Clearing site and grubbing up all small trees not exceeding 500mm girth and including

bushes, scrubs, undergrowth hedges etc

Considered Quantity : 1 Square

Ref
Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
No.
Unskilled labour 1 0.75 1,600.00 1,200.00
2.5% of Plant cost for
30.00
Tools
1 Sub-total for Labour 1,230.00

4 Total Basic Costs : (1)+(2)+(3) 1,230.00


5 Profit & Overhead (4) × 28.0% 344.40
6 Total Cost (4)+(5) 1,574.40
7 Unit Rate (6)/Q Rs/sq 1,574.40
Rs/m2 169.41
170.00

Unit Rate for Clearing site and grubbing up all small trees not
exceeding 500mm girth and including bushes, scrubs, Rs/m2 170.00
undergrowth hedges etc.