Sie sind auf Seite 1von 1

P-0010B-A

CONSTRUCTION CHECK SHEET


MECHANICAL
INSTALLATION OF PUMP
PROJECT DESCRIPTION n-BUTYL LITHIUM DILUTION FACILITY PROJECT No. 44 – NC – 2900

SYSTEM DESCRIPTION INSTALLATION OF PUMP SYSTEM No. 26

SERVICE DESCRIPTION TAG No. P-0010B

Sl.No: Checks to be performed Result


1. Verify nameplate data is correct and preservation intact.
2. Confirm installation is complete as per drawings and vendor procedure.
Check the machinery holding down bolts are correctly torqued, value recorded & that all
3.
shimming material is stainless steel. Ensure leveling screws are stress free.
4. Confirm grouting is completed, trimmed and specifications met.
Confirm piping supports next to suction & discharge nozzles are complete, in accordance with
5.
project drawings and fully secured/tightened.
6. Spring supports, hangers at correct cold setting.
Check that final alignment is completed; records generated & signed off (including coupling
7.
installation records).
8. Confirm that unit rotates freely by hand.
9. Confirm anti-spark coupling guards are available & fitted.
10. Confirm earth bonding is completed.
11. Check that the direction of rotation is clearly marked.
12. Confirm that the suction lines downstream of the strainer are blown clear & flushed.
13. Confirm the commissioning strainer & mesh is installed (record mesh size as required).
14. Desiccant bags removed prior to nozzles hook up with piping.
15. Doweling if required should be carried out after the machine signature has been proven.
16. Confirm air release valve is correctly fitted (as applicable).
17. Confirm all vendor supplied appurtenances, oil cups, etc are installed correctly.
18. Confirm correct type and quantity of lubricants have been filled as applicable.
Confirm crankshaft web deflection conforms to manufacturer requirements (reciprocating
19. compressors only). Note: Applicable if shaft alignment carried out on site and if web deflection
check is indicated by manufacturer).
20. Air Gap on single bearing motor is within specified tolerance limits (as applicable).
Remarks (Where applicable)