Sr.No.

DESCRIPTION MAN Project Timeline (Monthwise)


PEAK QTY
MONTH
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
A ALL KHATIYA STATIONS
1 CIVIL TEAM 40 95 40 35 20
2 INSTRUMENT TEAM 40 82 12 40 30 0
3 ELECTRICAL TEAM 24 48 0 24 24 0
4 PIPING TEAM 24 60 12 24 24 0
B JELAHA STATION - - 0
1 CIVIL TEAM 30 107 20 30 25 20 12 0
2 INSTRUMENT TEAM 24 96 0 24 24 24 12 12
3 ELECTRICAL TEAM 16 66 0 14 16 16 10 10 0
4 PIPING TEAM 20 66 0 0 14 20 20 12 0
C FAHAHIL SOUTH - -
1 CIVIL TEAM 22 102 18 22 17 15 12 10 8 0 0 0
2 INSTRUMENT TEAM 20 94 0 0 14 20 20 20 20 0 0 0
3 ELECTRICAL TEAM 12 56 0 0 12 12 12 10 10 0 0 0
4 PIPING TEAM 12 70 0 10 12 12 12 12 12 0 0 0
D FAHAHIL NORTH - - 0
1 CIVIL TEAM 25 109 22 25 22 20 10 10 0 0 0 0
2 INSTRUMENT TEAM 16 72 0 0 12 16 16 16 12 0 0 0 0 0
3 ELECTRICAL TEAM 12 64 0 6 12 12 12 12 10 0 0 0 0 0
4 PIPING TEAM 12 60 0 0 12 12 12 12 12 0 0 0 0 0
E FAHAHIL MAIN - - 0
1 CIVIL TEAM 22 130 16 22 22 20 20 15 15 0 0 0 0
2 INSTRUMENT TEAM 20 72 0 0 0 20 20 20 12 0 0 0 0 0
3 ELECTRICAL TEAM 12 64 0 6 12 12 12 12 10 0 0 0 0 0
4 PIPING TEAM 20 88 0 8 8 20 20 20 12 0 0 0 0

TOTAL 332 1,601 140 290 332 271 232 203 133 - - - - -
-
-
-
- REPLACEMENT THREE PHASE TEST SEPARATOR
-
00 ISSUED FOR APPROVAL 1-Nov-18 VS
REV NO DETAIL DATE BY
Sr.No. DESCRIPTION MAN Project Timeline (Monthwise)
PEAK QTY
MONTHS
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19
1 CONTRACT REPRESENTATIVE 1 9 1 1 1 1 1 1 1 1 1 0
2 DPEPUTY PROJECT MANAGER 1 9 1 1 1 1 1 1 1 1 1
2 CONSTRUCTION MANAGER 1 9 1 1 1 1 1 1 1 1 1
3 QA/QC MANAGER 1 9 1 1 1 1 1 1 1 1 1
4 HSE MANAGER 1 9 1 1 1 1 1 1 1 1 1
5 COMMISSIONG MANANGER 1 9 1 1 1 1 1 1 1 1 1
6 SR. PLANNING/COORDINATOR 1 9 1 1 1 1 1 1 1 1 1
7 SR. PLANNING ENGINEER 1 9 1 1 1 1 1 1 1 1 1 0
8 SITE PLANNING ENGINEER 1 9 1 1 1 1 1 1 1 1 1 0
9 LEAD HSE OFFICER 1 9 1 1 1 1 1 1 1 1 1
10 HSE OFFICERS 14 104 12 14 14 14 14 14 10 6 6 0
11 MECHANICAL ENGINEER 1 9 1 1 1 1 1 1 1 1 1 0
12 INSTRUMENT ENGINEER 1 9 1 1 1 1 1 1 1 1 1 0
13 ELETRICAL ENGINEER 1 9 1 1 1 1 1 1 1 1 1
14 QA/QC ENGINEER 1 9 1 1 1 1 1 1 1 1 1 0
15 QA /QC INSPECTOR 6 54 6 6 6 6 6 6 6 6 6
16 CIVIL ENGINEER 1 9 1 1 1 1 1 1 1 1 1
17 COMMISSIONG ENGINEER 1 6 1 1 1 1 1 1
18 ADMIN TEAM 6 54 6 6 6 6 6 6 6 6 6
19 PRO OFFICCER 1 9 1 1 1 1 1 1 1 1 1 0
20 PTW - COORDINATOR 1 9 1 1 1 1 1 1 1 1 1 0
21 SITE SUPERVISORS - PTW 20 164 20 20 20 20 20 20 20 12 12
- -
TOTAL 64 535 61 64 64 63 63 64 60 48 48 - - - -
- -
- DIRECT MANPOWER DEPLOYMENT SCHEDULE
- CIVIL, MECHANICAL AND E&I WORKS
- - TITLE: FOR
- REPLACEMENT THREE PHASE TEST SEPARATOR
00 ISSUED FOR APPROVAL 1-Nov-18 VS AT DUKHAN, QATAR
REV NO DETAIL DATE BY
M/C
Sr.No. DESCRIPTION PEAK QTY
MONTHS Project Timeline (Monthwise)

Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19
1 BOOM TRUCK 2 15 1 2 2 2 2 2 2 2
2 3-TON PICKUP 1 8 1 1 1 1 1 1 1 1
3 BOBCAT 2 12 1 2 2 2 2 1 1 1
4 DUMP TRUCK 2 12 2 2 2 2 2 2
5 WATER TANKER 3 21 2 2 2 3 3 3 3 3
6 VIBRATORS 2 9 2 2 2 1 1 1
7 VACCUM TRUCK 2 11 1 1 1 1 2 2 2 1
8 CONCRETE MIXER MACHINE 1 5 1 1 1 1 1
9 REBAR BENDING MACHINE 1 5 1 1 1 1 1
10 LOADER 1 5 1 1 1 1 1
11 HILTI MACHINE 1 8 1 1 1 1 1 1 1 1
12 JACK HAMMER 2 11 2 2 2 2 2 1
13 LEVELLING STAFF 3 17 3 3 3 2 2 2 2
14 CONCRETE CUTTING MACHINE 1 6 1 1 1 1 1 1
15 TOTAL STATION 3 18 3 3 3 2 2 2 2 1
16 PLATE COMPACTOR 1 6 1 1 1 1 1 1
17 JUMPING COMPACTOR 1 6 1 1 1 1 1 1
18 01 TON ROLLER 1 5 1 1 1 1 1
19 ASPHALT CUTTING MACHINE 1 7 1 1 1 1 1 1 1
20 BATTERY DRILL MACHINE 2 16 2 2 2 2 2 2 2 2
21 BATTERY HILTI MACHINE 2 16 2 2 2 2 2 2 2 2
22 JACK HYDRAULIC 07 TON 1 8 1 1 1 1 1 1 1 1
23 WELDING GENERATOR 10 63 7 8 10 10 10 10 6 2
24 CRANE 50T 3 11 1 1 1 1 2 3 1 1
25 CRANE 100T 2 10 2 2 1 1 1 2 1
26 TRAILER 20T 2 11 1 1 1 2 2 2 1 1
27 PWHT MACHINE 3 10 2 2 3 2 1
28 DIESEL GENERATOR 100KW 2 11 1 1 1 1 1 2 2 2
29 FORKLIFT 10T 5 13 2 2 3 3 3
30 SUV 3 27 3 3 3 3 3 3 3 3 3
31 PICK-UP 5 42 5 5 5 5 5 5 4 4 4
32 BUS 2 16 2 2 2 2 2 2 2 1 1
33 MINI BUS 3 17 2 2 2 2 2 2 2 2 1
-

TOTAL 66 458 56 59 62 63 66 64 47 32 9 0 0

REPLACEMENT THREE PHASE TEST SEPARATOR


00 ISSUED FOR APPROVAL 1-Nov-18 TAA
Rev. No. Detail Date BY