Sie sind auf Seite 1von 1

DDA COMMENTS CORRECTIVE MEASURES

1. Absence/Inadequate/Damaged Hoarding. As per your instruction, all the bracing support


for hoarding sheet has been fixed from inner
side. Please refer the photo attached.

2. Inactive Site. Your comments are noted, The site was closed
temporarily due to delay in the arrival of
materials. We are expected to resume the work
within 3/6/2020. Further we will ensure that the
appointed Security Guard will always be at Site
Entrance
3. Absence the consultant’s signature. As per your instruction, we will make sure that
the Consultant Inspects and signs the
construction site hygiene measures on daily basis
and displayed at site entrance. Please find
attached the Signed Copy.

Das könnte Ihnen auch gefallen