Sie sind auf Seite 1von 5

TECHNO-ECONOMIC FEASIBILITY

STUDY OF ZERO LIQUID DISCHARGE

Treatment of industrial wastewater has received


steadily increasing attention across the world. During
manufacturing, wastewater get generated at various
stages which are very complex in nature and highly
variable in quantity & quality. Unless & until we adopt a
DR. MRITUNJAY CHAUBEY structured approach towards collection, segregation &
treatment, it is difficult to achieve desired results.
There are several methods available for the treatment
ABSTRACT of wastewater. These may be classified into two categories
Zero liquid discharge (ZLD) is a wastewater : to meet the discharge norms and to meet the ZLD
management technique that eliminates liquid waste norms. In this paper, we have done comparative techno-
discharge going outside of operating plants. This has economic feasibility study for 2.5 MLD capacity effluent
attracted renewed interest worldwide in recent years. treatment plant (ETP) to meet the standard discharge
The concept of establishment of ZLD may be good norms and to meet ZLD norms based on environmental
but it cannot be generalized and implemented hastily parameters considering power consumption, CO2
and uniformly over the entire country as it emits more emission, solid waste generation and chemical
carbon leading to global warming and generate huge consumption and economic parameters considering
amount of hazardous solid waste occupying more capital expenditure and operational expenditure.

2
landfill land. Further ZLD also requires high operation
and maintenance cost for its execution and running. METHODOLOGY
In this paper, we have done comparative techno- Wastewater quantity, characteristics & treatment
economic feasibility study for 2.5 MLD capacity effluent scheme are described below:
treatment plant (ETP) to meet the standard discharge
norms and to meet ZLD norms based on environmental 2.1 WASTEWATER QUANTITY & CHARACTERISTICS
parameters considering power consumption, The wastewater treatment plant capacity considered
CO2 emission, solid waste generation & chemical in this case is 2.5 MLD. The untreated wastewater
consumption and economic parameters considering characteristics and treated wastewater characteristics are
capital expenditure & operational expenditure. shown in Table 1.
Implementation of ETP to meet ZLD norms will require
more land which may not be available with the industry 2.2 EFFLUENT TREATMENT SCHEME TO MEET STANDARD
within premises or in the adjoining area. Each state DISCHARGE NORMS
has its own uniqueness about its eco system and the The effluent treatment scheme to meet standard
environment. The disposal of treated effluent inside discharge norms is described below:
the Sea/Estuary is a better choice as huge dilution is A. Primary Treatment: The primary treatment consists
available and the impact on the marine eco system will of screening, equalization, neutralization, coagulation,
be minimum. flash mixing, flocculation and primary clarification for
removal of suspended particles and some organic

1
impurities.
INTRODUCTION B. Secondary Treatment: The secondary treatment
Zero liquid discharge is a wastewater management consists of activated sludge process where effluent
system that ensures that there will be no discharge will be received after primary treatment. In secondary
of industrial wastewater into the environment. It is treatment biological process take place for removal of
achieved by treating wastewater through recycling and organic impurities and further secondary clarification
then recovery and reuse for industrial purpose. Hence ZLD for solid impurities removal.
is a cycle of closed loop with no discharge. C. Sludge Dewatering: The Sludge dewatering technology

26 z CHEMICAL NEWS MARCH 2020


TABLE 1: UNTREATED WASTEWATER CHARACTERISTICS AND TREATED WASTEWATER CHARACTERISTICS
SR. NO. PARAMETERS UNIT UNTREATED WASTEWATER TREATED WASTEWATER CHARACTERISTICS
CHARACTERISTICS TO MEET DISCHARGE NORMS
1 PH - 1.5 to 11 6.5 to 7.5
2 COD mg/l 2000 to 5000 <250
3 BOD mg/l 500 to 2500 <100
4 Total Suspended Solids mg/l 50 to 300 <100
5 Total Dissolved Solids mg/l 2000 - 13500 NA
6 Oil and Grease mg/l Less than 10 <10
7 Ammoniacal Nitrogen mg/l 50 to 100 <50

will be implemented for removal of moisture / excess B. Secondary Treatment: The secondary treatment
water from sludge and collected water will be sent to consists of activated sludge process where effluent
equalization tank for further treatment. The dried Cake will be received after primary treatment. In secondary
sludge will be sent to authorized land filling site for treatment biological process occurred for removal of
disposal. organic impurities and further secondary clarification
The treated effluent discharged into Sea/Estuary for solid impurities removal.
directly or by CETP meeting the standard discharge C. Sludge Dewatering: The Sludge dewatering technology
norms. The effluent treatment scheme to meet standard will be implemented for removal of moisture / excess
discharge norms is given in Figure 1. water from sludge and collected water will be sent to
equalization tank for further treatment. The dried Cake
2.3 EFFLUENT TREATMENT SCHEME TO MEET ZERO sludge will be sent to authorized land filling site for
LIQUID DISCHARGE NORMS disposal.
The effluent treatment scheme to meet zero liquid D. Tertiary Treatment: The tertiary treatment consists of
discharge norms is described below: removal of residual organic, TSS & backwash water by
A. Primary Treatment: The primary treatment consists Tertiary clarifier, Filter Media and further treatment by
of screening, equalization, neutralization, coagulation, UF & RO for maximum wastewater recycling then RO
flash mixing, flocculation and primary clarification for reject will be sent to MEE and further ATFD to achieve
removal of suspended particles and some organic the Zero Liquid Discharge norms. Condensate from both
impurities. MEE & ATFD will be sent to Tertiary clarifier tank. RO

FIGURE – 1: PROCESS FLOW DIAGRAM FOR ETP TO MEET THE STANDARD DISCHARGE NORMS.

Incoming
Raw Effluent Primary
Equalisation Flash Mixing Flocculation
Clarification

Supernatant
Line

Sludge Sludge Holding Sludge


Dewatering Tank

Sludge for
Disposal

Treated Effluent Secondary Aeration


Discharge To CETP Clarification

Return Activated Sludge

CHEMICAL NEWS MARCH 2020 z 27


FIGURE – 2: PROCESS FLOW DIAGRAM FOR ETP TO MEET ZLD NORMS
Incoming
Raw Effluent
Equalisation Flash Primary
Mixing Flocculation Clarification Aeration Secondary
Clarification

Supernatant Line

Sludge Circulation
Sludge Sludge Sludge Wasting
Sludge For Disposal
Dewatering Holdering Tank

Condensate & Back Wash Water Line Clarified


Water Tank

UF Filtered Water Tertiary


UF Systems ACF PSF
Permeate Tank Clarification
Tank

Back Wash Feed Line

Feed Flow
R.O
Reverse Osmosis (R.O) Permeate For Process Uses Back Wash
Tank
Permeate

MEE
RO Reject

Condensate Water
Salt For Disposal

TABLE 2: TECHNO-ECONOMIC FEASIBILITY STUDY OF 2.5 MLD ZLD PLANT.


PARAMETERS UNIT OF ETP TO MEET ETP TO MEET DIFFERENCE
MEASUREMENT DISCHARGE NORMS ZLD NORMS
Power Consumption KW/Day 7740 30760 4 times higher power consumption in ZLD
CO2 Emission Tons/Day 6.3 25.2 4 times higher CO2 emission in ZLD
Solid Waste Generation Tons/Day 30 61 2 times higher waste generation in ZLD
Chemical Consumption Kg/Day 1160 2626 2 times higher chemical consumption in ZLD
Capital Cost INR in Crore 40 100 2.5 times higher capital cost in ZLD
Operational Cost INR/KL 500 1500 3 times higher operating cost in ZLD

permeate will be used in Cooling tower & other Process. parameters we have considered power consumption,
The dried Salt solid waste will be sent to authorized land CO2 emission, solid waste generation and chemical
filling site for disposal. The effluent treatment scheme consumption.
to meet ZLD norms is given in Figure 2. z Economic Parameters : Under economic parameters

3
we have considered capital expenditure and
RESULTS AND DISCUSSION operational expenditure.
Techno-Economic feasibility study of zero liquid
discharge plant has been done based on following The results of our techno-economic evaluation to meet
parameters: discharge norms and to meet ZLD norms are tabulated
z Environmental Parameters : Under environmental under Table 2.

28 z CHEMICAL NEWS MARCH 2020


FIGURE 3: ENVIRONMENTAL FEASIBILITY OF ZERO LIQUID DISCHARGE PLANT

Power Consumption Solid Waste Generation


35000 70
30760 61
30000 60
25000 50

TONS / DAY
KW / DAY

20000 40
30
15000 30
10000 7740 20
5000 10
0 0
ETP to meet Discharge norms ETP to meet ZLD norms ETP to meet Discharge norms ETP to meet ZLD norms

CO2 Emission Chemical Consumption


30 3000
25.2 2626
25 2500

20 2000
TONS / DAY

KG / DAY

15 1500
1160
10 1000
6.3
5 500

0 0
ETP to meet Discharge norms ETP to meet ZLD norms ETP to meet Discharge norms ETP to meet ZLD norms

3.1 ENVIRONMENTAL FEASIBILITY Paris agreement on climate change has identified


Under environmental feasibility, we have calculated the CO2 emissions as one of biggest root cause for
power consumption, CO2 emission, solid waste generation global warming hence this is responsibility of world
& chemical consumption. It has been found that power communities to reduce CO2 emissions. The concept
consumption & CO2 emission to meet ZLD norms are 4 of establishment of ZLD may be good but it cannot be
times higher than to meet the standard discharge norms. generalized and implemented hastily and uniformly
It has been also found that solid waste generation & over the entire country as it is emits more carbon
chemical consumption to meet ZLD norms are 2 times leading to global warming and generate huge amount of
higher than to meet the standard discharge norms. Power hazardous solid waste occupying more land fill land.
consumption, CO2 emission, solid waste generation and
chemical consumption to meet discharge norms as well as 3.2 ECONOMIC FEASIBILITY
to meet the ZLD norms are shown in Figure 3. Under economic feasibility, we have calculated the

Paris agreement on climate change has identified CO2 emissions as one of biggest
root cause for global warming hence this is responsibility of world communities
to reduce CO2 emissions. The concept of establishment of ZLD may be good but
it cannot be generalized and implemented hastily and uniformly over the entire
country as it is emits more carbon leading to global warming and generate huge
amount of hazardous solid waste occupying more land fill land.

CHEMICAL NEWS MARCH 2020 z 29


FIGURE 4: ECONOMIC FEASIBILITY OF ZERO LIQUID DISCHARGE PLANT

Capital Cost Operational Cost


120 1600
1500
100 1400
100
1200
INR IN CRORES

80
1000

INR / KL
60 800
40 600
40 500
400
20 200

0 0
ETP to meet Discharge norms ETP to meet ZLD norms ETP to meet Discharge norms ETP to meet ZLD norms

capital cost & operational cost. It has been found that treatment plant to meet standard discharge norms
capital cost to meet ZLD norms are 2.5 times higher than where Sea/Estuary discharge possible with below control
to meet the standard discharge norms. It has been also measures.
found that operational cost to meet ZLD norms are 3 z Target to reduce the fresh water consumption
times higher than to meet the standard discharge norms. & effluent generation with latest sustainable
Capital cost and operational cost to meet discharge technologies.
norms as well as to meet the ZLD norms are shown in z Implement effluent stream identification,
Figure 4. characterization & segregation at sources for better

4
effluent management & treatment.
SUMMARY AND CONCLUSION z Implement latest & advance technologies for
Zero Liquid Discharge is not an environmental maximum recycling of treated wastewater to reduce
friendly technique specially in costal area due to quantity of treated effluent discharge.
following reasons:
z 4 times higher power consumption in ZLD. REFERENCES
z 4 times higher CO2 emission in ZLD. 1. American Public Health Association. 1985.Standard Methods for
the Examination of Wastewater (16th edition). APHA, AWWA, WPCE,
z 2 times higher waste generation in ZLD. Washington, DC.
z 2 times higher chemical consumption in ZLD. 2. Birdi, G. S. and Birdi, J.S.. 1988. Water Supply and Sanitary
z 2.5 times higher capital cost in ZLD. Engineering. Dhanpat Rai Publishing Company, New Delhi.
z 3 times higher operating cost in ZLD. 3. Chaubey, Mritunjay. 2002. Computer Design of Wastewater Treatment
Implementation of ETP to meet ZLD norms will Plant Using Fixed Film Bioreactor Technology. Journal of Industrial
require more land which may not available with the Pollution Control, Vol. 18 (1), pp 107 – 117.
industry within premises or in the adjoining area. Each 4. Chaubey, Mritunjay and Kaushika, N. D. 2003. Performance Analysis
of Fixed Film Bioreactor Plants For Wastewater Treatment. Journal of
state has its own uniqueness about its eco system and Industrial Pollution Control, Vol.19 (2), pp.203 – 213.
the environment. The disposal of treated effluent inside
5. Kaushika, N. D. and Chaubey, Mritunjay. 2002. Energy Efficiency in
the Sea/Estuary is a better choice as huge dilution is Wastewater Treatment Plants. Environmental Pollution Control Journal .
available and the impact on the marine eco system will 6. Metcalf and Eddy. 1979. Wastewater Engineering. Tata Mc.Graw Hill,
be minimum. New Delhi.
Considering above adverse impact of ZLD on 7. Rudolfs, W. 1953. Tndustrial Waste Treatment. Reinhold Publishing
environment, it has been suggested to implement effluent Corp. , New York.

ABOUT THE AUTHOR: DR. MRITUNJAY CHAUBEY is sustainability, environment & water technology expert of international repute. He has done Ph.D.
in environmental engineering from Indian Institute of Technology (IIT) Delhi. He has nearly 23- years of professional working experience in renowned
MNCs Pentair, Shell, Unilever & UPL in field of sustainability, environmental engineering, water & wastewater treatment. Currently more than 100
environmental protection technologies are successfully working in Asia, Africa, Europe and America designed by him. More than 50 technical papers
has been published in renowned international journals & conferences with his name.
Dr. Chaubey is currently working as Global Vice President – Environment, Sustainability & Green Cell with UPL Limited. Recently Dr. Chaubey is awarded
with “Most Influential Sustainability Leader Award” and “CSO of the Year Award”.
E-mail : mritunjay.chaubey@upl-ltd.com

30 z CHEMICAL NEWS MARCH 2020

Das könnte Ihnen auch gefallen