1. UAE040/001-ACM-CE-DEP-PW-1053 indicates only breaker rating for 11kv Switching station.

Whereas details like Current transformer, Voltage Transformer and Relays are not indicated.
In absence of above details we have not included Supply and Installation of 11kV Switching
Station in our offer. However we have proposed provisional sum for the same in our offer
2. In absence of quote from the specified vendor, we have not included Supply of FOH,
Specialist and Façade light fitting in our offer. However we have included Supply and
Installation of BOH lighting.
3. In absence of quotation from the nominated subcontractor, we have not included Supply
and installation of CCTV system, Access Control system, Intrusion system and Parking
Management system in our offer. However we have proposed provisional sum for the same
in our offer
4. We have included power provision only for EV Charging station as indicated in Power layout
drawing. We have not included Supply and Installation of EV Charging Station in our offer.
5. We have not included Car park structure for Photo Voltaic system.
6. Temporary power supply for Mock up building
7. Bollards