PROJECT SUMMARY

Prepared By:
design

Date: November 3, 2005

Project Briefs: Engineering Room : 25.00 M2


A. Project title : The Rotaryana Prima Branch Office &
2. Second Floor : 245.00 M2
Cafe
Mezzarine showroom : 45.00 M2
Open plan office : 150.00 M2
B. Project description : The Branch Office, Showroom, Café
Side Office : 50.00 M2
& Staff Accommodation of
Virtual Office & Lounge : 200.00 M2
Rotaryana Prima
3. Third Floor : 81.00 M2
C. Location : Jl. By Pass Ngurah Rai, Nusa Dua,
Pond : 29.00 M2
Bali, Indonesia
Skylight : 52.00 M2
D. Land area : 1,124.30 M2
Total Building area : 1,124.30 M2
E. Project completion : To be determined

F. Project commencement date : To be determined


Design Conceptual
G. Construction time required : - months
A. Function: PT. Rotaryana Prima branch office complete with kitchen equipment show
H. Building and facilities:
room, workshop, café and staff accommodation.
1. First Floor : 798.30 M2
B. Architectural conceptual and approach: Unique Balinese Architecture with modern
Entry : 16.00 M2
standard of technology will shown dominantly
Foyer : 25.00 M2
to covered the function of building. Combination
Obin House : 130.00 M2
of natural local sand stone (Paras Silakarang
Galerry : 150.00 M2
and Paras Krobokan) with simplicity shape
Café & Display : 150.00 M2
appear on over all of building.
Show Kitchen, display & cafe : 105.00 M2
Private Dinning : 50.00 M2
C. Room Program:
Wash-up kitchen : 8.80 M2
Display : 13.50 M2
Storage & Work shop : 100.00 M2
Lockers Male & Female : 25.00 M2

Prepared by C – Design Page 1 of 3 Rotaryana Pima Project


PROJECT SUMMARY
Prepared By:
design

Date: November 3, 2005

Building Specifications Ceiling : Calciboard 6 mm painted

7. Display
First Floor Floor : Existing
Wall : Existing
1. Entry Ceiling : Calciboard 6 mm painted
Floor : Existing
Column : Karang bukit random 8. Cafe
Ceiling : Existing Floor : Sulawesi marble 30x30 cm
Wall :-
2. Foyer Ceiling : Calciboard 6 mm painted
Floor : Existing
Wall : Existing 9. Washup Kitchen
Ceiling : Existing Floor : Polished concrete
Wall : Plaster painted
3. Obin House Ceiling : Calciboard 6 mm painted
Floor : Existing
Wall : Existing 10. Locker Male & Female :
Ceiling : Existing Floor : Existing
Wall : Existing
4. Gallery Ceiling : Existing
Floor : Polished concrete & iron wood
Wall : Plaster painted 11. Engineering Room
Ceiling : Calciboard 6 mm painted w/ rel aluminium Floor : Ceramic tile
Wall : Plaster painted
5. Café & Display Ceiling : Existing
Floor : Polished terrazzo existing with deco floor
Wall : Existing 12. Storage & Work shop
Ceiling : Calciboard 6 mm painted Floor : Existing
Wall : Existing & partisi
6. Show Kitchen Ceiling : Calciboard 6 mm painted
Floor : Sulawesi marble 30x30 cm
Wall :- 13. Private Dinning

Prepared by C – Design Page 2 of 3 Rotaryana Pima Project


PROJECT SUMMARY
Prepared By:
design

Date: November 3, 2005

Floor : Existing & Deco floor Wall : Existing & partisi


Wall : Plaster painted Ceiling : Existing
Ceiling : Calciboard 6 mm
Third Floor
Second Floor
1. Pond
1. Mezzanine Showroom Floor : Sukabumi stone
Floor : Existing
Wall : Panel 2. Skylight
Ceiling : Existing Floor : Timber Existing
Wall : Paras kerobokan.
2. Virtual Office
Floor : Existing
Wall : Existing & partisi Architecture fee proposal:
Ceiling : Calciboard 6 mm
7.5% from the total of project cost estimation with scope of works with following :
3. Lounge 1. To provide conceptual design, design development drawing, tender document
Floor : Existing drawing until contract drawing :
Wall : Existing & partisi  Architectural drawing
Ceiling : Calciboard 6 mm  Interior drawing
 Hard landscape drawing
4. Side Office  Structure drawing
Floor : Ceramic tile  Mechanical, electrical and plumbing drawing (MEP)
Wall : Plaster painted 2. Provide technical specification
Ceiling : Calciboard 6 mm 3. Provide tender document and cost plan

5. Side Office Project supervision fee:


Floor : Existing
Wall : Plaster painted & Glass windows existing from Café existing 1st floor 4 % from total project cost estimation for supervision during construction.
Ceiling : Calciboard 6 mm

6. Open Plan Office


Floor : Existing ==== END OF SECTION ====

Prepared by C – Design Page 3 of 3 Rotaryana Pima Project


PROJECT SUMMARY
Prepared By:
design

Date: November 3, 2005

Prepared by C – Design Page 4 of 3 Rotaryana Pima Project