1 Overview Feasibility
3.3 Process flow
This section will describe the process of biodiesel production from vegetable oils where the
triglyceride oil is broken into alkyl (biodiesel) and glycerine by reaction with a mono alcohol.
The biodiesel and glycerine phases are then separate and purified. Production processes contain
the same stages, irrespective of the production scale, although the differences in equipment
may be significant.
2|Page
6) Methyl Ester Wash
Once separated from the glycerine, the biodiesel is sometimes purified by washing
gently with warm water to remove residual catalyst or soaps, dried, and sent to
storage.
To increases biodiesel purity.
7) Storage (by-product)
Glycerine is stored in suitable storage tanks.
8) Transport (by-product)
Transportation is required for the processed co-product glycerine.
9) Storage and Transport (Product)
Methyl Ester is stored in suitable storage tanks
Transportation of the final product to the vendor
3|Page
3.3 Process flow diagram (PFD)
4|Page
3.4 Piping and Instrumentation Diagram (P&ID)
5|Page
4.0 MIN MAPPING AND WORK BREAKDOWN STRUCTURE (WBS)
6|Page
4.2 Work Breakdown Structure (WBS)
7|Page
5.0 PROJECT SCHEDULING
The diagram shown below illustrates the network diagram for the processes in producing a
Fatty Acid Methyl Ester (FAME) and Glycerin which acts as a profitable by-product. There
are 3 networks involved in the manufacturing process which is ABCD network, ABCEGJK
network and ABCEFHI network. Of all the networks drawn, the longest duration for a network
is called the critical duration. It is calculated that the critical path network (the longest network
path) which is ABCEFHI network requires a total of 17 hours. This proves that the path cannot
be delay as it will be affecting the project duration as a whole.
8|Page
Figure: Activity on Node (AOA) diagram
9|Page
5.2 Activity on Nodes (AON) Diagram
The diagram shown below illustrates the network diagram for the processes in producing a
Fatty Acid Methyl Ester (FAME) and Glycerin which acts as a profitable by-product. There
are 3 networks involved in the manufacturing process which is ABCD network, ABCEGJK
network and ABCEFHI network. Of all the networks drawn, the longest duration for a network
is called the critical duration. It is calculated that the critical path network (the longest network
path) which is ABCEFHI network requires a total of 17 hours. This proves that the path cannot
be delay as it will be affecting the project duration as a whole.
10 | P a g e
Figure: Activity on Node (AON) diagram.
11 | P a g e
5.3 Gantt Chart
12 | P a g e