COMMISSIONING PLAN ‐ FAN

Project: MAYAN YAS ISLAND LIVING, Plot YS3‐4‐6
Date: 06/06/2020

Commissioning Date Required 
Sl No. Equipment Reference Equipment Model Qty Required Manpower Commissioning Activities Remarks
Starting Ending Days
Team‐3
Pre Commissioning, Air Balancing, 
1 GEF‐B5‐01 CC‐HP 710‐4P‐9‐8°T, 1.5kW, 415V/50Hz 2 Day 1 Day 2 2 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
2 SGEF‐B5‐01 TMF 315, 0.262kW, 230V/50Hz 1 Day 3 Day 3 1 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
3 SPF‐B5‐01 CC‐HT 800‐4P‐6‐26°T, 4.8kW, 415V/50Hz 2 Day 4 Day 6 3 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
4 SPF‐B5‐02A CC‐HT 630‐4P‐9‐16°T, 1.1kW, 415V/50Hz 2 Day 7 Day 9 3 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
5 SPF‐B5‐02B CC‐HT 710‐4P‐9‐24°T, 4kW, 415V/50Hz 2 Day 10 Day 12 3 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
6 CPF‐B5‐01 CC‐HT 710‐4/8P‐9‐12°T, 1.6/0.4kW, 415V/50Hz 2 Day 13 Day 15 3 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
7 FLPF‐B5‐01 CC‐HT 630‐4P‐9‐10°T, 0.75kW, 415V/50Hz 2 Day 16 Day 17 2 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
8 LPF‐B5‐01 CC‐HT 710‐4P‐9‐16°T, 2.2kW, 415V/50Hz 2 Day 18 Day 20 3 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
9 SEF‐B5‐01 CC‐HT 400‐2P‐9‐8°T, 0.75kW, 415V/50Hz 2 Day 21 Day 22 2 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
10 SEF‐B5‐02 CC‐HT 400‐2P‐9‐8°T, 0.75kW, 415V/50Hz 2 Day 23 Day 24 2 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
11 CPMF‐B1‐07 CC‐HT 1000‐4P‐9‐24°T, 18kW, 415V/50Hz 2 Day 25 Day 28 4 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Team‐3
Pre Commissioning, Air Balancing, 
12 CPEF‐B1‐07 CC‐HT 1120‐4P‐9‐20°T, 22.2kW, 415V/50Hz 2 Day 29 Day 32 4 Specialized Technecian ‐ 1nos
Checking Electrical Parameters
Helper‐ 1 nos
Note:
1) T&C can be start only after clearing the below mentioned conditions.
a) All building ceiling, partition doors & windows should be fully installed (To check the pressure for SPF‐B5‐01, SPF‐B5‐02A, SPF‐B5‐
02B, CPF‐B5‐01, FLPF‐B5‐01 & LPF‐B5‐01, the spaces should be architecturally sealed)
b) There should be electric power supply in building (either permanent or temporary).
c) Ducting work should be finished completely.
e) Installtion of Diffusers/Grilles should be completely finished.
2) Main Contractor has to provide required temporary access opening during the time of T&C

3) All the above mentioned dates are valid only if the working of equipment/installation is proper. If any rectification works required, the work duration may change.

Page 1 of 1