Beruflich Dokumente
Kultur Dokumente
DISCLAIMER
OCIMF DOES NOT WARRANT OPERATOR IDENTITY AND IS NOT RESPONSIBLE FOR THE CHOICE OF SHIPS INSPECTED, THE INSPECTORS
CHOSEN, THE PERFORMANCE OF THE INSPECTIONS OR THE CONTENT OF THE REPORTS, OPERATOR COMMENTS AND/OR VESSEL
PARTICULAR QUESTIONNAIRE OR TMSA RESPONSES DISTRIBUTED UNDER THE REVISED PROGRAMME. OCIMF IS INVOLVED ONLY IN
THE RECEIPT, ORGANISATION AND DISTRIBUTION OF THE FOREGOING PROGRAMME OUTPUT. OCIMF DOES NOT REVIEW OR
EVALUATE SUCH OUTPUT AND EXPRESSES NO OPINION CONCERNING ITS ACCURACY. WHILE OCIMF MAKES EVERY EFFORT TO
ENSURE THAT TMSA REPORTS ARE RECEIVED, ORGANISED AND DISTRIBUTED IN ACCORDANCE WITH THE SIRE COMPOSITE
GUIDELINES, OCIMF ACCEPTS NO LIABILITY FOR FAILURE TO DO SO.
[Reference]
1. Vision & Mission statement on the company Home-Page
-. http://www.hls.co.kr/en/who/company.do?m=company
2. Company Policies
3. 2018-2019 HLS ENVIRONMENTAL REPORT
4. 2019-2020 HLS ENVIRONMENTAL REPORT
[Procedure]
1. Main manual Ch.19 Management Review
2. SHOREBASED M. PROCEDURE PR-705 Management Review
-. Management review
[Reference]
-. 2018/2019 Annual Management Review
1.1.3 HSSE excellence is fully understood and supported by vessel and shore-based Yes
management teams.
The company promotes best practice throughout various methods. We shared lessons learnt
information by procedures, publications, poster, official letters, etc. For example, [The monitoring
of accidents & corrective action],[Near-miss feedback] and internal audits, DP/Superintendent visit.
[Reference]
1. 7 zero accident campaign
2. Monitoring of accidents and corrective action(include NMA)
3. Safety bulletin(Monthly)
4. 2018/2019 Annual Management Review
[Reference]
1. Training programs for the shore - onboard personnel
2. Safety seminar
1.2.2 Management strives to improve safety and environmental performance at all Yes
levels.
To achieve the goal and improve the performance of environment, health, safety and quality
management system(HSQS), the company held HSQS Committee (include Management review)
[Reference]
1. 2018/2019 Annual Management Review
2. HSQS COMMITTEE(1H 2019)
1.2.3 Vessel and shore-based management teams promote HSSE excellence. Yes
The company conduct ‘master’s review’ & ‘experience feedback’ to enhance sustainable
improvements for HSQS. The company applies BBS(Behaviour Based Safety management) on
Vessels. The master should make an inspection of ship at least once a day and the safety officer
(C/E) should carry out health & safety inspection at least once a month. CEO/DP visits available
vessels including informal meetings. Also the company conducts various reward program to
promote HSQS excellence.
[Procedure]
1. PT-652 Ch. 10 BEHAVIOR BASED SAFETY MANAGEMENT
2. PO-101 Organization, responsibility & authority
3. PO-107 Ship visit & awarding system
[Reference]
1. 2018 Shiping KPI Results and Improvements
2. Result record of DPA audit(2019)
3. Sfety Management countermeasure committe
[Procedure]
1. M1, Ch. 4 Environment planning, Health & safety planning, Quality planning
[Reference]
1. 2018/2019 Annual Management Review
2. HSQS COMMITTEE(1H 2019)
1.3.2 The steps required to HSSE excellence at each level of the action plan are clearly Yes
defined by management.
The key steps for establishing objectives, planning, performance measurement, evaluation &
continuously improvement of Safety & Environment activities are described in Main manual which
is highest level document.
[Procedure]
1. M1, Ch. 4 Environment planning, Health & safety planning, Quality planning]
[Reference]
1. 2018/2019 Annual Management Review
2. HSQS COMMITTEE(1H 2019)
3. 2018-2019 HLS ENVIRONMENTAL REPORT
[Procedure]
1. PO-101 Ch. 5 Shipboard Environment & safety-quality committee
2. PS-202 Ch.2.1 Environment & Safety-Quality committee
[Reference]
-. Shipboard HSQS MEETING
-. HSQS Committee
1.4.3 All vessel and shore-based personnel demonstrate their commitment to HSSE Yes
excellence.
The company obviously states master’s responsibility about priority authority regarding Safety &
Environment protection. The company applies BBS(Behaviour Based Safety management) on LNGC.
Furthermore, We are conducting the continuous education for all employees to make ensure that
Environment, Safety & Quality tasks take the first priority of others. Especially, awarding system are
showing the commitment of the company to boost the implementation of their understanding.
[Procedure]
1. PO-107 Ship-visit & awarding system
2. PT-652 Ch 10 BEHAVIOR BASED SAFETY MANAGEMENT
[Reference]
1. SAFETY INSPECTION AND BBS OBSERVATION CHECK LIST
1.4.4 A strategic plan ensures continual improvements in HSSE performance are Yes
achieved.
The company try to lead continual improvements through SWOT analysis, Mission & Vision
statement, KPI etc.
[Reference]
1. Vision & Mission SWOT analysis
2. Company policy
3. HSQS COMMITTEE(1H 2019)
[Reference]
1. Main manual F1 Company Policies
2. Ship Security Plan Ch.2 Company Policies
3. ALCOHOL & DRUGS POLICY
4. Ethics(Home-Page/What we value) & Code of Ethics
-. Chapter 8 ETHICS TO THE ENVIRONMENT AND THE SOCIETY
1A.1.2 Policy and procedures are formally reviewed at regular intervals to ensure Yes
robustness and effectiveness.
The company regularly reviews these policies throughout the ‘Management Review’ and
‘Environment & Safety-Quality committee (HSQS committee)’.
[Prodedure]
1. M Ch.19 Management review
2. PO-101 Ch.5 Shipboard environment safety committee
3. PS-202 Ch.2.1 Environment & Safety-Quality committee
[Reference]
-. 2018/2019 Annual Management Review
-. Shipboard HSQS Meetin
-. Safety Seminar
1A.1.3 Procedures and instructions are written in plain language and contain sufficient Yes
detail to ensure that tasks can be completed correctly and consistently.
The entire SMS documentation (including work instructions) are written in a plain, precise and
simple language. The system documents are in principle prepared in Korean and English. The
document are composed of the Main manual as highest level document to describe responsibilities
and authorities, procedures to who, when & where the operation should be done and instruction
to describe how operation should be carried out.
[Procedure]
1. M1, Ch.2 System document
2. SP1-701 APP 1 HSQS Document List
3. PO-103, Ch.2.5 Official & Working Language
[Procedure]
1. D2 Ch 1 Volumes of HSQS document per ship
[Reference]
-. TOMAS (Electronic Document System)
1A.1.5 A formal document control system is in place to ensure that the current SMS Yes
documentation is available.
The company has the documented procedures to ensure that only the current SMS documentation
is available. All revision items should be reviewed by the head of System management team(SMT) .
[Procedure]
1. PR-701 Ch 3 Repair/Review/Approve
2. PO-108 Document-Record Control App 2 HSQS document correction notice
3. PO-108 Document-Record Control Ch 6 Record control
[Reference]
1. D3 F2 REVISION STATUS
[Procedure]
1. PS-202 Ch.2.2 Safety management countermeasure committee
[Reference]
1. The environment & safety-quality committee(Semi-annually)
2. Safety management countermeasure committee(Quarterly)
1A.2.2 Managers’ roles, responsibilities and accountabilities for achieving objectives Yes
are defined within the SMS.
The company have the manuals & procedures to define roles & responsibilities for all
organizational structure & personnel. Also the company arranged procedure for reassigning
responsibilities during periods of absence of key personnel.
[Procedure]
1. M1, Main manual – Ch.1 Management responsibility
-. 1.9 Delegation of duty
2. PO-101 Ch 3 Masters responsibility and authority
-. 3.1 R&R, 3.7.3 Absence
[Reference]
1. Organization and personal work scope
2. Hand over letter for long-term business trip
1A.2.3 Relevant reference documents are provided as a supplement to the SMS both Yes
onboard and ashore.
The company provide reference documents including regulatory publications and industry
guidelines.
[Procedure]
1. D2 Ch 3 Mandatory Publication List
2. FMT Rules & Regulations
[Reference]
1. KR-CON
Safety Seminal involves vessel personnel and shore-based personnel to improve the SMS.
[Reference]
1. HLS-Open dialogue
1A.3.2 Instructions and procedures covering shore and vessel operations are Yes
developed in consultation with those who will have to implement them.
All shore staff and senior crew are involving in development and revision of company instructions
and procedures through the various meeting or committee called PDOS (Pre-departure Orientation
Seminar-Before embarkation), Safety Seminar (every half year).
[Procedure]
1. M1 Ch.1 Management responsibility
2. PO-101 Ch 6 Masters review and feedback
[Reference]
1. 2018/2019 Annual Management Review(include 1.3 Master review & 1.4 Experience
feed-back)
2. Safety Seminar
And then the company conducts a campaign and focused inspection to improve the weak area
found.
[Reference]
-.Reference of benchmarking
-. History of attending training, forums and seminars
1A.4.2 The company is innovative in improving the content, format and delivery of the No
SMS.
We have a separate department (SMT, Safety Management Team) to clarify and simplify the SMS
procedures. Our procedure system is coded so it’s easy for anyone to understand.
We have our own IT program called TOMAS. It includes Crew, Supply/PMS, Survey/Audit/Accident
& Report system.
[Procedure]
1) Personnel Management(PP-802) 2.4.5
2) On-shore officer’s Job(PP-805) 1.4.2 Qualifications
[Reference]
License, Certificate, Career Certificate, Dipolma (Major), Personnel Records
2.1.2 The company has a documented recruitment process for key personnel. Yes
The recruitment process for key personnel is specified in the regulations. That process includes
most of the procedures listed in best practices guidance.
2.1.3 A formal familiarisation process is in place for newly recruited key shore-based Yes
personnel.
We provide a familiarization process for new hires to quickly adapt and learn. The process applies
to all new hires as well as key shore-based personnel. That process includes all of the procedures
listed in best practices guidance.
Stage 2
2.2.1 A formal personnel appraisal system ensures that key personnel undergo a Yes
performance assessment at least annually.
Personnel evaluation is conducted annually for all employees. The evaluation items are composed
of two categories: performance and competence. The evaluation system consists of performance
review, competence understanding and comprehensive review, and the evaluator can list the
training and career development that the employee considered necessary. We use the KPI
definition for the annual goal setting.
2.2.2 Retention rates for key personnel over a two-year period are calculated. Yes
We calculate and record retention rates for key personnel. We can demonstrates how the retention
rate is calculated and calculate it in a similar way intertanko’s formula.
2.3.2 Sufficient shore-based personnel are provided to implement the SMS Yes
effectively.
The company strives to make safety management systems work effectively in every area, and to do
so, management sets and reviews business plans each year.The business plan includes organization
and manpower plans that considered various situations such as increasing in the size of a fleet,
introduction of new vessel type, new building programme, unplanned loss of personnel and new
legislation, etc.
[Reference] Business Plan
2.3.3 Targets for retention rates are formally reviewed and documented. Yes
Our target retention rate is 85 percent (based on key personnel). Our manpower retention rate is
very high, and the company is seeking and implementing various methods for the retention of
excellent employees. For example, fair evaluation and compensation for performance, pursuit of
work-life balance, career development opportunities, and providing a good working environment.
Retirement surveys are also conducted, and if there are problems in the survey, various methods
are used to improve them.
[Reference]
1) The retention rate for key personnel last 3 years.
- 2017=100%, 2018=100%, 2019=100%
2) The promotion rate last 3 years
- 2017=100%, 2018=100%, 2019=100%
3) Exit survey
2.4.2 The company aims to fill relevant shore-based positions from within the fleet Yes
wherever possible.
The company prioritizes and encourages transfer of verified crews to shore-based positions and has
a relevant regulations. In fact, most shore-based positions consist of crew or people who has on
boarding career.
[PROCEDURE]
-. MI-CH.1.4.3, & 1.7 / Management Responsibility / CM Division
-. PC-311 / Recruitment CH.3, APP.1, Ch.1 & 2
-. PC-305 / Manning Management APP.2
-. PC-310 / Foreign crew management
-. PC-308 / Promotion
[REFERENCE]
-. Team Manual.
-. PC-308 / Promotion
-. TOMAS V screen capture
-. Report of / Recruitment
-. Record of Crew competency check list
3.1.2 All vessel personnel have valid medical certificates in compliance with Flag State Yes
and/or relevant authority requirements.
The company maintains a copy of medical certificates
[Hard copy & Scan file]
We have designated medical center that has been approved by Government for crew medical
examinations.
[PROCEDURE]
-. PS-205 CH.1 / Frequency of medical examinations
[REFERENCE]
-. CODE305-401A / Crew competency check list
-. TOMAS V screen capture
[PROCEDURE]
-. PC-315 / Training & Familiarization
-. PC-315 APP.1 / Training matrix
[REFERENCE]
-. Record of training/education
-. TOMAS V screen capture
-. Long-term training/education plan
3.1.4 Formal familiarisation procedures are in place for vessel personnel, including Yes
contractors.
[PROCEDURE]
-. PC-315 CH.1.12.1 / Familiarization onboard
-. I9 / Crew shipboard Familiarization
-. PS-204 CH.1.3.3.2 / Working procedures
-. PS-204 APP.3 / General safety notice for contractors
[RECORD]
-. Record of General safety notice for contractors
-. PS 205 Control of drug & alcohol
3.1.5 Documented handover procedures for key vessel personnel are in place. Yes
Senior officers (Master, CE, CO, & 1E) have been defined as key personnel onboard.
[PROCEDURE]
-. PO-101 CH.3.6.3 / Defined key personnel
-. PO-101 CH.3.6, CODE101-301 / MASTER
-. PO-101 CH.4-1.12, CODE101-401 / CE
-. PO-101 CH.4-2a.30, CH.4-b.27 / CO
-. PO-101 CH.4-6.8, CH.4-6a.9, CH.4-6b.8 / 1E
Stage 2
3.2.1 Appraisal procedures are in place for all vessel personnel. Yes
[PROCEDURE]
-. PC-307 CH.1.4 / Crew evaluation period
-. PC-307 CH.1.3 / Authorized department
-. PC-307 APP.1 / Evaluation items
[REFERENCE]
-. PC-307 CH.2 Evlaualuation method
-. Report of deliberating of crew evaluation
-. CODE306-301A / Improvement request
[REFERENCE]
-. PC-315 / Crew training & Familiarization
-. Record of training/education
3.2.3 The company verifies that vessel personnel quality requirements are Yes
consistently met.
The company verifies that vessel personnel quality requirements as per procedure.
-. Crew management team verify crew quality requirement and correct the deficiency before
joining.
-. For onboard crew, Master verify crew quality requirement every month.
[PROCEDURE]
-. PC-305 CH.4.2 / Crew Qualification
-. PC-315 / Training & Familiarization
-. CODE305-401A / Crew competency checklist
[REFERENCE]
-. TOMAS V screen capture
-. Record of Crew competency check list.
3.2.4 Procedures to identify additional training requirements for individual personnel Yes
are in place.
[PROCEDURE]
-. PR-704 / Rules & Regulations management Ch.1.3.1
-. PC-315 / Crew training & familiarization Ch.4,6,11
-. PC-315 APP.1 / Training matrix
[REFERENCE]
-. Revision report of rules & regulations
-. Record of training/education
-. On-board job training course & other training.
-. Report of the education system improvement committee
[PROCEDURE]
-. PC-311 / Recruitment CH.3, APP. 1
[REFERENCE]
-. PC-311 / Recruitment CH.3, APP. 2.1
-. On-line Screen capture.
-. Result of interview chart.
3.2.6 The company monitors and records training results and effectiveness. Yes
The company convene the improvement committee for education system every year. The
committee reviews training results and discuss the improvement for effectiveness training.
The company keeps results of training for 3 years and received feed-back from trainees for all
training.
All training records of individual crew members are kept electronically.
Crew manager make an education plan and select trainees every month considering their
embarkation plan, qualification, appraisal records, vessel performance and audit/inspection trends
by outsourcing education provider
[PROCEDURE]
-. PC-315 / Crew training & Familiarization Ch.4, 6 & 11
-. PC-315 CH.1.11 / Operation of the education system
improvement committee
[REFERENCE]
-. Report of the education system improvement committee
-. Report of Training result (Incl. feedback from trainees)
[REFERENCE]
-. Report of crew evaluation result
-. Navigation audit by shore staff
3.3.2 The company provides career development for Junior Officers and aims to Yes
promote Senior Officers from within the company, where possible.
The company has procedures for promotion. There are clearly sets out the requirements necessary
for promotion such as minimum required sea service period.
The company provide the additional training for promoted duty to officers.
[PROCEDURE]
-. PC-308 CH.2 / Promotion
-. PC-315 APP.1 / Training matrix
3.3.3 Training for vessel personnel exceeds the minimum requirements of the Yes
International Convention on STCW or of the relevant authority for vessel trade.
The company provide additional training to vessel personnel in order to enhance the management
of safety, security and environmental performance.
[PROCEDURE]
-. PC-315 Crew training & familiarization
-. PC-315 APP.1 / Training matrix
[REFERENCE]
-. I9 Crew Shipboard Familiarization
-. Record of training/education
3.3.4 Personnel selection and recruitment is reviewed annually to ensure it complies Yes
with company policies and procedures.
The crew management team is audited by internal auditor per a year. The internal auditor audit
whether Crew management team complies with the company policies and procedures.
[PROCEDURE]
-. PR-706 / System Audit Ch 3.1 & 4.1.3
[REFERENCE]
-. Result of internal audit
[REFERENCE]
-. Evaluation report
-. CODE306-301A / Improvement request
-. Result of Psychometric test
3.4.2 A documented planning procedure is in place to ensures future manning needs Yes
can be met.
The company make a future plan on the manpower demand and supply this year based on
recruitment in bulk per a year.
[PROCEDURE]
-. PC-311 Ch.2.2.2.1
-. Team Manual
[REFERENCE]
-. Long-term & Annual recruitment plan
[REFERENCE]
-. Safety seminar
(Culture Awareness, etc.)
[PROCEDURE]
-. PO-102 CH.1.2 / Management of manning level
[REFERENCE]
-. Approval request for crew manning level for new building vessel
3A.1.2 Shore management provides adequate resources to ensure the wellbeing of Yes
vessel personnel.
The company make an effort to improve quality of life including factors such as quality of food,
accommodation, rest and recreation facilities, hygiene, medical services, etc. under corrective
bargain agreement and employment procedures & MLC.
[PROCEDURE]
-. PC-301 CH.6, PC-302 CH.9(별별)
-. PC-303 CH.2 / Victual management
-. PC-303 APP.2.1.12 / Cultural fee
[REFERENCE]
-. Safety compass
-. Telemedicine service
-. VSAT / SHIPPING DAILY / 별별별별별별
[PROCEDURE]
-. PO-102 CH.1.3 / Observance of minimum rest period
-. PO-102 CH.1.2.3 / Change of normal manning level
-. PC-305 CH.4.4 / Job Hand-over
[REFERENCE]
-. PC-301 Collective Bargain Agreement Ch.5
-. TOMAS V screen capture & view
-. Feedback Report
-. Employment Contract
-. Dispatch of crew support team at berthing(Code 102-506)
3A.1.4 A formal D&A policy is implemented and a system is in place to monitor it on a Yes
regular basis.
Formal D&A policy is in place on procedures and complies with OCIMF guidelines.
[PROCEDURE]
-. PS-205 CH.2 / Control of Alcohol & Drug
-. PS-205 APP.OCIMF DNA GUIDANCE
[REFERENCE]
-. Record of Alcohol consumption record
[REFERENCE]
-. PC-302 Regulation for Employment Ch. 6
-. Employment Contract
-. Flag and National requirements
3A.2.3 Documented procedures are in place to ensure high standards of hygiene are Yes
maintained.
[PROCEDURE]
-. PS-205 CH.1.8 / Sanitary including food and catering
inspection
[REFERENCE]
-. CODE205-107 / Checklist for sanitary inspection
including food and catering
-. Record of Checklist for sanitary inspection
3A.2.4 Retention rates for Senior Officers over a two-year period are calculated. Yes
The company calculate retention rate for Senior officers every year according to INTERTANKO
guidance.
The company monitors and records retention rate and retirement rate as KPI. This records are
periodically reviewed, trends are identified and appropriate action taken.
[REFERENCE]
-. TOP 4 Retention rate
-. Review of Retention / Retirement rate
Stage 3
The company monitors and records attendance of safety seminar to attend all crew member
evenly.
[PROCEDURE]
-. PC-315 APP.1 / Training Matrix
[REFERENCE]
-. Safety seminar
-. PR-704 / Rules & Regulations management Ch.1.3.1
-. Revision report of rules & regulations
[PROCEDURE]
-. PC-306 CH.3 / Disciplinary action
-. PC-309 CH.1 / Personnel management committee
[REFERENCE]
-. Result of Disciplinary action
[REFERENCE]
-. Safety campaign
The company monitors and records retention rate as KPI. This records are periodically reviewed,
trends are identified and appropriate action taken.
[PROCEDURE]
-. Team Manual 2.1.2, 2.2.1
[REFERENCE]
-. Officers’ retention rate (Y 2017 : 91.0% / Y 2018 : 92.4% / Y 2019 : 95.2 )
-. Review of Retention / Retirement rate
[PROCEDURE]
-. Safety Seminar
-. PC-315 APP.1 / Training Matrix
[REFERENCE]
-. PO-102 Special critical shipboard operation
-. PO-102 Ch. 3Special critical shipboard operation
-. PT-652E LNGC SAFETY MANUAL
[PROCEDURE]
-. D3 / Risk Assessment
[REFERENCE]
-. D4 / REGISTER OF RISK REDUCTION MEASURES
-. I10 Safety & Hazard Prevention
3A.4.3 The company provides career development opportunities by arranging shore- Yes
based assignments for vessel personnel.
The company provides the officers an opportunity to shore-based assignments such as instructor
for crew training, internship, data entry of PMS and etc.
[REFERENCE]
-. Internship
-. MMS data entry
-. Dept. of crew family counseling
[Procedure]
1. Machinery list in PMS
: Hull, hull equipment and any device include follow items.
: PM-401, Ch.3, 3.1.2 Scope of PMS Application
2. Spare part inventory in PMS
: PM-401, Ch.6, 6.3.1 MMS(Maintenance management system) program installed ships
(Management of inventory)
3. Computer-based of PMS
: Maintenance history and spare parts inventory should be managed with entering on MMS
program.
: PM-401, Ch.6, 6.1.1 MMS program installed ships
4. Planned maintenance tasks in PMS
: PM-401,Ch.3, 3.1.1 3.1.1 Establishment of PMS execute plan
5. Record of completed all machinery maintenance in PMS
: R/M record should be prepared by responsible officer(engineer). The maintained items condition
of machinery, consumed spare parts, stocked spare parts should be entered on R/M record and
attach measurement report, if possible
: PM-401, Ch.6, 6.2.1 Preparation of RM(Repair maintenance) record
: PM-401, Ch.6, 6.2.2 Scope of RM record (All machinery)
[Reference]
PMS Management (Total Machinery, Work Plan, Spare Item Master)
PMS Result
[Reference]
PMS Result
Outstanding items
Master report (B)
Repair Request (Request, Review, Inform, Result)
Class Survey Status (COC)
SIRE & PSC Inspection Report & Review
[Procedure]
1. Guideance of defect record and report
: PM-401, Ch.1, 1.3.3,1.3.4 Responsibility & Authority of Master, C/E
: PM-401, Ch.3, 3.1.8 Record & reporting of maintenance result (within one week)
: PM-401, App 1 How to prepare the application of running repair
: PM-401, App 2 How to prepare RM record
: PM-401, Ch.4, 4.1.1 Running repair (before 8 days at arrival)
: PM-401, Ch.2, 2.4 Flow chart of maintenance & repair
: PT-653, Ch.3 Inspcetion process
4.1.3 Company management regularly reviews the status of fleet maintenance. Yes
[Reference]
1. Status of defects.
: PMS Result defect review, postpone review,comment
: Master report (B),Motor condition check, Battery maintenance list review
: Water test, ICCP Condition check list review
: C/E’s Hand over report
3. Assistance
: PMS Overdue Item & Postpone Item Monthly Review Report
: Running repair schedule report
: Work Result Report in Port
: Plan of supply for spare part
[Procedure]
PM-401,Ch.1, 1.3.1,1.3.2 Responsibility & Authority of company, superintendent
PM-401, Ch.3, 3.1.6 Supervision for PMS overdue items
(Risk assessment, Approval of level, Time)
PM-401,Ch.3,3.1.5 Impossible with due date postpone
[Procedure]
PM-401, Ch.3, 3.1.6 Supervision for PMS overdue items (Within 2%)
[Reference]
PMS Overdue Item & Postpone Item Monthly Review Report
Record of PMS Overdue Status (year to date)
Stage 2
4.2.1 A procedure is in place to ensure the validity and accuracy of statutory and/or Yes
Classification certificates.
The company provide vessels with updated class survey status report once issued by class. All
certificates are being managed by computer-based program “TOMAS”
[Cert. Management]. Expired certificate is automatically highlighted in the system.
[Procedure]
1. Planning for surveys
: PM-402 Ch.3 Procedure of survey (3.1 Shipboard survey plan, Notify every 6 months)
: PM-402 Ch.4 Management of certificate
2. Verification
: PM-402 Ch.1,1.2. Master,The company
[Reference]
TOMAS [Cert. Management]
Audit Plan
Record of verification survey (Master & Company)
4.2.2 Cargo, void and ballast spaces are inspected to ensure their integrity is Yes
maintained.
The company has period of inspection by the applicable regulations of Class, Flag State, national
authorities and policy of company.
[Procedure]
1. Guidance and period of inspection
: Maintenance Guidance [HL-HUL-002 Guidance for hull inspection report]
: PM-401, Ch.3, 3.3.3 ~ 5 Record of inspection
[Reference]
KR Rules
: TOMAS-MMS- PMS Result (Hull inspection recording)
[Reference]
Code [107-103] Superintendent Inspection Check List
4.2.4 The company has a formal system to develop dry-dock specifications, which Yes
involves collaboration between the vessel and shore management.
The company has a procedures and guidance for dry dock repair and has formal system to develop
dry-dock specifications.
[Procedure]
1. Procedures and guidance
: PM-401, App.4 Management of drydocking repair
2. Health and safety responsibilities
: PM-401, App.4, 4.5 Safety measures
3. Generic dry-docking tasks
: PM-401, App.4, 4.2 Execution of docking repair
4. Manufacturer’s recommendations, Statutory and regulatory requirements
: PM-401, App.4, 4.1.4 Reference data preparation for the dock repair
5. Entering the dry dock and refloating
: PM-401, App.4, 4.3 Inspection and items to be inspected
: PM-401, App.4, 4.6 Matters to be checked before departure
[Reference]
Dock indent sample form
Request of health and safety for dry dock repair
Prepare dock indent in PMS
Dock result record in PMS
Stage 3
4.3.1 A common computer-based maintenance system onboard each vessel records Yes
all maintenance tasks and incorporates the defect reporting system.
The company has a computer-based maintenance system as PMS that include as below,
[Reference]
1. Manufacturer’s recommended maintenance requirements
: Maintenance guidance
2. Work instructions and associated risk assessments
: D3 Risk assessment & D4 Risk reduction measures
3. Equipment and machinery history
: PMS Result
4. Synchronization capability between ship and shore database & remote diagnostics
: Remote diagnostic & Data Back-up Check list
[Procedure]
PM-401, Ch.6, 6.3.4 Standard stock of spare part
PM-403 ,Ch.1, 1.3.8 Spare parts stock control
[Reference]
Law,Critical Item-Spare item master
4.3.3 Performance indicators have been developed to monitor fleet reliability. The Yes
performance indicators are measured for individual vessels and fleet wide.
[Procedure]
PM-401 Ch.2, 2.2.5 Critical function and items
: Critical function and items mean safety device & alarm function of each device, it should be
tested regularly in accordance with App. 3 Safety Device & Alarm Function Test and Ch.1.5
Important document list of maintenance & inspection record and compared the performance data
with maker's test data and keep recorded.
[Reference]
1. Breakdowns related to critical equipment.
: NMA (Notice of Marine Accident)
2. Number of days lost due to unplanned maintenance resulting in a vessel being taken out of
service./ Loss of manoeuvrability occurrences./ Blackout occurrences./ PMS overdue
: KPI Unscheduled delay time of ship operation, PMS overdue
3. Percentage of engines meeting optimal running conditions as per the company’s defined
baseline criteria
: M/T Heat Balance Report
4. Results of lub oil and hydraulic oil analyses
: Results of lub oil and hydraulic oil analysis
4.3.4 The frequency and extent of structural inspections of the vessel’s cargo ballast Yes
and void spaces is determined based upon risk criteria.
[Procedure]
PM-401, Ch.3, 3.3.3 ~ 5 Record of Inspection
[Reference]
KR Rules
Ballast Tank, Void spare repair interval-TOMAS
4.4.2 The maintenance and defect reporting system tracks all deferred repair items Yes
for inclusion in the dry-dock specification.
[Reference]
Prepare Dock Indent in PMS
4.4.3 The maintenance and defect reporting systems provide management with a real No
time status of fleet maintenance.
[Procedure]
PM-401 Ch.2, 2.2.1 Identification of Critical Equipment
PM-401 App 10 Risk Assessment to identify Critical Equipment
[Reference]
Critical Equipment Management – TOMAS
[Reference]
Code[651-505] Critical equipment work plan
Code[651-504] Critical equipment work permit
Postpone of maintenance for critical equipment
4A.1.3 A procedure is in place which requires shore management to be informed when Yes
critical equipment or systems become defective or require unplanned
maintenance.
All critical equipment should be report to shore according to the Accident report procedure
(PS-201 CH.3)
[Procedure]
PM-401 Ch.3, 3.1.1 1) Un-routine planned maintenance
PS-201 Ch.3 Types and reports guidance of accident
[Reference]
Minor accident report
[Reference]
PM-401 App.3 Safety device (Engine room machinery)
Weekly test (Em’cy machinery)
Pre-arrival test (Cargo equipment & system)
Nav. & comm. equipment, FFA & LSA check list
Stage 2
4A.2.1 Maintenance on critical equipment and systems requiring them to be taken out Yes
of service is subject to risk assessment and management approval.
If the agreed shut down period for critical equipment or systems cannot be achieved, any
extension or alternative action should be discussed with above person in charge ashore for their
review
[Procedure]
1. Shutdown period is agreed
: PM-401 Ch.3, 3.1.1 Establishment of PMS execute plan
[Reference]
D3 Risk assessment & D4 Risk reduction measures (Main condenser cleaning)
Code[651-505] Critical equipment work plan
Code[651-504] Critical equipment work permit
4A.2.2 Work instructions are available in the planned maintenance system for critical Yes
equipment and systems.
TOMAS enable ship’s crew to access work instructions about critical EQ.
By clicking the button, user can easily access work instruction and risk assessment about the
specific work.
[Reference]
Maintenance Guidance – TOMAS Standard Document Control
Superintendent inspection check list
4A.3.2 A procedure is in place to test and record performance data for all critical Yes
equipment and systems.
[Procedure]
PM-401 Ch.2, 2.2.5 Critical function and items
: Critical function and items mean safety device & alarm function of each device, it should be
tested regularly in accordance with App. 3 Safety Device & Alarm Function Test and Ch.1.5
Important document list of maintenance & inspection record and compared the performance data
with maker's test data and keep recorded.
[Reference]
Main Turbine Heat Balance Data
G/E condition report, crank shaft deflection measurement report
Safety device test
Stage 4
4A.4.1 The reliability and performance of critical equipment or systems and associated No
alarms is monitored and analysed.
[REFERENCE]
(I8(I) S&C check list N1 ~ N10)
5.1.4 The company has procedures that ensure all navigational equipment is Yes
maintained as operational.
[PROCEDURE]
• Defect reporting.
(PS-201, Ch.3.2 Types and reports guidance of accident)
• Suitably trained personnel to maintain navigational equipment or shore-based maintenance
support.
(PM-401, Ch.3 Shipboard Maintenance & Ch.4 Assist Repair)
-. MMS, In-house PMS program
-. Navigational equipment check List
-. Agreement for shore-based maintenance for navigational & communication equipment under
contract as Hanshin Electronics.
• Provision of spares as appropriate.
(PM-403, Supply & store control)
Stage 2
5.2.1 A procedure is in place requiring the Master to conduct a navigational audit to Yes
ensure compliance with navigational regulations and company procedures.
[PROCEDURE]
PO-109, Ch.6 Navigation audit
[REFERENCE]
Audit Format :
1) 109-601 / Navigation audit by the master (For officer)
2) 109-602 / Navigation audit by the master (For rating)
3) 109-603 / Non-conformity note (For navigation audit)
[REFERENCE]
1) 109-604 / Navigation audit by shore staff
2) 109-603 / Non-conformity note (For navigation audit)
5.2.3 The person(s) responsible for navigational standards ensures that navigational Yes
procedures are regularly reviewed and updated.
[PROCEDURE]
Main Manual – Ch.16 Rules and Regulations / Ch.9.4.4 Navigational Procedure Review
-. Internal audit/ ISM ▪ ISPS audit results
-. PSC/ FSC/ MAJOR results
-. Crew proposal about navigational procedures (Master’s review, Experience feedback etc.)
-. Statutory regulation, Industrial information
(HSQS meeting)
5.2.4 The company has a procedure to identify recurring defects in navigational Yes
equipment across the fleet.
[PROCEDURE]
Main manual – CH.14 Corrective and
prevent action of non-conformity, accident
and hazardous occurrence
PS-201, Ch.3.2 Types and reports guidance of accident
[REFERENCE]
I2E(II) Maintenance guidance
EP-COM – Navigation equipment maintenance guidance
5.3.2 A formal programme ensures that Senior Officers receive appropriate ship- Yes
handling training before promotion to Master or assignment to a new vessel
type.
[PROCEDURE]
PC-315 Ch.6.1 Evaluation and record of education
• Participation in manned models and/or simulator training.
The officers who will promote to Master have taken the advanced ship-handling simulation course
at contracted training center on a regular refresher courses, every 5 years.
The simulation of these centers can be embodied all vessels’ model of the company.
[REFERENCE]
1) 305-401A Crew competency checklist
[REFERENCE]
1) 109-604 / Navigation audit by shore staff
2) 109-603 / Non-conformity note (For navigation audit)
5.4.2 All navigational assessment and audit reports from the fleet are analysed, Yes
trends identified and improvement plans are developed.
Programme
ESQS meeting
All audit findings, incident/near miss cases, external inspections and industry trends in regard to
the navigational assessment are reviewed and reflected on SMS procedure by DCN (Document
Correction Notice).
Morevoer, navigational procedures has been reviewed quarterly with identification of weak area
and improvement measure.
5.4.3 Competency assessment programmes ensure that Masters and navigation Yes
officers maintain core and specialist skills.
Programme
SHS / Safety officer / LNG cargo handling
All officers including Masters have taken several programme for maintaining core and specialist
skills such as navigation, BRTM, accident investigation and cargo handling.
[REFERENCE]
1) 305-401A Crew competency checklist
5.4.4 Navigation officers undertake periodic refresher bridge resource management Yes
simulator training at a national or industry accredited shore establishment.
Programme
Leadership & Management skill (same as BRTM)
All officers including Masters have taken BRTM trainings at contracted training center (HMS
Training Center) on a regular basis including refresher courses every 5 years.
[REFERENCE]
1) 305-401A Crew competency checklist
[PROCEDURE]
1) PT-651 Ch.3 / Responsibility & Authorities
2) PT-651 Ch.6 / Cargo transfer plan & preparation
3) PT-651 Ch.7~9 / Cargo operation & ballasting
4) PT-651 Ch.5 / Operation (Bunkering)
5) PE-502 Ch.2 / Fuel and lub oil management
7) PE-502 App.3.3 / Record keeping
[REFERENCE]
1) 651-731 LNG loading & unloading log
2) 651-931 Ballasting-deballasting log
3) 102-644 / 645 / Bunkering check list
6.1.2 Procedures for pre-operational tests and checks of cargo and bunkering Yes
equipment are in place for all vessel types within the fleet.
Company procedure PT-651 Ch.6 and checklists cover the pre-operational test and checks of cargo
equipment. Procedure for pre-operational tests and checks of bunkering equipment is provided.
Also, procedure and check list for prevention of freezing when vessel is operating in cold weather
conditions are provided.
[PROCEDURE]
1) PT-651 Ch.6.2.3 / Preparation for cargo operation
2) PT-651 Ch.7.2.1 / Items to check before arrival at loading port
2) PO-102 Ch.11 / Cold weather condition
(Yellow)
3) PE-502 Ch.2.2.2 / Check before bunkering
5) PM-401 App.3 / Safety device & alarm function test checklist
5) Maintenance Guidance / ET-ETC-005 Hyd. Test guidance of bunker pipelines
[REFERENCE]
1) 651-621 / LNG before arrival
2) 102-630L / N10 Extreme cold weather check list
[PROCEDURE]
1) PT-651 Ch.1 / General
2) PT-651 Ch.6.2.3 / Preparation for cargo operation
3) PE-502 Ch.2.2.2 / Check before bunkering
4) PO-107 Ch.1 / Onboard visit
[REFERENCE]
1) 107-302 / Ship-visit inspection check list
2) 651-731 LNG cargo loading unloading log
3) 651-931 Ballasting deballasting log
4) 102-644 / 645 / Bunkering check list
5) Terminal satisfaction sheet
6.1.4 The company has procedures that address cargo specific hazards for all vessel Yes
types within the fleet.
The company procedure specifies the cargo specific hazards and toxic ingredient in PT651.
[PROCEDURE]
1) PT-651 Ch.2 Characteristic of LNG
Stage 2
6.2.1 A comprehensive procedure for planning cargo, ballast and bunkering Yes
operations is in place for all types of vessel within the fleet.
Detailed procedures for planning cargo, ballast and bunkering operation have been established
which include all activities relating to cargo, ballast and bunkering operations.
[PROCEDURE]
1) PT-651 Ch.2 Characteristic of LNG
2) PT-651 Ch.3 / Responsibility & Authorities
3) PT-651 Ch.6 / Cargo transfer plan & preparation
4) PT-651 Ch.7~9 / Cargo operation & ballasting
5) PT-651 Ch.5 / Operation (Bunkering)
6) PO-102 Ch.11 / Cold weather condition
[PROCEDURE]
1) PT-651 Ch.7.2 / Checks for loading operation before arriving at loading port
2) PT-651 Ch.7.3.3 / Arm connection
3) PT-651 Ch.7.3.2 / Ship/shore pre-loading meeting
4) PT-651 Ch.7.3.4 / CTM
5) PT-651 Ch.7.3.8 / LNG loading
6) PT-651 Ch. 7.1.1 / LNG loading work
7) PT-651 Ch. 7.3.8.5 / Pre-cautions in loading operation
8) PT-651 Ch. 7.3.11 Closing CTM
9) PT-651 Ch. 7.3.8.4 / Cargo tank pressure
10) PT-651 Ch. 7.3.9 Loading completion
11) PT-651 App.2 / Safe procedure guide of draining & purging
[REFERENCE]
1) 651-731 / LNG cargo loading unloading log
2) 651-541 / Ship-shore safety check list
3) 651-622 ESDS trip test record
4) 651-733 Float level gauge
6.2.3 Comprehensive procedures cover all aspects of ballast handling operations. Yes
The company procedure PT-651 Ch.9 covers ballast handling operations and PE-503 Ch.3 covers
ballast water management.
[PROCEDURE]
1) PT-651 Ch.9.2 / Ballast water exchange
2) PT-651 Ch.9.3 / Ballasting & deballasting operation
4) PE-503 Ch.3.3.2 / Ballast water exchange at sea
5) PE-503 Ch.3.3.3 / Precaution when ballast water exchange
6) PM-401 Ch.3.3 / Preventative Maintenance of hull / tank / hold
[PROCEDURE]
1) PT-651 Ch. 11.4.13 / One tank gas operation
2) 651-731 LNG loading & unloading log
3) 651-931 Ballasting-deballasting log
4) 102-644 / 645 / Bunkering check list
5) PM-401 Ch.3.3 / Preventative Maintenance of hull / tank / hold
6.2.5 Comprehensive procedures cover all aspects of bunkering operations for each Yes
vessel type within the fleet.
Company procedure PE-502 Ch.2 covers bunkering operation which include responsibility, pre-
arrival check, job performed during/after delivery, sampling, bunkering safety checklist, handling
bunkers containing H2S etc.
[PROCEDURE]
1) PE-502 Ch.2.1.1 / Ordering
2) PE-502 Ch.2.1.2 / Fuel delivery
3) PE-502 Ch.2.1.3 / Procedure for sounding bunker barge
4) PE-502 Ch.2.1.8 / Request for analysis of a FO sample
5) PE-502 Ch.2.1.9 / Request for analysis of LO sample
6) PE-502 Ch.2.2.2 / Check before bunkering
7) PE-502 Ch.2.2.3 / Jobs performed during delivery
8) PE-502 Ch.2.2.5 / Jobs at post-delivery
9) PE-502 Ch.2.2.8 / General safety precaution
10) PE-502 Ch.2.2.10 / Procedure for handling bunker containing H2S
[REFERENCE]
1) Bunkering plan
2) 102-644 / 645 / Bunkering check list
3) 651-601 / Bunkering safety check list
4) 502-201 / Pre-transfer bunkering check list
Stage 3
6.3.1 Standardised templates are used for planning and operational record keeping. Yes
The industry standard plan and record which are in use for cargo plan, cargo/ballast operation,
bunkering plan are applied to the company procedure.
[REFERENCE]
1) Cargo loading / discharging plan
2) Bunkering plan
[PROCEDURE]
1) PT-651 Ch.6.3.1 / Cargo tank pressure control
2) PT-651 Ch.10 / Pre/post dry dock operation
[REFERENCE]
1) 651-625 / Cargo operation log at sea
2) 651-731 LNG loading & unloading log
6.3.3 The SMS includes procedures for non-routine or specialised cargo and ballast Yes
operations undertaken in the fleet.
Company procedure covers non-routine or specialised cargo and ballast operations.
[PROCEDURE]
1) PT-651 Ch.10 / Pre post dry dock operation
2) PT-651 Ch.11.4.11/ Ship to ship transfer
6.3.4 The SMS requires Junior Officers/relevant personnel to be actively involved in Yes
planning, line setting and execution of the cargo, ballast, tank cleaning and
bunkering operations as part of their continuing personal development plan.
The duty officer must well understand the cargo handling equipment and instrument as well as
cargo operations.
The cargo plan was prepared by C/O and it will be briefed to all officer and signed by them.
According to shipping KPI, the vessel conducted onboard training in regard to cargo, ballast and
bunker handling.
The junior engineers also are briefed on bunkering plan and they engage in bunkering operation as
per PE-502 App.2.
Their knowledge and ability on each operation will be reflected in their evaluation.
[PROCEDURE]
1) PT-651 Ch.6.2.3.8
[REFERENCE]
1) Cargo loading & discharging plan
2) Bunkering plan
3) 315-102 / Training evaluation report (별별별별)
And, contracted training centre had LNG computer-based simulator that is covering normal cargo
operation and emergency situation.
[REFERENCE]
1) In house training center [LNG Training matrix]
The qualified and experienced superintendents have conducted audit and verified the efficiency of
each operation, crew’s ability/experience, supervision of each operation using general inspection
checklist.
[PROCEDURE]
1) PO-101 Ch.2.3.3 / Arrangement for entering & leaving Port
2) PO-102 Ch.3 / Departure/Arrival
3) PO-204 Ch.1 / Safety of working
4) I18 MSMP & LMP section 3 / Berthing & mooring planning
5) PO-MC-101-010 / Anchoring Guidance
6) D3 01-08-04 / Anchoring
7) D3 01-08-05 / Handling of tug boat
8) D3 01-08-06 / Handling of mooring line
[REFERENCE]
1) 102-621 / N1 Port arrival-departure check list
2) 102-624 / N4 Pilot card, N4-1 Checklist for master pilot
information exchange
3. Publication
1) HSQS I18 / Mooring system and line management plan
6A.1.2 Maintenance, testing and routine inspections of mooring and anchoring Yes
equipment is included in the planned maintenance system.
Maintenance, testing and routine inspections of mooring and anchoring equipment is being carried
out according to company planned maintenance system and the results are recorded accordingly.
[PROCEDURE]
1) HM-HM-004 / Maintenance & operation
guidance of winch & windlass
2) HM-HM-008 / Maintenance of mooring winch drum bush
3) I18 MSMP section 5 / Inspection
[REFERENCE]
1) 651-544 / Mooring winch brake holding power test
2) PMS recorded in MMS
[PROCEDURE]
1) HM-HM-001 / Guidance for administration of wire rope
2) HM-HM-014 / Guidance for administration of mooring tail rope
[REFERENCE]
1) Code 651-543 / Wire & Tail rope log
2) PMS recorded in MMS (3 month wire greasing)
6A.1.4 The company has procedures that address the use of tugs. Yes
Company procedure specifies the risk of tug operations which contain the communication during
tug operation, handling tug’s line, caution during towage operation, etc.
[PROCEDURE]
1) D3 01-08-05 / Handling of tug boat
2) MSMP section 3 / Mooring plan
Stage 2
6A.2.1 Detailed procedures address each different type of mooring operation likely to Yes
be undertaken by fleet vessels.
LNG carriers normally conduct mooring operation at conventional berth, and a few cases of STS
mooring can be possible.
Company procedure specified each type of mooring operation.
[PROCEDURE]
1) PT-651 Ch.11.4.11 / Ship to ship transfer
2) PT-651 Ch. 5.4.2.4 / Mooring line
3) PT-651 Ch. 5.4.3 / Works that require precaution at LNG terminals
3) D3 01-08-06 / Handling of mooring line
4) D3 01-08-12 / STS Operation
5) MSMP section 1 / 3
[PROCEDURE]
1) PO-MC-101-010 / Anchoring guidance
2) D3 01-08-04 / Anchoring
3) PT-651 Ch. 5.4.2.5 / Anchors
6A.2.3 Procedures ensure that vessels remain safely moored at all times. Yes
In keeping a safe watch in port, the deck officer shall make frequent rounds of the ship to ensure
the security of the moorings. Master shall ensure that sufficient number of officers and ratings are
retained on board to handle any emergency situation while at berth.
[PROCEDURE]
1) PO-102 Ch.5.2.1 / Minimum onboard crew
2) PT-651 Ch. 5.4.3 / Works that require precaution at LNG terminals
3) I23-E / Emergency response procedure
[REFERENCE]
1) 651-542 watch keeping log
6A.2.4 Procedures are in place for the inspection, maintenance and replacement of Yes
wires, ropes, tails and ancillary equipment.
The wires, ropes, tails and ancillary equipment are regularly inspected and maintained in
accordance with HM-HM-001,014 and the the results of inspection and maintenance are recorded
in Code 661-022.
[PROCEDURE]
1) HM-HM-001 / Guidance for administration of wire rope
2) HM-HM-014 / Guidance for administration of mooring Tail rope
[REFERENCE]
1) Code 651-543 / Wire & Tail rope log
2) PMS recorded in MMS
Stage 3
[PROCEDURE]
1) PO-101 Ch.2.3.3 / Arrangement for entering & leaving Port
2) PO-101 Ch.4-2 / Chief Officer
3) PO-101 Ch.4-4 / Second Officer
4) MSMP section 3 / Mooring plan
6A.3.2 Measures are taken to optimise onboard mooring arrangements to ensure the Yes
safety of vessel personnel.
Crew have been educated regularly about snap-back zone for safety of mooring line handling and
responsible officer has noticed properly with regard to the snap-back zone in accordance with
mooring arrangement on the scene through the TBM before mooring operation.
Moreover, there was a history of installation of new winches for optimize onboard mooring
arrangement for calling specific LNG terminal.
[PROCEDURE]
1) D3 01-08-06 / Handling of mooring line
2) D3 01-08-07 / Handling of mooring line by line boat
3) PS-MC-201-006 / To make full use of snap-back zone for safety of mooring line handling
[REFERENCE]
1) Code 651-543 / Wire & Tail rope log
2) Optimoor study result
3) PMS Record (mooring winch & windlass brake lining inspection)
4) LNG Vessel Split Drum Guide Modification
6A.3.3 Procedures address the use of all ancillary craft used in mooring and towage Yes
operations.
Company procedure PT-661 Ch.7.7 specifies the tug operations which contain the communication
during tug operation, handling tug’s line, caution during towage operation, etc.
[PROCEDURE]
1) D3 01-08-05 / Handling of tug boat
2) D3 01-08-07 / Handling of line by line boat
3) MSMP section 3 / Mooring plan
[REFERENCE]
1) LNGC new panama canal - mooring arrangement review
2) LNGC mooring chock & bollard modification – Australia project
[REFERENCE]
1) DSLNG ship-shore compatibility study & new winch installation at accommodation side. (P&S)
6A.4.2 All available means are used to ensure that vessels can safely moor at terminals Yes
being visited for the first time.
When LNGC is decided to call LNG terminal for the first time, SSCS (Ship Shore Compatibility Study)
should be completed before calling. During the study, mooring arrangement and analysis will also
be reviewed by shore staffs by using Optimoor study software programme.
Optimum mooring arrangement of vessel which meets the criteria of OCIMF mooring equipment
guidance will be decided in consideration of vessel mooring equipment arrangement and
characteristic of vessel and mooring line.
[REFERENCE]
1) Result of OPTIMOOR study
6A.4.4 The company actively seeks out available or innovative technology to enhance Yes
safe mooring operations.
There are CCTV cameras were installed at fwd/aft mooring station and manifold in all LNGC.
Moreover, tension monitoring system was equipped at LNGC for line status monitoring during her
berthing.
In regard to the wind force and direction, anemometer display was installed at CACC. In case of
new ships which delivered in 2017, anemometer monitoring & alarm system was installed at CACC.
[PROCEDURE]
[PS-210 Management of change]
Ch.2 Management of change
7.1.2 A procedure is in place to ensure that the impact of any proposed change is Yes
assessed.
The company describes the assessment of the impact on any proposed change in the procedure.
[PROCEDURE]
[PS-210 Management of Change]
Ch.2.3.3 Review / Approval
7.1.3 The management of change procedure clearly defines the levels of authority Yes
required for the approval of any changes.
The company describes the level of authority required for the approval of a change in the
procedure ;
[PROCEDURE]
[PS-210 Management of change ]
Ch.2.2 Approval of management of change
Moreover, the company has received industrial news from P&I, and Class technical information
regularly for updating legislative or industry best practice.
[PROCEDURE]
[PS-210 Management of Change]
Ch. 2.3 Flow chart for management of change
Stage 2
[PROCEDURE]
[PS-210 Management of change]
Ch. 2.3 Flow chart for management of change
Ch. 2.3.3 Review / approval
7.2.2 Management of change identifies all personnel that may be affected by the Yes
change and ensures that they understand the extent and likely impact of any
planned change.
The company verifies that management of change was notified to personnel who are affected by It
in the procedure.
[PROCEDURE]
[PS-210 Management of change]
-. CH.1.3.3 The head of each team
-. APP.1 The proposal for MoC form
7.2.3 Management of change procedures ensure that training needs arising from any Yes
proposed changes are identified and documented.
The company has management of change procedure identifying the need of training and education
should be considered.
[PROCEDURE]
[PS-210 Management of change]
-. Ch. 2.3.5 Monitoring
-. Ch. 2.3.6 Subsequent management
-. APP.1 The proposal for MoC form
Moreover, the company has document & record control procedure separately. In the ship, the
master and chief engineer also handed over their job following with the hand over procedures.
[PROCEDURE]
[PS-210 Management of change]
-. Ch. 2.3.5 Monitoring
-. Ch. 2.3.6 Subsequent management – documentation
-. APP.1 The proposal for MoC form
[PO-108 Document & record control]
7.2.5 Regular reviews are conducted of management of change plans being Yes
implemented.Any changes not carried out within the proposed timescale are
reviewed, revalidated and approved.
The company has management of change procedure identifying that management of change plans
being implemented within time scale.
[PROCEDURE]
[PS-210 Management of change]
-. Ch. 2.1.5 Temporary change
-. Ch. 2.3.4 Implementation
-. Ch. 2.3.5 Monitoring
The company has procedures to assure that superintendents and crew can familiarize newly
acquired vessels entering into the fleet.
[PM-406 New building ship crew job]
[Code[401-111] Secondhand ship inspection checklist
[Master plan of new ship, secondhand ship & ship management company change]
7.3.2 There is a periodic review of the outcome of all changes to ensure objectives Yes
have been met.
The company reviews environment, health-safety, and quality system periodically by management
review.
It includes system revision, master’s review, and all HSQS related review
7.3.3 A software management procedure covers all shipboard and shore systems. Yes
The company has procedure for software management including cyber security, management of
software version, compatibility check, proper update and back up.
[PROCEDURE]
[PS-210 Management of change]
-. Ch.2.1.3 Personnel or organization change
7.4.2 The company actively seeks out improvements for new build design Yes
specifications.
The company applied new LNG carrier MEGI engine & PRS (Partial Re-liquefaction System) for
improving energy efficiency.
Especially,new VLGC has been under construction with improvement of environment and Safety.
-. Environmentally Acceptable Lubicants (EALs) usage for deck manchinery, crance, davit,
accommodation ladder’s wire.
-. Application of MESQAC 2017
-. Vessel’s fatigue life increase from 20 to 25 years results hull strength.
-. Safety hook installation for over 4 meter vertical ladder at cargo hold, cargo tank, and ballast
tank.
[PROCEDURE]
-. PS-201 Ch.1 General
-. PS-201 Ch.2 Reports of the accident, hazardous occurrence and non-conformities
-. PS-202 Ch.3.6 The responsible team by the type of accident
-. PS-202 Ch.3.7 Investigation/analysis of accident, hazardous occurrence/non-conformity
-. Code[201-101] Report of Accidents, Hazardous Occur.(Near miss) and Non-conformities
-. Code[201-102] Accident /Hazardous occur. (Near miss) Analysis
8.1.2 The reporting and investigation procedures ensure that all mandatory Yes
notifications are carried out within the required time frame.
The company describes mandatory reporting items including notifications like flag administration,
port authorities, classification society, insurer, ERS, QI and etc.
[PROCEDURE]
-. PS-201 Ch.2 Reports of the accident, hazardous occurrence and non-conformities
-. PS-202, Ch.3.2 Report / notification flow of emergency situation
-. SOPEP
8.1.3 Procedures ensure the fleet is rapidly notified of urgent information related to Yes
incidents and near misses.
We have documented procedures to ensure that the urgent safety-related information is notified
to all fleet immediately via e-mail(Notice of marine accident, Safety alert) in order to prevent the
similar marine accidents.
[PROCEDURE]
-. PS-201 Ch.1 General
-. PS-202 Ch.3.9 Feedback
[REFERENCE]
-. NMA (Notice of Marine Accident)
-. Monthly Monitoring of accident & corrective action
-. Monthly Near Miss F/back
[PROCEDURE]
-. PS-202 Ch.3.7.2 Organization of investigation team]
-. PS-201, Ch2 Reports of the accident, hazardous occurrence and non-conformities]
-. PS-201, Ch4 procedure related accident]
-. Code[201-102] Accident /Hazardous occur. (Near miss) Analysis
-. Code[100-164] Corrective action request
8.1.5 Procedures ensure that the appointed incident investigation team are Yes
appropriately trained and qualified to conduct the investigation and analysis.
The procedure describes the qualification for incident investigation team. The investigation team
may include third party.
[PROCEDURE]
-. PS-202 Ch.3.7.2 Organization of investigation team
[REFERENCE]
-. Personnel training status
-. Safety Officer Training Course (Ship Crew)
Stage 2
8.2.1 The incident-investigation procedure ensures that the root causes and factors Yes
contributing to an incident or significant near miss are accurately identified.
The company has arranged procedure to determine root cause and factors. All available
information can be used in this process.
[PROCEDURE]
-. PS-201, Ch.2 Reports of accident, hazardous occurrences
-. PS-201, Ch.4 procedure related accident
-. PS-201, APP.4 BASIC CAUSE
-. PS-201, APP.3 IMMEDIATE CAUSE
-. PS-202 Ch 3.7.3.3 Method of accident investigation
-. PS-202 App.9 Incident investigation report guide
[REFERENCE]
- TOMAS Sample
- TOMAS Sample
[PROCEDURE]
-. PS-202 Ch.3.7.1 Investigation team
-. PS-202 Ch.3.7.2 Organization of investigation team
8.2.3 External training in incident investigation and analysis is given to at least one Yes
member of the shore-based management teams.
The procedure describes the qualification for incident investigation team. The investigation team
may include third party. In addition, the education course for safety officers in the company
includes the incident investigation techniques.
[PROCEDURE]
-. PS-202 Ch.3.7.2 Organization of investigation team
8.2.4 The safety culture encourages reporting of all near misses and incidents. Yes
The company shares all near misses and incidents with fleet by monthly. In case of urgent
information, the company issues ‘Notice of Marine Accident’. These cases are reviewed at
shipboard ESQ meetings.
[PROCEDURE]
-. PO-101 Ch.5 Shipboard environment safety committee
[REFERENCE]
-. Monthly Near Miss Feedback
-. Shipboard ESQ Meeting Record
-. TOMAS Program Manual
-. TOMAS Incident Report Sample
-. Safety Seminar to encourage reporting of incident
8.2.5 Lessons learnt from incidents are used to prevent any recurrence. Yes
The company draws prevention measure from all incidents and ‘Notice of Marine Accident’ form
has lessons learnt item.
[PROCEDURE]
-. PS-202 Ch.3.9 Feedback
[REFERENCE]
-. Incident investigation record
Stage 3
[PROCEDURE]
-. PS-202 Ch.3.9 Feedback
[REFERENCE]
-. Annually Management Review
-. Annual Ship’s KPI
-. Semi-Annually Environment & Safety-Quality committee
-. Quarterly Safety Management Countermeasure Committee
-. Quarterly Step Change for Safety Campaign
-. Monthly Safety Bulletin
-. Monthly Monitoring of accident & corrective actionent
-. Step Change for Safety Campagin (Shell Company)
8.3.2 Analysis of company incidents and significant near misses is conducted at Yes
periodic intervals.
The company reviews all incidents and near misses by issuing ESQ performance every half year. In
addition, the company identifies trends & common issues, measures the effectiveness of
preventive measures and establishes action plans to improve ESQ Performance.
[PROCEDURE]
-. PS-202 Ch2.1 The environment & safety-quality committee
[REFERENCE]
-. Monthly Near Miss Feedback
-. Semi-Annually Environment & Safety-Quality committee
-. Quarterly Safety Management Countermeasure Committee
-. TOMAS Incident Statistic List (Real-Time)
8.3.3 Incidents and subsequent investigations are reported to oil major vetting Yes
departments.
The company arranged the procedure to report to oil major vetting department.
[PROCEDURE]
-. PS-202 Ch.3.10 Oil major company reporting
[PROCEDURE]
-. PS-202 Ch.3.7.2 Organization of investigation team
[REFERENCE]
-. Plan for training marine incident investigation for personnel
Stage 4
8.4.1 Incident analysis data is shared with industry groups. No
We are joining the membership of SIGTTO, P&I Clubs, class & other industries to get many pieces of
information, lesson learnt from accident etc.
The safety operations and technical meetings are held twice a year by terminals and ship’s
operators. The regular meeting result shares and consults regarding accidents, problems and
technical matters etc
The ship & shore compatibility meeting is annually held by terminal, chaterer and ship’s operators.
The regular meeting result shares and consults regarding accidents, problems and technical
matters etc
[REFERENCE]
-. Result of the safety operations and technical meetings
-. Result of the ship & shore compatibility meeting
8.4.2 Procedures ensure that, where possible, all trained personnel are given the No
opportunity to participate in incident investigation and analysis.
The procedures ensure that trained personnel are given the opportunity to participate in incident
investigation and analysis.
[PROCEDURE]
-. PS-202 Ch.3.7.2 Organization of investigation team
[PROCEDURE]
-. PO-107 Ch.1 Ship-visit & awarding system
[REFERENCE]
-. Code[107-103] Superintendent Inspection Check List
-. Code[109-407] General Inspection Check List
-. Code[109-604] Navigation audit checklist by shore staff
9.1.2 During vessel visits, every opportunity is taken to promote a strong safety Yes
culture across the fleet.
Ship’s proposal and opinion of working improvement must be reviewed by the management
ashore. The results of review should be replied to the ship and it may be used to improve the
company’s safety procedures.
The safety meeting with the ship's crews on safety related matters to be conducted during ship
visits..
Visitor should identify the ship’s management condition, discussion details, any problem and
proposal in details and correctly, then they should report ship’s current situation to the senior
management accurately & rapidly.
[PROCEDURE]
-. [PO-107 Ch.1.5~1.6 Ship-visit & awarding system]
[REFERENCE]
-. Code[107-103] Superintendent Inspection Check List
-. Code[109-407] General Inspection Check List
-. Code[109-604] Navigation audit checklist by shore staff
-. Improvement Record of Safety Procedure by visit and experience feedback
[PROCEDURE]
-. PO-101 Ch.5 Shipboard environment safety committee
-. PS-209 Ch.3.7~3.9 Risk management
-. D3 Risk assessment (Category 8. Health & Hygiene)
-. D4 Register of risk reduction measures
[REFERENCE]
-. Code [209-402E] Risk assessment sheet
-. Code [209-403E] Risk reduction measures
-. Code [102-505] Weekly work plan
[PROCEDURE]
-. PS-204 Ch.1.4 Permit to work system
-. PT-652 Ch.4.8 Entry into enclosed spaces
-. PT-652 Ch.8.5.2 Hot work procedure
-. PM-401 Maintenance & repair, Ch.3.1.1
[REFERENCE]
-. Code[651-504] Critical equipment work permit
-. Code[652-841] Hot work permit
-. Code[651-241] Enclosed space entry permit
Stage 2
[PROCEDURE]
-. PS-209 Ch.3.1 & 3.9 Risk management
-. D3 TASK INVENTORY LIST
[REFERENCE]
-. RA 1-8-12 STS operation (OCIMF guideline)
-. RA 14-01~06 Cyber Security (Reference from BIMCO Guideline)
-. PS-MC-201-010 Standard hand signal for crane operation
(code of safe working practices)
-. PO-102, App.11 Bridge watch level & manning matrix (ICS-bridge procedure guide)
-. I9, Ch.2 & PO-MC-104-009 Social media guidance for seafarers (Intertanko guidance)
-. Code [102-505] weekly work plan
9.2.2 The risk assessment process includes provision for assessing new, non-routine Yes
and unplanned tasks.
The risk assessment should be conducted by competent persons who has been performed the
pertinent task more than 2 years and has completed a risk assessment training course which is
provided by the system management team.
(PS-209 Risk management, Ch.3.2.3 / 3.3.1)
Review work scope again whether the task can be achieved without using Hot Work and
alternative methods of work, for example cold work, to be considered to ensure safe completion.
(PT-652, Ch.8.5 / 8.8)
[PROCEDURE]
-. PS-209 Ch.2 Flow Chart of risk management
-. PS-209 Ch.3.2.3 & 3.3.1 & 3.5.3 & 3.7.2 & 3.6.2.4 & 3.8.2 Risk management
-. PT-652 Ch.8 Hot work procedure (Ch.8.5 / Ch.8.8)
-. D4, Task 4.9.4 Hot work - Risk reduction measures
[REFERENCE]
-. RA for Non-routine and unplanned work
[PROCEDURE]
-. PS-209 Ch.1.2 General
-. PS-209 Ch.3.8 / 3.9 Risk management
[REFERENCE]
-. Safety officer training course curriculum
-. TOMAS RA Sample
-. Training Record for Shore Personnel
-. D3/D4 Acknowledgement Sheet
[PROCEDURE]
-. PS-204 Ch.1.4.3 Safety of working
-. PS-209 Ch.3.5.3 Risk management
[REFERENCE]
-. Code[102-601] Permit to work
-. Code[652-481] Enclosed space entry permit
-. Code[652-841] Hot work permit
-. Risk reduction measure record
[PROCEDURE]
-. M1 Ch.8.7.2 Identify onboard contractors
-. PS-204 Ch.1.4.3.2 Safety of working
-. PS-204 App.3 Safety Notice for contractors
[REFERENCE]
-. Code[102-602E] Permit to work(Outside workers)
Stage 3
[PROCEDURE]
-. PS-209 Ch.1.2 General
-. PS-209 Ch.3.1.1 & 3.1.2 & 3.8.7 Risk management
-. D3, Ch.F2 Revision status
[REFERENCE]
-. Periodical risk assessment (Annual)
9.3.2 Proprietary safety tools are used to encourage hazard identification and to Yes
improve safety awareness throughout the organisation.
[PROCEDURE]
-. PT-652 Ch.10 Behaviour based safety management
-. PS-204 Ch 1.1 Stop work procedure
-. PS-ET-220-001 Guidance for practical use of the Safety Bulletin
[REFERENCE]
-. Code [652-101] Safety inspection and BBS observation Check List
-. Safety Seminar Plan & Result Report regarding awards
-. Annual Shipping KPI regarding awards
-. Shipboard ESQ Meeting
-. Monthly Near Miss Report
-. Monthly Safety Bulletin
[PROCEDURE]
-. M1-Ch.8.7.4 Evaluation of suppliers & 8.8 Supplier management flow
-. Team Manual for contractor management
[REFERENCE]
-. List of approved contractors.
-. Evaluation of approved contractors.
Stage 4
[PROCEDURE]
-. PS-209 Ch.2 / Flow chart of risk management
-. PS-209 Ch.3.8 / 3.9 Risk management
9.4.2 Periodic (at least quarterly) safety related publication(s) are issued. Yes
Safety Bulletin consist of the following contents.
-. Focus on this month
-. A case study on marine accidents
-. Health Issues
-. Cybersecurity Awarness
[REFERENCE]
-. Safety Bulletin
[PROCEDURE]
-. M1-Ch.8.7.4 Evaluation of suppliers& 8.8 Supplier management flow
[REFERENCE]
-. Annual evaluation list of approved contractors
[PROCEDURE]
-. PO-101 Ch.4-1.2.3 Duties as a Safety officer
-. PT-652, Ch 10 Behavior based safety management
-. PC-305 App.1 Standard Criteria of Fleet Crew Qualification
-. PC-315 App.2 Curriculum depending on the ranks of Korean seafarers
[REFERENCE]
-. Shipboard ESQ Committee Report
-. Safety Officer Training Curriculum
-. Code[652-101E] SAFETY INSPECTION AND BBS OBSERVATION CHECK LIST
9A.1.2 The company safety culture encourages all personnel to identify, report and Yes
where applicable address hazards.
Any crews identifying hazards or near-miss cases can report it to the master and company through
the reporting of near-miss Code [201-101]
All crews are encouraged to make a suggestion for improvement of identified hazards to the
seafarer safety representative (SSR) or safety officer.
(PO-101 Ch.5.6 Seafarer safety representative)
All crews are encouraged to participate in the BBS process by using the Check List (652-101E) and
best endeavor to share the safe behavior and risk behavior during shipboard ESQ meeting. (PT-652.
Ch.10.2.5)
[PROCEDURE]
-. PO-101 Ch.5.6 Seafarer safety representative
-. PS-204 Ch.1.7 Safety Woring
-. PS-209 Ch.3.7.6 Determining risk ranking and Action plan
-. PT-652. Ch.10 BBS
[REFERENCE]
-. TOMAS – Report – Shipboard ESQ committee
-. TOMAS Near Miss Record
[PROCEDURE]
-. PO-101, Ch 5.5 & 5.3.2 Shipboard environmant safety committee
[REFERENCE]
-. Shipboard ESQ Meeting after incident
[PROCEDURE]
-. PS-209 Ch.3.9.3
-. PS-204 Ch.1.2 / Ch.1.7
-. Code[102-505] Weekly Work Plan
-. PS-204 App.2 PPE Matrix
[REFERENCE]
-. Record of Shipboard ESQ Meeting
9A.2.2 Appropriate training in hazard identification and risk assessment is provided to Yes
vessel personnel.
All senior officers are participating in the safety officer training course.
All crews are participating in the safety seminar.
Both programme have hazard identification and risk assessment session.
[PROCEDURE]
-. PC-315 App.2 Curriculum depending on the ranks of Korean seafarers
[REFERENCE]
-. Safety Officer Curriculum
-. Safety Seminar
-. Training Plan & Result for Newly joined officer
-. Annual Training Schedule for Officer & Crew.
[REFERENCE]
-. Ship KPI Result for awards
-. Result of zero accident ship
-. Result Report of Safety Seminar
9A.3.2 Procedures measure and compare the strength of the safety culture across the Yes
fleet to identify areas for improvement and to provide motivation to vessel
personnel.
[PROCEDURE]
-. PS-201, Ch.2.2 Minor accident, Hazardous occurrence (Near-miss) report
-. PT-652 Ch.10 Behavior Based Safety Management
[REFERENCE]
-. Monthly Safety Bulletin
-. Code 652-101E Safety Inspection and BBS Observation Check List
-. TOMAS - Incident Management
-. Safety officer (C/E) daily patrol
-. Summary of near-miss report (monthly basis)
-. Circulation of experience feedback
-. Accident free ship (Quarterly and yearly)
-. Result of ESQ Committee
9A.3.3 Management identifies opportunities to strengthen their safety culture through Yes
interaction with fleet personnel.
The management and crew members are participated in following company interaction
programme.
[REFERENCE]
-. PDOS (Pre-departure orientation seminar)
-. Safety Seminar for Officer / Rating
-. Safety Seminar for ratings
-. Senior management ship visit
-. Shore based em’cy drill
-. PDOS Time Schedule
-. Code[107-103] Superintendent Inspection Check List (Safety Meeting)
-. Code[109-407] General Inspection Check List (Safety Meeting)
9A.4.2 Fleet safety trainers sail with the vessel to conduct training and promote the No
company values and safety culture.
[PROCEDURE]
-. M1 / Ch. F1 Environment and Health-Safety & Quality Policy
-. M1 / Ch .4 Environmental planning and Quality planning
-. M1 / Ch. 17 Document and Record control
-. PE-502 Oil & Waste Management
-. PE-503 Air & Others Pollution Prevention
-. I22 Ship Energy Efficiency Management Plan
[REFERENCE]
-. Company policy posted on board vessel (W/H, CACC, ESCR)
-. Company policy posted in office (Conference room)
-. Environmental Management Plan for 2019/2020
-. Environmental Performance for 2019
10.1.2 All sources of marine and atmospheric emissions attributable to company and Yes
vessel activities have been systematically identified.
Not only limitation and restriction of all effluent discharges in accordance with MARPOL &
company procedures.
[PROCEDURE]
-. PE-501 Ch.3 Identification of Environmental Aspects / 3.3 Environmental Areas
-. I13 Garbage Management Plan / Ch 3.1 Prevention of pollution from garbage
-. PE-502 Oil & Waste Management
Ch. 1.3 General
Ch. 3 Oil And Waste Management
-. PE-503 Air & Others Pollution Prevention
Ch. 1.3 General
Ch. 2 Control Requirement Management of Air Pollution
Ch. 3 Ballast Water Management
Ch. 6 Other pollutant management
Ch. 5 Local regulation for pollution prevention
App 2 Controlled figures of exhaust gas in California waters of the USA
App 7 USA MFSA and WSMC field guide
App 8 Prevention scope in east Canada..
[REFERENCE]
-. PE-501 / Code 501-402 Environmental Evaluation Sheet
[PROCEDURE]
-. PE-501 Environmental Planning
-. PE-502 / Ch. 3 Oil and Waste Management
-. PE-502 / App. 5 Waste Management techniques
-. PE-503 Air & Others Pollution Prevention
Ch. 2 Control Requirement Management of Air Pollution
Ch. 3 Ballast Water Management
Ch. 6 Other pollutant management
Ch. 5 Local regulation for pollution prevention
App. 2 Controlled figures of exhaust gas in California waters of the USA
App. 7 USA MFSA and WSMC field guide
App. 8 Prevention scope in east Canada..
App. 10 National ballast water management regulations
-. I13 Garbage Management Plan
-. I22 Ship Energy Efficiency Management Plan
[REFERENCE]
-. Environmental plan for 2019/2020
-. PE-501 / Code 501-402 Environmental Evaluation Sheet
-. Ballast Water record book
-. Oil Record Book
-. Garbage Record Book
-. EEOI
-. Vessel VPS Bunker Analysis Operational Report
Stage 2
[PROCEDURE]
-. PE-501 Ch.5 Establishment-implementation of environmental plan
-. PO-102 Shipboard Operation / App 1 Abstracted log instruction
-. I22 Ship Energy Efficiency Management / Ch. 4 Performance Evalution
[REFERENCE]
-. Environmental Energy Plan for 2019
-. Energy Efficiency Performance Record & Checklist
-. Voyage EEOI Calculation Sheet
-. AB-Log, Noon Report
System management team distribute information to each team for field application after
understanding of revisions and establishment of countermeasure.
The Head of System management team shall evaluate compliance with applicable legal
requirements and other requirements to which the Company subscribes through the Internal audit,
Ship visit inspection, Management review and etc., and shall keep the records of evaluation.
[PROCEDURE]
-. M1 / Ch.16 Rules and regulations
-. PR-704 Ch. 2 Rules & Regulations Management
-. PE-501 / CH. 5 Establishment-implementation of environmental plan
-. PE-502 / Ch. 3 Oil and Waste Management
-. PE-502 / App. 5 Waste Management Techniques
-. I22 SEEMP / Ch. 4 Performance Evaluation
-. M1 / Ch.19 Management review
[REFERENCE]
-. Shipboard Environmental Safety Committee minutes
/ Vessel Environmental-Energy Plan
-. Results of Management review for 2019 / HLS Environmental performance for 2019
-. Master(B) Report, Quarterly
-. Voyage Heat Balance, Performance Report, Generator Engine Condition Report
-. ESQS Performance Report, Monthly
[PROCEDURE]
-. I22 SEEMP / Ch. 3 Guidelines for the energy efficiency management
[REFERENCE]
-. Environmental plan for 2019/2020
-. I22 SEEMP / App. 2 Energy Efficiency Performance Record & Checklist
A ship-visitor checks ship’s actual condition by utilizing ‘Internal Audit Checklist’ and submits those
to the System management Team along with vessel boarding report.
[PROCEDURE]
-. PE-502 / Ch. 2 Fuel & Lub. Oil Management
2.1.1 Ordering
2.1.2 Fuel delivery
2.1.4 Sampling of the fuel oil
2.1.8 Request for analysis of a fuel oil sample
2.1.6 Issuing a Note of Protest
2.1.10 Reports
-. I2 / ET-ETE-011 Fuel Oil Change-over Procedures in SOx Emission Control Areas
-. I22 SEEMP / Ch. 3.14 Fuel Oil Control
-. M1 / Ch. 18 System audit
-. PO-109 Operation M. Procedure / Ch. 3 Internal audit procedure
[REFERENCE]
-. Internal Audit Checklist
-. Environmental performance report
Stage 3
10.3.1 The potential environmental impact of all company and vessel activities is Yes
subjected to evaluation.
Environmental targets are established annually and evaluated semi-annually by both vessels and
company offices.
The targets include Air pollutant (CO2, SOx, NOx, PM), Water pollution (Oil spill, Ballast water, Gray
water), Waste Management (Waste Oil, Plastics, Garbage) and Office Management (Direct GHG,
Indirect GHG).
[PROCEDURE]
-. PE-501 Environment M. Procedure
[REFERENCE]
-. Environmental plan for 2019/2020
-. PE-501 / Code 501-402 Environmental Evaluation Sheet
-. PE-501 / Code 501-301 Process Flow Sheet
The company has established environmental objectives and targets by identifying environmental
aspects and evaluating their significant impacts of the company’s activities and services.
This plan has been periodically verified by third party, KR. HLS has been issued ISO 14001
certificate.
[PROCEDURE]
-. Cert. for ISO 14001
-. PE-501 Environment M. Procedure
[REFERENCE]
-. Environmental performance for 2019
-. Environmental plan for 2019/2020
[PROCEDURE]
-. M1 / Ch. 4 Environmental planning and Quality planning
[REFERENCE]
-. HLS Long-Term Plan
-. Environmental plan for 2019/2020
[PROCEDURE]
-. PM-404 Ship recycling procedure
[REFERENCE]
-. Statement of Compliance International Inventory of Hazardous Materials(174K)
10.3.5 Environmental performance improvements are incorporated during the new Yes
build process.
HLS has been actively involved in new building project. The company evaluates energy saving
technology which is compatible for each kind of ship before contracting the project, and asks
shipyard to optimize the hull form reflecting expected operating profile upon contract.
[PROCEDURE]
-. I22 SEEMP / Ch .3 Guidelines for the energy efficiency management
[REFERENCE]
-. H/No. 3132, Energy saving device for new built
[REFERENCE]
-. Energy Saving Device for new built
-. Real time performance monitoring is working at 174K LNGC
-. Applicated silicone paint
-. ME-GI Engine for 174K LNGC (Duel Fuel, de-rating, auto-tuning)
10.4.2 The company explores new ideas and engages in technology partnerships Yes
related to environmental performance.
HLS signed a contract with Daewoo Shipyard for the development of smart ship. Refer to the news
that Daewoo shipyard works with Hyundai LNG Shipping to develop smart ship technology.
The company is planning to change the facility to use LSMGO as main boiler fuel in preparation for
IMO2020.
In addition, MEGI engines were installed on recently constructed ships.
[REFERENCE]
-. Decision of boiler modification for 125K & 135K LNGC
-. Decision of ME-GI Engine for 174K LNGC
-. Decision of equipment for new built
-. https://ajudaily.com/view/20191218142921309
[REFERENCE]
-. HLS-Environmental Performance for 2019
[PROCEDURE]
-. M1 Ch.19.3.5
-. M1 19.3.3 Evaluation items for the Management review
-. PR-705 Ch.1
-. PR-705 Ch.3.1
11.1.2 A detailed shore-based emergency response plan covers all credible emergency Yes
scenarios.
a) Report should be notified within one hour of the accident
b) In case written report is impossible due to time or conditions, it should be made through
telephone. In this case, written report also should be submitted after telephone report.
c) If in emergency, use emergency contact as below. For the rest, use electronic system
communications. But non- computerization vessels use E-mail.
[PROCEDURE]
-. PS-201 Ch.2.1.1 / Method of initial report
-. PS-202 Ch.3 Shore based emcy response procedure
[PROCEDURE]
-. PS-202 Ch.2.3.3 Responsibilities & job
-. PS-202 Ch.2.3.6 The ship/shore joint drill
[REFERENCE]
-. SOPEP Emergency contact list
-. Professional Accident Investigation
-. DPA
-. Personnel training status
-. DPA Qualifications checklist
Stage 2
11.2.1 The company provides suitable emergency response facilities. Yes
Emergency response room is operated independently with facilities such as fax, phone
connections, computer network points, a whiteboard, satellite television, video, electric chart and
projector with large screen.
Also, company’s staff is able to monitor own managing vessel by vessel monitoring system(FDSS)
that is showing vessel tracking and position.
Breakout rooms :
Conference room & BOD room
we are regularly reviewed to take account of new technology for Incident room facilities.
[REFERENCE]
-. Video Conference and Real-time vessel tracking
[PROCEDURE]
-. PS-203 Ch.3.2 Drills, instruction & training
-. SSP Ch. 6.4 -Training, drills and exercises plan
-. PS-202 Ch. 2.3.6 - The ship/shore joint drill
[REFERENCE]
-. Result of 2019 ship shore joint exercise (piracy attack)
11.2.3 The plan includes procedures and resources to interact with media. Yes
1) PS-202 2.3.5 / Media management procedure in a major accident or a crisis situation
b) Responsibilities and function of media manage. team
-. Management of the press release, statements and home
page on website
-. The Company spokesman, media interview, press
conference, etc
-. Control of the media consultants
-. Maintaining the emergency contact point
-. Monitoring of news broadcasts
-. Monitoring and responding to social media
c) Convening and operation
Hire the media consultants, or local media control firms, if necessary. Local P & I club
correspondent could carry out this role and, in the case of accident in U.S. waters, the information
of local media control firms could be given by Q.I.
[PROCEDURE]
-. PS-202 2.3.5 / Media management procedure in a major accident or a crisis situation
[REFERENCE]
-. Media Training Certificate
-. ERS Cert
[PROCEDURE]
-. PS-202 Ch. 2.3.6 c) Record result of ship/shore joint emergency response drill after completion
-. M1 19.3.3 Evaluation items for the Management Review
[REFERENCE]
-. Incident Investigation Report
-. NMA
-. Result of 2019 ship/shore joint exercise
-. Result record of improvement of emergency precodure
Stage 3
11.3.1 Records are kept of participants who have been involved in emergency drills Yes
and exercises.
1) PS-202 Ch.2.3.6 / The ship/shore joint drill
.1 Objective
The designated person(s) must perform the ship/shore joint emergency response drill to operate
the team effectively at the time of emergency. The team in charge of each drill shall keep the
record of drill carried out.
2) PS-202 Ch.2.3.3 / Responsibilities & job
Provided that the head of emergency response team is absent, the head of fleet management
team shall substitute for his/her responsibilities and jobs, and the head of team is absent, the sub-
alternation at relevant team shall substitute for his/her responsibilities and jobs.
[PROCEDURE]
-. PS-202 Ch.2.3.6 The ship/shore joint drill
-. PS-202 Ch.2.3.3 Responsibilities & job
[REFERENCE]
-. Emergency contact list
-. Result of 2019 ship shore joint exercise (Incl. attendance list)
[REFERENCE]
-. The contact detail located in Emergency response room
-. Salvage, towing, media consultant, flag states, local authorities.
11.3.3 Drills and exercises test the effectiveness of arrangements to call on external Yes
consultants and resources.
1) PS-202 Ch.2.3.6 / The ship/shore joint drill
.1 Objective
The designated person(s) must perform the ship/shore joint emergency response drill to operate
the team effectively at the time of emergency. The team in charge of each drill shall keep the
record of drill carried out.
.
We will check communication link by joining 3rd parties (authority, maritime police, Class, P&I,
agent, etc.) during the drill as a result of 2019 ship/shore joint exercise
[PROCEDURE]
-. PS-202 Ch.2.3.6 The ship/shore joint drill
-. PS-202 Ch.2.4 Outside organization related to emergency response
[REFERENCE]
-. Result of 2019 ship/shore joint exercise
11.3.4 Business continuity, in the event of potential disruption to the main place of Yes
business, has been addressed.
1) PS-202 Ch.7 Business continuity plan
In the event of a disaster in shore-based business, Pre-emergency response measure planned to
minimize the impact on vessels safety and shore-based business.
[PROCEDURE]
-. PS-202 Ch.7 Business continuity plan
2) PS-202 Ch.3.7.3.3 Method of accident investigation may consider the use of all available
information such as;
d) Photographic evidence/CCTV
e) VDR and/or ECDIS data
5) PS-202 Ch.3.3.2.4 The Head of team in charge should identify the states of damage including the
ship’s loaded condition at the time of accident and departure of last port and the Head of team in
charge should notify class the ‘E.R.S. condition report’ and get the information of ship’s stability
etc.
[PROCEDURE]
-. PS-202 Ch.3.7.2 Organization of investigation team
-. PS-202 Ch.3.7.3.3 Method of accident investigation may consider the use of all available
information
-. PO-ET-120-005 Bridge CCTV guidelines
-. PS-202 Ch.3.3.2.4
-. PS-202 3.6 The responsible team by the type of accident
[PROCEDURE]
-. PS-202 Ch.7 Business continuity plan
[PROCEDURE]
1) PS-202 Ch. 2.3.6 / The ship/shore joint drill
[PROCEDURE]
-. PS-205 Ch.3.1.8
[Reference]
1. Code[109-405] General Inspection Check List
2. Code[107-103] Superintendent Inspection Checklist
3. Code[109-7104] Navigation audit by shore staff
12.1.2 An inspection plan covers all vessels in the fleet, with at least two inspections of Yes
each vessel a year.
The company has an inspection plan covers all vessels in the fleet with at least two inspections of
each vessel a year.
[Procedure]
1. PO-107, Ch.1 Ship Visit
2. PO-109 Ch 3 Internal audit procedure 3.2 Audit team, 3.4 Report of audit result, 3.5
Closing of Audit
[Reference]
1. Inspection, audit plan for 2019/2020
2. Monthly visit plan
[Reference]
12.2.2 A system records any deficiencies identified by the inspections and tracks them Yes
through to close out.
The results of inspection and corrective actions are recorded in the company form and tracked and
monitored to close out deficiencies by inspector in accordance with procedure PO-107 Ch.1.4
[Procedure]
1. PO-107 Ship-Visit Ch.1 Onboard visit(Corrective action for deficiencies)
2. PO-109 System AUdit Ch 3 Internal audit procedure(3.4 Report-3.5Closing audit)
[Reference]
1. Result of General Inspection Check List
2. Result of Superintendent Inspection Checklist
3. TOMAS-Survey/Audit/Accident/Cert -Audit Management & PSC Management – NC Graph List &
PSC Point Out Graph
[Procedure]
1. PS-202 Ch 2 Organizational structure(MEETING)
2. M1 Ch19 Management review
[Reference]
1. 2018/2019 Annual Management Review
2. HSQS Meeting Review(Include SMCC, 2019)
12.3.2 In order to improve the inspection process, analysis of inspection results is Yes
compared with data from third party inspections.
The company compares own inspection results with the results of inspections such as PSC/FSC,
OCIMF SIRE
[Reference]
-. TOMAS-Survey/Audit/Accident/Cert -Audit Management & PSC Management – NC Graph List &
PSC Point Out Graph
-. compared with data from third party inspections
12.3.3 The inspection process identifies weaknesses in personnel familiarity with Yes
equipment and operations.
The company conducts internal audit & navigation audit to identify weakness in personnel
familiarity.
[Reference]
-. Code[109-405] General Inspection Check List
-. Code[107-103] Superintendent Inspection Checklist
-. Code[109-701] Navigation audit by master for officer
-. Code[109-7104] Navigation audit by shore staff
[Reference]
1. Benchmarking against peer companies(Cyber security, social media, BRIDGE WATCH
LEVEL & MANNING MATRIX, etc.)
2. Evaluation result of Superintendent
3. Evaluation Result of subcontract(sludge)
4. Evaluation Result of sbucontract(repair supplier)
[Procedure]
1. PO-107, Ch.1 Ship Visit
2. PO-109 Ch 3 Internal audit procedure 3.2 Audit team, 3.4 Report of audit result, 3.5
Closing of Audit
[Reference]
1. Code[109-405] General Inspection Check List
2. Code[107-103] Superintendent Inspection Checklist
3. Code[109-7104] Navigation audit by shore staff
4. Code[109-601] Navigation audit by shore staff
12A.1.3 An audit plan covers all vessels and company offices. Yes
The company has audit procedure to ensure that an audit plan covers all vessels and company
offices.
[Procedure]
1. PO-109 Ch 2 Audit implementation planning
[Reference]
-. Internal audit & Visit plan for 2019/2020
[Reference]
1. General inspection result result
2. Superintendent inspection check list
3. TOMAS(Survey/Audit/Accident/Cert) NC Graph list - Integrated Analysis
12A.2.2 Audits are performed in line with the audit plan. Yes
The company has procedure to perform audits according to the audit plan. The company holds
Safety management countermeasure committee quarterly, then management confirms audit
progress rate and decides whether to support the resource.
[Procedure]
1. PO-109 Ch 2 Audit implementation planning
[Reference]
- Result of Audit and visit 2019
Stage 3
12A.3.1 All audit non-conformities are closed out within the prescribed time frame. Yes
The company monitors the non-conformities status in real time through computer programme
(TOMAS).
The Company shall discuss all non-conformities at the Safety Management countermeasure
committee quarterly and ensure that the results of the corrective actions are effectively
terminated.
[Procedure]
1. PO-107 Ch.1 Onboard visit 1.4 Corrective action for deficiencies
2. PO-109 Ch 3 Internal audit procedure(3.4 Report -3.5 closing Audit)
[Reference]
-. Safety management countermeasure committee minutes
-. TOMAS(Survey/Audit/Accident/Cert) NC Monitoring
[Procedure]
1.M1 Ch.19 Management Review
[Reference]
1. Annual Management Review(2019/2020)
[Reference]
-. TOMAS(Survey/Audit/Accident/Cert)
12A.4.3 A contractor management system which includes periodic auditing is in place. Yes
The company has a procedure for evaluating suppliers (Dry docks, Third party service providers)
and shall be conducted once a year.
However, the evaluation system is not computerized
[Procedure]
1. Subcontractor management
[Reference]
-. Evaluation Result of subcontract(sludge)
-. Evaluation Result of sbucontract(repair supplier)
[Procedure]
1. All aspects of activies
-. CSP(Cyber Security Plan) Ch.6. Security Measures(include company & personal)
-.SSA(Ship Security Assessment) Ch.2 Assessment Data
-.SSP(Ship Security Plan) Ch.10 Security level and related measures
2. Personnel responsible for security
-. SSP Ch.3.2 Company Security Officer & Ch.3.4 Ship Security Officer
-. CSP Ch 3 Organization, Responsibility & Authority
13.1.2 The company has documented procedures in place to identify security threats Yes
applicable to vessels trading areas and shore-based locations.
The Company has established and implements documented individual procedures to mitigate
security risks and minimize the consequences of any breaches of security affecting personnel and
assets of the Company whether on-board or shore.
[Procedure]
1. Security threats
-. SSP Ch.2.1 Objectives and related regulation & Ch.2.3 Security duties and development of
security measures
-. SSP Ch.6.4 Training, drills and exercises plan
-. CSP Ch.4 Cyber security treats
-. PS-206 PS206 Ch 2 Identification if high risk area of the stowaway
-. PS-207 Anti-Piracy Ch 2 The trend of piracy attack
-. PS-208 Prevention of Drug & Smuggling Ch 2 Identification of high risk area of drug smuggling
2. Code102-201 Master’s Passage Plan
3. The identified threats are reviewed
-. SSP Ch.9.1.2 Procedures for periodic review and updating
-. PO-MC-104-010 Ship Cyber Security Instruction Ch.2.4 the threat posed and the potential
consequences
-. CSP Ch.7.2.2 Review of security related information
[Procedure]
1. Mitigating measures
-. SSP Ch.10 Security levels and related measures
(Ch.10.1 Measures according to the security levels / Ch.10.2 Ship access control/ . Ch.10.3.3
Security patrol instruction / Ch.10.4.3.1 Searching of unaccompanied baggage on board)
-. SSP Ch.6 Training, drills and exercises
-. SSP Ch.3.2.4 Knowledge and training of the CSO & 3.4.4 SSO.
-. SSP Ch.8.1.3.g) Knowledge of the emergency procedures and contingency plans
-. CSP(Cyber Security Plan) Ch.6. Security Measures
2. Contingency plan of security potential breaches
-. PS-202 App.1.25 Kidnapped by pirate
13.1.4 Procedures are in place to obtain, manage and review current security related Yes
information.
The company is obtained information and circular from the flag, PMSC(Private Maritime Security
Companies), P&I club and website.
[Procedure]
1. Security information
-. SSP Ch.4.1.3 Collecting security threat information
-. CSP Ch.7.2 Management of security information
2. Review & Guidance
-. CSP Ch.7.2.2 Review of security related information
-. SSP Ch 03 Company Security Office Responsibilities and duties)
[Reference]
1. Emergency Contect List(Korea military & SOPEP)
2. Instruction of Self piracy act prevention measures
3. Maritime Security Chart up-date
4. Passing guidline of Oman Sea and Hormuth Strait
[Procedure]
1. Reporting Procedure
-. SSP CH.5.1.2 Reporting of security incident and analysis
-. CSP Ch 4.7 Security Incident and Infringment Reporting
[Reference]
-. PS-202 Ch.3 Shore based emergency response procedure(Vessel-company-external authorities)
-. PS-MC-205-001 Guideline on the safety measure against piracy attack in High Risk Area (2.1.4)
Voluntary Reporting)
Stage 2
13.2.1 Formal risk assessments of company activities are undertaken to identify and Yes
mitigate potential security threats.
The following risk assessments (D3, D4) are regularly being reviewed and amended as necessary.
-. 7-8-1 Terrorism
-. 7-8-2 Stowaway
-. 7-8-3 Piracy / armed thief / striker / mental patient
-. 7-8-4 Drug
-. 7-8-5 Piracy attack during transit HRA
-. 7-8-6 Deploying Armed Pirate Maritime Company
-. PS-209 Ch.3 risk assessment procedure(include interval)
Prior to entering in HRA, a risk assessment about the use of a armed guard should be carried out
by master.
-. PS-207 Ch.7.2 ARMED GUARDS Risk assessment
-. PS-207 App.3 Risk assessment for boarding armed guards in HRA
-. Code [102-201] Master’s Passage Plan 2.2 transit security risk assessment
-. I17 Vessel Hardening Plan App 3 Voyage Specific Risk assessment
-. The results of SSO’s Review 2018(Emergency Contect list)
The vessels have a vessel-specific hardening plan which includes as a minimum detail of hardening
arrangements and other ship specific hardening measures that prevent access to the
accommodation block, bridge, engine room and funnel casing.
-. I17 Vessel Hardening Plan Ch 3 First layer of defence
Latest security information and company procedure are provided to all staff through the security
briefing and security seminar and all crews through the DCN(Document Correction Notice), various
guidance and during PDOS (Pre-Departure Orientation Seminar).
Every 5 years, the Master and CSO have completed the Precautionary education to avoid piracy
activity carried out in accordance with the "Act on Prevention of Piracy Damage to International
Vessels, etc."
[Procedure]
1. SSP Ch 3.2.4 Knowledge and training CSO 3.4.4 nowledge and training SSO
2. SSP Ch.6 Training, drills and exercises
3. PS-207 Ch.1.5 Training and Education
[Reference]
-. Qualification of DP/CSO(include Alternate DP/CSO)
-. Certification sample (CSO/SSO)
13.2.3 Policy and procedures include cyber security and provide appropriate guidance Yes
and mitigation measures.
The company provide appropriate guidance and mitigation measures for Cyber security in
accordance with relevant guidance such as “The guidelines on cyber security onboard ships by
BIMCO, CLIA, ICS, INTERCARGO and INTERTANKO ” & other published by classification societies.
[Procedure]
1. Risk IT system
-. PO-MC-104-010 Ship Cyber Security Instruction
(Ch.2 Identify Threats / Ch.4 Risk Assessment)
2. vulnerable to external threat(include navigation, engineering, control and
communication systems)
-. PO-MC-104-010 Ship Cyber Security Instruction Ch.3 Identify Vulnerabilities
(Vulnerabilities of onboard system)
3. Industry guidance
-.PO-MC-104-010 Ship Cyber Security Instruction 1.1.4
The company provide proper means by relevant procedure & guidance to enhance cyber security
awareness level.
Also provide individual guideline to promote cyber security awareness such as “The social media
guide for shore-based personnel, vessel personnel and third parties when they are onboard”.
[Procedure]
1. PO-MC-104-010 Ship Cyber Security Instruction Att. Caution for Regarding Cyber Attack
2.PO-MC-104-010 Ship Cyber Security Instruction Ch.5 Protection measures against Cyber threats
3.PO-MC-104-009 Social Media Guidance for Seafarers
Stage 3
13.3.1 A travel policy is in place to minimise security threats to personnel. Yes
We provide Business travellers with travelling information to minimize security threats through
internet such as ministry foreign affairs in advance of business trip.
Business travellers should check if travelling region is dangerous or restricted and record it on the
business trip report before submitting.
We restrict business trip if travelling region is designated as tourism-prohibited & restricted area by
Korea government.
During business trip, travellers should comply with minimum hours of rest and company
procedures related to safety and health on board.
[Prodedure]
1. PP-812, Ch.1 / Business trip rules
2. PS-204, Ch.1 / Safe working practices
3. PS-205, Ch.1 / Health & Hygiene
4. Po-102, Ch.1 /Shipboard Operation
[Reference]
1. 별별별별별
2. www.0404.go.kr
The company DML (Document Muster List) includes the latest editions of relevant security related
publications.
[Procedure]
1. CSP Ch.1.4 Update Planl
[Reference]
1. D2 Ch 3 Mandatory Publication List(UP-DATE)
2. Maritime Security Chart up-date
13.3.3 The security policy and related procedures are included in the internal audit Yes
programme.
The superintendent and internal auditors are checking the compliance of the implementation,
personal awareness and behaviour during internal audit or periodical ship visit according to the
company General inspection check list.
[Procedure]
1. SSP Ch.4.2 Ship security Assessment and Ship Security Audit
2. CSP Ch 8.2 Security Assessment and Security Audit
3. Code[109-407] General Inspection Check List
[Reference]
1. Result of General Inspection Check List
Stage 4
13.4.1 Assessments are undertaken of the company’s security measures and Yes
preparedness.
The Ship Security Plan is annually reviewed by the CSO and by SSO within his sea service.
The CSO is responsible for performing the security assessment of the company and ship, and if
necessary, can organize the assessment team.
The SSA shall be included the on scene survey and the result of SSA shall be documented.
[Procedure]
1. SSP Ch 4.1 SSA and Review
2. CSP Ch 8.1 Company and ship security assessment and review
[Reference]
1. Ship Security Assessment
2. Cyber Security risk assessment
[Reference]
1. Operation Guidance PS-MC-205-001(: Guideline on the safety measure against piracy
attack in High Risk Area)
2. PS-207 Ch.7 Armed Guards
3. Contract for the employment of security guards on vessels.
13.4.3 Vessels are provided with enhanced security and monitoring equipment. Yes
Hardening measure in place onboard the vessel
1. Fire hose, water jet
2. Razor wire in double layer
3. Lock external doors/hatches with additional locking device
4. Additional barrier for external ladders and windows
5. Citadel including additional mobile phone
13.4.4 Security enhancements are considered for inclusion in refit specifications and Yes
new-build design.
Example of the security enhancements which were reflected to the new-building ship.
-. Citadel
-. Bullet proof vest/Helmet
-. Night vision binoculars
-. Window Barricaded
[Reference]
1. I17 Vessel Hardening Plan(App.1 Vessel Specific Hardening Plan)
2. Additional Security Equipment
13.4.5 The company is involved in the testing and implementation of innovative Yes
security technology and systems.
The company has conducted several measures to improve security for IT system
1. System improvement(TOMAS)
2. Regular software up-grade including vaccine.
3. Regular inspection and monitoring by technician
4. Cyber Security Joint Research and Development(HLS-KR)
[Reference]
1. TOMAS capture
2. Service report
3. Cyber Security Joint Research and Development Plan