Doc. Title M ethod Statement of Painting W ork TOA-TOYO JOINT VENTURE
CONTENT
1. Purpose Page 3
2. Scope of Work Page 3
Appendix 1-2
Page 2
Doc. Title M ethod Statement of Painting W ork TOA-TOYO JOINT VENTURE
1. PURPOSE
The Purpose of this Method Statement is to describe the process of painting works for exterior
and interior emulsion paint in compliance with all the required specifications, standards, and
proper construction procedures for the building finishing works of the project.
2. SCOPE OF WORK
The scope of work for the construction of the items are as follows :
Supply, rub down and apply emulsion paint for plastered surface (Exterior)
Supply, rub down and apply emulsion paint for plastered surface (Interior)
4. SHOP DRAWING
Shop drawings shall be submitted to the Engineer by separated document for review and
approval before carrying out the works.
5. WORK PROCEDURE
5.1. General Flow Chart
Surface preparation
Applying Skimcoat
Thickness Checking
Dry Surface
Finishing Coat (Layer 1)
Surface preparation
Cement mortar surfaces to be painted shall be dry and prepared by removing dust, dirt,
grease, oil, efflorescence and any other substance
For imperfect surfaces with cavities, tiny holes, can use Matex Putty for making smooth
surfaces
Applying Skimcoat
Use Skimcoat for mastic
Mix 1 bag of skimcoat with 16 liters of water
Use mixing machine of appropriate machine to mix in 3 minutes to get a unified admixture
Wait for 10 minutes, stir again by mixing machine then apply mastic within 2 hours
Apply first layer on prepared surfaces to 0.8 – 1mm wet layer thickness ( 0.5 - 0.6mm thick
after dried)
Wait till dry within 16 hours at 300C or when mastic layer is firmed then apply second layer
with method same as previous one.
Dry surface
Minimum drying time : 16 hours at 250C
Confirm Surface
Use appropriate device for checking to make sure dried surface meet the required thickness
is not greater than 1mm
Surface must be dry and firm
Surface Grinding
Use sandpaper to grind coated surface to make a smooth and fine surface
Apply Sealer
Dilute sealer with 5% of water if necessary.
Stir up within 3 minutes
Apply sealer paint on grinding surface by paint roller to get 100±3 microns wet face
thickness (dry face thickness approx. 35±3 microns)
Wait 2 hour at 300C before applying finishing coat.
Thickness checking
Use Elcometer device to check, ensure the required dry face thickness (35±3 microns) to
prevent foreign object and increase bond between painting layers
Finishing Coat – Layer 1
Page 4
Doc. Title M ethod Statement of Painting W ork TOA-TOYO JOINT VENTURE
6. QUALITY CONTROL
6.1. Inspection and Testing Plan
Before start Painting, Inspection and Testing Plan shall be established to keep proper quality
of the works in accordance with specification and standard. ITP shall be submitted to the
Engineer for approval.
6.2. Delivery Inspection
After deliver the materials to the site, delivery inspection shall be conducted with witnessed by
the Engineer. Frequency of delivery inspection shall be indicated in the ITP.
6.3. Thickness measurement :
Thickness of painted layer can be check be Elcometer device.
7. SAFETY CONTROL
7.1. Fundamental Policy
“Safety is the First Priority"
7.2. Key Activities
Implementation of Safety & Health Education
Prevention of Human Error and Machinery Accidents
7.3. Development and implementation of Activity
Implementation of Safety & Health Education
Pick up hazardous factors of each work activity and always reflect them at the safety
meetings.
Page 5
Doc. Title M ethod Statement of Painting W ork TOA-TOYO JOINT VENTURE
7.4. Point out them every day at the meetings in order to let individual worker to renovate his safety
consciousness
Prevention of Human Error and Machinery Accidents
Be consistent with inspection at beginning of works, regular maintenance of working
platform, machinery tools designation of working area.
7.5. Others
Safety signboards and barricades shall be installed around working area if necessary.
Security guard should observe all passengers around the site.
MSDS must be prepared before carry out painting work.
Page 6
Doc. Title M ethod Statement of Painting W ork TOA-TOYO JOINT VENTURE
Appendix – 1
Inspection and Testing Plan
Page 7