PROJECT: FENCING WORK

LOCATION: TIGMAN ABORLAN, PALAWAN


OWNER:
Aborlan Price no hauling of Materials Needed

We are pleased to submit our quotation for the proposed fencing work
located at ,Tigman Aborlan, Palawan with a total labor and material cost of.
Below is the Scope of Work

DESCRIPTION QTY UNIT UNIT COST TOTAL COST


I. EXCAVATION , HAULLING
Excavation 49.8 cu.m 250 12,450.00
Hauling 5 trips 300 1,500.00
I. Total Cost 13,950.00
II. MASONRY WORKS
CHB 4" 3192 pcs 16 51,072.00
Cement (40kg) 416 bags 240 99,840.00
Screened Sand 22 cu.m 1400 30,800.00
Gravel 3/4 21 cu.m 1400 29,400.00
Fine Sand 6 cu.m 1800 10,800.00
Material Cost 221,912.00
Labor Cost 110,956.00
II. Total Cost 332,868.00
III. STEEL WORKS
Ø16mm RSB X 6m 36 pcs 398 14,328.00
Ø12mm RSB X 6m 319 pcs 210 66,990.00
Ø10mm RSB X 6m 333 pcs 145 48,285.00
Tie Wire #16 4 rolls 2400 9,600.00
Material Cost 139,203.00
Labor Cost 69,601.50
III. Total Cost 208,804.50
IV. CARPENTRY WORKS
2"x2"x8' Form Lumber 240 pcs 75 18,000.00
Plywood 1/4 Ordinary 30 pcs 500 15,000.00
CW Nail 4" 15 kls 55 825.00
CW Nail 3" 15 kls 55 825.00
CW Nail 1 1/2" 6 kls 65 390.00
Material Cost 35,040.00
Labor Cost 17,520.00
IV. Total Cost 52,560.00
V. WELDING WORKS
Plain Sheet #18 10 pcs 1400 14,000.00
GI Pipe 2" Schd. 40 12 pcs 1750 21,000.00
Cut-off Blade 4 pcs 320 1,280.00
Angular Bar 3/16 x 1 1/2 70 pcs 470 32,900.00
Welding rod 3/32 5 kls 80 400.00
Epoxy Metal Primer 2 gal 640 1,280.00
Epoxy Paint 2 gal 900 1,800.00
Epoxy Reducer 2 gal 500 1,000.00
Material Cost 73,660.00
Labor Cost 36,830.00
V. Total Cost 110,490.00
SCOPE OF WORK

I. EXCAVATION , HAULLING ----------- 13,950.00


II. MASONRY WORKS ----------- 332,868.00
III. STEEL WORKS ----------- 208,804.50
IV. CARPENTRY WORKS ----------- 52,560.00
V. CARPENTRY WORKS ----------- 110,490.00
TOTAL COST 718,672.50

ROEL S. ASPERAS "Weng"


CONTRACTOR

ORNEL C. ASPERAS ME 1
ENGINEER