Sie sind auf Seite 1von 4

Licensed copy: morgan , Morgan Est, 28/02/2009, Uncontrolled Copy, ®The Concrete Society

A single copy of this

Concrete Society

publication is licensed to

morgan
on
28/02/2009

This is an uncontrolled copy - not for contract use


Morgan Est

This is an uncontrolled copy. Ensure use of the most current version of this document
by searching the Construction Information Service at http://uk.ihs.com
CONCRETE Advice
CONCRETE ADVICE No. 03

Straightening and rebending


reinforcement on site
Licensed copy: morgan , Morgan Est, 28/02/2009, Uncontrolled Copy, ®The Concrete Society

Dick Roberts BSc CEng MICE FCS

The requirement to bend or rebend reinforcement partly cast into concrete falls
into two broad categories; planned situations and correcting errors. An example of
a planned situation is where a vertical member is cast and a slab is subsequently
joined to the vertical face. A temporary opening in a slab would be another typical
example. Codes of Practice restrict the rebending of reinforcement on site. This
document reviews the specifications and provides appropriate guidance.

1 Code requirements more detail in the commentary. It states


that although construction conditions may
make it necessary to bend bars that have
been embedded in concrete, such field
BS 8110 (1) Section 7, Specification and bending should not be done without the
workmanship: reinforcement, discusses authorisation of the Engineer. The com-
cutting and bending reinforcement, and mentary continues by stating that if the
states that where it is necessary to reshape reinforcing bars cannot be bent cold up to
previously bent reinforcement this should 90° at or near the minimum dia-meter
only be done with the Engineer’s specified, and straightened, the steel can
approval and each bar should be inspected be heated to a maximum temperature of
for signs of fracture. The same Standard 1500°F (815°C) to avoid cracking or
states that where it is necessary to bend breaking of the bars.
reinforcement projecting from concrete
this can be done if the reinforcement is a 2 Approaches for planned
Grade 250, but that if it is a Grade 460 it situations
should not be bent, rebent or straightened
without the Engineer’s approval. This
implies that reinforcement protruding Continuity systems
from concrete can be rebent or The preferred solution for planned situ-
straightened, but it does not give any ations is to use a properly designed pro-
advice as to how this should be done. In prietary continuity system for bar sizes up
fact there appears to be little information to 12 mm in Grade 460. These systems
on this subject. comprise pre-bent reinforcement housed
The American Code (ACI 318(2)) is similar in a purpose designed carrier case fab-
to the British Standard but gives a little ricated off-site Such devices are also
available for size 16 mm although recting errors. A typical example is • Cutting the bar and welding on
particular care is needed to avoid where a vertical column bar has a new bar. If carried out with
damage on straightening. A properly been fixed and cast out of its correct great care, this can be an accept-
designed continuity system will position, thus causing problems able solution. However, the
ensure that sufficient space is when the next lift of steel fixing or standard of welding commonly
available for fitting a straightening concreting is to take place. If the available on site is not of
tool and that the bar is bent at the error is such that the specified cover acceptable quality. With a properly
Licensed copy: morgan , Morgan Est, 28/02/2009, Uncontrolled Copy, ®The Concrete Society

correct radius as specified in is encroached and such cover is certified welder and close super-
BS8666(3). A tube slipped over the important (as it usually is) there is vision acceptable full strength
bar to provide leverage for bending no alternative but to cut back the welds can be achieved. All bars to
is not acceptable practice. Where the concrete until an acceptable cover is British reinforcement standards
device incorporates a metal pro- reached. Apart from maintaining are weldable and recommen-
tection system to be cast in, care cover the problem is to get the dations for metal welding are
needs to be taken to ensure that the reinforcing bar back to or near its given in BS 7123(5).
specified cover is maintained both correct position without damaging
• Partly cutting back the con-
to the reinforcement and to the the bar or the concrete. The methods
crete, cutting off the bar and
metal protection. to be considered for bars currently
swaging on a new bar. This is an
available to BS 4449(4) are:
Couplers acceptable solution if the require-
• Cold bending or rebending. ments on cover and alignment can
An alternative for 12 mm and 16 mm
Unless the bar is size 12mm or be met. A specialist swaging
is the use of a cast-in coupler, which
less, it is virtually impossible to company and a trained operator
can be located against the formwork
bend it manually at the correct should be employed.
by using a temporary form fixer.
radius without damaging the bar
Couplers should be used for all bars • Cutting back the concrete to a
or the concrete. If it is a bent bar
larger than 16 mm. point where a new bar can be
to be rebent the operation is not
lapped with the acceptable por-
Use of Grade 250 reinforcement only difficult but potentially dan-
tion of the cast-in bar. Although
An alternative approach for joints gerous as the bar can fracture and
costly, this as an acceptable
primarily under static stress is to use injure the operative. For small
solution.
8, 10 or 12 mm Grade 250 plain sizes of bar a grooved and
round bars bent into the vertical face radiused tool should be used (the 3 Summary
of the concrete and subsequently radius for 8, 10 and 12 mm, Grade
straightened out. This system has 250 should be at least 16, 20 and
the disadvantage that it is difficult to 24 mm respectively, and for
Grade 460, 24, 30 and 48 mm To sum up, therefore, in planned sit-
locate and rebend the cast-in bars
respectively). Suitable power uations the designer and detailer
without damaging the surrounding
bending devices for cold bending should use a proprietary continuity
concrete or without bending the bars
larger bars at the correct radius device, small diameter high yield or
at too small a radius. Even with a
are not known to exist. mild steel bars or some form of
correct rebending tool it is difficult
mechanical coupling. In unplanned
to avoid bending the bars where • Hot bending or rebending.
situations, bars 12 mm in diameter
they emerge from the concrete at a Heating the bar to 800 to 900°C
or less can probably be manually
small radius. Bars should not be and bending while hot can signif-
bent, but care should be taken to
bent out in the direction of the icantly reduce the effort required;
ensure that the bar is bent around the
surface as damage may result. Even lower temperatures do not give
correct radius; it should never be
with bending in the direction away great enough strength reduction.
kinked or distorted.
from the specified cover damage However, the operation is difficult
may still occur unless great care is to control, hazardous, and has the Larger diameter bars can be heated
exercised. It is also very difficult to disadvantage that high yield bars to reduce the effort required to bend
achieve a perfectly straight bar in may revert to mild steel. In such bars, but high yield bars of the
such a rebending operation. addition, above 300°C the cold worked variety will probably
concrete may spall or crack, revert to mild steel if heated, and it
3 Dealing with errors would be preferable to ensure that
leading to severe reductions in
strength. Such limitations and no cold worked high yield bars are
potential hazards are not normally heated. To ensure that the tem-
acceptable. perature does not go above that
The other main area where the need
required, temperature indicating
to bend or rebend occurs is in cor-
crayons, or other means such as elec-
tronic thermometers, should be used.
Care should also be taken to ensure that
the concrete itself is not heated. Using
suitable insulation can reduce this, but
even then there is some risk that the heat
may travel along the bar into the concrete.
Licensed copy: morgan , Morgan Est, 28/02/2009, Uncontrolled Copy, ®The Concrete Society

Cutting the bar and swaging on a new bar,


although it sounds simple, may be dif-
ficult due to the position of the bar to be
cut and swaged, the cover of the bar and
the new sleeve, and the room in which the
swaging tool has to work.

FURTHER READING AND ADVICE

References
1. BRITISH STANDARDS INSTITUTION, BS 8110, Structural use of concrete, Part 1: Code of practice for design and construction,
BSI, London, 1997.
2. AMERICAN CONCRETE INSTITUTE, ACI 318, Building code requirements for reinforced concrete, American Concrete Institute,
Farmington Hills, USA.
3. BRITISH STANDARDS INSTITUTION, BS 8666, Scheduling, dimensioning, bending and cutting of steel reinforcement for concrete,
BSI, London, 2000.
4. BRITISH STANDARDS INSTITUTION, BS4449, Specification for carbon steel bars for the reinforcement of concrete, BSI, London, 1997.
5. BRITISH STANDARDS INSTITUTION, BS 7123, Specification for metal arc welding of steel for concrete reinforcement, BSI, London,
1989.

Impartial advice can be sought from The Concrete Society. Members are Contacts
entitled to substantial discounts on services and products including site visits
and investigations, dependant on status. For publications and information, The Enquiries and advice
Concrete Society Bookshop holds a wide range of books and pamphlets along
The Concrete Society 01276 607140
with an extensive library stock. We provide many services such as literature
Bookshop 07004 607777
searches and notification of new references to our extensive catalogue.
www.concrete.org.uk

Issued: July 2003

CONCRETE Advice Sheets are produced and published by The Concrete Society. The information and advice contained in the
Advice Sheets is based on the experience and knowledge of the Concrete Society’s Technical Staff. Although The Society does
its best to ensure that any advice, recommendation or information it gives is accurate, no liability or responsibility of any kind
(including liability for negligence), howsoever and from whatsoever cause arising, is accepted in this respect by The Concrete
Society, its servants or agents. Readers should also note that all Concrete Society publications are subject to revision from time
to time and should therefore ensure that they are in possession of the latest version.

Das könnte Ihnen auch gefallen