Estimate No. M&A/2020-21/1 of Year 2020-21
Note: The entries against each item below should be made in accordance with the
classification prescribed in Appendix No. 4 CPWD Code
Name of Work Name of work- Estimate for minor repair at Directorate Office Building at
Block No. 10, SDA Complex, Kasumpti, Shimla
2701 80.800.11.00.27
Estimate framed by Junior Engineer(Hq), M&A Directorate, Central Water Commission, Shimla at a probable
cost of Rs. 1,66,000/- (Rupees one Lakh Sixty six Thousand) only.
REPORT
The estimate amounting to Rs. 1,66,000/- (Rupees one Lakh Sixty six Thousand) only. has been framed to cover
the probable expenditure on " minor repair of Directorate Office Building at Block No. 10, SDA Complex,
Kasumpti, Shimla".
For preparation of Estimate, Quantities have been workout from actual measurement of office building, Rates
have been taken from the DSR 2012, with a cost index of 138%. Contingencies @5% has been included in the
estimate.
Prepared By
(Rajat Sharma)
JE(HQ)
Recommended for Technial sanction for Rs. 1,66,000/- (Rupees one Lakh Sixty six Thousand) only.
(Manoj Kumar)
Deputy. Director
Technially and financially sanctioned for Rs. 1,66,000/- (Rupees one Lakh Sixty six Thousand) only.
(O. P. Gupta)
Director
State : Central Division: M&A Directorate, CWC, Shimla
Bill of Quantities
Name of work- Estimate for minor repair at Directorate Office Building at Block No. 10, SDA Complex, Kasumpti, Shimla
2
21.3.2 With float glass panes of 5.50 mm
thickness
90% of Area 1.43 2.9 3.73 m2
3 0…..
a Horizontal Pannels
top 1.7 0.6 1.02 m2
bottom 1.7 0.6 1.02 m2
Center 1.7 0.6 1.02 m2
Vertical Pannels
Along wall 1.7 0.90 1.53 m2
parallel to wall 1.7 0.90 1.53 m2
Support Pannels 4 0.6 0.9 2.16 m2
Total for a 8.28 m2
b Horizontal Pannels
top 0.8 0.6 0.48 m2
bottom 0.8 0.6 0.48 m2
Vertical Pannels
Along wall 0.8 0.9 0.72 m2
parallel to wall 0.8 0.9 0.72 m2
Support Pannels 2 0.6 0.9 1.08 m2
Total for b 3.48 m2
c Horizontal Pannels
top 1.5 0.5 0.75 m2
bottom 1.5 0.5 0.75 m2
Center 1.5 0.5 0.75 m2
Vertical Pannels
Along wall 1.5 0.90 1.35 m2
parallel to wall 1.5 0.90 1.35 m2
Support Pannels 4 0.5 0.90 1.8 m2
Total for a 6.75 m2
9
Grill outside 1.5 2.5 3.75 m2
Estimate
Name of work- Estimate for minor repair at Directorate Office Building at Block No. 10, SDA Complex, Kasumpti, Shimla
2
21.3.2 With float glass panes of 5.50 mm thickness
m2 3.73 905.75 3380.53
Providing and fixing white vitreous china flat back half stall
urinal of including painting of fittings and cutting and making
good the walls and floors wherever require size 580x380x350
mm with white PVC automatic flushing cistern, with fittings,
standard size C.P. brass flush pipe, spreaders with unions
and clamps (all in C.P. brass) with waste fitting as per IS :
2556, C.I. trap with outlet grating and other couplings in C.P.
10 brass,
17.5.1 Single half stall urinal with 5 litre P.V.C. automatic
flushing cistern No. 1 5,354.50 5354.50
12
21.3.3 With float glass panes of 8 mm thickness m2 1.50 1227.8 1841.70
Wiring for light point/ fan point/ exhaust fan point/ call bell
point with 1.5 sq.mm FRLS PVC insulated copper conductor
single core cable in surface / recessed steel conduit, with
piano type switch, phenolic laminated sheet, suitable size
MS box and earthing the point with 1.5 sq.mm FRLS PVC
16 insulated copper conductor single core cable etc. as required.
1.1.3 Group C Point 3.00 1189 3567.00
TOTAL 109699.60
Cost Index @ 38% (Excluding item-No-4,16) 31780.39
Total 141479.99
Contingency @5% 7074.00
Total 148553.99
GST @ 12 % 17826.48
Total 166380.46
Say 166000.00
State : Central Division: M&A Directorate, CWC, Shimla
Rate Analysis
Name of work- Estimate for minor repair at office of Directorate Office Building at Block No. 10, SDA
Complex, Kasumpti, Shimla
Financial Year : 2020-21
No. 10, SDA Complex, Kasumpti, Shimla
Providing and fixing Modern HDHMR Bathroom Vanity Unit with a jaguar Lyric Single Lever
Basin Mixer pillar taps, complete
3
a Modern HDHMR Bathroom Vanity Unit each 1 15000 15000
Jaquar Lyric Single Lever Basin Mixer for Bathroom
b Fittings each 1 3600 3600
c C.P. brass waste 32 mm each 1 55 55
d C.I. bracket for wash basin and sinks each 1 53 53
e Red lead, white lead and gasket L.S. 16.12 1.49 24.0
f Cement, sand and grit etc. L.S. 13.39 1.49 20.0
g Painting of brackets, fittings etc L.S. 26.91 1.49 40.1
h Carriage of materials L.S. 13.52 1.49 20.1
LABOUR:
Fitter (grade 1) each 0.33 301 99.3
Mason (brick layer) 1 st class each 0.33 301 99.3
Beldar each 0.67 247 165.5
TOTAL 19176.4
Cost Index @ 38% (c to h) 219.02
TOTAL 19395.38
Add Water Charges @ 1% 193.95
TOTAL 19589.33
Add CPOH @ 15% 2938.40
Cost of each 22527.73
Round off total 22500
State : Central Division: M&A Directorate, CWC, Shimla
Rate Analysis
Name of work- Estimate for minor repair and water proofing of drainage system Directorate Office
Building at Block No. 10, SDA Complex, Kasumpti, Shimla
Financial Year : 2020-21
No. 10, SDA Complex, Kasumpti, Shimla
Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan)
1 with seat and lid, 10 litre combined and inbuild white vitreous china flushing cistern, including
flush pipe, with manually controlled device (handle lever), conforming to IS : 7231, with all
fittings and fixtures complete, including cutting and making good the walls and floors wherever
required:
W.C. pan with ISI marked white solid plastic seat and lid
Code No Description Unit Quantity Rate Amount
Details of cost for 1 pan
MATERIAL:
White Vitreous China Wash basin size 550x400 mm with a jaguar Lyric Single Lever Basin Mixer
pillar taps
Details of cost for one no. MATERIAL:
a Vitreous china flat back wash basin 550x400 each each 1 3000 3000
Jaquar Lyric Single Lever Basin Mixer for Bathroom
b Fittings each 1 3600 3600
c C.P. brass waste 32 mm each 1 55 55
d C.I. bracket for wash basin and sinks each 1 53 53
e Red lead, white lead and gasket L.S. 16.12 1.49 24.0
f Cement, sand and grit etc. L.S. 13.39 1.49 20.0
g Painting of brackets, fittings etc L.S. 26.91 1.49 40.1
h Carriage of materials L.S. 13.52 1.49 20.1
LABOUR:
Fitter (grade 1) each 0.33 301 99.3
Mason (brick layer) 1 st class each 0.33 301 99.3
Beldar each 0.67 247 165.5
TOTAL 7176.4
Cost Index @ 38% (c to h) 219.02
TOTAL 7395.38
Add Water Charges @ 1% 73.95
TOTAL 7469.33
Add CPOH @ 15% 1120.40
Cost of each 8589.73
Round off total 8600