Beruflich Dokumente
Kultur Dokumente
Summary
The wire rope on the winch was over-spooled instead of under-spooled as required by the client. This
problem was identified at the client work site and actions taken to rectify this. The winch wire was changed
to under-spooled in the Swee Bee yard in Singapore using a spooling machine provided by Franklin.
The spooling machine was set up approximately 20m from the winch to allow for adequate fleeting angles.
Suitable ballast was used to anchor both the winch and spooling machine. The wire rope was spooled off
the winch onto the spooling machine. Three wire rope wraps were laid onto the spooling machine before
rope tension was increased slightly. Then at five wraps tension was raised to 5 tonnes. This tension was
maintained throughout the transfer of the remainder of the wire rope from the winch to the spooling
machine.
The winch was turned around to allow the wire rope to be under-spooled. The wire rope wraps on the
winch were laid with minimal tension until a total of five wraps were on the winch and the wire rope
tension was increased to 5 tonnes. Wire rope was laid at this tension until the last five wraps on the
spooling machine when the tension was reduced until the wire rope was released from the spooling
machine drum. The remaining 20m of wire rope was spooled onto the winch with no tension other than a
nylon rope restraint for guidance.
The combination of 20m between the winch and the spooling machine and the last five wraps from the
spooling machine laid down with decreasing tension resulted in approximateky 35m of wire rope slack
spooled on the winch drum.
Two technicians from ACE Winches were mobilised to conduct the on-site load testing of the winch.
Winch acceptance testing was carried out on site by a full capacity loading of the winch. As part of the set
up for the load test, 25m of wire rope was paid off through a snatch block down to the j-tube anchor point
where the wire rope was connected to for load testing. This left the wire on the drum at the last wrap
before climbing to the next layer. The test load was increased to the final load required in three stages;
20Te, 40Te amd 55Te. As the test load increased, the wire rope was pulled down into the narrowing gap
of the final wrap the layer below. This resulted in the rope jamming between the winch drum flange and the
space on the last wrap before continuing the next layer (Photographs 1 and 2).
Immediate action
To release the jammed wire rope, it was re-connected to the anchor point at the j-tube and a two tonne
chain block was used to pull the wire rope free. The wire rope was visually inspected by both V Ronald and
D Collins (certification of rope inspection attached) and was found to have a slight kink as seen in
Photograph 3. There was no evidence of broken wire damage or crushing to the wire rope.
The winch load testing and release of the jammed rope was conducted under the supervision of Benoit
Gourguechon of Technip.
Photograph 3
A root cause analysis of the incident was completed using the TapRooT Root cause Analysis technique. The
output is shown in the TapRooT chart (Attachment 1) and TapRooT table (Attachment 2).
2. The wire rope was not packed for the load test and the load test was conducted with the wire rope at
the winch drum flange.
Root Causes
From the analysis of the initial causes the basic causes and root causes were indentified. The root causes as
follows.
Actions
Recommendations
The visual inspection of the wire rope shows no damage which should affect its capacity and it is suitable
for continued use at its original capacity.
The project is due to be carried out in September / October 2013 and the wire rope will require re-
certification before 28 October 2013 when current certification expires.