PROPOSED RESIDENTIAL BUILDING FOR MR.

N S ALAUDEEN, ERODE @ TAMIL NADU


BASIC PRICE
SL.NO MATERIAL UNIT

1 CEMENT BAG

2 STEEL MT

3 STRUCTURAL STEEL MT

4 TEAK WOOD CFT

5 SAL WOOD CFT

6 HONNE WOOD CFT

7 MARBLE SFT

8 POLISHED GRANITE SFT

9 VITRIFIED TILE SFT

10 CERAMIC TILE SFT

11 TERRACOTA WEATHER PROOF TILE SFT


UDEEN, ERODE @ TAMIL NADU

BASIC PRICE

400.00

56000.00

62000.00

6500.00

3200.00

2500.00

120.00

75.00

65.00

45.00

30.00
PROPOSED RESIDENTIAL BUILDING FOR MR. N S ALAUDEEN, ERODE @ TAMIL NADU
SUMMARY OF PRICES
SL.N SECTIONS Rs. AMOUNT
O MAIN BUILDING

A EARTH WORK EXCAVATION Rs. 54,952.50

B PLAIN CEMENT CONCRETE Rs. 95,186.00

C REINFORCED CEMENT CONCRETE Rs. 473,747.00

D FORM WORK Rs. 246,818.00

E REINFORCING STEEL Rs. 651,420.00

F STRUCTURAL STEEL FABRICATION AND ERECTION Rs. 190,453.00

G MASONRY Rs. 538,855.00

H JOINERIES Rs. 367,400.00

I PLASTERING / POINTING Rs. 466,335.00

J FLOORING & DADOING Rs. 692,664.90

K PAINTING Rs. 149,988.00

L WATERPROOFING Rs. 79,215.00

N MISCELLANEOUS Rs. 970,333.49

TOTAL AMOUNT OF CIVIL WORK Rs. 4,977,367.89

ELECTRICAL WORK Rs. 398,189.43


PLUMBING & SANITARY WORK Rs. 398,189.43

TOTAL AMOUNT

(Rupees Sixty Lakhs Nine Thousand Nine Hundred and Fifty Four only)
Iportal Engineering Consultancy LLP 2/16
@ TAMIL NADU

AMOUNT
COMPOUND WALL

7,291.00

21,300.00

18,750.00

105,760.00

65,610.00

17,496.00

236,207.00

6,009,954.00

ty Four only)
SI. BOQ DESCRIPTION OF THE WORK UNIT QTY RATE
NO CODE

A EXE - 00 EARTH WORK EXCAVATION

EXE-01 Earthwork excavation in all types of soil for Footing, Raft, RC wall
foundations, Lift pits, Trenches, etc. stacking the excavated earth &
disposable material where ever indicated in site, excluding back filling but
including filling depressions and loose pockets wherever necessary including
watering, consolidating etc., complete. Rate to include disposing of excess
earth within the site and spreading in layers to required levels, shoring,
bailing out water, etc. complete. Contractor shall get aquinted with site
conditions and soil report and submit method statement for dewatering
and getting the surface reasonably dry for laying PCC. Note:Authorised
working space shall be considered as per IS 1200

a. Lift upto 1.5M depth


CFT 2687.00 7.50

EXE-02 Back filling in plinths, for sides of foundation, trenches, liftpits, area
developement else where as directed including breaking clods, watering and
consolidating in 150mm thick layers, compacting each layer with vibratory
compactor and at inaccessible places with wooden/steel rammers to
achieve 90 to 95% proctor density at optimum moisture content, all leads
and lifts, bailing/ pumping out water to keep site dry while backfilling
cost shall include conveyance of all materials, labour, ,hire and fuel
charges for tools and plants and other incidental charges etc.complete
as per detailed specification.

a. With excavated earth available at site


CFT 1520.00 6.00

b. With approved earth brought from outside.


CFT 900.00 12.00

EXE-03 Disposing surplus excavated soils/debris of all types outside the site upto a
lead of 5 KM including cost of labour, cost of equipment and machinery,
loading and unloading, transportation, all other incidental charges at
all leads and lifts etc. complete. The work shall be carried out as per the
directions of the Engineer-In-Charge.

LOAD 7.00 800.00

EXE-04 Supplying, diluting and injecting chemical emulsion for PRE-


CONSTRUCTIONAL Anti-termite treatment and creating a continuous
chemical barrier under and all-round the column pits, wall trenches,
basement excavation, top surface of plinth filling, junction of wall and
floor, along the external perimeter of building, expansion joints, over the
top surface of consolidated earth on which apron is to be laid, surroundings
of pipes and conduits etc. complete to required depths as per specifications
(Plinth area of the building at ground floor only shall be measured for
payment). Chlorpyriphos 20% Emulsifiable Concentrate injected with
1% concentration at all levels & heights

SFT 1160.00 8.00


SUB TOTAL- EARTH WORK EXCAVATION
B PCC-00 PLAIN CEMENT CONCRETE

PCC-01 Providing & laying 3" thick DAMP PROOF COURSE with cement concrete
1:2:4(1cement:2coarse sand:4graded stone aggregate 12.5mm nominal
size) including mixing of waterproofing admixture of Sika/Fosroc/MC
Bauchemie/Roffe or equivalent as per manufacturers specifications
etc., complete for SSM toping

CFT 60.00 154.00

PCC-02 Providing and laying P.C.C 1:4:8 of specified thickness wherever specified
using river sand, 40mm and downsize metal including sub grade preparation,
levelling, compacting, all leads and lifts, rough finishing if required at the
top surface with necessary curing and shuttering etc. complete at all
levels.

a. In Foundation
CFT 160.00 110.00

b. In below floor
CFT 517.00 110.00

PCC-03 Providing and laying Screed concrete in 1:2:4 with 20mm and down graded
stone aggregates wherever to required thickness, slope and trowel finished
smooth as directed including levelling, compacting, all leads and lifts
with necessary curing and shuttering etc. complete at all levels.

a. 50mm Average thickness for Toilets above sunken CFT 20.00 151.00
b. 75mm average thickness for Sill /coping for Window,Parapet etc., CFT 56.00 151.00

SUB TOTAL-PLAIN CEMENT CONCRETE

C RCC-00 REINFORCED CEMENT CONCRETE

RCC-01 SITE MIX CONCRETE


Providing and laying cast in-situ design mix Reinforced Cement Concrete
(RCC) using cement, coarse sand, granite, basalt or trap stone graded
aggregate 20mm & down as per design & drawing including dewatering,
preparing surface, machine batching, machine mixing, pouring in
place, mechanical compaction, providing cement cover blocks,
making construction joints, finishing, curing etc. complete as directed by
the Engineer . The rate to include all labour, material, equipment, plant &
machinery, conveyance, lowering, hoisting, wastages and all
incidentals excluding formwork and reinforcement which shall be measured &
paid for separately. Grade of concrete-M20

a. Column up to Plinth CFT 36.00 158.00

b. Plinth beam CFT 348.00 155.00

c. Columns at all levels CFT 304.00 158.00

d. Staircase including landings CFT 225.00 155.00

e. Lintel,Chajja,Loft etc. CFT 122.00 160.00

RCC-03 READY MIX CONCRETE


Providing, batching, mixing, transporting through transit mixers, pumping
and laying Reinforced Cement Concrete of specified grade at all levels and
heights specified below using ordinary Portland cement of grade 53 from
approved manufacturer, river sand, 20mm and down size coarse aggregates,
necessary admixtures approved by Consultants (Conplast SP 430SRV from
Fosroc or equivalent), including all leads and lifts, pumping using line
pump or boom placer, vibrating/ compaction, scaffolding wherever
necessary, curing as directed, excluding cost of shuttering, centering and
staging etc

(Design mix shall be as approved by the consultants. W/C ratio shall be as per
consultants recommendation)- GRADE OF CONCRETE FOR ALL MEMBERS - M20

a. Footing/Raft CFT 520.00 145.00

b. Roof slab at all levels CFT 987.60 145.00

c. Roof Beam at all levels CFT 642.00 145.00

SUB TOTAL-REINFORCED CEMENT CONCRETE

D FRM-00 FORM WORK

Note: Rate shall be included under propping with steel jack until upper roof
slab concreting & desuttering etc., complete

FRM-01 Providing, fabricating and erecting form work for all RCC works at places
wherever needed / specified as per drawing including striking /
deshuttering with steel / marine ply board with adjustable steel
props to full height and with sufficient bracing etc. complete. Cost to include
sealing the joints with heavy duty brown self adhesive tape, applying mould
releasing agents (Rebol from Fosroc or equivalent) aligning to line and
levels including M S Ties, PVC spacer etc.Complete & as directed at all levels.

Formwork shall be designed for rigidity, durability, strength, water tightness,


easy deshuttering etc. Formwork designed with proposed material (approved
prior to making), shall be able to withstand its shape, line, dimensions, level
within the allowable tolerances. Only steel jacks and steel spans shall be used.
Bracing in both directions as specified by the structural engineer shall be
provided. Necessary arrangements for providing camber as required shall
be made. Formwork shall have adequate openings for cleaning. Formwork for
construction joints shall be submitted for approval. All slabs shall be
progressively deshuttered and back propped as per instructions by structural
engineer.

Shuttering below the shrinkage strip at every level shall be retained in place
without disturbing for a time as specified by the structural engineer.

Shuttering materials shall be MS shuttering sheets for slabs and plywood


of approved thickness for beams, columns, shear walls, lift walls etc.

a. Footing/Raft
SFT 420.00 26.00

b. Column till plinth top


SFT 270.00 26.00
c. Plinth beam
SFT 1919.00 26.00

d. Columns at all levels


SFT 1905.00 26.00

e. Roof slab at all levels


SFT 1982.00 26.00

f. Roof Beam at all levels


SFT 2181.00 26.00

g. Staircase including landings


SFT 381.00 26.00

h. Lintel,Chajja,Loft etc.
SFT 435.00 26.00

SUB TOTAL- FORM WORK

E RST-00 REINFORCING STEEL

RST-01 Fabricating & Placing Reinforcement Steel of High Yield Strength Deformed
(HYSD) bars of various diameters of grade Fe 415 conforming to IS codes
& make ISPAT or SAIL or VIZAG or TATA including straightening, cutting,
bending, hooking, lapping and/or welding wherever required as directed,
placing in position, tieing with 18G black annealed binding wire double fold,
cost of binding wire and anchoring to the adjoining members wherever
necessary, all laps and wastages etc. complete as per structural drawings.
Rate also to include cost of all materials, cost of labour, cost of
equipment and machinery, loading and unloading, transportation, all
other incidental charges and work at all leads and lifts etc. complete.

Note: Unless noted otherwise the measurements will be in


accordance with IS: 1200 or equivalent BS. However reinforcement shall be
measured only in lengths of bars as actually placed in position on
standard weight basis, no allowance being made in the weight for rolling
margin. Authorised laps and splices only will be measured. Chairs of any
shape & profile, spacer bar of any shape & profile, concrete cover blocks,
wastages, binding wire etc., will not be measured and shall be included in the
quoted rates. Quoted rate shall be deemed to have considered the above
stipulation.(Basic price of steel Rs.34000/MT)

At all levels and heights MT 10.34 63000.00

SUB TOTAL-REINFORCING STEEL

F SST-00 STRUCTURAL STEEL FABRICATION AND ERECTION

SST-01 Providing, fabricating and fixing in position Window Grills at all levels
with Semi-decorative MS grill work made out of 12mm MS square bars
and 19mm x6mm MS flats as per design weighing approx. 15 kg/sqm with
necessary screw lugs inserts, spot welding and buffing etc., all as detailed in
drawing and as directed.

SFT 418.00 170.00


SST-02 Providing, Fabricating & fixing 900mm high MS railing with 2" dia b class 16
gauge pipe as railing with 3/4" MS pipe of horizontal members & 2" dia
MS pipe for balustrade etc., all inclusive cutting, welding, grouting to
floor/masonry, grinding, Buffing,wastages, labour, etc., complete( Steel
shall be taken 15kg/Sqm)Rate to be quoted inclusive of Spray enamel paint
finish etc., complete

a. Staircase railing SFT 167.00 150.00


b. Balcony Hand railing RFT 80.78 120.00

SST-03 Providing and fixing MS Spiral Staircase at First Floor Terrace


including Painting etc. complete No 1.00 52000.00

SST-04 Providing and fixing MS Grill Door for staircase entrance at First
Floor including Painting etc. complete SFT 25.00 250.00

SST-05 Providing fabricating and welding structural steel Trellies work for
staircase at First Floor including Painting etc. complete SFT 132.00 200.00

SUB TOTAL-STRUCTURAL STEEL FABRICATION AND ERECTION

G MSR-00 MASONRY

MSR-01 Providing and constructing 230mm thick brick masonry in CM 1:6 using
approved quality table moulded bricks of minimum 50kg / Sq.cm
including raking, curing, scaffolding and staging, lead and lift, in all
situations such as walls / pillasters / pillars / stub supports etc.
complete as per drawing and as directed at all levels and heights

CFT 2597.00 155.00

MSR-02 Providing and constructing 115mm thick brick masonry in CM 1:4. Cost to
include necessary 1:2:4 concrete bands 75mm depth at every 5th course
with nominal reinforcement of 8mm dia steel 2nos including fabrication,
shuttering, scaffolding and staging,compacting, raking, curing, all
lead and lift etc. complete as per drawing and as directed at all levels and
heights

Main Building SFT 1704.00 80.00


SUB TOTAL-MASONRY

H JNR-00 JOINERIES

JNR-01 Providing & fixing in position Teak Wood frame Door with Machine Finished I
class Sal Wood frame of 21/2"X5" fixed to the masonry/Column with MS
clamp/Anchor fastener grouted with M20 grade concrete after anti termite
coat at wall face of frame with 32mm thick OST shutter with 1mm thick
approved shade laminate finish with 6mm thick TW edge lipping including
enamel paint finish on frame &shutter edge over a coat of primer & polish
finish on TW face of shutter including all hardwares & fixtures like SS hinges,SS
Tower Bolts,Doorset Locks,SS Handles, SS Stoppers (SS fixtures shall taken
Rs.150/Sft) etc., complete

a. Main door & Pooja Door SFT 64.00 1100.00


JNR-02 Providing & fixing in position Sal Wood frame Door with Machine Finished I
class Sal Wood frame of 21/2"X5" fixed to the masonry/Column with MS
clamp/Anchor fastener grouted with M20 grade concrete after anti termite
coat at wall face of frame with 32mm thick OST shutter with 1mm thick
approved shade laminate finish with 6mm thick TW edge lipping including
enamel paint finish on frame &shutter edge over a coat of primer & polish
finish on TW face of shutter including all hardwares & fixtures like SS hinges,SS
Tower Bolts,Doorset Locks,SS Handles, SS Stoppers (SS fixtures shall taken
Rs.100/Sft) etc., complete

a. All internal Doors SFT 138.00 600.00


b. All toilet doors SFT 53.00 600.00

JNR-03 Supplying,Providing & Fixing Honne Wood Glass Shutter Open able and fixed
Windows with Machine Finished I class Padok Wood frame of 3"X5" projecting
out by 1/4" from Plastered wall surfaces shall be fixed with heavy duty MS
clamp grouted to masonry with M20 concrete with shutter shall be in 11/2"x3"
PW frame with 6mm toughened siant gobain series tinted glass to be held in
place with 1/2"X1/2"TW Beading etc.,all as per Architect details & drawing etc
to complete. The Rate shall be include of Melamine polish for both Frame &
Shutters and all hardwares & fixtures like SS hinges,SS tower bolt,SS
lock/hook,SS handle (SS fixtures shall be taken @ Rs. 75/Sft) etc complete

For all windows and ventilators SFT 304.00 600.00

SUB TOTAL-JOINERIES

I PLS-00 PLASTERING / POINTING

PLS- Cement plastering on internal ceilings 15 mm thickness in C.M. (1:4)


01 finished smooth including corridor ceilings, including providing and removing
scaffolding, smooth lime rendering (hydrating the lime 24 hours before
starting of the work), curing, hacking etc., complete. With all lead & lift
as directed by engineer incharge.

SFT 2582.00 30.00

PLS-02 Prepare the surface and provide 15mm thick plastering on Internal
walls, columns, beams, etc., in cement mortar 1:6 finishing to line
and level with lime rendering, rounding off all corners wherever
required, finished smooth to required profile at all levels and lifts,
hydrating the lime 24 hours before starting of work including GI plaster
mesh for joints, scaffolding, curing etc, complete at all levels and heights.

SFT 5198.00 30.00


PLS-03 Providing 20 mm THICK CEMENT PLASTER IN TWO COATS under layer 12
mm thick cement plaster 1:4 (1 cement: 4 coarse sand) top
layer 8 mm thick cement plaster 1:6 (1 cement: 6 fine sand)and
finished as specified, including providing necessary plaster grooves at
junctions wherever required and for all exterior heights etc. for top layer
finish & finished rough with sponge for sand face plaster. The quoted rate
shall include addition of approved water-proof compound (dosage as per
manufacturer),GI Dimond/plaster mesh for joints, as directed by the
Engineer-in-charge at all levels

SFT 4719.00 45.00

PLS-04 Providing 15 mm thick sponge finish plastering in duct and lift shaft one coat
in CM 1:4 at all levels SFT RO

PLS-05 Cement plastering as rough plaster 20 mm thick for all cladding, dadoing, in
C.M 1:6, including providing & removing scaffolding, curing, hacking etc.,
complete. With all lead and lift as directed by engineer incharge.

SFT 686.00 30.00

SUB TOTAL-PLASTERING / POINTING

J FLR-00 FLOORING & DADOING/CLADDING

Note: All flooring item shall be inclusive of providing & removing POP
protection with polythene sheet & Non porus coating etc., complete

FLR-01 Providing & laying of approved quality/colour/size of Marble flooring laid over
20mm tk CM 1:4 base mortor Bed Jointed with White cement slurry @
4.4kg/Sqm & joints to be filled using white cement mixed with matching
colour oxide & cleaning etc all as per drawing, specifications & as directed,the
rate shall be include of rubbing,polishing,non porus coating etc to
complete(Basic price of Marble Rs.120/Sft)(The rate shall be inclusive of
inlay,border,band,groove etc.,)-In Living, dining & Kitchen

SFT 899.00 220.00

FLR-02 Do-do the same of above but for 3" high Skirting with Marble etc.,
complete(edge to chamfered or Half nosing to be done as per Architectural
detail)
RFT 307.00 90.00

FLR- Providing & laying of approved quality/colour/size of approved Polished


03 Sadarahalli stone flooring laid over 20mm tk CM 1:4 base mortor Bed Jointed
with White cement slurry @ 4.4kg/Sqm & joints to be filled using white
cement mixed with matching colour oxide & cleaning etc all as per drawing,
specifications & as directed,the rate shall be include of rubbing & polishing
,Cleaning etc to complete(Basic price of stone Rs.70/Sft)-In staircase

SFT 490.00 150.00


FLR- Do-do the same of above but for 3" high Skirting with Granite etc.,
04 complete(edge to chamfered or Half nosing to be done as per Architectural
detail)
RFT 136.00 75.00

FLR- Providing and laying of approved quality/colour/Vitrified tile flooring at all


05 levels,laid over 20mm tk CM(1:4) base mortar bed jointed with cement slurry
@ 3.3kg/Sqm,pointing using approved tile grout matching to tile shade and
washing finally with diluted hydrochloric acid including lead,lift,wastages
etc., all as per drawing, specifications and as directed, complete (Basic Price
of Vetrified tile Rs.60/Sft)

SFT 1136.00 110.00

FLR- Do-do the same of above but for 4" high Vitrified tile skirting with CM 1:3 etc.,
06 complete RFT 223.00 55.00

FLR- Providing and laying of approved quality/colour/Ceramic tile flooring at all


07 levels,laid over 20mm tk CM(1:4) base mortar bed jointed with cement slurry
@ 3.3kg/Sqm,pointing using approved tile grout matching to tile shade and
washing finally with diluted hydrochloric acid including lead,lift,wastages
etc., all as per drawing, specifications and as directed, complete

a. In G.Floor utility & First floor balcony (Basic Price of Ceramic tile
Rs.50/Sft) SFT 210.00 90.00

b. In toilets (Basic Price of Ceramic tile Rs.40/Sft) SFT 245.00 80.00

FLR- Do-do the same of above but for 4" high Ceramic tile skirting with CM 1:3 etc.,
08 complete

a. In G.Floor Utility & First floor balcony RFT 173.22 45.00

FLR- Providing & laying of approved quality/colour/-Ceramic tile in DADO on 12


09 mm tk cement plaster 1:3(1 cement: 3 coarse sand)and jointed with gray
cement slurry (at the rate of 3.3 kg cement per sqm) including pointing in
approved tile grout matching to tile shade,washing finally with diluted
hydrochloric acid including wastages,lead,lift etc., all as per drawing,
specifications and as directed etc., complete at all levels(Basic price of tile
Rs.40/Sft)

a. In toilets SFT 771.00 85.00


b. In Kicthen & Utlity SFT 150.00 85.00

FLR-10 Providing and laying of approved quality of cement tile flooring ,laid over
20mm tk CM(1:4) base mortar bed jointed with cement slurry @ 3.3 Kg/Sqm
with water proof admixture & sapcer joints ,pointing using white cement
mixed with matching colour oxide and Cleaning etc.,, all as per drawing,
specifications and as directed(Basic price of tile Rs.50/Sft)

In Car park SFT 345.00 90.00


FLR-11 providing and laying Granite counters, 20mm thick laid on 20mm thick CM
1:4 fixed with angle support as per drawing and including providing fascias
and making openings in the Granite counter for seating wash basins/sinks
and supporting the same with MS plates as required etc. and pillar cock. Rate
to include for washing with light acid, polishing,sink cutting, pillar cock
cutting and double edge polishing and rounding of edges, sealing the joints
with pigmented mastic etc. as approved and as directed. Plan area shall
be measured, with all lead and lift and as directed by Architect
/Engineer in charge at all levels and heights.(Basic price of Granite
Rs.170/Sft)

In Kitchen counter SFT 34.00 300.00

FLR-12 Providing & Laying Flagging Course with 4" thick PCC 1:2:4 & Finished top with
20mm thick CM 1:3 plaster of smooth finish including thread lining, curing,
cost of labour & material atc., complete

SFT 220.00 75.00

FLR-13 Providing and fixing Slate cladding to Parking wall with 20mm thick back
mortar in CM 1:4 inlcuding pointing with Match colour tile grout, curing, final
wash etc. complete
SFT 400.00 160.00

SUB TOTAL-FLOORING & DADOING/CLADDING

K PNT-00 PAINTING

PNT-01 Providing & painting 2 or more coats of Acrylic emulsion paint of approved
colour & shade for ceilings over one coat of primer & putty including necessary
centering, scaffolding, cleaning of paint stains where ever necessary including
curing etc,complete with all lead & lift as directed by the engineer incharge
at all levels

SFT 2582.00 12.00

PNT-02 Providing & painting two or more coats of Acrylic Emulsion paint of approved
colour & shade to internal surfaces over one coat of primer including
necessary centering, scaffolding,cleaning of paint stains where ever necessary
including curing etc,complete with all lead & lift as directed by the engineer
incharge.at all levels

SFT 5198.00 12.00

PNT-03 Providing & painting 2 or more coats of Exterior Acrylic Emulsion Paint(Dulux
Weather shield)of approved colour & shade to external surfaces over one coat
of primer including necessary centering,scaffolding, cleaning of paint stains
where ever necessary including curing etc,complete with all lead and lift as
directed by the engineer in charge at all levels

SFT 4719.00 12.00

SUB TOTAL-PAINTING

L WTP-00 WATERPROOFING
Sub contractor to be approved by Client/ Architect/Consultants/ Project
NOTE Managers

WTP-01 TOILETS
Providing waterproofing for the Toilets by chemical method as
follows:Brushing,cleaning & hacking the surface area to provide Brush
bond/ equivalent in 2 layers one after the other with 1mm tk as per
manufacturers' specification.The cost to include 2coats of waterproofing
plaster done with 12mm agg fixing in CM1:4 with waterproofing
admixture mixing with rough finished to required slope with an avg tk of
30mm with a minimum guarantee period of 10yrs.

SFT 227.00 45.00

WTP-02 TERRACE
Providing waterproofing for Terrace as per the specifications listed below with
a minimum guarantee period of 10yrs.

Provide Brick Bat Coba Water Proofing to the terrace by surface method
of average thickness 110mm with water proof admixture as per
manufacturer's(Fosroc/Equivalent) specification with a minimum
guarantee period of 10 years. Cost to include application of cement slurry
with water proofing compound over the surface, laying of brick bat coba to
necessary gradient and joints filled with CM 1:3 with water proofing
compound, providing joint less waterproof plastering with CM 1:4 and
water proofing compound, finished smooth and impression marking of size
300x300 Square with 3mm rod. Treatment shall continue along parapet for
300mm height in shape of round wata, curing etc., Cost to include the
treatment along parapet and no extra 'measurements shall be accounted
for the same (only Plan area shall be accounted). Brickbats shall be
soaked 24 hours in soaking tank before using the same for
waterproofing & only Seived river sand shall be used

SFT 920.00 75.00

SUB TOTAL-WATERPROOFING

N MSL-00 MISCELLANEOUS

MSL-01 Providing & Constructing UNDER GROUND SUMP of capacity 6000 lts at a
suitable location which includes,(1)Excavation for sump,(2) PCC 1:4:8 for
base(3) RCC for base in M20 grade concrete with 20mm & down size
aggregates, river sand & approved water proofing material,(4)side walls shall
be of 150mm thick M20 grade concrete walls which are plastered smooth with
CM1:3 along with approved waterproofing compound, (5) Top slab shall be of
RCC slab of M20 grade concrete with nominal steel reinforcement of
8mm@8"c/c with a provision for a cast iron heavy duty manhole of size
2'0"X2'0",(6) Collection sump in base slab shall be provided,(7) Heavy duty PVC
rungs @ 300mm c/c etc.,complete all as per specifications & as directed by
the Architect & the Engineer-in-charge.

a. In Domestic sump LTS 10000.00 12.00

MSL-02 Providing and constructing external staircase including finish etc.


complete LS 1.00 50000.00
MSL-03 Providing Complete interior work(Wardrobe, kitchen cabinets, pooja
unit,TV unit,Cot etc.) LS 1.00 800333.49

SUB TOTAL-MISCELLANEOUS
AMOUNT IN
FIGURES

20152.50

9120.00

10800.00

5600.00

9280.00
54952.50

9240.00

17600.00

56870.00

3020.00
8456.00

95186.00

5688.00

53940.00

48032.00

34875.00

19520.00
75400.00

143202.00

93090.00

473747.00

10920.00

7020.00
49894.00

49530.00

51532.00

56706.00

9906.00

11310.00

246818.00

651420.00

651420.00

71060.00
25050.00
9693.00

52000.00

6250.00

26400.00

190453.00

402535.00

136320.00
538855.00

70400.00
82800.00
31800.00

182400.00

367400.00

77460.00

155940.00
212355.00

20580.00

466335.00

197780.00

27630.00

73500.00
10200.00

124960.00

12265.00

18900.00

19600.00

7794.90

65535.00
12750.00

31050.00
10200.00

16500.00

64000.00

692664.90

30984.00

62376.00

56628.00

149988.00
10215.00

69000.00

79215.00

120000.00

50000.00
800333.49

970333.49
PROPOSED RESIDENTIAL BUILDING FOR MR. N S ALAUDEEN, ERODE @ TAMIL NADU
BILL OF QUANTITY
COMPOUND WALL
SI. BOQ
NO CODE
DESCRIPTION OF THE WORK UNIT

A EXE - 00 EARTH WORK EXCAVATION

EXE-01 Earthwork excavation in all types of soil for Footing, Raft, RC wall
foundations, Lift pits, Trenches, etc. stacking the excavated earth & disposable
material where ever indicated in site, excluding back filling but including filling depressions
and loose pockets wherever necessary including watering, consolidating etc., complete.
Rate to include disposing of excess earth within the site and spreading in layers to
required levels, shoring, bailing out water, etc. complete. Contractor shall get
aquinted with site conditions and soil report and submit method statement for dewatering
and getting the surface reasonably dry for laying PCC. Note:Authorised working space shall
be considered as per IS 1200

a. Lift upto 1.5M depth


CFT

b. Lift from 1.5M depth to 3.0M


CFT

EXE-02 Back filling in plinths, for sides of foundation, trenches, liftpits, area developement
else where as directed including breaking clods, watering and consolidating in 150mm thick
layers, compacting each layer with vibratory compactor and at inaccessible places with
wooden/steel rammers to achieve 90 to 95% proctor density at optimum moisture content,
all leads and lifts, bailing/ pumping out water to keep site dry while backfilling cost
shall include conveyance of all materials, labour, ,hire and fuel charges for tools and plants
and other incidental charges etc.complete as per detailed specification.

a. With excavated earth available at site


CFT

b. With approved earth brought from outside.


CFT

SUB TOTAL- EARTH WORK EXCAVATION

B PCC-00 PLAIN CEMENT CONCRETE

PCC-01 Providing & laying 3" thick DAMP PROOF COURSE with cement concrete
1:2:4(1cement:2coarse sand:4graded stone aggregate 12.5mm nominal size) including
mixing of water proofing admixture of Sika/Fosroc/MC Bauchemie/Roffe or
equivalent as per manufacturers specifications etc., complete for SSM toping including
necessary shuttering etc.,

CFT
AMIL NADU

AMOUNT IN
FIGURES
QTY RATE

650.00 7.50 4875.00

RO

604.00 4.00 2416.00

RO

7291.00

60.00 125.00 7500.00


SI. BOQ
NO CODE
DESCRIPTION OF THE WORK UNIT

PCC-02 Providing and laying P.C.C 1:4:8 of specified thickness wherever specified using river
sand, 40mm and downsize metal including sub grade preparation, levelling, compacting, all
leads and lifts, rough finishing if required at the top surface with necessary curing and
shuttering etc. complete at all levels.

a. In Foundation
CFT

SUB TOTAL-PLAIN CEMENT CONCRETE

D SST-00 STRUCTURAL STEEL


SST-01 Providing, fabricating and fixing in position Compound Gate as per design
weighing approx. all as detailed in drawing and as directed. SFT

SUB TOTAL-STRUCURAL STEEL

E MSR-00 MASONRY

MSR-01 Providing and constructing granite size stone masonry for Foundation and / or Basement upto
ground / plinth level of any and varying thicknesses and profiles using stones hammer
dressed in courses not less than 20 cms high with bond stones at 2M apart in each
course in CM 1:6 including providing and removing necessary scaffolding & staging
wherever required, watering, curing etc., complete including the cost of all materials, cost
of labour, cost of equipment and machinery, all lead and lift, loading and unloading,
transportation, and all other incidental charges etc., complete as per design and
specification. The stonework shall be constructed to receive plastering on both sides. The
work shall be carried out as per the directions of the Engineer in charge.

CFT

MSR-02 Providing and constructing 115mm thick brick masonry in CM 1:4. Cost to include
necessary 1:2:4 concrete bands 75mm depth at every 5th course with nominal
reinforcement of 8mm dia steel 2nos including fabrication, shuttering, scaffolding
and staging,compacting, raking, curing, all lead and lift etc. complete as per drawing and
as directed at all levels and heights

SFT

SUB TOTAL-MASONRY

F PLS-00 PLASTERING / POINTING


PLS-01 Providing 20 mm thick single coat sponge finish plaster with CM 1:5 finished as
specified, including providing necessary plaster grooves at junctions wherever
required and for all exterior heights etc. for top layer finish & finished rough with
sponge for sand face plaster all as directed by the Engineer-in-charge at all levels

SFT

SUB TOTAL-PLASTERING / POINTING

G PNT-00 PAINTING

PNT-01 Providing & painting two or more coats of Acrylic Emulsion paint of approved colour & shade
to internal surfaces over one coat of primer with 2 coat of ready made putty + 2nd coat of
primer including necessary centering, scaffolding,cleaning of paint stains where ever
necessary including curing etc,complete with all lead & lift as directed by the engineer
incharge.at all levels

SFT

SUB TOTAL-PAINTING
AMOUNT IN
FIGURES
QTY RATE

120.00 115.00 13800.00

21300.00

75.00 250.00 18750.00

18750.00

320.00 110.00 35200.00

882.00 80.00 70560.00

105760.00
1458.00 45.00 65610.00

65610.00

1458.00 12.00 17496.00

17496.00