Ref
Labour Costs No. of Units No.of Days Rate (Rs) Amount (Rs)
No.
Skilled labour 1 2.25 2,200.00 4,950.00
Unskilled labour 1 3.75 1,600.00 6,000.00
Add for Small tools & Scafolding
328.50
3% of Labour
1 Sub-total for Labour 11,278.50
Ref
Material Costs Unit Qty Rate (Rs) Amount (Rs)
No.
Bricks No 1090 10.00 10,900.00
Allow 5% of Wastage 545.00
Cement Bag 3 990.00 2,970.00
Sand Cu 0.2 19,000.00 3,800.00
Water Gal 115 1.00 115.00
3 Sub-total for Materials 18,330.00