Beruflich Dokumente
Kultur Dokumente
According to the proposed work I need to complete the code on MATLAB for designing of the pipeline
with different flow equations and I have completed the same. The details of the simulation and
problem statement is given below:
For giving the real touch to the project I have used the real time composition of the City gas used by
GAIL India Ltd. for CGD.
Composition of Gas:
1. Flow rate of gas or demand of natural gas in the compressor= 4 Million m3/Day
2. Length of pipe from processing plant to the compressor station= 100 KM
3. Delivery pressure at the compressor station= 5500 kPa
4. Gas compressibility factor (Z)= 0.920
5. Base temperature= 15o C
6. Base pressure= 101 kPa
Pipeline Specifications:
Now I have used the 4 types of flow equations for prediction of Inlet pressure required to for delivery
pressure of 5500 kPa with the given conditions that are:
Feeding the Input values available with us in the MATLAB program the following results are obtained:
From above simulation it is clearly seen that the Inlet pressure required for the given conditions from
general flow equation is 9109 kPa and pressure at 25% length i.e. at 25 KM is 6590 kPa and pressure
can be fined at any point on the pipeline by the same method.
B. Weymouth Equation:
Feeding the Input values available with us in the MATLAB program the following results are obtained:
From above simulation it is clearly seen that the Inlet pressure required for the given conditions from
general flow equation is 8656 kPa and pressure at 25% length i.e. at 25 KM is 6436 kPa and pressure
can be fined at any point on the pipeline by the same method.
C. Panhandle-A Equation:
Feeding the Input values available with us in the MATLAB program the following results are obtained:
From above simulation it is clearly seen that the Inlet pressure required for the given conditions from
general flow equation is 7863 kPa and pressure at 25% length i.e. at 25 KM is 6176 kPa and pressure
can be fined at any point on the pipeline by the same method.
D. Panhandle-B:
Feeding the Input values available with us in the MATLAB program the following results are obtained:
From above simulation it is clearly seen that the Inlet pressure required for the given conditions from
general flow equation is 7553 kPa and pressure at 25% length i.e. at 25 KM is 6076 kPa and pressure
can be fined at any point on the pipeline by the same method.
PSEUDO-CODE FOR THE MATLAB CODE DEVELOPMET
Now we will see all these steps in detail with the real time photos explaining all these steps:
1) Surveying and Laying:
Before construction activity begins, the first is to mark the limits of approved area ( i.e.
construction boundaries, additional temporary workspace), this comes under surveying of the
area of the land used for pipeline laying. In this step we also move all the equipment required
in pipeline laying to on-site from the store house and prepare a temporary warehouse near the
site.
2) Clearing and Grading:
After the equipment is accessible in the staging area, work will begin to clear cut the pipeline
right-of-way. Landowners have the option of selling the timber themselves, or allowing the
company responsibility for its sale or disposal. Large trees are stockpiled or hauled off, while
the branches and tree tops are placed into piles and burned. A stump grinder then removes the
remaining tree stumps in the ROW.
3) Trenching:
Trench is provided to depth that satisfies the PNGRB regulations to provide sufficient cover
for the pipeline. Normally depth of 1m is sufficient. T4S regulations by PNGRB gives
guidelines. Fig. shows typical dimensions.
4) Pipe Stringing and Welding:
When the trench is completed, pre-coated segments of pipe, usually 40 ft in length,
are transported from stockpiles in the staging area to the right-of-way. Pipes are laid
above ground beside the trench, or within the trench on top of supportive sandbags in
steep terrain. Certain pipe sections are bent using a pipe bending tool to allow the
pipeline to follow the planned route and the terrain. The pipe sections will then be
welded together, sand blasted, and the weld joints coated with epoxy to prevent
corrosion. Finally, the weld joints are inspected with x-ray to ensure their quality.
Connected lengths of pipe can then be lowered into the trench.
7) Hydrostatic Testing:
After the pipe is inspected, the trench is filled in. Before completing the project, the pipeline
integrity must be verified using hydrostatic testing. Pipeline companies receive permits to
withdraw millions of gallons of water from streams and rivers along the pipeline path. This
water is sent through the pipeline and the pressure is increased to above the maximum
operational level. If the pipeline remains intact during this test, it is deemed operational. After
this, the surface of the ROW is seeded and fertilized, and above-ground markers are placed
along the pipeline path.
8) Commissioning:
After hydrostatic testing, pipeline is cleaned and dried. Commissioning activities involved by
purging line with air and loading the line with natural gas.