Refractory Activity schedule of Boiler in Saudi Aramco Safania

Sr No Activity Detail days 24-Dec 25-Dec


1 Mobilization 1
2 Formwork Fabrication and fixing 1
3 Back up layer insulating castable lining alternative segment(50%
of total surface area) 1
4 Curing of the back up layer alternative segment 1
5 Back up layer insulating castable lining aremaining
segment(remaining 50% of total surface area) 1
6 Curing of the back up layer remaning segment 1
7 formwork Fabrication and fixing for hot face final layer 1
8 hotface layer alternative layer castable lining 1
9 hotface layer layer castable lining completion 1
10 curing 1
11 Demolition of damaged refractory lining 1
12 alternative segment casting of the bottom 120 degree portion of
boiler shell. 1
13 casting completion of the bottom 120 degree portion of boiler
shell. 1
14 refractory lining of boiler shell upper 120degree by gunning 1
15 Refractory Lining of boiler roof 1
16 Final Boxup 1