Beruflich Dokumente
Kultur Dokumente
A A
650
159
B B
C C
NOTES:
1. DIMENSION, COORDINATES AND ELEVATIONS IN
MILLIMETERS, UNLESS OTHERWISE INDICATED.
2. THE AMOUNTS LISTED DO NOT INCLUDE MATERIAL LOSSES
PER CUT OR OVERMETAL FOR ADJUSTMENTS.
3. THE FIELD WELDING, ADJUSTMENTS AND PAINTING
REPAIRS ARE RESPONSIBILITY OF THE STEEL
FRONT VIEW SIDE VIEW STRUCTURE ERECTION COMPANY.
4. PIPING SUPPORT CONCRETE BASES MUST HAVE IT
LOCATION CONFIRMED BEFORE IT BE CONCRETED.
5. ALL SECONDARY PIPING SUPPORTS SHOULD DE IDENTIFIED
BY STAMP MARKING.
D 6. INFORMED PROFILES CUTTING ANGLES ARE GUIDELINES
D
AND MUST BE ADJUSTED DURING
THE SITE ERECTION.
6. INFORMED PROFILES CUTTING ANGLES ARE GUIDELINES
AND MUST BE ADJUSTED DURING
THE SITE ERECTION.
7. FOR DETAILS OF THE CD's, SEE SECONDARY SUPPORT
BOOK ( ST5005741047552).
1
E 50 50 558 E
CERTIFIED
2
100
REF. POINT
200
747-S8600
100
G G
TOP VIEW 3D VIEW PROJ. No.
ELABORADO DATA
RR 03/03/2020
1 2 3 4 5 6 7 8 9 10 11 12
1:5
unset