SCHEDULE OF 15.0M GANTRY FOR 50.0M STRECTH WITH REINFORCEMENT ‐  MONTHLY PROGRESS AS PER THIS SCHEDULE= 206.

37 m
ACTIVITIES DURATION FOR 45.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat &  Setting time plush pump shifing 24.00 Hrs
2 Curb‐Reinforcement binding (15.0m)
10.0 Hrs 10.0 Hrs 10.0 Hrs
3 Overhead reinforcement binding (15.0m)
Gantry de‐shuttering alignment fixing & bulk 
4
heading (9.0m)
6.0 Hrs 6.0 Hrs 6.0 Hrs
Gantry de‐shuttering alignment fixing & bulk 
5
heading (6.0m)
Concrete Pouring ‐ 9.0m  (During Concrete pouring of overhead after it, 
6
the curb will be poured) 15.0 Hrs 15.0 Hrs 15.0 Hrs
7 Pump alignment & Placement of pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
8 Pump cleaning  1.0 Hrs 1.00 Hrs 1.0 Hrs
9 Transport of materials (Rebars) 3.0 Hrs 3.00 Hrs 3.0 Hrs
10 Cleaning & Reinforcement binding of Invert
11 Invert Concreting 16 Hrs
12 Deberis cleaning for every 3 gantry 12 Hrs
Thus, 45.0m (3Nos of gantry) completes in  6.54 Days
NOTE: REQUIREMENT OF MACHINARY
           1. Small TM ‐(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
           2.  Hydraulic Gantry
           3. Vibrators
           4. Welding Machine ‐ 3 Nos (1nos Spair) in proper working condition.
           5. De‐watering Pumps ‐2 Nos (1 Nos Spair) in proper working condition.

        : Manpower 
           1. A gang of labours should prepared required rebars outside the tunnel.
           2.  There should be 3nos gangs for rebar placement. ( 1 gangs will work curb rebar placement & other 2nos of gangs will work for 
crown overhead. Aprox. total numbers of labours should be 60 to 70 nos.  ( including cleaning gangs, concreting gangs)
          3. Days shift and Night Shift
          3.1 Foreman / Supervisor ‐2Nos for each shift.
          3.2 Electrician ‐2Nos for each shift.
          4. Surveyor ‐1Nos (Call duty)
          5. Mechanic & helper ‐1 Nos for each shift.
          6. All drivers should be on call duty.
         7. Face‐Incharge ‐ Nos. 
       :HURDLE/OBSTRUCTION
          1.  Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as      mentioned 
above.
          2.    It is assumed that labours shall be paid regularly.