Sie sind auf Seite 1von 30

COBACABANA (CONTROL OF

BALANCE BY CARD BASED


NAVIGATION): A CARD-BASED
SYSTEM FOR JOB SHOP CONTROL

Seminar Report
By
Lijo John
CONTENTS

1. INTRODUCTION

2. PARADIGM SHIFT

3. WLC PARADIGM

4. WLC CONCEPTS

5. WLC FEATURES FOR JOB SHOP

6. CONCEPTUAL BACKGROUNDS

7. THE COBOCABANA SYSTEM

8. EXAMPLE

9. CONCLUSION

10. REFERENCE
ABSTRACT
Since late 1940’s Kanban, a card based control system was in use, but kanban is
still being used for the repetitive manufacturing. Thus in case of a make to order
job shop manufacturing this card based system fails. Thus a need for a new card
based system was realized for the job shops. The Cobacabana ( control of
balance by card based navigation) system is being proposed here by the
author. This system is based on the concept of work load control (WLC). Due to
recent developments in the understanding of the concepts of the work load
control it has become possible to convert the work load into a robust card
system. Here the card system is being divided into two. First is the release cards
which form a loop catering to release functions of the job to shop floor. Second
is the acceptance cards that forms the basis of accepting a order by the sales
department. Finally the implementation issues are also discussed in general
1. INTRODUCTION

Small- and medium-sized enterprises (SMEs) in the make-to-order (MTO) sector


are of great interest, as they are a relevant part of the industrial infrastructure.
These companies have to react on turbulent environments: they have to cope
with changes in product mix and volume, production rate changes, a high
number of rush orders, and lot of internal uncertainty. As a consequence,
production planning and control (PPC) in MTO companies is rather complex and
often based on insecure data. Since a good functioning of the PPC concept is
crucial for the economic success of the enterprise, the selection of a fitting PPC
concept is an important decision process.

Industrial practice shows that hardly any job shop is able to use the planning and
control modules provided in its ERP-package. Many solutions provided in ERP-
packages focus on Gantt chart or Leitstand scheduling, which is generally
doomed to fail in job shops because of the high data maintenance
requirements and because of their high sensitivity to uncertainty, resulting in
unstable schedules. Other ERP- packages only provide material-oriented
planning solutions such as MRP, while capacity planning and control is critical in
most job shops. To prevent from turning back to legacy systems, these
companies often opt for a planning and control system which can be
implemented with limited software support. This creates an obvious need for
card-based systems in job shops.

The popularity of card-based control systems has been rising since the
introduction of Kanban as a material control system for repetitive manufacturing
environments. During the last decennium new card-based systems such as
POLCA (Suri, 1998) have been developed, which can be implemented in
capacity-oriented control situations. The Generic POLCA system (Fernandes and
do Carmo-Silva, 2006) can be seen as an important step to make POLCA
principles suitable for the specific situations of job shops. It links POLCA card loops
with capacity allocations at the order release decision. Still, the basic idea of
POLCA to use card loops for each possible combination of successive work
centers will reduce its practical applicability in shops with high routing mix
variability. In a computerized system, POLCA principles have been adapted for
use in a job shop. But, as also concluded by Stevenson et al. (2005), none of the
currently available card-based systems will meet the dynamic requirements of
job shop manufacturing.

2. WLC PARADIGM

The WLC concept is based on principles of input/output control. Input control


relates to both accepting orders and releasing them to the shop floor. WLC
conceptualizes the job shop as a queuing system. In front of each work station,
an arriving job finds a queue of jobs waiting to be processed. The principle of
WLC concepts is to control the length of these queues. The main instrument for
this purpose is the release decision. The release decision allows a job to enter the
queue of its first work station in the shop. Once released, a job remains on the
floor until all its operations have been completed. The progress of jobs on the
shop floor is controlled by priority dispatching at each work

station.

WLC concepts do not release jobs to the shop floor if they are expected to
cause queue lengths to exceed certain workload norms. It results in a pool of
jobs waiting for release. As illustrated by Fig. 1 we refer to waiting time in the pool
as the pool time and to the interval between release and completion of a job as
the shop floor flow time. The shop floor flow time of a job can be subdivided into
station flow times. The pool is a new object of control. Unrestricted acceptance
of jobs at the entry could cause excessive pool times.
Fig. 1. Lead time components.

A hierarchical control concept emerges [Kingsman et al, 1989], with three levels
which respectively relate to job entry, job release and priority dispatching (Fig. 2).
At each level, we distinguish two means of control, input control and output
control. Input control regulates the allowance of jobs to the next stage,
respectively accepting jobs for entry into the pool, releasing jobs to the shop
floor, and dispatching jobs for processing (thus allowing a job to enter the queue
of its next operation). On the output side, capacity management contributes to
the control of workload through regulation of the outward flow, by means of
respectively medium-term, short-term and daily capacity adjustments.
Fig. 2. The hierarchical WLC concept.

The job entry level is very important, if one can influence the incoming orders. In
that case, order acceptance and due date assignment/acceptance can
support the release decision, providing it with a 'releasable' set of jobs, thus
keeping pool times small. In fact, the job pool between entry and release acts as
the visualized imbalance between job supply and production capacities. The
role of priority dispatching in WLC is a very modest one, because the choice
among jobs is limited due to short queues. Generally, WLC concepts favor
dispatching priorities such as first come- first-served (FCFS) which stabilize
operation flow times or due date oriented priorities which correct progress
differences among jobs. These kinds of priorities facilitate a good timing of job
release. However, the major strength of WLC concepts is withholding jobs from
the shop floor, reducing average queue lengths. Besides a reduction of work-in-
process, withholding jobs from shop floor has numerous additional advantages
as it enables management to delay final production decisions [Irastorza et al,
1974]. It reduces waste due to cancelled orders, facilitates later ordering of raw
materials, takes away the need of expediting of rush orders, etc. Fluctuations in
the incoming order stream should be absorbed by the pool. Altogether, it should
create a stable stationary situation on the shop floor. Only restricting queue
lengths is generally not sufficient. If average queue lengths decrease but
variances do not, the idle time at work stations will increase. This situation is not
allowable for the common job shop, where many work stations can be
temporary bottlenecks. The loads of potential bottlenecks should be kept close
to a norm level instead of below a norm level. The release function which aims at
short queue lengths and a reduced variability of queue lengths is called load-
balancing.

In summary, WLC concepts try to create a situation on the shop floor of short and
stable queues. A pool of unreleased jobs, buffers the shop floor against external
dynamics, the incoming non-stationary job stream. The queuing of jobs on the
shop floor is turned into a stationary process. Release performs a key-role in
reaching this stationary situation. It is the most elaborated function within WLC
concepts.

3. WLC CONCEPTS

In the preceding section we have seen that release should control the queue
lengths in front of each work station. The queues must be short and stable, the
load-balancing function. On the other hand, each job should be released timely
with respect to its planned due date and expected flow time, the timing
function.

Leaving out capacity decisions at the release level, two components of the
release decision are distinguished: a sequencing decision and a selection
decision. The sequencing decision can be described as the setting of priorities for
jobs to be released, 'selection' decides whether a job will be released or not at
some specific moment. Most WLC concepts focus the sequencing decision on
timely release and create due date based sequences. Taking into account this
sequence, release selects a set of orders that keep the workload of work stations
at certain norms. These workload norms are the main instrument of workload
control.

Three WLC concepts have been discussed in detail here.

3.1. Bechte's WLC concept

The release procedure proposed by Bechte [1988] builds on three parameters: a


release period, a time limit and a load limit. The decision to release jobs is taken
periodically, at the beginning of each release period. All jobs in the pool are
sequenced in order of their planned release date. The planned release date is
determined by backward scheduling from the job due date: norm station flow
times for all work stations in the routing of the job are subtracted from its due
date. All jobs within the time limit from their planned release date are candidates
for release. In the established sequence, jobs are released, until the workload
norm of a work station, the load limit, is exceeded for the first time. All other
candidates visiting this station have to wait in the job pool until the next moment
of release. The selection process goes on for the remaining candidates.

The workload considered in the concept of Bechte is the queue length at a work
station (in units of processing time). The workload is controlled by the load limit.
The load limit LLs of a work station s consists of two components: the planned
output during the release period and the planned queue length at the end of
the release period. The actual output Os, during the release period and the
actual queue length QEs at the end of the release period satisfy the balance
equation:

QEs + Os = QBs + Is

with

QBs: the queue length at the beginning of the release period,

Is : the input to the queue from jobs arriving during the release period.

The release decision at the beginning of the release period must bring QEs + Os at
the norm level LLs. The above balance equation is used. QBs is known at the
moment of release, the queue input Is is influenced by the jobs on the floor
upstream of s and by the release of new jobs.

3.2. Bertrand's WLC concept

Bertrand developed a WLC concept for the diffusion department of a


semiconductor plant [1981]. Bertrand does not discuss the release sequence, but
elaborates the workload norms extensively. The release decision is taken
periodically and the release of jobs is allowed if the workload of each work
station remains below its norm value.

The workload definition of Bertrand covers the processing time of all jobs on the
shop floor which still have to be processed at the work station concerned. The
corresponding workload norm consist of two components: the planned work
station output during the release period and the planned quantity of work
upstream or in the queue at the end of the release period. An extended
balance equation can be used to determine the actual workload of a work
station s at the end of the release period:

( UEs + QEs ) + Os = ( UBs + QBs ) + Rs

with UEs as the processing time (on s) of jobs upstream at the end of the release
period, UBs as the processing time of jobs upstream at the beginning of the
release period, Rs as the processing time of jobs released at the beginning of the
release period. At the moment of release the right-hand side of this equation is
completely known. The processing times of all jobs which are newly released are
the input to the workload. Thus, the release of new jobs directly influences the
workload. The release decision can be made without a sophisticated estimation
procedure.

3.3. Tatsiopoulos WLC concept

Tatsiopoulos [1993] developed a WLC concept for a small subcontracting


component manufacturer. The common push release takes place periodically,
intermediate push release can be forced by rush orders or orders with retarded
material availability, and an intermediate pull release can be triggered from the
floor when a foreman sees his station threatened by unplanned idleness. The
periodic release decision considers the orders in the sequence of their planned
latest release date. The calculation of the planned release dates is rough
compared with Bechte. For each job the same norm shop floor flow time is
subtracted from the job due date. The release of jobs is allowed unless a
workload norm is exceeded, which applies to the intermediate pull releases as
well. Additionally, a minimum workload is suggested. This definition covers all
work on the shop floor, even work completed at the work station concerned. For
each work station a norm is set for the accumulated processing times of jobs
upstream, job in the queue, and jobs downstream. The corresponding actual
workload satisfies the following balance equation
( UEs + QEs + DEs) + Cs = ( UBs + QBs + DBs) + Rs

with DEs as the processing time (on s) of jobs downstream at the end of the
period, DBs as the processing time of jobs downstream at the beginning of the
period, Cs as the processing time of jobs which leave the shop during the release
period. All other variables as defined before. Again all right-hand-side
components are known at the moment of release. The WLC concept does not
clarify whether the shop output Cs from jobs fully completed during the release
period is included in the workload norm. Notice that the workload definition
further simplifies keeping up with the actual workload as it avoids the need for
data regarding the completion of single operations. The completion of the job
can be reported when it leaves the shop floor.

4. WLC FEATURES FOR JOB SHOP

Most classical variants of the WLC concept take the release decision periodically
according to the following procedures. Orders in the pool are considered for
release in the sequence of their planned release dates. The order being
considered is added to the release selection as long as its release will not cause
any workload norm to be exceeded. Otherwise the order will have to wait in the
pool until the next release opportunity. An order with a later planned release
date maybe selected when it does fit in the norms. After this procedure is
completed, selected orders are sent to the capacity groups performing the first
operation and remain on the shop floor until all operations have been finished.

The five most distinguishing elements of the WLC approach to shop floor control
are the control point at release, the use of aggregate measures, resource
buffering, shop floor buffering, and central load buffering.
5.1 Control point at release

The main control point of the WLC concept is the release decision. This decision
precedes the first shop floor operation of the orders. At this point fitting the orders
into workload norms should create predictable operation lead times.
Downstream on the shop floor, simple priority rules at capacity group s are
sufficient (Bechte, 1994). Examples of priority rules are first-come-first served,
which guarantees the smallest variation of operation lead times, or due-date-
oriented rules to correct for individual progress disturbances among orders. No
sophisticated methods are used for controlling the downstream operations of the
orders. Although some of the orders arriving at a capacity group may come
directly from the pool, a significant amount may come indirectly via other
capacity group s which perform the upstream operations of the order ( Fig. 3).

Fig. 3. Control point at release.

5.2 Aggregate measures

The decision to allow an order for release depends on the shop floor situation,
which is reflected in workloads. Workloads are calculated as an aggregate of
individual processing times. Most workload definitions also count up the
processing times of orders waiting in front of a capacity group (direct load) and
those of orders upstream (indirect load), as shown in Fig. 4. The general
assumption is that variations within an aggregate measure of summed
processing times will be relatively small. Therefore, decisions will be rather
insensitive to individual processing time deviations.

Fig. 4. Use of aggregate measures—summing individual processing times.

5.3 Resource buffering

Control within the WLC concept is not based on filling the capacities of resources
in a time-phased plan as for finite loading or deterministic scheduling
approaches. Instead it is based on maintaining a buffer for the resources in a
capacity group, by keeping workloads at norm levels. Although different types of
workload norms can be used,

the orders allowed on the shop floor after release will normally contain more
work than the capacity groups can handle before the next release moment (see
Fig. 5), resulting in queues of orders in front of the capacity group s. WLC is
essentially designed for situations where queues are inevitable, coping with
variations in order arrival and processing times

Fig. 5. Resource buffering.

5.4 Shop floor buffering

Even though resources are buffered by queues, these queues are kept small. As
far as possible the waiting time is placed before the first operation in the form of
pool waiting time. Thus, the main buffer is placed before the shop floor (Fig. 6).
The pool should absorb all kinds of fluctuations in the arriving order flow in order
to keep the resource buffers small and stable. Pool waiting times of orders may
vary according to their urgency, which is reflected in the slack to planned
release dates, and whether they fit well into the shop floor situation, which is
reflected in the workloads.

Fig. 6. Shop floor buffering.


5.5 Central load balancing

The main decisions of WLC are made centrally. The release decision compares
the urgency of orders and balances loads among capacity group s. This requires
a global view of the shop. As mentioned before, local decisions at individual
capacity group s can be based on simple priority dispatching rules not requiring
global information.

The central balancing of loads by fitting the orders from the pool into workload
norms (Fig. 7) will keep the resource buffers stable, despite variations in the
arriving order flow.

Fig. 7. Central load balancing

6. CONCEPTUAL BACKGROUNDS

The philosophy underlying WLC is based on creating predictable and short


throughput times for each critical workstation. Particularly, predictable and short
through- put times are lacking in most job shops because of all types of variability
that characterize this environment. Nevertheless, predictable throughput times
are important for a good timing of order releases, for quoting realistic delivery
times and for a good timing of capacity adjustments. Short shop floor throughput
times increase the flexibility to deal with possible customer order changes,
changes which are not uncommon in most job shops. Besides, short throughput
times encompass the direct advantages of a transparent shop floor with low WIP.
A predictable short throughput time at a workstation is enabled by keeping its
direct load at a constant level, the direct load being measured as the sum of the
processing times of orders waiting or already being processed at the workstation.
Before being released orders will wait in a centrally controlled order pool. The
pool buffer can absorb both fluctuations in capacity requirements and capacity
availability. It is obvious that constant direct loads can only be realized by
releasing an appropriate set of orders to the shop floor. This function of order
release has been indicated as its load-balancing function (Land and Gaalman,
1996). It should be recognized that order release is the last moment one can
effectively contribute to a constant direct load. The effectiveness of load-
balancing dispatching rules (e.g. Work-In-Next-Queue) after release is limited.

The direct load LDst of workstation s at time t being the sum of processing time so
fall orders waiting or being processed can be specified by equation .In the
calculations below orders will be addressed as jobs.

with pjs is the processing time of job j at station s; J the set of all existing jobs; tQjs
the time of arrival of job j at station s; tCjs the time of completion of job j at station
s. The indicator function I(t) is defined as I(t) = 1 at the specified interval, I(t) = 0
otherwise.

Notice that the release of a job will not directly affect the direct load of a
workstation, unless the station performs the first operation in the routing of the
job. Therefore a group of classical release methods focuses on controlling
aggregate loads. Aggregate loads additionally incorporate all work which is still
upstream of the workstation being considered. The aggregate load LAst of station
s at time t can be specified by

with tjR time of release of job j (all other variables as defined before).

The control of aggregate loads does not necessarily leads to control of direct
loads in case of a fluctuating routing mix (Land ,2004). Moreover, the average
direct load LDst resulting from the set of jobs in the aggregate load of a
workstation will be at the level calculated as

Therefore ,the adjusted aggregate load norms as presented by Oosterman et


al.(2000) can be used for keeping the average direct loads as calculated by
equation at a constant level. Not the full processing times pjs of a job being
released are considered to be its contribution to the calculated loads but the
processing times multiplied with the fraction (tCjs- tQjs)/(tCjs- tRj). This fraction is the
ratio between the throughput time of the workstation considered and the up-to-
station throughput time. This up- to-station through put time consists of the
summed throughput times of all stations in the routing of the job upstream of the
station considered plus the station itself. When throughput times are well
controlled , the station throughput times can be estimated by their planned
values(TDs), which results in a workload calculated for workstation s.

with Ujs: the set of stations in the routing of j ‘up to and including’ station s.
In the simple case of equal planned values for all workstations the estimated
ratio will simply be equal to 1/njs with njs being the routing position of station s. In
that case each job being released will in crease the workload with pjs/njs for
each station s in its routing. After the respective operation at a station is
completed, the workload will decrease accordingly.

The above equations have been developed in WLC research to facilitate the
specification of a constant norm level independent of routing mix changes. The
norm level forestation can be specified as its planned direct load level and
according to Little’s result (specified in terms of processing time units, see Land,
2004) the planned direct load should be proportional to the planned station
throughput time. But even when the planned throughput times to be realized are
the same, each station may still require a different workload level, since
capacities may differ among stations. Therefore, further standardization can be
realized by depreciating the direct load contributions by the maximum output
O*Ds of station s during the planned station throughput time (T*Ds ). The maximum
output is a fraction of the station’s capacity as100%utilizationcannotberealized. It
is measured in processing time. After transforming this into a percentage, the
workload calculation results in the following:

Thus, when each job contributes an amount Cjs as specified to the calculated
workload, this can further simplify norm setting. The norm for the workload LDst
can simply be set at 100% for each station and planned station throughput times
T*Ds are the main parameters to be specified.

Analogously to traditional WLC approaches, there lease method may allow


release of a job j as long as its load contribution Cjs will
notcausethe100%normofanystation in its routing to be exceeded. A job is
included in the workload of each station in its routing from the moment it is
released to the shop floor until completion of the operation at a station. The load
contribution Cjs can be interpreted as the percentage of the planned average
station throughput time T*Ds which is filled by releasing this job.

The sequence of considering jobs for release is classically based on their planned
latest release dates t*Rj which can be derived from the due date δj and the
planned station throughput times T*D .

with sj is the set of stations in the routing of job j.

By creating constant norm levels, the above definitions and calculations can be
used for translating workload requirements into numbers of cards. This forms the
starting point for development of the card-based system for job shop control.

7. THE COBOCABANA SYSTEM

The system will be briefly addressed as the Cobacabana system. The


Cobacabana system has been organized around the order acceptance and
order release decisions, being key decisions in job shop control.

7.1 Order release and shop floor control


The Cobacabana system uses card loops between the planner performing there
leases and all critical workstations. Fig. 8 shows these loops for an example order
having the routing sawing-turning-drilling- finishing . In the figure each operation
has a different texture. In practice each operation has its own color.

Fig. 8. Cobacabana release card loops ,between release and workstations.

The release cards authorize the planner to release new orders. To release an
order the planner has to attach the right amount of cards for each work station
in the order routing to the order guidance form. The cards relating to a certain
work station return to the planner after completion of the operations performed
by the considered station. The system balances the work load for all critical
workstations by allowing a fixed number of cards summing to 100% per station on
the shop floor.

The task of the planner is supported by a display for collecting and distributing
the cards. The simple display, as shown in Fig. 9, gives a quick overview of the
situation on the shop floor. In Fig. 9 each card represents 5 percent. Empty card
positions indicate the percentage of the planned station throughput time
already filled by released orders. The available cards on the display show the
possibilities for new releases. An even distribution of released cards a cross
stations indicates a workload which is well-balanced across stations. Similarly,
momentary bottle necks can be easily identified, which is mandatory for focused
decision making in a job shop. E.g. the lathes required for turning seem to be the
restrictive resource for new releases in the situation depicted in Fig. 9.

Fig 9:Display of available release cards, indicating the actual shop floor situation

7.2. Order acceptance and due date promising

The release system can be extended for support of the order acceptance and
due date promising function. A minimal delivery time djmin for an order can be
determined by adding an estimated waiting time T*Pj in the order pool before
release to the sum of planned throughput times T*Ds for stations in the routing of
the order

Since the Cobacabana system keeps station throughput times at a constant


level, the waiting time T*Pj before release is the only variable component of the
delivery time. It can be estimated from the requirements of orders already
waiting for release. The station with the largest amount of work in the pool
determines the waiting time before release. Thus, estimating this waiting time can
be supported by a card loop between the planner performing release and the
sales department accepting the orders. The card loop for the acceptance cards
is depicted in Fig. 10.

Until it is being released, each accepted order requires a number of


acceptance cards Ajs per workstation s as

Fig 10 Cobacabana acceptance card loops, between order acceptance and release

Notice that the denominator O*Ds /T*Ds specifies the maximum output (in
processing time units) per day. Thus each card represents a fraction of a working
day.

The acceptance cards are withdrawn from an acceptance display as depicted


in Fig. 11. In Fig. 11 each card represents one-fifth of a day. A number of cards
amounting to 3 working days have been withdrawn from this display for turning.
This means that a minimal pool waiting time of 3 days is to be expected for
orders requiring a turning operation, since orders already waiting for release will
require 3 days of turning work. To determine a realistic delivery time the
estimated pool waiting times can be

used and some slack should be added.

7.3. Use of the system

The Cobacabana system, in a job shop in real time would work like as
summarized below. The steps are given in the order it has to be followed in the
job shop

1. New order is being placed.


2. Sales department estimates realistic the delivery dates.
3. Process planner determines the routing and processing time of the order
received.
4. Latest release date is calculated.
5. Numbers of acceptance cards are determined.
6. Percentage requirement of release planning is determined and being
translated into number of cards.
7. Required numbers of release cards are removed from the display and are
being attached to the order guiding forms. If enough cards are not
available then the non-priority jobs are being released depending on the
availability of the cards.
8. After releasing the job the acceptance cards are removed from the order
guiding form and are placed back on the acceptance display.
9. Release planner sorts them into order of latest release dates.
10. Releases the order by removing the required number of cards from the
display.
11. On the floor the order are served as FCFS.
The role of the cards in the Cobacabana system can be summarized as follows.

The constant number of cards moving between the release function and the
workstation will keep the station throughput time within their planned levels,
allowing for a good timing of order releases and for predictable throughput
times when promising delivery dates. The procedure of selecting orders for
release will ensure that also the relative urgency of orders is considered .The use
of acceptance cards—withdrawn from the acceptance display—enables a
good estimate of the waiting time before release, which is the main variable
component to be estimated for quoting a realistic delivery date.

8. EXAMPLE
Consider a job arriving at the job shop which requires the following operation in
the sequence-

TIME

OPERATION (mins)

SAWING 20

TURNING 30

POLISHING 40

DRILLING 15

FINISHING 25

Calculations for the implementation of Cobacabana system can be summerised


as below

1. Minimum delivery time


Assuming this is the first order, therefore no waiting time (T*Pj = 0)

djmin = 20 + 30 + 40 + 15 + 25

= 130 min

2. Latest release date

Assuming due date to be 150 min

t*Rj = 150 – 130

= 20 min

3. Acceptance cards

Assuming O*Ds (maximum output) turning operation is 100 min(assuming no


machine failure)

Then O*Ds / T*Ds = 100/20

= 5 uts/hr

Therefore Ajs (turning) = 20/5

= 4 cards

4. Contribution to workload
C js = 20%

Calculation for other operations are being summarized in the table below

Table.1 calculations for the number of cards

TIME Ods/Tds

OPERATION (mins) Ods (uts/hr) Ajs Cjs

SAWING 20 100 5 4 20%

TURNING 30 180 6 5 4%

POLISHING 40 160 4 10 10%

DRILLING 15 45 3 5 11%

FINISHING 25 125 5 5 5%

9. CONCLUSION

A new card based system has been designed by using the workload control as
the controlling factor. Due to the recent advances in understanding the
concept of workload control, it is possible to convert the workload into cards.
These cards can be effectively managed, controlled and navigated to obtain
the balance in the system. Cobacabana is essentially a link between the sales
department and the operations department of the industry. It has enabled the
sales department to quote realistic delivery dates with the help of the
acceptance cards and operations planner to release new orders with the help
of the release cards.

Cobacabana tries to achieve the control in the system by controlling the


throughput times, since the throughput time control is the factor which allows
good timing of the order release and promising realistic delivery dates. The
restricted number of cards in the system restricts the workload from increasing
indefinitely. The card based system gives the planner a very accurate idea of the
shop floor by just looking at the display. This helps the planner to identify the
bottleneck station immediately and take necessary actions. This information can
be crucial in other strategic and planning activities. This system lets the cards to
go around in a loop between the acceptance and release of the order,
therefore, by observing the number of cards in the loop will give an idea about
the length of the waiting time in the queue before the release. Simple priority
dispatching rule is being used to process the jobs, once they are in the shop
floor. Thus without using a computerized system we can effectively manage the
complexities arising in the job shop. The developed Cobacabana system
enables this control of balance by card based navigation.
10. REFERENCE

• Land,M.J,2009,Cobacabana(control of balance by card-based navigation):


A card based system for job shop control, International Journal of Production
Economics, 117,97-103

• Suri, R.,1998.Quick Response Manufacturing: A Company wide Approach to


Reducing Lead Times. Productivity Press ,Portland , OR.

• Fernandes, N.O.,doCarmo-Silva,S.,2006.GenericPOLCA—A production and


materials flow control mechanism for quick response manufacturing.
International Journal of Production Economics104, 74–84.

• Stevenson,M.,Hendry,L.C.,Kingsman,B.G.,2005. A review of new and


established production planning and control (PPC)methods and their
applicability to make to order (MTO) companies. International Journal of
Production Research ,43,869–898.

• Land,M.J.,Gaalman,G.J.C.,1996.Workload control concepts in job shops: A


critical assessment .International Journal of Production Economics 46–47,535–
548

• Kingsman , B.G, Tatsiopolous, I.P and Henry, L.C, 1989, A structural


methodology for managing lead times for make to order companies,
European Journal of Production Research, 40, 196-209.

• Irastorza, J.C and Deane, R.H, 1974, Loading and balancing methodology for
job shop control, AIIE Transactions, 6, 302-307.

• Bechet ,W, 1988, Theory and practice of load oriented manufacturing


control, International Journal of Production Research, 26, 375-395.

• Bertrand, J.W.M and Wortmann, J.C, 1981, Production control and


information sytems for component manufacturing shops, Dissertation, Elsevier,
Amsterdam, The Netherlands

• Tatsiopolous , I.P, 1993, Simplified production management software for small


manufacturing firm, Production Planning and Control, , 17-26.
• Henrich,P.,Land,M.J.,Gaalman,G.J.C.,2004a.Exploring applicability of the
workload control concept. International Journal of Production Economics
,90,187–198.

• Bechte, W., 1994. Load-oriented manufacturing control just-in time


production for job shops. Production Planning and Control ,5, 292–307.

• Henrich,P.,Land,M.J.,Gaalman,G.J.C.,vanderZee,D.J.,2004b.Reducing
feedback requirements of workload control. International Journal of
Production Research , 42,5235–5252.

• Oosterman,B.,Land,M.J.,Gaalman,G.J.C.,2000.The influence of shop


characteristics on workload control International Journal of Production
Economics68,107–119

Das könnte Ihnen auch gefallen