Contents
1. Purpose......................................................................................................................................2
2. Scope of Work...........................................................................................................................2
3. Responsibilities.........................................................................................................................3
4. Work Methodology....................................................................................................................3
5. Resources..................................................................................................................................4
5.1 Manpower................................................................................................................................4
5.3 Equipment...............................................................................................................................4
6. Safety Precautions
--------------------------------------------------------------------------------------------------5
7. ENVIRONMENTAL PROTECTIONMEASURES----------------------------------------------------------5
8. Annexes..................................................................................................................................5-9
1. Purpose
To described and outline the methodology and work procedures for roadway Embankment Utilizing
equipment such as Grader, Vibratory Roller, Backhoe, Dump truck and Wheel Loader.
2. Scope of Work
Roadway Embankment covers handling, loading, transporting, placing and Grading of acceptable materials
excavated from roadway or from borrow sites for roadway construction at project up to the approved design
level.
3. Responsibilities
Project Manager/Deputy Project Manager shall direct when and where to start the
Embankment works and established deadlines for activity to be finished with the time frame
set forth on the construction schedule.
Field Engineer/Site Engineer shall be responsible for the execution of roadway embankment.
Quality Control Engineer shall be responsible in monitoring quality of works and materials
brought at site.
Surveyor shall be responsible for establishing boundaries, limits, elevations and extend of
roadway embankment.
Safety officer shall ensures that the safety of the workers ha taken into consideration at all
times. He makes sure that the stake, poles and barricades with warning tapes on it shall be
in placed whenever required as the roadway embankment progresses. Warning lights shall
likewise be introduced if found necessary.
4. Work Methodology
5. Resources
5.1 Manpower
i. Project Manager
ii. Deputy Project Engineer
iii. Field Engineer
iv. Site Engineer
v. General Foreman
vi. Backhoe operator
vii. Bulldozer operator
viii. Dump truck operator.
ix. Water truck operator
x. Loader Operator
xi. Tower Light Operator
xii. Flagman
xiii. Safety Engineer.
xiv. Surveyor
xv. Survey Aide.
xvi. Mechanic
xvii. Lead man
xviii. Laborer
5.3 Equipment
i. Bulldozer
ii. Backhoe
iii. Dump tuck
iv. Grader
v. Loader
vi. Water truck
vii. Vibratory roller
viii. Tower light
5. Safety Precautions.
Safety tool box meeting shall be conducted everyday to remind workers about concerning the safety.
All workers shall be provided with PPE(PERSONAL PROTECTIVE EQUIPMENT) and shall be
Worn at all time on site. Safety Manager/Safety supervisor shall insure all the workers wear all the Safety
equipment provided.
All workers shall be advised to report any accident or injury to supervisor.
Proper and adequate provision of signage’s and barricades at diversions and temporary haul road as
Necessary.
Prime importance shall be given for personnel safety and protection of utility lines/services. It shall be
insure that the personnel involved are aware about the company safety regulation and confirmed that the
machinery are regularly maintained. Further to above, the following key points shall be considered
important.
All workers shall educate on good environment management practices and well discipline to environment. The
garbage bin shall be provided at the working area and supervisor shall insure its must be collected regularly and
disposed off at the approved dump site.
All workers shall insure that all tools and equipment machinery are in good condition to avoid any oil leakage that
could harm to environment.
6. Annexes
Survey works.
Established elevation.