PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.

5320248 AT DIC, DUBAI-UAE.

MONTHLY PROGRESS REPORT NO. 2

May 2020
for the month of April 2020

PROJECT: PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND


RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

M/S MANAR AL OMRAN SCAFFOLDING RENTALS

-Client-

M/S DESIGN HOUSE ENGINEERING CONSULTANCY


- Consultant-

M/S LOYAL BUILDING CONTRACTING L.L.C.


-Main Contractor-

1|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

TABLE OF CONTENTS

ITEM NO. DESCRIPTION PAGE NO.

1. Contract Particulars 03

2. Authority Approvals 05

3. Progress Summary & Schedule 07

4. Monthly Manpower/ Equipment 25

5. HSE Statistic summary 28

6. Payment/ Variation & Issue Details 31

7. Sub-contractor’s List 33

8. Site progress photos 35

9. Inspection Log 41

10. Procurement log 43

11. Test Report 51

12. Finishes Approval 79

2|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 1

CONTRACT PARTICULARS

3|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

PROJECT DETAILS

PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND


Project
RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

LOCATION PLOT NO. 5320248 @ DIC, DUBAI-UAE.

CLIENT M/S MANAR AL OMRAN SCAFFOLING RENTALS

CONSULTANT M/S DESIGN HOUSE ENGINEERING CONSULTANCY

MAIN CONTRACTOR M/S LOYAL BUILDING CONTRACTING L.L.C

CONTRACT VALUE AED. 18,800,000.00

COMMENCEMENT DATE 24th FEBRUARY 2020

PROJECT COMPLETION
25th NOVEMBER 2020 (FINAL BCC)
DATE

CONTRACT PERIOD 275 DAYS

4|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 2

AUTHORITY APPROVALS

5|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

AUTHORITY APPROVALS

Sl. Approved
Approvals & NOC’s Remarks
No. date
1. DEWA - Electrical NOC 08-07-2019 Approved

2. DU NOC 04-07-2019 Approved

3. DEWA-Water NOC 08-07-2019 Approved

4. Affection Plan 14-02-2019 Approved

5. Gate level 09-05-2019 Approved

6. Sewerage connection design review 28-08-2019 Approved

7. Land demarcation certificate 14-04-2019 Approved

8. Land re-demarcation certificate 24-02-2020 Approved

9. Mobilization Permit 23-02-2020 Approved

10. Building Permit 20-02-2020 Approved

11. Revised DDA drawing 10-03-2020 Approved

12. Trial pit NOC 09-04-2020 Approved

13. HV Approval 14-04-2020 Approved

14. DCD Approval 16-04-2020 Approved


DEWA – ELECTRICAL CONSTRUCTION
15. 14-04-2020 Approved
NOC
16. DU CONSTRUCTION NOC To be secure

17. RTA CONSTRUCTION NOC (ACCESS) To be secure

6|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 3

PROGRESS SUMMARY & SCHEDULE

7|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

WORK PROGRESS STATUS


as of April 2020

Project Commencement Date: 24th February 2020

Project Completion Date: 25th November 2020 (FINAL BCC)

% % Actual
Activity ID Activity Name
Completion Completion
AMS-2 Al Manar Scaffolding

AMS-2.1 Milestone / Key Dates for the project

MAN1000 Project Start 100 100

MAN1010 Substation Handover 0 0

MAN1020 DCD Wet Riser 0 0

MAN1030 DCD Final Inspection 0 0

MAN1040 DDA Inspection - Conditional BCC 0 0

MAN1050 Final BCC 0 0

MAN1060 LV First Inspection 0 0

MAN1070 LV Final Inspection 0 0

MAN1080 Taking over certificate 0 0

AMS-2.2 Mobilization

MAN1090 Mobilization 100 100

MAN1100 Mobilization Snag 100 100

MAN1110 Snag Inspection by Consultant 0 100

MAN1120 Snag Closure 0 100

AMS-2.9 Authority Submission

MAN1130 Machinery details from client 100 100

MAN1140 Electrical drawing preparation 100 100


Electrical drawing submission to consultant for
MAN1150 100 100
approval
MAN1160 Electrical drawing submission & approval from DEWA 100 100

8|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN1170 Substation Location Approval 100 100

MAN1180 Substation Handover 0 0

MAN1190 Transformer installation by DEWA 0 0

MAN1200 Furniture layout from consultant 0 0

MAN1210 DU Construction Drawing preparation 0 0

MAN1220 DU Construction NOC to Authority 0 0

MAN1230 DCD Drawing Preparation 100 100

MAN1240 DCD Drawing - Authority Submission 100 100

MAN1250 CCTV SIRA approved drawing from Consultant 0 0

AMS-2.4 PS & PC Items

MAN1260 CCTV & Access control - Nomination 0 100

MAN1270 CCTV & Access control - Consultant & Client Approval 0 0

MAN1280 Lift Nomination - Preparation 0 100

MAN1290 Lift - Consultant & Client Approval 0 0

MAN1300 Weigh Bridge (WB) Nomination - Preparation 100 100

MAN1310 Weigh Bridge (WB) - Consultant & Client Approval 79 0

MAN1320 Light Fitting & Fixtures Catalogue arrangement 0 100


Light Fitting & Fixtures Sample approval by Consultant
MAN1330 0 0
& Client
MAN1340 Light Fitting & Fixtures -Quotation Preparation 0 100
Light Fitting & Fixtures -Quotation Approval by
MAN1350 0 0
Consultant & Client
MAN1360 Sanitary Fitting & Fixtures Catalogue arrangement 0 100
Sanitary Fitting & Fixtures Sample approval by
MAN1370 0 0
Consultant & Client
MAN1380 Sanitary Fittings & Fixtures -Quotation Preparation 0 0

MAN1390 Sanitary -Quotation Approval by Consultant & Client 0 0

MAN1400 Signages Nomination 0 100

MAN1410 Signages approval by Consultant & Client 0 0

MAN1420 Kitchen Cabinet Nomination 0 100

9|P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN1430 Kitchen Cabinet - Consultant & Cllient Approval 0 0

MAN1440 Landscaping Nomination 0 100


Landscaping Nomination Approval by Consultant &
MAN1450 0 0
Client
MAN1460 Yard Announcement System - Details from Consultant 0 0

MAN1470 Yard Announcement System Nomination Preparation 0 0


Yard Announcement System -Consultant & Client
MAN1480 0 0
Approval
MAN1490 PC item - Sample arrangement 0 0

MAN1500 PC item approval by Client & Consultant 0 0

MAN1510 PC Item Quotation Preparation 0 0

MAN1520 PC Item Quotation Approval 0 0

AMS-2.5 Prequalification(PQ), Material Submittal(MS) & Procurement


UPVC Drainage Pipe & Fittings, UPVC Pressure Pipe &
MAN1530 100 100
Fittings, PEX & PPR - MS Submission
UPVC Drainage Pipe & Fittings, UPVC Pressure Pipe &
MAN1540 100 100
Fittings, PEX & PPR - Consultant Approval
MAN1550 PVC Water Stopper, Bitumen Protection Sheet - MS 100 100
PVC Water Stopper, Bitumen Protection Sheet -
MAN1560 100 100
Consultant Approval
MAN1570 Bitumen Torch & Protection Board - MS & PQ 100 100
Bitumen Torch & Protection Board - Consultant
MAN1580 0 100
Approval
MAN1590 GRP Lining - MS & PQ 100 100

MAN1600 GRP Lining - Consultant Approval 0 0

MAN1610 Sectional Door PQ Submission 100 100

MAN1620 Sectional Door PQ - Consultant Approval 0 0

MAN1630 Firefighting MS & PQ 100 100

MAN1640 Firefighting MS & PQ - Consultant Approval 100 0

MAN1650 Pump Procurement & Delivery 11 0

MAN1660 Cladding PQ Submission 100 100

MAN1670 Cladding Color Approval 100 0

MAN1680 Mast Light - PQ 100 0

10 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN1690 Mast Light - PQ - Consultant Approval 50 0

MAN1700 Mast Light - Procurement 0 0

MAN1710 Lift PQ 0 0

MAN1720 Lift - Consultant Approval 0 0

MAN1730 Lift Procurement 0 0

MAN1740 Doors & Windows - PQ 0 0

MAN1750 Door & Window - Consultant Approval 0 0

MAN1760 Fire Exit Door - PQ 0 100

MAN1770 Fire Exit Door - Cosultant Approval 0 0

MAN1780 Gate Barrier - MS & PQ 0 0

MAN1790 Gate Barrier - Consultant Approval 0 0

MAN1800 Gate Barrier Procurement & Delivery 0 0

MAN1810 Sectional Door - Procurement & Delivery 0 0

MAN1820 Wet Area Water Proofing - MS & PQ 0 0

MAN1830 Wet Area Water Proofing - Consultant Approval 0 0

MAN1840 Light Fixtures & Fittings - Procurement 0 0

MAN1850 Weigh Bridge (WB) - PQ 0 0

MAN1860 Weigh Bridge (WB) - PQ - Consultant Approval 0 0

MAN1870 Weigh Bridge - Procurement 0 0

MAN1880 Sanitary Fixtures & Fittings - Procurement 0 0

MAN1890 Signages Procurement 0 0

MAN1900 Kitchen Cabinet - Procurement 0 0

MAN1910 Yard Announcement System - Procurement 0 0

MAN1920 Roof Water Proofing - MS & PQ 0 0

MAN1930 Roof Water Proofing - Consultant Approval 0 0

MAN1940 GRP Water Tank - MS & PQ 0 0

MAN1950 GRP Water Tank - Consultant Approval 0 0

11 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN1960 GRP Water Tank - Procurement & Delivery 0 0
HVAC & Electrical Material Submittal &
MAN1970 100 0
Prequalification
HVAC & Electrical Material Submittal &
MAN1980 0 0
Prequalification - Consultant Approval
MAN1990 Tile & False Ceiling Procurement 0 0

MAN2000 Cladding Procurement & Delivery 0 0

MAN2010 Door & Window - Procurement 0 0

MAN2020 Fire Exit Door - Procurement 0 0

AMS-2.6 Shop Drawing Submission to Consultant

MAN2030 Plumbing - SD Preparation 100 80

MAN2040 Fire Protection - SD - Preparation 38 100

MAN2050 Fire Protection - SD -Consultant Approval 0 0

MAN2060 Weigh Bridge - SD 0 0

MAN2070 Weigh Bridge SD - Consultant Approval 0 0

MAN2080 AC Unit Procurement 0 0

MAN2090 HVAC - SD - Preparation 0 100

MAN2100 HVAC - SD - Consultant Approval 0 0

MAN2110 Cladding SD Preparation 47 0

MAN2120 Cladding Consultant Approval 0 0

MAN2130 Grade Slab & Machine Foundation SD 0 0


Grade Slab & Machine Foundation Consultant
MAN2140 0 0
Approval
MAN2150 Lift SD 0 0

MAN2160 Lift SD Consultant Approval 0 0

MAN2170 Lift Finishes 0 0

MAN2180 Lift Finishes Approval by Client & Consultant 0 0

MAN2190 Doors & Windows SD Preparation 0 0

MAN2200 Doors & Windows SD Consultant Approval 0 0

MAN2210 Sectional Door - SD Preparation 0 0

12 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN2220 Sectional Door - SD Consultant Approval 0 0

MAN2230 Weigh Bridge SD Preparation 0 0

MAN2240 Fire Exit Door SD - Preparation 0 0

MAN2250 Fire Exir Door - SD - Consultant Approval 0 0

AMS-2.7 Boundary Wall

AMS-2.8 Elevation D

AMS-2.8.1 Substructure

MAN2260 Excavation 100 100

MAN2270 Levelling, Compaction & PCC 100 100

MAN2280 Footing 100 100

MAN2290 PCC For Plinth Beam 100 100

MAN2300 Blockwork For Plinth Beam 100 100

MAN2310 Plinth beam & Pedestal 100 100

MAN2320 Antitermite, Curing, Bitumen Application & Backfilling 100 100

AMS-2.8.2 Superstructure

MAN2330 Column 69 50

MAN2340 Blockwork 26 100

MAN2350 Coping Beam 0 0

MAN2360 Plastering 0 0

AMS-2.38 Elevation C

AMS-2.38.1 Substructure

MAN2370 Excavation 100 100

MAN2380 Levelling, Compaction & PCC 100 100

MAN2390 Footing 70 100

MAN2400 PCC For Plinth Beam 46 100

MAN2410 Blockwork For Plinth Beam 0 100

MAN2420 Plinth beam & Pedestal 0 70

13 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN2430 Antiternite, Curing, Bitumen Application & Backfilling 29 60

AMS-2.38.2 Superstructure

MAN2440 Column 0 0

MAN2450 Blockwork 0 0

MAN2460 Coping Beam 0 0

MAN2470 Plastering 0 0

AMS-2.39 Elevation A & 8

AMS-2.39.1 Substructure

MAN2480 Excavation 100 100

MAN2490 Levelling, Compaction & PCC 100 100

MAN2500 Footing 55 100

MAN2510 PCC For Plinth Beam 35 100

MAN2520 Blockwork For Plinth Beam 0 100

MAN2530 Plinth beam & Pedestal 0 30

MAN2540 Antitermite, Curing, Bitumen Application & Backfilling 25 60

AMS-2.39.2 Superstructure

MAN2550 Column 0 0

MAN2560 Blockwork 0 0

MAN2570 Coping Beam 0 0

MAN2580 Plastering 0 0

AMS-2.40 Elevation E & F

AMS-2.40.1 Substructure

MAN2590 Excavation 0 100

MAN2600 Levelling, Compaction & PCC 0 100

MAN2610 Footing 0 100

MAN2620 PCC For Plinth Beam 0 100

MAN2630 Blockwork For Plinth Beam 0 100

14 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN2640 Plinth beam & Pedestal 0 60

MAN2650 Antiternite, Curing, Bitumen Application & Backfilling 0 60

AMS-2.40.2 Superstructure

MAN2660 Column 0 50

MAN2670 Blockwork 0 60

MAN2680 Coping Beam 0 50

MAN2690 Plastering 0 0

AMS-2.41 Elevation G & H

AMS-2.41.1 Substructure

MAN2700 Excavation 0 70

MAN2710 Levelling, Compaction & PCC 0 70

MAN2720 Footing 0 70

MAN2730 PCC For Plinth Beam 0 70

MAN2740 Blockwork For Plinth Beam 0 70

MAN2750 Plinth beam & Pedestal 0 0

MAN2760 Antiternite, Curing, Bitumen Application & Backfilling 0 50

AMS-2.41.2 Superstructure

MAN2770 Column 0 0

MAN2780 Blockwork 0 0

MAN2790 Coping Beam 0 0

MAN2800 Plastering 0 0

AMS-2.37 Elevation J

AMS-2.37.1 Substructure

MAN2810 Excavation 100 100

MAN2820 Levelling, Compaction & PCC 100 100

MAN2830 Footing 100 100

MAN2840 PCC For Plinth Beam 100 100

15 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN2850 Blockwork For Plinth Beam 100 100

MAN2860 Plinth beam & Pedestal 39 100

MAN2870 Antiternite, Curing, Bitumen Application & Backfilling 57 100

AMS-2.37.2 Superstructure

MAN2880 Column 0 30

MAN2890 Blockwork 0 100

MAN2900 Coping Beam 0 0

MAN2910 Plastering 0 0

AMS-2.42 Substation (SS) & LV

AMS-2.42.1 Substructure

MAN2920 Excavation 100 100

MAN2930 Levelling & Compaction 0 50

MAN2940 Antitermite Treatment & PCC 0 0

MAN2950 Footing 0 0

MAN2960 PCC For Plinth Beam 0 0

MAN2970 Blockwork For Plinth Beam 0 0

MAN2980 Plinth beam & Pedestal 0 0

MAN2990 Curing, Bitumen Application & Backfilling 0 0

AMS-2.42.2 Superstructure

MAN3000 Column 0 0

MAN3010 Roof Beam & Slab 0 0

MAN3020 Grade slab & Trench 0 0

MAN3030 Blockwork 0 0

MAN3040 Plastering 0 0

MAN3050 Painting 0 0

AMS-2.43 Open Shed & Office

AMS-2.43.1 Substructure

16 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN3060 Excavation 100 100

MAN3070 Levelling, Compaction & PCC 100 100

MAN3080 Footing & Raft for Lift 100 100

MAN3090 PCC For Plinth Beam 25 100

MAN3100 Blockwork For Plinth Beam 0 100

MAN3110 Pedestal, Plinth Beam (Anchor Bolt) & Lift Wall 0 65

MAN3120 Antitermite, Curing, Bitumen & Backfilling 4 70

MAN3130 Delivery of steel structure 0 0

AMS-2.43.2 Superstructure

MAN3140 Erection 0 0

MAN3150 Erection Secondary Member 0 0

MAN3160 Decking Sheet & Decking Slab Casting 0 0

MAN3170 Cladding Installation 0 0

MAN3180 Flashing 0 0

MAN3190 Grade Slab Preparation 0 0

MAN3200 Grade slab & Machine Foundation Casting 0 0

MAN3210 Machinery Installation 0 0

MAN3220 Lift Core wall & Ramp 0 0

MAN3230 Lift Installation 0 0

MAN3240 Wall Footing & Block Work (Stiffner beam & Column) 0 0

MAN3250 RCC Slab 0 0

MAN3260 Encasement 0 0

MAN3270 Staircase Erection 0 0

MAN3280 Plastering - Interior 0 0

MAN3290 Vanity Counter 0 0

MAN3300 Wet Area Water Proofing 0 0

MAN3310 Plastering Exterior 0 0

17 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN3320 Wall & Floor Tile 0 0
Glass Partition, Aluminium Door & Window, Wooden
MAN3330 0 0
Door
MAN3340 Sectional Door 0 0

MAN3350 Fire Exit Door 0 0

MAN3360 False Ceiling (Entire Site) 0 0

MAN3370 Kitchen Cabinet Installation 0 0

MAN3380 Handrail 0 0

MAN3390 Painting 0 0

AMS-2.44 MEP

AMS-2.44.1 First Fix

MAN3400 UG Drainage & Water Supply 0 10

MAN3410 UG Electrical Sleeves & Conduits 0 0

AMS-2.44.3 Second Fix

MAN3420 Plumbing & Drainage Isolation Valve 0 0

MAN3430 HVAC Duct Works 0 0


Installation of Wire, DB Cable Tray, Trunking,
MAN3440 0 0
Telephone works
MAN3450 CCTV Conduiting & Cable Laying 0 0

AMS-2.44.2 Final Fix

MAN3460 Installation of AC Unit 0 0

MAN3470 Light Fittings 0 0

MAN3480 Sanitaryware 0 0

MAN3490 CCTV & Access Control & Equipments Fixing 0 0

AMS-2.45 Firefighting

AMS-2.45.1 First Fix

MAN3500 Installation Branch Pipe 0 0

MAN3510 Installation of Hydrant 0 0

AMS-2.45.2 Second Fix

18 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN3520 Installation of Firefighting Equipments & Main Line 0 0
Installation Fire protection branches & Insulation of
MAN3530 0 0
Pipes
AMS-2.45.3 Final Fix

MAN3540 Installation of Sprinkler Head 0 0

MAN3550 Fire pump installation 0 0

AMS-2.46 Asphalt Area

AMS-2.46.1 Storm Water Tank 3

MAN3560 Excavation 100 100

MAN3570 Levelling & Compaction 100 100

MAN3580 Antitermite Treatment 100 100

MAN3590 Base slab 100 100

MAN3600 Side Wall 100 100

MAN3610 Top Slab 100 50

MAN3620 Curing, Bitumen & Backfilling 91 70

AMS-2.46.2 Storm Water Tank 2

MAN3630 Excavation 100 100

MAN3640 Levelling & Compaction 100 100

MAN3650 Antitermite Treatment 100 100

MAN3660 Base slab 50 100

MAN3670 Side Wall 0 0

MAN3680 Top Slab 0 0

MAN3690 Curing, Bitumen & Backfilling 0 0

AMS-2.46.3 Storm Water Tank 1

MAN3700 Excavation 0 0

MAN3710 Levelling & Compaction 0 0

MAN3720 Antitermite Treatment 0 0

MAN3730 Base slab 0 0

19 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN3740 Side Wall 0 0

MAN3750 Top Slab 0 0

MAN3760 Curing, Bitumen & Backfilling 0 0

AMS-2.46.4 Holding Tank

MAN3770 Excavation 0 0

MAN3780 Levelling & Compaction 0 0

MAN3790 Antitermite Treatment 0 0

MAN3800 Base slab 0 0

MAN3810 Side Wall 0 0

MAN3820 Top Slab 0 0

MAN3830 Curing, Bitumen Torch, Protection Board & Backfilling 0 0

MAN3840 GRP Lining (All UG Tank) 0 0

AMS-2.46.47 Underground Works

AMS-2.46.47.1 Storm Water Line

MAN3850 Excavation 0 30

MAN3860 Levelling 0 30

MAN3870 UG Network 0 30

MAN3880 Manhole 0 20

AMS-2.46.47.2 Firefighting

MAN3890 Excavation 0 0

MAN3900 Levelling 0 0

MAN3910 UG Network 0 0

AMS-2.46.47.3 Mast Light

MAN3920 Mast Light Foundation 0 0

MAN3930 Mast Light Cabling Work 0 0

MAN3940 Mast Light Erection 0 0

MAN3950 Backfilling 0 0

20 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
AMS-2.46.47.4 Weigh Bridge

MAN3960 Excavation 0 0

MAN3970 Weigh Bridge (Civil work) 0 0

MAN3980 Curing, Bitumen Application & Backfilling 0 0

MAN3990 Weigh Bridge Installation 0 0

AMS-2.46.6 Asphalt Work

MAN4000 Preparation, Levelling & Compaction 0 40

MAN4010 Road base & Compaction 0 0

MAN4020 Laying of Asphalt 0 0

MAN4030 Kerbstone Preparation & Laying 0 0

AMS-2.47 Pump Room

AMS-2.47.1 Substructure

MAN4040 Excavation 0 0

MAN4050 Levelling & Compaction 0 0

MAN4060 Antitermite Treatment & PCC 0 0

MAN4070 Footing 0 0

MAN4080 PCC For Plinth Beam 0 0

MAN4090 Blockwork For Plinth Beam 0 0

MAN4100 Plinth beam & Pedestal 0 0

MAN4110 Curing, Bitumen application & Backfilling 0 0

AMS-2.47.2 Superstructure

MAN4120 Column 0 0

MAN4130 Roof beam & Slab 0 0

MAN4140 Blockwork 0 0

MAN4150 Grade Slab 0 0

MAN4160 Plastering & Painting 0 0

MAN4170 Roof Cladding 0 0

21 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
AMS-2.48 Fire Water Tank

MAN4180 Excavation 0 0

MAN4190 Levelling, Compaction & Antitermite 0 0

MAN4200 Raft Casting & Bitumen Application 0 0

MAN4210 Tank installation 0 0

AMS-2.49 Guard Room & Weigh Bridge Office

AMS-2.49.1 Substructure

MAN4220 Excavation 0 0

MAN4230 Levelling, Compaction, Antitermite & PCC 0 0

MAN4240 Footing 0 0

MAN4250 PCC For Plinth Beam 0 0

MAN4260 Blockwork For Plinth Beam 0 0

MAN4270 Plinth beam & Pedestal 0 0

MAN4280 Curing, Bitumen application & Backfilling 0 0

AMS-2.49.2 Superstructure

MAN4290 Column 0 0

MAN4300 Roof beam & Slab 0 0

MAN4310 Blockwork 0 0

MAN4320 Grade Slab 0 0

MAN4330 Plastering 0 0

MAN4340 Tile Finishes 0 0

MAN4350 Painting 0 0

AMS-2.50 External

MAN4360 Covered Car Parking 0 0

MAN4370 Roof Water Proofing Work 0 0

MAN4380 Grill & Gate 0 0

MAN4390 Gate Barrier Installation 0 0

22 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

% % Actual
Activity ID Activity Name
Completion Completion
MAN4400 GRP Water Tank - Installation 0 0

MAN4410 Road Marking, Wheel Stoppers & Signage 0 0

MAN4420 Boundary Wall Painting 0 0

MAN4430 Interlock Preparation & Laying 0 0

MAN4440 Landscaping Work 0 0

MAN4450 Garbage Trolly 0 0

MAN4460 Yard Announcement System - Installation 0 0

MAN4470 Interlock Paving 0 0

AMS-2.52 Landscaping

MAN4480 Landscape work along Elevation C 0 0

MAN4490 Landscape work along Elevation B & A 0 0

MAN4500 Landscape work along Elevation G & H 0 0

AMS-2.53 Testing & Commossioning

MAN4510 Fire Protection System 0 0

MAN4520 HVAC 0 0

MAN4530 Sectional Door 0 0

MAN4540 Weigh Bridge & Lift 0 0

MAN4550 Electrical 0 0

MAN4560 Plumbing 0 0

MAN4570 Initial Snag - Completion 0 0

23 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

FORECAST
(01-05-2020 TO 31-05-2020)

Sl. % Planned
Activity
No. completion
01. Storm water 1& 2 – Top slab 

02. Substation – Column 

03. Boundary wall – Tie beam 

04. Openshed & Office – Tie beam 

05. Storm water - Network 

06. Erection 

07. Trial Trench 

08. Housekeeping 

24 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 4

MONTHLY MANPOWER/ EQUIPMENT

25 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

LIST OF RESOURCES

SR.NO. DESCRIPTION NO. / Day REMARKS

A STAFF

1. Project Manager 1

2.Project Engineer 1

3.Mechanical / Safety Manager 1

4.Site Manager - Electrical 1

5. Engineers (Site, Erection, MEP) 3

6. Safety Officer 1

7. Charge hand 3

8. Storekeeper 1

9. Document Controller 0

10. Office Boy 1

Total 13

B. WORKERS

1. Mason 10

2. Carpenter 15

3. Steel fixer 10

4. Plumber 5

5. Flag man 1

6. Helper 8

Total 49

C. EQUIPMENT

1. Generator 1

2. Excavator 1

3. Shovel 2

4. Roller Compactor- 1ton 1

5. Plate Compactor 1

6. Cutting & Bending Mach. 2

7. Backhoe Loader (JCB) 2

8.Skid Loader (BOBCAT) 0

9.Grinding machine 9” 2

10.Hand cutting machines 2

11.Drilling machine 2

26 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

12.Scissor Lift 0

13.Boom Lift 0

27 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 5

HSE STATISTIC SUMMARY

28 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

HSE STATISTIC SUMMARY

Project site M/s Manar Al Omran Month reported April 2020

Number of employees 49 Total man hours 8190

No of safety staff 1 Number of Engineers 4

Key performance indicators(KPIs) and monthly Metrics Number


(this month)
Fatality(FAT) 0

Lost time injury(LTI) 0

Medical treatment cases(MTC) 0

First aid cases(FAC) 3

Lost workdays(LW) 0

Occupational ill-health 0

Near miss(NM) 0

Incident -property damage 0

Incident –vehicle 0

Environmental incidents 0

Violation letter to workers 0

Violation letter to Sub- Contractor. 0

Safety observation reported(open) 10

Close-out safety observations(closed) 10

Non –conformance reported (NCR)(open) 2

Non-conformance reported(NCR)(closed) 2

Safety inspections 0

Safety Audits 0

Emergency drills conducted 0

Conducted (TBT)-weekly mass tool box 4

Employees Attended the site safety Orientation/ induction 20

29 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.
Brief summary of safety campaigns, activities and highlights.
Safety supervision & corrective actions related to irrigation landscaping work, electrical landscaping works,
hard landscaping work, installation of landscaping furniture & soft landscaping.

Weekly tool box meeting & daily site inspection conducted.

Prepared by: Mr. Mannu Eldose Approved by: Mr. Joshua Praveen

Designation: Safety Officer Designation: Mechanical / Safety Manager

30 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 6

PAYMENT/VARIATION & ISSUE


DETAILS

31 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

STATUS OF CONTRACTOR'S PAYMENT

TOTAL VALUE OF CONTRACT: DHS 18,800,000.00/-

INTERIM PAYMENT INVOICE GROSS CERTIFIED AMOUNT RECEIVED


VAT AMOUNT
CERTIFICATE REF & DATE AMOUNT AMOUNT RECEIVED DATE

Bill 1290
588,856.56 29,442.83 618,299.39 618,299.39 30/04/2020
No.1 30/03/2020

32 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 7

SUB-CONTRACTOR’S LIST

33 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

LIST OF SUB- CONTRACTORS

SL.NO. APPROVED SUB-CONTRACTORS ITEMS

1. M/S ROOFING MIDDLE EAST PEB

2. M/S ROOFING MIDDLE EAST CLADDING

3. M/S NEW JEWEL BUILDING CONTRACTING ASPHALT

4.

5.

6.

7.

8.

34 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 8

PROGRESS SITE PHOTOS

35 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

BOUNDARY WALL

36 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

BOUNDARY WALL

37 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

OFFICE & OPENSHED –


PLINTH BEAM

38 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

STORM WATER TANK &


SUBSTATION EXCAVATION

39 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

STORMWATER –
UNDERGROUND WORK

40 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 9

INSPECTION LOG

41 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

LOG SHEET FOR STRUCTURAL


INSPECTION (DDA)

INSPECTION
WORK INSPECTED STATUS
DATE

16/Mar/2020 Approved
Boundary wall – Footing – Grid 1 – 65 (Elevation D)

16/Mar/2020 Boundary wall – Footing – Grid 1 – 54 (Elevation J) Approved

18/Mar/2020 Boundary wall – Footing – Grid 5 – 31 (Elevation A)


Approved

18/Mar/2020 Boundary wall – Footing – Grid 2 – 51 (Elevation C)


Approved
Boundary wall – Footing – Grid 55 – 85 (Elevation J)
18/Mar/2020 Approved
Boundary wall – Footing – Grid 1 – 26 (Elevation B)
18/Mar/2020 Approved
Boundary wall – Footing – Grid 32 – 89 (Elevation A & C)
23/Mar/2020 Approved

23/Mar/2020 Boundary wall – Footing – Grid 52 – 67 (Elevation C)


Approved
Boundary wall – Footing – Grid 1 – 32 (Elevation E)
23/Mar/2020 Approved
Boundary wall – Footing – Grid 1 – 10 (Elevation F)
23/Mar/2020 Approved
Boundary wall – Footing – Grid 11 – 25(Elevation F)
26/Mar/2020 Approved
Boundary wall – Footing – Grid 1 – 25 (Elevation G )
26/Mar/2020 Approved
Storm water tank – 3 – Base slab
31/Mar/2020 Approved
Open shed & Office - Footing
07/Apr/2020 Approved
Storm water tank – 2 – Base slab
28/Apr/2020 Approved

42 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 10

PROCUREMENT LOG

43 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

MATERIAL SUBMITTAL LOG - (CIVIL MATERIALS) 3-May-20

REV-1

Sn Ref No. Material Description Manufacturer/ Supplier Approved/ Approved/ Status /


Submission Date Status / Remarks Submission Date
Comment Date Comment Date REMARKS

M/S SAQER AL MADEENA PEST


1 MAN-CIVIL-01 PROTHOR SC II TERMICIDE 1-Mar-20 7-Mar-20 APPROVED
CONTROL SERVICES

2 MAN-CIVIL-02 CONCRETE BLOCKS M/S UNIMIX BLOCK FACTORY 1-Mar-20 7-Mar-20 APPROVED

M/S DUPLAST GENERAL TRADING


3 MAN-CIVIL-03 POLYTHYEENE SHEET 1-Mar-20 7-Mar-20 APPROVED
LLC

4 MAN-CIVIL-04 JINDAL STEEL REBARS M/S UNION REBAR FACTORY 1-Mar-20 9-Mar-20 APPROVED

5 MAN-CIVIL-05 CONCRETE MIX DESIGN M/S UNION CEMENT PRODUCTS 2-Mar-20 APPROVED

6 MAN-CIVIL-06 READY MIX CONCRETE M/S UNION CEMENT PRODUCTS 3-Mar-20 7-Mar-20 APPROVED

M/S AL GURG BUILDING SERVICES


7 MAN-CIVIL-07 BRC Mesh 3-Mar-20 15-Mar-20 APPROVED
LLC
M/S HENKEL POLYBIT BUILDING MATERIALS REVISE &
8 MAN-CIVIL-08 POLYCOAT (BITUMEN PAINT) 3-Mar-20 7-Mar-20 14-Mar-20 15-Mar-20 APPROVED
TRAIDING LLC RESUBMIT

9 MAN-CIVIL-09 CEMENT M/S JABEL ALI CEMENT FACTORY 3-Mar-20 7-Mar-20 APPROVED

M/S ORYX MIX CONCRETE


10 MAN-CIVIL-10 READY MIX CONCRETE 5-Mar-20 7-Mar-20 APPROVED
MANUFACTURING LLC

11 MAN-CIVIL-11 PVC WATERSTOP M/S EMIRATES SPECIALITIES 14-Mar-20 19-Mar-20 APPROVED

AWAITING
12 MAN-CIVIL-12 GRP LAMINATIONS M/S POLAR PLASTIC FACTORY LLC 14-Mar-20
APPROVAL
SBS MODIFIED BITUMEN WATER PROOFING M/S HENKEL POLYBIT BUILDING MATERIALS
13 MAN-CIVIL-13 TRAIDING LLC
18-Mar-20 24-Mar-20 APPROVED
MEMBARANE
M/S HENKEL POLYBIT BUILDING MATERIALS
14 MAN-CIVIL-14 BITUMEN BOARD 18-Mar-20 24-Mar-20 APPROVED
TRAIDING LLC
M/S NEW JEWEL BUILDING
15 MAN-CIVIL-15 AC WEARING COARSE 1-Apr-20 6-Apr-20 APPROVED
CONTRACTING LLC
M/S NEW JEWEL BUILDING
16 MAN-CIVIL-16 AC BASE COARSE 1-Apr-20 5-Apr-20 APPROVED
CONTRACTING LLC

17 MAN-CIVIL-17 STEEL STRUCTURE PAINT M/S ROOFINNG MIDDLE EAST 19-Apr-20 27-Apr-20 APPROVED

18 MAN-CIVIL-18 CEMENT (ALTERNATIVE) M/S ULTRATECH CEMENT 18-Apr-20 21-Apr-20 APPROVED

AWAITING
19 MAN-CIVIL-19 REBAR (ALTERNATIVE) - JINDAL & HAMREIYAH M/S RAKMET 25-Apr-20
APPROVAL

44 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

MATERIAL SUBMITTAL LOG - (PRE QUALIFICATION & SUBCONTRACTOR SUBMITTALS)

REV-1
Sn Ref No. Work Description Subcontractor/ Supplier
Approved/ Status /
Submission Date Status / Remarks Submission Date Approved Date
Comment Date REMARKS

M/S SAQER AL MADEENA PEST CONTROL


1 MAN-PQ-01 ANTI TERMITE TREATMENT 1-Mar-20 7-Mar-20 APPROVED
SERVICES
M/S ORYX MIX CONCRETE MANUFACTURING
2 MAN-PQ-02 READY MIX CONCRETE 5-Mar-20 7-Mar-20 APPROVED
LLC
M/S GLOBAL SOIL TESTING
3 MAN-PQ-03 MATERIAL TESTING LABORATORY 14-Mar-20 24-Mar-20 APPROVED
LABORATORY
M/S HENKEL POLYBIT BUILDING MATERIALS
4 MAN-PQ-04 WATER PROOFING MEMBRANE (BITUMEN) 18-Mar-20 24-Mar-20 APPROVED
TRAIDING LLC
M/S NEW JEWEL BUILDING
5 MAN-PQ-05 ASPHALT 1-Apr-20 5-Apr-20 APPROVED
CONTRACTING LLC
M/S AFPA FIREFIGHTING & SAFETY AWAITING
6 MAN-PQ-06 FIRE PROTECTION SYSTEM 23-Apr-20
EQUIPMENT INSTALLATION LLC APPROVAL
M/S ALIGN ELECTROMECHANICAL AWAITING
7 MAN-PQ-07 FIRE WATER TANK 26-Apr-20
WORK LLC APPROVAL
AWAITING
8 MAN-PQ-08 SECTIONAL DOOR M/S DESERT ROOFING 26-Apr-20
APPROVAL
AWAITING
9 MAN-PQ-09 STEEL & CLADDING M/S ROOFING MIDDLE EAST 30-Apr-20
APPROVAL

10

45 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

MATERIAL SUBMITTAL LOG - (FIRE FIGHTING & FIRE ALARM MATERIALS)

REV-1
Sn Ref No. Material Description Manufacturer/ Supplier
Approved/ Status /
Submission Date Status / Remarks Submission Date Approved Date
Comment Date REMARKS

AWAITING
1 MAN-FPS-01 ABOVE GROUND PIPES 30-Apr-20
APPROVAL
AWAITING
2 MAN-FPS-02 CLEAN AGENT SYSTEM 30-Apr-20
APPROVAL
AWAITING
3 MAN-FPS-03 EMERGENCY LIGHTING SYSTEM 30-Apr-20
APPROVAL
AWAITING
4 MAN-FPS-04 FIRE ALARM SYSTEM 30-Apr-20
APPROVAL
AWAITING
5 MAN-FPS-05 FIREFIGHTING SYSTEM 30-Apr-20
M/S AFPA FIREFIGHTING & APPROVAL
EQUIPMENT INSTALLATION LLC AWAITING
6 MAN-FPS-06 FIRE PUMP 30-Apr-20
APPROVAL
AWAITING
7 MAN-FPS-07 PIPE FITTING 30-Apr-20
APPROVAL
AWAITING
8 MAN-FPS-08 SPRINKLER SYSTEM 30-Apr-20
APPROVAL
AWAITING
9 MAN-FPS-09 UNDERGROUNG PIPES 30-Apr-20
APPROVAL
AWAITING
10 MAN-FPS-10 FIRE RESISTANT CABLE 30-Apr-20
APPROVAL

46 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

MATERIAL SUBMITTAL LOG - (MEP MATERIALS)

REV-1
Sn Ref No. Material Description Manufacturer/ Supplier
Approved/ Status /
Submission Date Status / Remarks Submission Date Approved Date
Comment Date REMARKS

1 MAN-MEP-001 UPVC DRAINAGE PIPES & FITTINGS M/S COSMOPLAST 11-Mar-20 14-Mar-20 APPROVED

2 MAN-MEP-002 UPVC PRESSURE PIPES & FITTINGS M/S COSMOPLAST 11-Mar-20 17-Mar-20 REVISE & RESUBMIT

3 MAN-MEP-003 CROSS LINKED POLYTHENE (PEX) SYSTEM M/S COSMOPLAST 11-Mar-20 17-Mar-20 APPROVED

4 MAN-MEP-004 POLYPROPYLENE (PP-R) PIPES & FITTINGS M/S COSMOPLAST 11-Mar-20 17-Mar-20 APPROVED

AWAITING
5 MAN-MEP-005 FAHU M/S EUROVENT 26-Apr-20
APPROVAL
AWAITING
6 MAN-MEP-006 AC UNIT M/S CARRIER 29-Apr-20
APPROVAL

47 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

MATERIAL SUBMITTAL LOG - (SHOP DRAWINGS)

REV-1
Sn Ref No. Material Description Manufacturer/ Supplier
Approved/ Status /
Submission Date Status / Remarks Submission Date Approved Date
Comment Date REMARKS

1 MAN-SD-01 ELECTRICAL 25-Mar-20 1-Apr-20 REVISE & RESUBMIT 20-Apr-20 27-Apr-20 APPROVED

AWAITING
2 MAN-SD-02 LEVEL DRAWING & STORM WATER NETWORK 7-Apr-20 REVISE & RESUBMIT 23-Apr-20
APPROVAL
AWAITING
3 MAN-SD-03 WATER SUPPLY 23-Apr-20
APPROVAL
AWAITING
4 MAN-SD-04 DRAINAGE 23-Apr-20
APPROVAL
AWAITING
5 MAN-SD-05 HVAC 26-Apr-20
APPROVAL
AWAITING
6 MAN-SD-06 FIREFIGHTING 29-Apr-20
APPROVAL
AWAITING
7 MAN-SD-07 FIRE ALARM & ELS 29-Apr-20
APPROVAL
AWAITING
8 MAN-SD-08 FALSECEILING LAYOUT 30-Apr-20
APPROVAL

48 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

PS ITEM 5-May-20

REV-1 REV-2
Sn Ref No. Material Description Manufacturer/ Supplier
Approved/ Status / Submission Status /
Submission Date Status / Remarks Submission Date Approved Date Approved Date
Comment Date REMARKS Date REMARKS
AWAITING
1 LBC-MAO-DT-11 LIFT COMPARISION 12-Apr-20
APPROVAL
AWAITING
2 LBC-MAO-DT-14 PANTRY CABINET 18-Apr-20
APPROVAL
AWAITING
3 LBC-MAO-DT-15 SANITARYWARE CATALOUGE 19-Apr-20
APPROVAL
AWAITING
4 LBC-MAO-DT-17 WEIGH BRIDGE 20-Apr-20
APPROVAL
AWAITING
5 LBC-MAO-DT-18 SIGNAGE 20-Apr-20
APPROVAL
AWAITING
6 MAN-DT-001 LIGHT QUOTATION & COMPARISION 27-Apr-20
APPROVAL

49 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO. 5320248 AT DIC, DUBAI-UAE.

LONGLEAD ITEM 5-May-20

REV-1 REV-2
Sn Ref No. Material Description Manufacturer/ Supplier
Approved/ Status / Submission Status /
Submission Date Status / Remarks Submission Date Approved Date Approved Date
Comment Date REMARKS Date REMARKS
AWAITING
1 LBC-MAO-DT-11 LIFT COMPARISION 12-Apr-20
APPROVAL
AWAITING
2 MAN-PQ-10 SECTIONAL DOOR M/S ASSA ABLOY (CRAWFORD) 3-May-20
APPROVAL
M/S AFPA FIREFIGHTING & AWAITING
3 MAN-FPS-06 FIRE PUMP 30-Apr-20
EQUIPMENT INSTALLATION LLC APPROVAL
AWAITING
4 LBC-MAO-DT-17 WEIGH BRIDGE 20-Apr-20
APPROVAL
AWAITING
5 MAN-MEP-005 FAHU M/S EUROVENT 26-Apr-20
APPROVAL
AWAITING
6 MAN-MEP-006 AC UNIT M/S CARRIER 29-Apr-20
APPROVAL
M/S PETROYAS GROUP OF AWAITING
7 MAN-PQ-11 FIRE EXIT DOOR 4-May-20
COMPANIES APPROVAL

8 GATE BARRIER

9 HIGHMAST LIGHT TO BE SUBMIT

10 YARD ANNOUNCEMENT SYSTEM

50 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 11

TEST REPORT

51 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

52 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

53 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

54 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

55 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

56 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

57 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

58 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

59 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

60 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

61 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

62 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

63 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

64 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

65 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

66 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

67 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

68 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

69 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

70 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

71 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

72 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

73 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

74 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

75 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

76 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

77 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

78 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

ITEM NO. 12

FINISHES APPROVAL

79 | P a g e
PROPOSED CONSTRUCTION OF OPENSHED, (G+M) OFFICE AND RELATED ANCILLARY ON PLOT NO.
5320248 AT DIC, DUBAI-UAE.

FINISHES APPROVAL

SL
DISCRIPTION COLOR/FINISHES REMARKS
NO

01 PEB RAL 7046

ROOF & WALL


02 WAITING FOR APPROVAL
CLADDING
Sample not yet submitted

80 | P a g e