Sub-grade that does not conform to the requirements as
to grade, cross-section, moisture content or density shall be reworked until such requirements are met.
 Provide rigger to control the sequencing in dumping of Borrow materials.
 Provide Flagman on both ends of work areas to control the traffic.
 Note : Strict traffic management will be implemented.
 Attached traffic scheme for implementation.

5. Resources

5.1 Manpower

i. Project Manager
ii. Deputy Project Engineer
iii. Field Engineer
iv. Site Engineer
v. General Foreman
vi. Backhoe operator
vii. Loader Operator
viii. Water truck operator
ix. Tower Light Operator
x. Rigger
xi. Flagman
xii. Safety Engineer.
xiii. Surveyor
xiv. Survey Aide.
xv. Mechanic
xvi. Lead man
xvii. Laborer

5.2 Materials and tools.


i. Wooden stake
ii. Warning tapes
iii. Spray paint and Markers
iv. Steel bar for staking (elevations).
v. Shovel
vi. Wheel borrow
vii. Concrete nails.
viii. Hammer

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
5 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

5.3 Equipment

i. Bulldozer
ii. Backhoe
iii. Dump tuck
iv. Grader
v. Loader
vi. Vibratory roller
vii. Water truck
viii. Tower light

5. Safety Precautions.

As what has been the company’s standard operating procedure, safety of everyone including materials and
equipment is almost of our utmost concern..

Normal safety procedures being required at site are the following.

1) Safety tool box meeting shall be conducted everyday to remind workers about concerning the safety.
All workers shall be provided with PPE(PERSONAL PROTECTIVE EQUIPMENT) and shall be
Worn at all time on site. Safety Manager/Safety supervisor shall insure all the workers wear all the Safety
equipment provided.
2) All workers shall be advised to report any accident or injury to supervisor.
3) Proper and adequate provision of signage’s and barricades at diversions and temporary haul
road as Necessary.
4) Provision of rigger to guide the dump truck while unloading the borrow materials.
5) Provision of 2 Flagman to control traffic at both ends.
6) Prime importance shall be given for personnel safety and protection of utility lines/services. It
shall be insure that the personnel involved are aware about the company safety regulation and
confirmed that the machinery are regularly maintained. Further to above, the following key points
shall be considered important.

a) All moving vehicle/equipment shall have reverse horn.


b) Transporting of person per vehicle is restricted to the number of seats available.
c) Road safety sign /road diversion sign shall be installed wherever applicable for the safe Movement of
vehicles or equipment.

7. Environmental Protection Procedures.

All workers shall educate on good environment management practices and well discipline to environment. The
garbage bin shall be provided at the working area and supervisor shall insure its must be collected regularly and
disposed off at the approved dump site.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
6 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

All workers shall insure that all tools and equipment machinery are in good condition to avoid any oil leakage that
could harm to environment.

6. Annexes

Survey works.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
7 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Established elevation.

Embankment laying using Dump truck.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
8 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Leveling/Grading of borrow materials.

Compaction of Embankment materials.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
9 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
10 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Sub-base course laying @
11 of 11 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Print Date: 05/Jun/2020