Sie sind auf Seite 1von 6

The I-280 Veterans’ Glass City Skyway: New Landmark

Cable-Stayed Bridge, Ohio


Wade S. Bonzon, PE, Resident Engineer, FIGG, Toledo, Ohio, USA

Introduction heavily traveled truck route and serves The superstructure is comprised of
as the fastest land connection between twin precast segmental trapezoidal
The new Interstate 280 bridge over the the industrialized cities of Cleveland, box girders. At stay anchorage loca-
Maumee River in Toledo, Ohio, USA Ohio and Detroit, Michigan. Approxi- tions, the two box girders are con-
opened to traffic on 24th June 2007. mately 70 000 vehicles use this portion nected together into a rigid frame
This landmark cable-stayed bridge, of I-280 each day, with a large percent- using a precast concrete delta frame
named the Veterans’ Glass City Sky- age of those being trucks involved in (Fig. 2). This triangle-shaped element
way, is the largest bridge project ever interstate commerce. The new cable- is connected with concrete closure
undertaken by the Ohio Department stayed bridge replaces one of the few pours and post-tensioning tendons to
of Transportation (ODOT) and incor- remaining movable bascule bridges on the adjacent box girders. Along with
porates unique structural and aesthetic the Interstate system. diagonal concrete struts cast into the
features. The centerpiece of the new adjacent box girder interiors, the delta
Keywords: precast segmental cable-
crossing is a 464,8 m long cable-stayed frames transfer traffic loads from the
stayed span; stay cradle; stainless steel;
main span unit featuring a 132,8 m tall bridge deck transversely to the cen-
LED bridge lighting; unidirectional
single pylon. All four sides of the up- trally-anchored stay cables. A post-
cantilever; glass.
permost 60,7 m of the pylon are faced tensioned concrete slab is also cast
in glass to honor Toledo’s heritage in to fill in the deck area between delta
the glass-making industry. At night Project Overview frames. The use of delta frames to con-
384 light emitting diode (LED) based nect two box girders greatly reduces
fixtures behind the glass display more Main Span Unit the size and weight of the precast ele-
than 16 million programmable color ments needed to carry six lanes of
The cable-stayed main span crosses the
combinations. The aesthetic features in interstate traffic.
Maumee River with two 187 m spans
the main pylon are made possible by
that flank the main pylon (Fig. 1).
the development of the new cradle sys- Main Pylon
Twenty stay cables in a combined fan/
tem for the stay cables. The stay cradles
harp arrangement support the precast The pylon (Fig. 3) is founded on 17
carry the stay strands through a series
concrete segments of the superstruc- drilled shafts each with a diameter of
of parallel stainless steel tubes inside
ture with deck-level anchorages locat- 2,44 m and socketed 4,6 m into the
a larger stainless steel outer sheathing.
ed every 8,53 m. The stays are aligned bedrock below the river. The drilled
The cradle eliminates the need for stay
in a single plane along the axis of the shafts are connected with a 4,88 m
anchorages embedded into the pylon
pylon and pass through the upper thick circular concrete footing with
and their associated high tensile forces.
pylon at 2,74 m intervals. The bridge a diameter of 31,7 m. The lower por-
Instead, the stay forces are transferred
superstructure provides more than tion of the pylon rises 48,4 m from the
to the pylon concrete using compres-
37,8 m of vertical clearance and much footing to the underside of the bridge
sive stresses, taking advantage of the
more than the required 61,0 m of hori- superstructure. Except for the bottom
natural strength of the concrete and al-
zontal clearance for the existing navi- 9,14 m, the pylon is generally rectan-
lowing for a more structurally efficient
gation channel. The main span unit is gular in cross-section, varying from
pylon cross-section. The main span unit
designed to carry three 3,66 m lanes of 15,8 m in length and 8,5 m wide at the
was erected over the Maumee River
highway traffic with two 3,05 m wide base to 8,8 m long and 4,1 m wide near
using precast concrete superstructure
shoulders in each direction. roadway level. The pylon diaphragm
segments, allowing shipping traffic to
the Port of Toledo to continue uninter-
rupted during the entire construction
process.
It carries Interstate 280 traffic over
the Maumee River, approximately one
mile east of downtown Toledo, Ohio.
The Maumee is the largest tributary
to the Great Lakes, emptying into the
western end of Lake Erie and at the
location of the bridge it is approxi-
mately 300 m wide. Because of its size
and location, the Maumee serves as
access to the Port of Toledo, one of
45 720 186 690 186 690 45 720
the busiest ports in the Great Lakes
shipping system. Interstate 280 is a Fig. 1: Elevation view of the main span unit (units: mm)

Structural Engineering International 1/2008 Structures in North America 43

x299.indd 43 1/1/70 1:06:16 PM


3048 3658 3658 3658 3048 4674 3048 3658 3658 3658 3048
(Shoulder) (Lane) (Lane) (Lane) (Shoulder) (Median) (Shoulder) (Lane) (Lane) (Lane) (Shoulder)

3708
(Typ.)

Southbound lanes Northbound lanes


Main span cross section

3658 3658 3658 3048 3048 3658 3658 3658


3048 3048
(Shoulder) (Lane) (Lane) (Lane) (Shoulder) (Shoulder) (Lane) (Lane) (Lane) (Shoulder)

Delta frame
Southbound lanes Northbound lanes
Main span cross section
at stay anchorages

Fig. 2: Main span typical cross-section and cross-section at stay anchorages (units: mm)

Main Span Erection Method


6,30 to 8,84 Maintaining shipping traffic to and
from the Port of Toledo was deemed
a top priority during the design
phase of the project. The main ship-
4,06

ping channel is located just north of


79,88

B B Section B-B the central pylon, and is heavily used


during all seasons except winter. This
meant that any erection method for
8,84
the main span unit would need to
avoid placement of barges, cranes, or
other erection equipment within the
limits of the shipping channel. Erec-
8,53
4,57

tion of the main span superstructure


using the balanced-cantilever method
53,04

would have required placing seg-


A A ments and possibly cranes on barges
15,80 in the main shipping channel. Moving
Footing Section A-A this equipment out of the way for Port
4,88 of Toledo shipping traffic during the
spring, summer, and autumn seasons
Seal slab
Longitudinal Transverse could adversely impact the construc-
elevation elevation tion schedule. Therefore, the main
span unit was designed to be erected
Fig. 3: Elevation and cross-section views of the main pylon (units: m)
from above using a combination of
span-by-span and unidirectional can-
tilever construction.
is located at the level of the roadway, from 8,84 to 6,30 m in length and has
and frames the continuous superstruc- a constant 4,06 m width. This cross- Erection Sequence
ture into the pylon. It also provides sectional shape provides locations for
an anchorage diaphragm for longi- glass panels incorporated into four The erection of spans in the main span
tudinal post-tensioning tendons run- sides of the pylon. The glass panels unit began after completion of the
ning through the superstructure. The and the curved faces of the pylon con- southern approach spans leading to
upper portion of the pylon reaches to crete form four cavities through which the main span using the span-by-span
80,7 m above the level of the roadway. maintenance elevators can travel to method. Temporary steel truss towers
The upper pylon has a unique “cruci- access the entire height of the upper were assembled on temporary footings
form”-shaped cross-section that varies pylon. founded on groups of steel pipe piles.

44 Structures in North America Structural Engineering International 1/2008

x299.indd 44 1/1/70 1:06:18 PM


ded several steps when the temporary
piers supporting the back spans were
removed (Fig. 4).

Typical Cantilever Erection Sequence


The structural system and layout of
the main cantilever was intentionally
designed to be as repetitive as possible
26 27 A B C 29 30
Pylon to simplify the cantilever erection pro-
Temporary pier supports cess. Each cycle of segment erection
and stay cable installation followed the
same basic set of steps.
Upon completion of the previous stay
installation and stressing, the first step
in the typical cantilever erection cycle
was the delivery and erection of six
superstructure segments in two “mini-
cantilevers” of three segments each.
26 27 A B C 29 30 The last pair of segments had block-
Pylon
outs in their web walls into which
Temporary pier supports the lower corners of the precast delta
frame fit. The 82 t cantilever segments
were erected using Demag AC400 hyd-
raulic truck cranes located on the pre-
viously erected segments (Fig. 5). The
new segments were delivered to the
ends of the cantilevers using special
12-axle hauler trailers. All segments
were epoxied and post-tensioned to-
26 27 A B Pylon
29 30 gether using a series of post-tensioning
bars and multistrand tendons.
Temporary pier supports
Immediately after erection of super-
structure segments was complete, the
precast delta frame was delivered
to the cantilever tip using the same
12-axle hauling trailer and lifted into
position using one of the hydraulic
cranes (Fig. 6). Once the weight of the
86 t delta frame was transferred to sup-
port beams it was surveyed and aligned
26 27 A 29 30
Pylon for the proper angle of the stay guide
Temporary pier support pipe at that phase of construction.
The precast delta frame and the two
mini-cantilevers were then connected
structurally to each other with cast-in-
place closures at the bottom corners
of the delta frame and at the median
deck slab. After the concrete achieved
a minimum compressive strength of
27,6 MPa a series of transverse post-
29 30 tensioning tendons were stressed to
26 27 Pylon
complete the transverse structural sys-
Fig. 4: General sequence of main span erection tem, making the cantilever ready for
installation and stressing of the next
stay cable.
The back span portion of the main route to transport precast segments
span unit was then erected on the tem- and delta frames to the main cantilever
porary towers, creating four temporary for erection. As erection of the main Stay Cable System
spans that would later make up the cantilever progressed and stay cables
General Layout
187 m long permanently cable-stayed began supporting both the main canti-
span directly south of the main pylon. lever and the back span, the structural The stay cable system for the Veterans’
The completed back span portion of system of the main span unit began to Glass City Skyway incorporates seve-
the main span unit then provided a change. The erection sequence inclu- ral unique features. The main tensile

Structural Engineering International 1/2008 Structures in North America 45

x299.indd 45 1/1/70 1:06:22 PM


Fig. 5: Erection of precast superstructure segments in cantilever Fig. 6: Precast delta frame is lifted into place using a crane on the
cantilever tip

element consisted of 15 mm diameter, Stay Cradle System to efficiently handle large compressive
epoxy-coated seven-wire strands, vary- loads. This more efficient load transfer
Many modern cable-stayed bridges
ing from 82 to 156 strands per stay. The resulted in a reduction in reinforcement
incorporate stay anchorages in the
156-strand stays represented the lar- and cross-sectional area of the pylon
pylon. However, this requires design-
gest known stay cables of any bridge concrete. Because the cradle kept all of
ers to counteract the high tensile forces
in the world. Each stay’s strands run the stay’s strands parallel and prevent-
generated between these anchors with
continuously from deck-level anchor- ed strand-to-strand contact, it was fully
large amounts of reinforcement and
age, through the main pylon, and back compatible with the monostrand stres-
post-tensioning. More recently heavy,
down to the opposing deck-level an- sing systems that have revolutionized
complex, and expensive steel anchor-
chorage (Fig. 7). No stay anchors were the stay cable installation process in
age boxes have been embedded in con-
located within the pylon itself. This arr- recent years. This effectively removed
crete pylons for the same reason.
angement was made possible through the limits on stay cable sizes previously
the use of an innovative cradle system The cable-stay cradle system was devel- imposed by the large size and difficulty
that kept all the strands parallel to one oped by the author's company during of using multistrand jacking systems.
another in separate individual steel the design phase of the Veterans’ Glass
The cradle system consisted of an ex-
sheaths as they passed through the City Skyway. Instead of generating
ternal stainless steel curved pipe. Inside
pylon. The strands remained parallel large tensile forces, the cradle system
this outer sheathing, a series of indi-
to each other throughout the length transferred the load of the stay cables
vidual 25 mm diameter stainless steel
of the stay into each anchor, and were to the pylon concrete through direct
tubes carried each of the seven-wire
further protected by a stainless steel radial compressive stresses, taking ad-
strands of the stay cable’s main tensile
outer sheathing. vantage of concrete’s inherent ability
element (Fig. 8). The individual strand
sleeves remained parallel to each other
throughout the length of the cradle
pipe, and their ends were flared to avoid
Pylon damaging the strands’ epoxy coating
during their installation in the field. The
Cradle
interstitial space between the individual
sleeves was filled with a structural grout
with a minimum compressive strength
of 34,5 MPa to provide a load transfer
path for the radial compressive stres-
Main sheathing ses generated by each individual stay
strand as it passed through its curved
sleeve inside the cradle.
Termination After grouting, the stay cradles weighed
sheathing approximately 4,5 t each, and were
Guide
lifted into place using a tower crane
pipe attached to the pylon. Installation and
Damper
alignment of the cradles, similar to a
Damper
saddle pipe or a tendon deviator pipe,
was relatively straightforward. The
cradles were stamped with alignment
Anchorage Superstructure deck Anchorage markings at each end and at the mid-
point, and those marks were surveyed
Fig. 7: General layout of stay cable system for proper elevation and alignment.

46 Structures in North America Structural Engineering International 1/2008

x299.indd 46 1/1/70 1:06:22 PM


Space between sleeves Stay
is grouted cradle

Individual 25 mm stainless steel


sleeves for each strand Stay
sheathing

Stay
sheathing

Outer stainless
steel sheathing

Section A-A L Pylon


C

Internal sleeves
(number varies by stay) Grout vents

A
PC PT

Arc length

A
Tan
g ent gen
10 mm Tan t
Grout
end plate vent

Fig. 8: General layout of stay cradle

Monostrand Stay Stressing Each stay was stressed in two phases. “Glass” was chosen to guide the deci-
The first stage, which included instal- sion-making process and determine
A monostrand jacking system was
lation and stressing of the strands, what special aesthetic features would
used to stress the strands in each stay.
brought the stay force to approxi- be incorporated into the bridge. It was
Stressing the stay cable in this manner
mately 80% of its final target force. At decided that glass would be a signifi-
required the construction engineer to
that time, the behavior of the structure cant part of the aesthetics of the main
calculate an initial strand force high-
was evaluated and the master strand pylon.
er than the final desired target force,
force needed to achieve the proper
because force was lost in all strands The development of the stay cradle
final stay force was determined. Stage
as they shortened during stressing of and the resultant elimination of stay
two stay stressing lasted for only a few
the next strand. The initial force selec- anchors in the pylon allowed much
hours, minimizing the chances of un-
tion for stressing this first strand was a greater freedom to incorporate glass
expected load changes on the bridge
function of several parameters includ- into the design. The final configura-
and the effects of thermal changes in
ing the required “target” force, the ac- tion chosen by the Task Force includ-
the structure.
tual surveyed length of the stay at the ed glass panels on four sides of the
beginning of installation, the expected Each strand was stressed simultane- upper 60,7 m of the pylon as well as a
movement of the stay work points ously at both anchors so that the nec- glass-clad, pyramid-shaped pylon top.
during cable stressing, and the nomi- essary force could be achieved without Behind the glass were access shafts
nal cable weight. For proper long-term overcoming the coefficient of friction through which interior maintenance
fatigue performance of the stay cables, in the cradle sleeve and causing the lifts could operate for maintenance
the individual strands’ forces must be strand to slip. Due to the asymmetrical and cleaning. The glass panels were
as close to identical as possible. To method of cantilever construction, the partially mirrored to reflect the sky
achieve this, the monostrand stressing stay forces on the cantilever side of the during the day but allow backlighting
system relied on two electronic load pylon were slightly higher than those to shine through at night. The laminat-
cells at each stay anchorage. One load on the back span side. ed panels incorporated seven layers
cell was attached to the first strand that with a total thickness of 33 mm. Each
was stressed, which was designated as glass panel (Fig. 9) was approximately
the “master” strand. The second load
Main Pylon Aesthetic Features 2,3 m wide and 1,4 m tall and weighed
cell was a part of the internal compo- approximately 204 kg. Forty-four glass
Pylon Glass
nents of the monostrand jack. Each panels were attached to each quad-
time a new strand was stressed, it was A series of public meetings was held rant of the pylon using an aluminum
tensioned until its force from the jack’s during the early stages of the design framing system made waterproof with
load cell matched the force as read of the project to establish an aesthetic structural silicone caulking, similar to
from the master strand’s load cell. To theme and choose from a variety of systems found in high rise buildings.
maximize the accuracy of this match- design options. Toledo has historically The system was designed so that indi-
ing, control of the stressing jack was had a strong presence in the glass-mak- vidual glass panels could be removed
taken over by a computer just prior to ing industry, and is still known as “the and replaced without disturbing sur-
its final stroke. Glass City”. Consequently, a theme of rounding panels. Installation of the

Structural Engineering International 1/2008 Structures in North America 47

x299.indd 47 1/1/70 1:06:36 PM


Fig. 9: A partially mirrored glass panel is prepared for installation Fig. 10: The pylon is lit with a patriotic color scheme during the
into the upper pylon Grand Opening ceremonies on 23 June 2007

glass panels progressed quickly once Conclusion service life. However, the aesthetic im-
the aluminum framing was in place. pact of these first-of-a kind features is
All 176 glass panels were installed in The new Veterans’ Glass City Skyway profound, and the bridge is expected
the pylon in approximately 10 working in Toledo, Ohio incorporates many to become a new landmark not only
days over the course of 2 months. unique structural and aesthetic fea- for Toledo but for the United States as
tures. It was constructed from above well (Fig. 10).
Aesthetic Lighting by cantilevering from the main pylon
over the main shipping channel of the
Perhaps the most spectacular and Maumee River. All precast segments Acknowledgement
versatile aesthetic feature of the new were delivered over the completed
Veterans’ Glass City Skyway becomes Significant contributions to this article were
back spans, allowing uninterrupted made by Michael Gramza, P.E., Ohio Depart-
visible each night. A total of 384 LED shipping to the busy Port of Toledo. ment of Transportation Project Manager for
lighting fixtures were located behind The stays are the largest of any known the Veterans’ Glass City Skyway.
the glass panels of the upper pylon and cable-stayed bridge in the world, with
pylon peak. These fixtures were com- up to 156 strands of 15 mm diameter.
pletely programmable using a personal The bridge is the first in the United
computer and were customized to dis- States to use low maintenance stainless SEI Data Block
play color schemes of the community’s steel stay sheathing, and the first to be
choosing. Owner:
designed with the new cradle system Ohio Department of Transportation,
Each fixture contained a group of red, for passing the stay cables through the OH, USA
green, and blue light emitting diodes. pylon. The stay cradle provides an effi-
By varying the intensity of each of cient means of transferring cable for- Structural Design:
these colors each LED fixture produc- ces to the pylon concrete, eliminating FIGG Engineering Group, Tallahassee,
FL, USA
es any of 16,7 million separate colors. the need for anchorages in the pylon
The fixtures were combined to display and the associated additional rebar, Contractor:
either static or dynamic “shows” that posttensioning, or steel anchorage box. Fru-Con Construction Corporation,
represented various holidays, sea- The highly efficient force transfer also Ballwin, MO, USA
sons, and special events throughout allowed the cross-sectional shape of (Quantities for Main Span Unit only)
the year. The entire system was con- the pylon to incorporate, for the first Concrete (m3): 23 690
nected to an astronomical time clock time in any cable-stayed bridge in the
to run from dusk to dawn every night world, glass panels and multicolored Reinforcing steel (t): 2356
of the year. The highly efficient LED LED lighting for the upper 60,7 m of Prestressing steel (t): 716
fixtures were completely watertight the pylon above deck level. The glass
Stay cables (t): 700
for use in outdoor applications, and panels and LED aesthetic lighting rep-
were expected to last approximately resent less than 1% of the total project Total cost (USD millions): 237
20 years before they would need to be cost and are expected to require mini- Service Date: June, 2007
replaced. mal maintenance during the bridge’s

48 Structures in North America Structural Engineering International 1/2008

x299.indd 48 1/1/70 1:06:39 PM

Das könnte Ihnen auch gefallen