Sie sind auf Seite 1von 136

DETAIL OF MEASUREMENT

Name of Work:- Construction of Pump House cum attendant quarter in frame structures. ( below 50BHP)
Sr. Description. No. L B H Total
No. Qty.
1 Excavation in foundation
trenches.
Column. 8 1.2 1.2 1.6 18.43 Cum
2 P/L C.C 1:6:12
P/House. 1 5 3.6 ------- 0.1 1.8
Att. Qtr. 1 2.75 3.6 ------- 0.1 0.99
Out side. 1 29.26 0.6 ------- 0.1 1.76
Tatal 4.55 Cum
3 P/L C.C 1:4:8
Column. 8 1.2 1.2 0.23 2.65 Cum
Bed.
4 P/L RCC 1:1.5:3 work
a) In footing area 8 1.2 1.2 0.25 2.88
In Trap. Portion.
----- 0.67 1.53 4.5 4.04
8x0.50/6 (1.20)²+(0.30)²+4x(1.20+0.30)² Total 6.92 Cum
2
b) For Column :---
Above Trap. Portion upto
ground level. 8 0.30 0.30 0.60 0.43

Above ground level upto


slab level. 8 0.30 0.30 3.30 2.38
Total 2.81 Cum
c) In plinth in lintels beams.
Long side. 2X2 4 8.1 0.3 0.3 2.92
Short side. 2X3 6 3.83 0.3 0.3 2.07
5 Vert. F/Side. 1x2 2 1.5 0.3 0.3 0.27
Shalves 4 3.5 0.6 0.075 0.63
4 1.4 0.6 0.075 0.25
For slab. 1X1 1 9.3 5.03 0.1 4.68
Slopping surface 2 3 1.95 0.1 1.17
Total 11.99 Cum
5 Providing form work for steel plate
a). Foundation and footing. 8X4 32 0.6 ------ 0.3 5.76 Sqmt
b). Column. 8X4 32 3 ------ 0.3 28.8 Sqmt
c). Plinth and lintels beams.
Outer side L/Side. 2X2 4 8.1 ------ 0.3 9.72
Outer side S/Side. 2X2 4 3.83 ------ 0.3 4.6
Inner side L/Side. 2X2 4 5 ------ 0.3 6
-do- S/Side. 2X4 8 3.6 ------ 0.3 8.64
Vert. F/Side. 2X4 8 1.5 ------ 0.3 3.6
Total 32.56 Sqmt
d). Slab. 1 9.3 5.03 ------ 46.78 Sqmt
Shalves 4 3.5 0.6 ----- 8.4
4 1.4 0.6 ----- 3.36

Slopping surface 2 3 1.95 ----- 11.7 Sqmt


Total QTY. 70.24 Sqmt
f) Edge of slab. 2 9.3 ------ ------ 18.6
2 5.03 ------ ------ 10.06
Total 28.66 Sqmt
6 Providing mild steel.
Qty.carry over from item Nos (.4,a,b,c,d) 6.92 2.81 11.99 0 21.72 Cum
21.72 105 kg/cum 2280.6 Kg
7 Half brick masonry 1:3
P/House. L/side. 2 4.83 ------ 3.3 31.88
-do- S/side. 2 2.58 ------ 3.3 17.03
Att.Qtr. L/Side. 2 3.37 ------ 3.3 22.24
-do- S/side. 1 3.37 ------ 3.3 11.12
Gabal area 2 2.5 0.75 0.5 1.88
Terrace wall 2 9.3 ------ 0.4 7.44
Cub Board wall 2 9.3 ------ 0.4 7.44
2 3.3 ------ 0.4 2.64
Total 101.67 Sqmt
Deduction.
D 1 1.2 ------ 2.55 3.06
D1 2 0.95 ------ 2.55 4.85
W 3 1.65 ------ 1.65 8.17
W1 1 0.6 ------ 1.65 0.99
V 1 1.65 ------ 0.55 0.91
Total 14.92 Sqmt

Page 1 of 136
Net Qty 101.67 14.92 86.75 Sqmt

Page 2 of 136
8 Providing woodwork in frames of
doors, windows, clerestory,
windows and other frames wrought,
doors & windows.
Profile(A)
Ventilator. H 2 1.65 --- ---- 3.30
V 2 0.55 --- ---- 1.10
W1 H 2 1.6 --- ---- 3.20
V 2 0.6 --- ---- 1.20
Total 8.80 Rmts
Profile(B).
Doors. D H 1 1.2 --- ---- 1.20
V 2 2.55 --- ---- 5.10

D1 H 1 0.95 --- ---- 0.95


V 2 2.55 --- ---- 5.10

Window. W H 2x3 6 1.65 --- ---- 9.90


V 2x3 6 1.65 --- ---- 9.90
Total 32.15 Rmts
Profile -C)
Doors D H 1 1.2 --- ---- 1.2
D1 H 2 0.95 --- ---- 1.9
Windows. W H 2x3 6 1.65 --- ---- 9.9
V 2x3 6 1.65 --- ---- 9.9
Total 22.9 Rmts
63.85 Rmts.
Therefore Qty of wood 63.85 x 0.075 x 0.125 0.60 Cum.

9 P/F paneled & glazed shuttering


for doors and windows.

Door. D 1 1.12 -------- 2.05 2.30


1 1.12 -------- 0.4 0.45
D1 1 0.87 -------- 2.05 1.78
1 0.82 -------- 0.4 0.33

Window. W 3X3 6 1.13 -------- 0.4 2.71


3X3 6 0.4 -------- 0.4 0.96

W1 1 1.13 -------- 0.4 0.45


1 0.4 -------- 0.4 0.16

Ventilator. V 3 0.4 -------- 0.4 0.48


Tatal 9.62 Sqmt
10 P/F wire gauge shuttering
for doors and windows.
Door D 1 1.12 -------- 2.05
1 1.12 -------- 0.4 0.45

D1 1 0.87 -------- 2.05 1.78


1 0.82 -------- 0.4 0.33

Window. W 1x3 3 1.13 -------- 0.4 1.36


1x3 3 0.4 -------- 0.4 0.48
Tatal 4.40 Sqmt

11 15mm thick cement plaster


1:6 Fair side.

Outer side L/side. 2 9.3 3.3 ----- 61.38


-do- S/side. 2 3.83 3.3 ----- 25.28
Mid wall. 2 3.6 3.3 ----- 23.76
Shalves 2 4 3.5 0.6 ---- 16.8
2 4 1.4 0.6 ---- 6.72
Shalves wall 2 2 3.3 0.6 ---- 7.92
Tatal 141.86 Sqmt
Deduction. D 1 1.2 ----- 2.55 3.06
D1 2 0.95 ----- 2.55 4.85
W 3 1.65 ----- 1.65 8.17
W1 1 0.6 ----- 1.65 0.99
V 1 1.65 ----- 0.55 0.91
Total 17.98 Sqmt

Net Qty 141.86 17.98 123.88 Sqmt

Page 3 of 136
12 20mm thick cement plaster
1:6 rough side
P/House Inner side L/Side 2 5 ------ 3.3 33
-do- S/Side. 2 3.6 ------ 3.3 23.76
Att/Qtr.Inner side L/Side. 2 2.75 ------ 3.3 18.15
-do- S/Side. 2 3.6 ------ 3.3 23.76
Total 98.67 Sqmt

13 6mm thick cement plaster 1:3


Pump Room 1 5 3.6 ------ 18
Att.Qtr. 1 2.75 3.6 ------ 9.9

Projected slabs Front & back. 2 9.3 0.6 ------ 11.16


2 5.03 0.6 ------ 6.04

Sloped slab. 2 3 1.95 ------ 11.7


Total 56.8 Sqmt
14 Kota stone slab flooring 20 mm
(average) thick base of cement
mortor 1:4
P/House. 1 5 3.6 ----- 18
Att.Qtr. 1 2.75 3.6 ----- 9.9
Ver. 1 1.5 5.05 ----- 7.58
b)Step and dado etc.
Trad. 3 1.8 0.3 ----- 1.62
Riser. 4 1.8 0.18 ----- 1.3
Landing. 1 0.6 1.8 ----- 1.08
sloped slab. 1x2 2 3 1.95 ----- 11.7 Sqmt

Net qty. Tatal 51.18 Sqmt

15 White washing

Same qty. of item No.( 11 ,12 ,13) 123.88 98.67 56.8 279.35 Sqmt

16 Distempering two coats with


oil bound.
Same qty. as per item No. 12 Total 98.67 Sqmt

17 Finishing with water proofing


cement paint.
Same qty. as per item No. 11 Total 123.88 Sqmt

18 Appling priming coats on wood Work.


a) Door D 2X1 2 1.2 2.55 1.33 8.14 Sqmt
D1 2X1 2 0.95 2.55 1.33 6.44 Sqmt
Window. W 2X3 6 1.65 1.65 0.8 13.07 Sqmt
W1 2X1 2 0.6 1.65 0.8 1.58 Sqmt
Ventilator. V 2X1 2 1.65 0.55 0.8 1.45 Sqmt

P/F wire gauge shuttering


for doors and windows.
b) Door. D 1X2 2 1.12 2.05 0.8 3.67 Sqmt
1X2 2 1.12 0.4 0.8 0.72 Sqmt
Sqmt
D1 1X2 2 0.87 2.05 0.8 2.85 Sqmt
1X2 2 0.82 0.4 0.8 0.52 Sqmt
Window. W 2X2 6 1.13 0.4 0.8 2.17 Sqmt
2X3 6 0.4 0.4 0.8 0.77 Sqmt

Painting two coat other than white paint. Dv 1 1.2 0.4 -------- 0.48
1 0.95 0.4 -------- 0.38
3x3 9 1.65 0.4 -------- 5.94
1 1.65 0.6 -------- 0.99
3 1.65 0.55 -------- 2.72
Total 51.89 Sqmt
19 Painting two coat over wood work
Same qty. as per item No. 18 Total 51.89 Sqmt

Page 4 of 136
20 Prov. Steel work for Grill.
a)Flat 12x6mm thick. V 2 3 3 1.65 29.7
H 2 2 3 1.65 19.8
W1 V 2 1 1 1.65 3.3
H 1 1 3 1.65 4.95
V V 2 1 3 0.55 3.3
H 1 1 2 1.65 3.3
Total 64.35 Rmts
Total 64.35 0.6 Kg/Rmts 38.61 Kg -a
b).Squar bar 10mm dia V 3 5 3 1.65 74.25
H 1 3 3 1.65 14.85
W1 V 1 1 5 1.65 8.25
H 1 1 3 0.6 1.8
V V 1 3 5 0.55 8.25
H 1 1 1 1.65 1.65
Ver. 1 1 1.2 55 66
Total 175.05 Rmts
Total 175.05 0.78 Kg/Rmts 136.54 Kg -b
Net Qty 38.61 136.54 175.15 Kg
21 Stone soling 15mm thick.
P/House. 1 5 3.6 0.15 2.7
Att. Qtr. 1 2.75 3.6 0.15 1.49
Out side. 1 29.26 0.6 0.15 2.63
Total 6.82 Cum

22 P/F MS sliding door. 2 1 2 Nos

23 P/F MS tower bolts barred.

Door. 2 2 4 Nos
Window. 2 3 6
2 3 6 16
Ventilator. 2 2 4 Nos

24 Providing & fixing MS handles


Door. 2 2 4 Nos
Window. 2 3 6
W1 1 2 2 10
Ventilator. 1 2 2 Nos

25 Providing & fixing iron hold fast. 2 1 2 Nos

26 Providing flat iron hold fast 40mm long.


Door 2 6 12
Window. 4 4 16
Ventilator. 2 1 2
Total 30 Nos

27 Prov. Plinth protection 50mm thick


in C.M 1:3:6
Front & back 2 9.3 0.6 ------ 11.16
Side. 2 3.83 0.6 ------ 4.6
Ver. 2 1.5 0.45 ------ 1.35
Drain bed/side. 1 29.26 0.6 ------ 17.56
Total 34.67 Sqmt

28 Providing under layer for plinth protection of 75


mm thick (uncolsolidated) bed dry brick/stone
aggregated 40 mm nominal size

Front & back 2 9.3 0.6 ------ 11.16


Side. 2 3.83 0.6 ------ 4.6
Ver. 2 1.5 0.45 ------ 1.35
Drain bed/side. 1 29.26 0.6 ------ 17.56
Total 34.67 Sqmt

29 sloped slab. 1x2 2 3 1.95 ----- 11.7 Sqmt

Page 5 of 136
Name Of Work-: C/O LIS FROM BONDA GAD TO ADARSHNAGAR IN SUB TEHSIL NANKHARI DISTT. SHIMLA (HP)
SH:-- Construction of Pump House cum attendant quarter in frame structures.

40 115 CM THICK BRICK WALL RCC SLAB 10 CM THICK

75

RCC SHELF V RCC DOWN FACRA


20CM
LINTAL BEAM 10CM
380
THICK
165 255
W
W
330
ATT. ROOM 210 PUMP ROOM

HALF BRICK WALL


90
85

45
GL L

STONE SOLING 15 CM THICK 40 mm th. C.C FLOORING

SECTION AT " XX "

ASSISTANT ENGINEER EXECUTIVE ENGINEER


IPH SUB DIVISION NANKHARI IPH DIVI. RAMPUR
RCC DOWN FACRA
20CM
LINTAL BEAM 10CM
THICK

HALF BRICK WALL


Abstrtact of Cost Annexure-A

Name Of Work-: C/O LIS FROM BONDA GAD TO ADARSHNAGAR IN SUB TEHSIL NANKHARI DISTT. SHIMLA (HP)
( SH--: C/O/ Pump House at Stage- 1st ( 50.00 Sq. mterrs)

Sr.No Discription of Items Quantity Unit Rate Amount

1 Excavation in earth work in all kind of soil stacking excavated soil in the plinth 18.43 m3 377.00 6948.00
sides of foundation and then disposing of all surplus soil in all leads & lifts as
directed by Engineer in Charge.

3 P/L CC 1:6:12 1cement:6 sand:12 graded aggregates 40mm nominal size curing 4.55 m3 6373.25 28998.00
complete excluding cost of form work infoundation & plinth

2 P/L CC 1:4:8 1cement:4 sand:8 graded aggregates 40mm nominal size curing 2.65 m3 7471.15 19799.00
complete excluding cost of form work infoundation & plinth

4 Providing & laying CC 1:1.5:3 1cement:1.5 sand 3 graded aggregates 20mm


nominal size curing complete excluding cost of form work & reinforcement for
RCC work in:-

a) IN Footing 6.92 m3 9426.25 65230.00

b) For Coulmens 2.81 m3 10152.80 28529.00


c) In Plinth Beam ,Suspended floor , roof, landing & shelves & their supports, 11.99 m3 9630.75 115473.00
Balconies, beams, griders& cantilevers up to all floor level.

5 Providing form work with steel plates 3.15mm thick welded with angle iron in
frame 30x30x5mm so as to give a fair finish i/c centering shuttering etc. with
wooden batten & ballies height of propping & centering below supporting floor
to ceiling not exceeding 4mt. Height & removal of same for in situ reinforce
ment concrete & plain with in all lead & lifts.

Foundation, footing basis of columns etc and mass concrete. 5.76 m2 213.80 1231.00
Columns, Pillars, Posts and struts. Square rectangular or polygonal in plan. 28.80 m2 421.35 12135.00
Flat surfaces such as soffits of suspended floors, roofs, landing and the like 70.24 m2 379.25 26639.00
floor upto 200 mm in thickness up to floor all level

Sides and soffits of beams, beam haunching, cantilevers, bressumers and lintels 32.56 m2 323.00 10517.00
not exceeding 1 Mtr. In depth in all heights from floor.

Edges of slabs and breaks in floors and walls. up to floor all level. 28.66 Rmt. 112.80 3233.00

6 Providing mild steel/tor steel reinforcement I/c bending binding and placing in 2280.60 kg 65.55 149493.00
position complete

7 Half Brick work using comman burnt clay building bricks ( IInd class) in 86.75 m2 1514.05 131344.00
superstructure above plinth level up to floor to level in cement mortar 1:4 ( 1
cement 4 sand ) in all lead & lifts.

8 Providing woodwork in frames of doors, windows, clerestory, windows and 0.60 m3 100490.25 60294.00
other frames wrought, framed and fixed in position complete in all respect
within all leads and lifts as per direction & to the entire satisfaction of
Engineer-in-charge. 2nd class Deodar wood

9 Providing and fixing Pannelled and glazed shutters for doors windows and 9.62 m2 4022.95 38701.00
clear storey windows including bright finish black enamel led iron butt with
necessary screws 40mm thick: 2nd class deodar wood in all lead & lifts.

10 P/F wire gause shutters using MS wire gause of IS gause designation 85 G for 4.40 m2 2882.25 12682.00
doors windows clerestorey windows I/c bright finished black enamelled iron
hinges with necessary secrews 30 mm thick 2nd class deodar wood.

11 15 mm thick cement plaster on Fair sides of brick/stone masonery convrete 123.88 m3 209.30 25928.00
walls for interior plastering upto floor two level including arises internal
rounded angles not exceeding 80mm girth in cm 1:4 (1cement:4sand) with in
all lead & lift.
12 20 mm thick cement plaster on rough sides of brick/stone masonery convrete 98.67 m3 257.05 25363.00
walls for interior plastering upto floor two level including arises internal
rounded angles not exceeding 80mm girth in cm 1:4 (1cement:4sand) with in
all lead & lift.

13 6 mm thick cement plaster in CM 1:4( 1cement 4 sand in roof slabs 56.80 m3 113.30 6435.00

14 Kota stone slab flooring 20 mm (average) thick with jaiselmer yellow 51.18 m2 1720.00 88030.00
band/strips 7.5cm wide base of cement mortor 1:4 (1 cement :4 sand) laid over
and jointed with grey cement slurry mixed with pigment to match the shade of
the slab. Including rubbing and polishing complete. 40 mm thick. including
carriage of material within all leads and lifts and as per direction of Engineer-
in-charge.

15 White washing with lime on decorated wall surfaces (two coats) to give an even 279.35 m2 11.30 3157.00
shade and including throughly brushing the surface dirt dust mortar dropping
and other foreign matters.in all lead & lifts.

16 Distemper with dry distemper of approved brand and manufacture (Two 98.67 m2 75.85 7484.00
coats0and of required shade on undecorated wall surface to given and even
shade over and including primer coat of whiting after thoroughly brushing the
surface free from mortar droppings and other foreign matter including
preparing the surface even and sand papered smooth.

17 Fininshing wall with water proofing cement paint of approved brand 123.88 m2 52.95 6559.00
manufacturs of required . shade as undercreatd wall surface Two coat to give
an even shade after throughly brushing surface to removal all dirt & dust.

18 Applying two coat on new wood based surface after and including preparing 51.89 m3 38.15 1980.00
the surface by throughly cleaning dirt dust & other forigen matter with in all
leads & lirfts
19 Painting two coats(excluding priming coat) on new wood and wood based 51.89 m2 82.15 4263.00
surfaces with ready mixed paint brushing to give even shade including cleaning
all dirt, dust and other foreign matters other than white paint

20 Providing & Fixing M.S Grills of required pattern in wooden frames of 175.15 Kg. 100.45 17594.00
windows etc. withM.S flats,square or round bars with round handed bolts and
nuts or by screws.(Plain Grill.)

21 Stone soling properly hand packed filling interstices with spalls and 6.82 m3 1832.35 12497.00
consolidating with power road roller to the required gradient and camber
including spreading watering and rolling of binding materials moorum or earth
etc. 100mm spread thickness (finished work including materials and labour)
within all leads and lifts an da directed by the Engineer-in-charge.

22 Providing and fixing anodized aluminium sliding door bolts withnuts and 2.00 178.95 358.00
screws complete I) 250mmX16mm

23 Providing and fixing anodized aiuminium. tower bolts barrel type with screws 0.00
etc. complete.
a) 200mmX10mm 16.00 59.00 944.00

b) 150mmx10mm 4.00 44.55 178.00

24 Providing and fixing anodized aluminium .handles with screws etc. complete.

a) 125mm dia 10.00 56.45 565.00


b) 100mm dia 2.00 44.40 89.00
25 Providing 40x3 mm flat iron hold fast 40cm. Long including fixing to frame 30.00 Nos. 145.65 4370.00
with 10mm dia metres bolts, nuts and wooden plug and embedding in cement
concrete block 30x10x15cm. 1:3:6( 1cement:3sand:6 graded stone att. 20mm
nominal size) within all leads and lifts and as directed by the Engineer-in-
charge.

26 Providing & Fixing M.S fane clamp ( Type- I of 16mm dia M.S. Bar bent to 2.00 Nos. 145.65 291.00
shape with hooked & ends in PCC including painting the exposed portion of
loop all as per standered design .

27 Providing plinth protection 50mm thick in cement concrete 34.67 m2 419.05 14528.00
1:3:6(1cement:3sand:6graded stone agg. 20mm nominal size) i/c finishing the
top surface of concrete smooth within all leads and lifts and as directed by the
Engineer-in-charge.

28 Providing under layer for plinth protection of 75 mm thick (uncolsolidated) bed 34.67 m2 408.95 14178.00
dry brick/stone aggregated 40 mm nominal size will rammed and consolidated
and grouted with fine sand including preparation of ground

Rs. 946037.0

Add 7.50% for Eletrification Installation Rs. 70953.0


Add 7.50% for Sanitary . Installation Rs. 70953.0
G.Total 1087943.0
Rs.

Executive Engineer,
I&PH Division, Rampur.
DETAIL OF MEASUREMENT PHASE
S H :- Construction of Pump House cum attendant quarter in frame structures. (above 50BHP)
Sr. Description. No. L B H Total
No. Qty.
1 Excavation in foundation
trenches.
Column. 8 1.2 1.2 1.6 18.43 Cum
2 P/L C.C 1:4:8
Column. 8 1.2 1.2 0.23 2.65 Cum
Bed.
3 P/L C.C 1:6:12
P/House. 1 6.75 4.55 ------- 0.1 3.07
Att. Qtr. 1 2.75 4.55 ------- 0.1 1.25
Out side. 1 35.8 0.6 ------- 0.1 2.15
Tatal 6.47 Cum
4 P/L RCC 1:2:4 work
a) In footing area 8 1.2 1.2 0.25 2.88
In Trap. Portion.
----- 0.67 1.53 4.5 4.04
8x0.50/6 (1.20)²+(0.30)²+4x(1.20+0.30)² Total 6.92 Cum
2
b) For Column :---
Above Trap. Portion upto
ground level. 8 0.3 0.3 0.6 0.43

Above ground level upto


slab level. 8 0.3 0.3 3.3 2.38
Total 2.81 Cum
c) In plinth in lintels beams.
Long side. 2X2 4 9.85 0.3 0.3 3.55
Short side. 2X3 6 4.78 0.3 0.3 2.58
5 Vert. F/Side. 1x2 2 1.5 0.3 0.3 0.27
Shalves 4 3.5 0.6 0.075 0.63
4 1.4 0.6 0.075 0.25
For slab. 1X1 1 11.05 5.98 0.1 6.61
Slopping surface 2 3 1.95 0.1 1.17
Total 15.06 Cum
d) Stria Case 1 3.8 1.2 0.15 0.68
12 0.2 0.15 0.5 0.18
Total 0.86 Cum
5 Providing form work for steel plate
a). Foundation and footing. 8X4 32 0.6 ------ 0.3 5.76 Sqmt
b). Column. 8X4 32 3 ------ 0.3 28.8 Sqmt
c). Plinth and lintels beams.
Outer side L/Side. 2X2 4 9.85 ------ 0.3 11.82
Outer side S/Side. 2X2 4 4.78 ------ 0.3 5.74
Inner side L/Side. 2X2 4 6.75 ------ 0.3 8.1
-do- S/Side. 2X4 8 4.55 ------ 0.3 10.92
Vert. F/Side. 2X4 8 1.5 ------ 0.3 3.6
Total 40.18 Sqmt
d). Slab. 1 11.05 5.98 ------ 66.08 Sqmt
Shalves 4 3.5 0.6 ----- 8.4
4 1.4 0.6 ----- 3.36
Total 77.84 Sqmt
e) Slopping surface 2 3 1.95 ----- 11.7 Sqmt
f) Edge of slab. 2 11.05 ------ ------ 22.1

Page 14 of 136
2 5.98 ------ ------ 11.96
Total 34.06 Sqmt
g) Stria Case 1 3.8 1.2 --- 4.56
12 1.2 0.15 --- 2.16
Total 6.72 Sqmt

6 Providing mild steel.


Qty.carry over from item Nos (.4,a,b,c,d) 6.92 2.81 15.06 0.86 25.65 Cum
25.65 105 kg/cum 2693.25 Kg
7 Half brick masonry 1:3
P/House. L/side. 2 6.58 ------ 3.3 43.43
-do- S/side. 2 2.58 ------ 3.3 17.03
Att.Qtr. L/Side. 2 4.32 ------ 3.3 28.51
-do- S/side. 1 4.32 ------ 3.3 14.26
Gabal area 2 2.5 0.75 0.5 1.88
Terrace wall 2 11.05 ------ 0.4 8.84
Cub Board wall 2 11.05 ------ 0.4 8.84
2 3.3 ------ 0.4 2.64
Total 125.43 Sqmt
Deduction.
D 1 1.2 ------ 2.55 3.06
D1 2 0.95 ------ 2.55 4.85
W 3 1.65 ------ 1.65 8.17
W1 1 0.6 ------ 1.65 0.99
V 1 1.65 ------ 0.55 0.91
Total 14.92 Sqmt
Net Qty 125.43 14.92 110.51 Sqmt

8 Prov. Press steel frame for


doors & windows.
Profile(A)
Ventilator. H 2 1.65 --- ---- 3.3
V 2 0.55 --- ---- 1.1
W1 H 2 1.6 --- ---- 3.2
V 2 0.6 --- ---- 1.2
Total 8.8 Rmts
Profile(B).
Doors. D H 1 1.2 --- ---- 1.2
V 2 2.55 --- ---- 5.1

D1 H 1 0.95 --- ---- 0.95


V 2 2.55 --- ---- 5.1

Window. W H 2x3 6 1.65 --- ---- 9.9


V 2x3 6 1.65 --- ---- 9.9
Total 32.15 Rmts
Profile -C)
Doors D H 1 1.2 --- ---- 1.2
D1 H 2 0.95 --- ---- 1.9
Windows. W H 2x3 6 1.65 --- ---- 9.9
V 2x3 6 1.65 --- ---- 9.9
Total 22.9 Rmts
9 P/F paneled & glazed shuttering
for doors and windows.
Door. D 1 1.12 -------- 2.05 2.3
1 1.12 -------- 0.4 0.45
D1 1 0.87 -------- 2.05 1.78

Page 15 of 136
1 0.82 -------- 0.4 0.33

Window. W 3X3 6 1.13 -------- 0.4 2.71


3X3 6 0.4 -------- 0.4 0.96

W1 1 1.13 -------- 0.4 0.45


1 0.4 -------- 0.4 0.16

Ventilator. V 3 0.4 -------- 0.4 0.48


Tatal 9.62 Sqmt

10 P/F wire gauge shuttering


for doors and windows.
Door D 1 1.12 -------- 2.05
1 1.12 -------- 0.4 0.45

D1 1 0.87 -------- 2.05 1.78


1 0.82 -------- 0.4 0.33

Window. W 1x3 3 1.13 -------- 0.4 1.36


1x3 3 0.4 -------- 0.4 0.48
Tatal 4.4 Sqmt

11 15mm thick cement plaster


1:6 Fair side.

Outer side L/side. 2 9.85 3.3 ----- 65.01


-do- S/side. 2 4.78 3.3 ----- 31.55
Mid wall. 2 4.55 3.3 ----- 30.03
Shalves 2 4 3.5 0.6 ---- 16.8
2 4 1.4 0.6 ---- 6.72
Shalves wall 2 2 3.3 0.6 ---- 7.92
Tatal 158.03 Sqmt
Deduction. D 1 1.2 ----- 2.55 3.06
D1 2 0.95 ----- 2.55 4.85
W 3 1.65 ----- 1.65 8.17
W1 1 0.6 ----- 1.65 0.99
V 1 1.65 ----- 0.55 0.91
Total 17.98 Sqmt

Net Qty 158.03 17.98 140.05 Sqmt

12 20mm thick cement plaster


1:6 rough side
P/House Inner side L/Side 2 6.75 ------ 3.3 44.55
-do- S/Side. 2 4.55 ------ 3.3 30.03
Att/Qtr.Inner side L/Side. 2 2.75 ------ 3.3 18.15
-do- S/Side. 2 4.55 ------ 3.3 30.03
Total 122.76 Sqmt

13 6mm thick cement plaster 1:3


Pump Room 1 6.75 4.55 ------ 30.71
Att.Qtr. 1 2.75 4.55 ------ 12.51

Projected slabs Front & back. 2 11.05 0.6 ------ 13.26

Page 16 of 136
2 5.98 0.6 ------ 7.18

Sloped slab. 2 3 1.95 ------ 11.7


Total 75.36 Sqmt
14 White washing

Same qty. of item No.( 11 ,12 ,13) 140.05 122.76 75.36 338.17 Sqmt

15 Distempering two coats with


oil bound.
Same qty. as per item No. 12 Total 122.76 Sqmt
16 Finishing with water proofing
cement paint.
Same qty. as per item No. 11 Total 140.05 Sqmt

17 Precast.trrazo tile flooring


a)20mm thick floor.
P/House. 1 6.75 4.55 ----- 30.71
Att.Qtr. 1 2.75 4.55 ----- 12.51
Ver. 1 1.5 5.05 ----- 7.58
Tatal 50.8 Sqmt
b)Step and dado etc.
Trad. 3 1.8 0.3 ----- 1.62
Riser. 4 1.8 0.18 ----- 1.3
Landing. 1 0.6 1.8 ----- 1.08
Tatal 4 Sqmt
18 Appling priming two coats
a) Door D 2X1 2 1.2 2.55 1.33 8.14
D1 2X1 2 0.95 2.55 1.33 6.44
Window. W 2X3 6 1.65 1.65 0.8 13.07
W1 2X1 2 0.6 1.65 0.8 1.58
Ventilator. V 2X1 2 1.65 0.55 0.8 1.45
P/F wire gauge shuttering
for doors and windows.
b) Door. D 1X2 2 1.12 2.05 0.8 3.67
1X2 2 1.12 0.4 0.8 0.72

D1 1X2 2 0.87 2.05 0.8 2.85


1X2 2 0.82 0.4 0.8 0.52
Window. W 2X2 6 1.13 0.4 0.8 2.17
2X3 6 0.4 0.4 0.8 0.77
Total 41.38 Sqmt
19 Painting two coat over new wood.with paint
Same qty. as per item No. 18 Total 41.38 Sqmt
Painting two coat other than white paint. Dv 1 1.2 0.4 -------- 0.48
1 0.95 0.4 -------- 0.38
3x3 9 1.65 0.4 -------- 5.94
1 1.65 0.6 -------- 0.99
3 1.65 0.55 -------- 2.72
Total 10.51 Sqmt
20 Prov. Steel work for Grill.
a)Flat 12x6mm thick. V 2 3 3 1.65 29.7
H 2 2 3 1.65 19.8
W1 V 2 1 1 1.65 3.3
H 1 1 3 1.65 4.95
V V 2 1 3 0.55 3.3
H 1 1 2 1.65 3.3

Page 17 of 136
Total 64.35 Rmts
Total 64.35 0.6 Kg/Rmts 38.61 Kg ---a
b).Squar bar 10mm dia V 3 5 3 1.65 74.25
H 1 3 3 1.65 14.85
W1 V 1 1 5 1.65 8.25
H 1 1 3 0.6 1.8
V V 1 3 5 0.55 8.25
H 1 1 1 1.65 1.65
Ver. 1 1 1.2 55 66
Total 175.05 Rmts
Total 175.05 0.78 Kg/Rmts 136.54 Kg ---b
Net Qty 38.61 136.54 175.15 Kg
21 Stone soling 15mm thick.
P/House. 1 6.75 4.55 0.15 4.61
Att. Qtr. 1 2.75 4.55 0.15 1.88
Out side. 1 35.8 0.6 0.15 3.22
Total 9.71 Cum

22 P/F MS sliding door. 2 1 2 Nos

23 P/F MS tower bolts barred.

Door. 2 2 4 Nos
Window. 2 3 6
2 3 6 16
Ventilator. 2 2 4 Nos

24 Providing & fixing MS handles


Door. 2 2 4 Nos
Window. 2 3 6
W1 1 2 2 10
Ventilator. 1 2 2 Nos

25 Providing flat iron hold fast 40mm long.


Door 2 6 12
Window. 4 4 16
Ventilator. 2 1 2
Total 30 Nos

26 Prov. Plinth protection 50mm thick


in C.M 1:3:6
Front & back 2 11.05 0.6 ------ 13.26
Side. 2 4.78 0.6 ------ 5.74
Ver. 2 1.5 0.45 ------ 1.35
Drain bed/side. 1 35.8 0.6 ------ 21.48
Total 41.83 Sqmt
27 Prov. Brick clay tile over 1x2 2 3 1.95 ----- 11.7 Sqmt
sloped slab.

Junior Engineer, Assistant Engineer, Executive Engineer,

Page 18 of 136
IPH Sub- Division, IPH Sub-Division, I P H Division, Rampur.
Nankhari Nankhari

Page 19 of 136
0
S H :- Construction of Pump House cum attendant quarter in frame structures. (above 55BHP)

PHASE #REF! PUMP HOUSE CUM ATTENDENT ROOM


1105
985

V
RCC SHELF PANEL BOARD
COOKING WORK W -60 AT
TAP SHELF 140X60 C 210 HT
AT 85 HT

W ATT. ROOM PUMP ROOM M &P


478 60
275X455 W1 675 X 455 W

583
M & P

RCC SHELF 60 W AT 210 HT RCC BEAM 30 X30

D1 D
W
60

45 SLAB PROJECTION 60 CM
ENT.VER. 150 WIDE
150 WITH RCC SLOPY SLAB HALF BRICK MASONARY

RCC COLUMN 30 X 30

505
PLAN (FOR PUMPING SETS 55 TO 125 HP )
( 62.95 SQMT )

JUNIOR ENGINEER ASSISTANT ENGINEER EXECUTIVE ENGINEER


VERMA
CHIRHAON CHIRGAON IPH DIVI. ROHRU
Sr.No Discription of Items Quantity Unit Rate Amount

1 Excavation in earth work in all kind of soil stacking excavated soil in the plinth sides of foundation and then 18.43 m3 175.40 3233.00
disposing of all surplus soil in all leads & lifts as directed by Engineer in Charge.
2 P/L CC 1:4:8 1cement:4 sand:8 graded aggregates 40mm nominal size curing complete excluding cost of form 2.65 m3 4390.50 11635.00
work infoundation & plinth
3 P/L CC 1:6:12 1cement:6 sand:12 graded aggregates 40mm nominal size curing complete excluding cost of form 6.47 m3 4068.14 26321.00
work infoundation & plinth
4 Providing & laying CC 1:2:4 1cement:2 sand 4 graded aggregates 20mm nominal size curing complete excluding
cost of form work & reinforcement for RCC work in:-

I) foundation footing and bases of columns & like mass concrete. 6.92 m3 5419.50 37503.00

ii) Column.pillar & post upto floor two level 2.81 m3 5492.10 15433.00
iii) In suspended floor roofs landing shalves & their support balconies,beams, girders bressumers cantilevers upto 15.06 m3 5464.50 82295.00
floor two level
iv) Stair cases (except spiral stair cases) excluding landing I/c preparation of surfaces 0.86 m3 5464.50 4699.00
5 Providing form work with steel plates 3.15mm thick so as to give fair finish I/c centering shuttering propping etc. 0.00
height of propping below supporting floor to ceiling not exceeding 4mt. Height & removal of same in situ
reinforce ment concrete and plain concrete work in :-
a) Foundation footing bases of columns & mass concrete. 5.76 m2 112.77 650.00
b) Column.pillar & post upto floor two level square, rectangular& polygonal in plan. 28.80 m2 112.77 3248.00
c) Beams, cantilever Girders& lintals sides&soffits of beams, beams,haunching cantilever girders not exceeding 40.18 m2 272.90 10965.00
1mtr. Depth.
d) Flat surfaces such as soffits of suspended floor roofs landing & like floor etc.,upto 200mm thickness. 77.84 m2 272.90 21243.00
-----2----
e) Slopping and battering surfaces I/c folding plates where inclination to horizontal plane not exceeding 30 degrees. 11.70 m2 147.80 1729.00

f) Edge of slab and break in floor 20 cm wide 34.06 Rmts 35.10 1196.00
g) Stair cases (except spiral stair cases) excluding landing I/c preparation of surfaces 6.72 m2 91.50 615.00

6 Providing mild steel/tor steel reinforcement I/c bending binding and placing in position complete 2693.25 Kg 46.40 124967.00
7 Half Brick masonary using common burnt clay building bricks above plinth upto floor two level in cm 110.51 m2 892.70 98652.00
1:4(1cement:4sand)conventiohal brick first class
8 Providing and fixing pressed steel door, frames, manufactured from comercial mild steel sheet of 1.25 mm 0.55 Cum. 61823.50 34003.00
thickness including hinges jump block Jamb, beed, and if required angle threshold of mil steel angle of section
50x25mm or base ties of 1.25mm pressed mild steel welded or regidly fixed together by machanical means
adjustable lugs with split and tails to each Jamb i/c steel but things 2.5mm thick with guards lock strike plate and
shock as specified and applying a coat of applying steel primer after pretreatment of the surfaces directed by the
Engineer-in-charge

9 Providing and fixing Pannelled and glazed shutters for doors windows and clear storey windows including bright 14.48 m2 2550.00 36924.00
finish black enamel led iron butt hinges with necessary screws 40mm thick: 2nd class deodar wood.

10 P/F wire gause shutters using MS wire gause of IS gause designation 85 G for doors windows clerestorey 14.48 m2 1875.30 27154.00
windows I/c bright finished black enamelled iron hinges with necessary secrews 30 mm thick 2nd class deodar
wood.
11 15 mm thick cement plaster on fair sides of brick/stone masonery convrete walls for interior plastering upto floor 140.05 m2 104.10 14579.00
two level including arises internal rounded angles not exceeding 80mm girth in cm 1:6 (1cement:6sand)

12 20 mm thick cement plaster on rough sides of brick/stone masonery convrete walls for interior plastering upto floor 122.76 m2 104.10 12779.00
two level including arises internal rounded angles not exceeding 80mm girth in cm 1:6 (1cement:6sand)

13 6 mm thick cement plaster in CM 1:3( 1cement 3 sand in roof slabs 75.36 m2 62.99 4747.00
14 White washing with lime on undecorated wall surfaces(two coats) to give an even shade I/c thoroughly brooming 338.17 m2 5.76 1948.00
the surface to remove all dust dirt & other foreign matter.
15 Distempering (two coats) with oil bond distemper of approved brand and manufacture and of required shade on 122.76 m2 37.00 4542.00
undecorated surfaceto give an even shade and including priming coat with distemper after throughly brushing the
surface free from mortar dropping and other foreign matters.

---------3--------
16 Finishing wall with water profing cement paint of approved brand and manufacture and of rerquired shade on 140.05 m2
undecorated wall surfaces (two coats) to give an even shade after thoroughly brushing the surface to remove all dirt
and remains of loose powdered materials.

17 Precast terrazo tiles 20m thick (with marble chipsof specified shadeand of specified laid in floor treads of steps and 50.80 m2
landingon bed on10mm thick cement plaster 1:6 (1cement6sand) jointed withneat cement slurry mixed with
pigment to match the shade of tiles. selvary grey

b) In Skirting & riser ofsteps and dado incement plaster 1:3 (1cement:3sand) and jointed with white slurry. 4.00 m2
Selvary grey
18 Applying priming coat over new wood and wood based surfaces after and including preparing the surface by 41.38 m2 25.50 1055.00
throughly cleaning oil grease & dirt and other foreigm matter
19 (a) Painting two coats(excluding priming coat) on new wood and wood based surfaces with ready mixed paint 41.38 m2 44.74 1851.00
brushing to give even shade including cleaning all dirt, dust and other foreign matters white paint
20 Providing and fixing of MS grill of required patttern in wooden frame of window etc. with MS rounded headed 175.15 Kg
bolts and nuts or by screw: Plain Grill.
21 Stone soling properly hand packed filling interstices with spalls and consolidating with power road roller to the 9.71 m3
required gradient and camber including spreading watering and rolling of binding materials moorum or earth etc.
100mm spread thickness (finished work including materials and labour) within all leads and lifts an da directed by
the Engineer-in-charge.
22 Providing and fixing anodized aluminium sliding door bolts withnuts and screws complete I) 250mmX16mm 2.00 Nos
23 Providing and fixing anodized aiuminium. tower bolts barrel type with screws etc. complete.
I) 200mmX10mm 4 Nos
ii) 150mmx10mm 16 Nos
24 Providing and fixing anodized aluminium .handles with screws etc. complete.
I)125mm dia 4 Nos
ii) 100mm dia 10 Nos
25 Providing 40x3 mm flat iron hold fast 40cm. Long including fixing to frame with 10mm dia metres bolts, nuts and 30 Nos
wooden plug and embedding in cement concrete block 30x10x15cm. 1:3:6( 1cement:3sand:6 graded stone att.
20mm nominal size) within all leads and lifts and as directed by the Engineer-in-charge.

26 Providing plinth protection 50mm thick in cement concrete 1:3:6(1cement:3sand:6graded stone agg. 20mm 42 /Sqmt.
nominal size) i/c finishing the top surface of concrete smooth within all leads and lifts and as directed by the
Engineer-in-charge.
27 Providing and laying brick tiles over mumty roofs grouted with cement mortar 1:3 over a 12mm layer of cement 11.70 m2
mortar 1:3 and finished needly within all leads and lifts and as directed by the Engineer-in-charge.
Tatal Rs
Say Rs
Cost of Nos Rs

Junior Engineer, Assistant Engineer, Executive Engineer,


IPH Sub- Division, IPH Sub-Division I P H Division, Rampur.
Nankhari. Nankhari.
ABSTRACT OF COST
0 ANN.
0 0
Sr.No Discription of Items Quantity Unit Rate

1 Excavation in earth work in all kind of soil stacking excavated soil in the plinth sides of foundation and then 18.43 m3 #REF!
disposing of all surplus soil in all leads & lifts as directed by Engineer in Charge.
2 P/L CC 1:4:8 1cement:4 sand:8 graded aggregates 40mm nominal size curing complete excluding cost of form 2.65 m3 #REF!
work infoundation & plinth
3 P/L CC 1:6:12 1cement:6 sand:12 graded aggregates 40mm nominal size curing complete excluding cost of form 6.47 m3 #REF!
work infoundation & plinth
4 Providing & laying CC 1:2:4 1cement:2 sand 4 graded aggregates 20mm nominal size curing complete
excluding cost of form work & reinforcement for RCC work in:-

I) foundation footing and bases of columns & like mass concrete. 6.92 m3 #REF!

ii) Column.pillar & post upto floor two level 2.81 m3 #REF!
iii) In suspended floor roofs landing shalves & their support balconies,beams, girders bressumers cantilevers upto 15.06 m3 #REF!
floor two level
iv) Stair cases (except spiral stair cases) excluding landing I/c preparation of surfaces 0.86 m3 #REF!
5 Providing form work with steel plates 3.15mm thick so as to give fair finish I/c centering shuttering propping
etc. height of propping below supporting floor to ceiling not exceeding 4mt. Height & removal of same in situ
reinforce ment concrete and plain concrete work in :-
a) Foundation footing bases of columns & mass concrete. 5.76 m2 #REF!
b) Column.pillar & post upto floor two level square, rectangular& polygonal in plan. 28.80 m2 #REF!
c) Beams, cantilever Girders& lintals sides&soffits of beams, beams,haunching cantilever girders not exceeding 40.18 m2 #REF!
1mtr. Depth.
d) Flat surfaces such as soffits of suspended floor roofs landing & like floor etc.,upto 200mm thickness. 77.84 m2 #REF!
-----2----
e) Slopping and battering surfaces I/c folding plates where inclination to horizontal plane not exceeding 30 degrees. 11.70 m2 #REF!

f) Edge of slab and break in floor 20 cm wide 34.06 Rmts 35.10


g) Stair cases (except spiral stair cases) excluding landing I/c preparation of surfaces 6.72 m2 #REF!

6 Providing mild steel/tor steel reinforcement I/c bending binding and placing in position complete 2693.25 Kg #REF!
7 Half Brick masonary using common burnt clay building bricks above plinth upto floor two level in cm 110.51 m2 #REF!
1:4(1cement:4sand)conventiohal brick first class
8 Providing and fixing pressed steel door, frames, manufactured from comercial mild steel sheet of 1.25 mm
thickness including hinges jump block Jamb, beed, and if required angle threshold of mil steel angle of section
50x25mm or base ties of 1.25mm pressed mild steel welded or regidly fixed together by machanical means
adjustable lugs with split and tails to each Jamb i/c steel but things 2.5mm thick with guards lock strike plate and
shock as specified and applying a coat of applying steel primer after pretreatment of the surfaces directed by the
Engineer-in-charge

9 Providing and fixing Pannelled and glazed shutters for doors windows and clear storey windows including 14.48 m2 #REF!
bright finish black enamel led iron butt hinges with necessary screws 40mm thick: 2nd class deodar wood.

10 P/F wire gause shutters using MS wire gause of IS gause designation 85 G for doors windows clerestorey 14.48 m2 #REF!
windows I/c bright finished black enamelled iron hinges with necessary secrews 30 mm thick 2nd class deodar
wood.
11 15 mm thick cement plaster on fair sides of brick/stone masonery convrete walls for interior plastering upto floor 140.05 m2 #REF!
two level including arises internal rounded angles not exceeding 80mm girth in cm 1:6 (1cement:6sand)

12 20 mm thick cement plaster on rough sides of brick/stone masonery convrete walls for interior plastering upto 122.76 m2 #REF!
floor two level including arises internal rounded angles not exceeding 80mm girth in cm 1:6 (1cement:6sand)

13 6 mm thick cement plaster in CM 1:3( 1cement 3 sand in roof slabs 75.36 m2 70.65
14 White washing with lime on undecorated wall surfaces(two coats) to give an even shade I/c thoroughly 338.17 m2 #REF!
brooming the surface to remove all dust dirt & other foreign matter.
15 Distempering (two coats) with oil bond distemper of approved brand and manufacture and of required shade on 122.76 m2 #REF!
undecorated surfaceto give an even shade and including priming coat with distemper after throughly brushing
the surface free from mortar dropping and other foreign matters.

---------3--------
16 Finishing wall with water profing cement paint of approved brand and manufacture and of rerquired shade on 140.05 m2 #REF!
undecorated wall surfaces (two coats) to give an even shade after thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials.

17 Precast terrazo tiles 20m thick (with marble chipsof specified shadeand of specified laid in floor treads of steps 50.80 m2 #REF!
and landingon bed on10mm thick cement plaster 1:6 (1cement6sand) jointed withneat cement slurry mixed with
pigment to match the shade of tiles. selvary grey

b) In Skirting & riser ofsteps and dado incement plaster 1:3 (1cement:3sand) and jointed with white slurry. 4.00 m2 #REF!
Selvary grey
18 Applying priming coat over new wood and wood based surfaces after and including preparing the surface by 41.38 m2 #REF!
throughly cleaning oil grease & dirt and other foreigm matter
19 (a) Painting two coats(excluding priming coat) on new wood and wood based surfaces with ready mixed paint 41.38 m2 #REF!
brushing to give even shade including cleaning all dirt, dust and other foreign matters white paint
20 Providing and fixing of MS grill of required patttern in wooden frame of window etc. with MS rounded headed 175.15 Kg #REF!
bolts and nuts or by screw: Plain Grill.
21 Stone soling properly hand packed filling interstices with spalls and consolidating with power road roller to the 9.71 m3 #REF!
required gradient and camber including spreading watering and rolling of binding materials moorum or earth
etc. 100mm spread thickness (finished work including materials and labour) within all leads and lifts an da
directed by the Engineer-in-charge.
22 Providing and fixing anodized aluminium sliding door bolts withnuts and screws complete I) 250mmX16mm 2.00 Nos #REF!
23 Providing and fixing anodized aiuminium. tower bolts barrel type with screws etc. complete.
I) 200mmX10mm 4 Nos #REF!
ii) 150mmx10mm 16 Nos #REF!
24 Providing and fixing anodized aluminium .handles with screws etc. complete.
I)125mm dia 4 Nos #REF!
ii) 100mm dia 10 Nos #REF!
25 Providing 40x3 mm flat iron hold fast 40cm. Long including fixing to frame with 10mm dia metres bolts, nuts 30 Nos #REF!
and wooden plug and embedding in cement concrete block 30x10x15cm. 1:3:6( 1cement:3sand:6 graded stone
att. 20mm nominal size) within all leads and lifts and as directed by the Engineer-in-charge.

26 Providing plinth protection 50mm thick in cement concrete 1:3:6(1cement:3sand:6graded stone agg. 20mm 42 /Sqmt. #REF!
nominal size) i/c finishing the top surface of concrete smooth within all leads and lifts and as directed by the
Engineer-in-charge.
27 Providing and laying brick tiles over mumty roofs grouted with cement mortar 1:3 over a 12mm layer of cement 11.70 m2 #REF!
mortar 1:3 and finished needly within all leads and lifts and as directed by the Engineer-in-charge.
Tatal Rs
Say Rs
Cost of #REF! Nos Rs

Junior Engineer, Assistant Engineer, Executive Engineer,


IPH Sub- Division, IPH Sub-Division I P H Division, Rohru.
Chirgoan. Chirgoan

:--- Er.VERMA (Gr.J.E)


0
0
Amount

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!
#REF!
#REF!

#REF!

#REF!

1196.00
#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

5324.00
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!

#REF!

#REF!
#REF!
#REF!

Executive Engineer,
I P H Division, Rohru.
CARRIAGE OF MATERIAL BY MECHANINCAL TRANSPORT
Sr. Average (n) No. of No. of Ltrs. of Cost of Ltrs. of Cost of Cost of Hire Total Cost Cost Increase
No. Km. 6 Charges per in cost/Km
over
previous
km.
lead speed trips done Diesel Diesel @ M/oil M/Oil @ Beldar @ @ 6+8+9+10 trip
in Km km/ 8/ ** ** **
"L" "s" "N" consu - 35.75 consu - 110.00 116.67 1500.00
hr (s) (2L/s+1.25) (2NL+6) med per litre. med per litre per day per day
1. 2. 3. 4. 5. 6 7. 8. 9. 10. 11. 12. 13.
1 12.00 5.65 17.29 5.77 206.28 0.22 24.20 700.00 1500.00 2430.48 430.40
2 12.75 5.12 26.46 8.82 315.32 0.33 36.30 700.00 1500.00 2551.62 498.75 68.36
3 13.12 4.69 34.11 11.38 406.84 0.43 47.30 700.00 1500.00 2654.14 566.43 67.68
4 13.50 4.34 40.73 13.58 485.49 0.51 56.10 700.00 1500.00 2741.59 631.53 65.10
5 13.88 4.06 46.60 15.53 555.20 0.58 63.80 700.00 1500.00 2819.00 694.34 62.81
6 14.25 3.82 51.89 17.28 617.76 0.65 71.50 700.00 1500.00 2889.26 755.58 61.24
7 14.63 3.62 56.75 18.89 675.32 0.71 78.10 700.00 1500.00 2953.42 814.75 59.17
8 15.00 3.45 61.25 20.40 729.30 0.77 84.70 700.00 1500.00 3014.00 872.80 58.05
9 15.38 3.30 65.49 21.86 781.50 0.82 90.20 700.00 1500.00 3071.70 929.47 56.66
10 15.75 3.17 69.50 23.14 827.26 0.87 95.70 700.00 1500.00 3122.96 983.67 54.20
11 16.13 3.06 73.32 24.44 873.73 0.92 101.20 700.00 1500.00 3174.93 1037.54 53.87
12 16.50 2.96 77.04 25.68 918.06 0.96 105.60 700.00 1500.00 3223.66 1089.82 52.27
13 16.88 2.87 80.53 26.87 960.60 1.01 111.10 700.00 1500.00 3271.70 1141.31 51.49
14 17.25 2.78 83.96 27.95 999.21 1.05 115.50 700.00 1500.00 3314.71 1190.47 49.17
15 17.63 2.71 87.30 29.10 1040.33 1.09 119.90 700.00 1500.00 3360.23 1239.98 49.50
Avg. cost
per km
after
5 kms.

14.

Avg.
57.87 (6-10)

Avg.
Analysis of Rate
Providing and fixing Pressed steel doors frames manufactured from commercial mild sheet of 1.25 mm .
thickness i/c hings jump lock
Detail of cost for 5 metres.
Sr.No. Description Unit Quantity
Material :
Press steel frame size 1 mtr x2 mtr.
Vertical 2x2 4
Top 1x1 1
Total : 5 Rmt
Press sheetof 1.25mmthick
Weight per Rmt.2.44 Kg. 2.44 Kg.
per mtr lugs tail and head port.
.037+0.077 0.114 Kg.
Hinghes weightrequired for Rm 0.128
Lode strike plate shock 0.012 Kg.
weight for Rmt. 2.694
Weight for 5 Rmt. 13.47 Kg. Kg. 13.47 Kg.

Carriage L-S
LABOUR :
Fitter Each 0.15 No.
Beldar Each 0.2 No.

Add 10% conttractor profit & 5% O.H. Charges except priming coat :
Cost for 5 Rmt.
Cost for 1 Rmt.

Analysis of Rate

Providing and fixing Pressed steel doors frames manufactured from commercial mild sheet of 1.25 mm .
thickness i/c hings jump lock
Detail of cost for 5 metres.
Sr.No. Description Unit Quantity
MATERIALS

7.8Kg./Sqm= 45.216 Kg.


Wastage @ 10%= 4.522 Kg. Quintal 0.497 Qtl.
Total : 49.738 Kg.or 0.497 Qtl.
Gusset plate .3x.04 0.012
1x0.26 (0.04+0.03)/2 0.0442
Total : 0.0562
8x 0.0562 0.4496
2x22 (.3) 2 0.0414
Total 0.491
@ 24.73 Kg/Sqrm 14.62
Add 10% wasted 1.462
total: 16.082 Kg.or .161 Quintal 0.161
Angle iron 40x40x6mm@ 3.5 Kg/m
side 4x2.4 9.6 M
Top& Bot. 4x1.2 4.8 M
Diagonal 2x2.5 5 M
2x2.45 4.9 M
Total:- 24.3 M
Add 10% wasted 2.43
Total:- 26.73 M
Angle iron @ 3.5 Kg/m 93.555 Kg
0r .936 Quintal Quintal 0.936
M.S cleats bolt and nuts Each 4
Hocks Each 2
Priming Coat
M.S sheet 11.52 Sqr.
A/Iron .16x24.3 3.89 Sqr.
total:- 15.41 Sqr. Sqr 15.41
handle & Locking L-S
Revets etc. L-S
Carriage Steel
Km.By mechanical transport Tonne 0.2158 Tonne
Km.By head load Tonne 0.2158 Tonne
LABOUR :
Fitter Each 2.4 No.
Black smith Ist class Each 3.6 No.
Black smith 2nd class Each 4.8 No.
Beldar Each 0.6 No.
Mason Ist Class Each 0.07 No.
Mason IInd class Each 0.07 No.
Sundries : LS

Add 1.5% water charges except priming coat :

Add 10% conttractor profit & 5% O.H. Charges except priming coat :
Cost for 5.76 Sqrm.
Cost for one Sqrm.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Providing and fixing 1mm thick MS sheet sliding shutters with frame and diagonal braces of 40x40x 6mm
angle iron 3.15mm MS gusset plates at junction and corners 25mm dia pulley 40x40x6mm angle and T.iron
guide at the top and bottonm respectively , including applying a priming coat of red lead paint.
Detail of cost for one double leaf door , size 2.4mx2.4m= 5.76 Sqm.
Sr.No. Description Unit Quantity
Material :
MS sheet 1mm thick 5.76 Sqm @
7.8Kg./Sqm= 45.216 Kg.
Wastage @ 10%= 4.522 Kg. Quintal 0.497 Qtl.
Total : 49.738 Kg.or 0.497 Qtl.

Gusset plate 3.15mm Quintal 0.16 Qtl.

Anglre iron 40x40x6mm Quintal 1.39 Qtl.

Channel 25x25x6mm Quintal 0.11 Qtl.

Pulley 25mm dia Each 8 Nos.

Applying priming coat of red lead Sqm 18 Sqm


paint to MS sheet :

Pulley guide block drilling hole LS

Handle & locking arrangement LS

Bolts and rivets LS

Cement concrete. LS

Carriage of steel :
Km.By mechanical transport Tonne 0.2158 Tonne
Km.By head load Tonne 0.2158 Tonne
LABOUR :
Fitter Each 2.4 No.
Black smith Ist class Each 3.6 No.
Black smith 2nd class Each 4.8 No.
Beldar Each 4.8 No.
Mason Ist Class Each 0.07 No.
Mason IInd class Each 0.07 No.
Sundries : LS
Total :
Add 1.5% water charges except priming coat :

Add 10% conttractor profit & 5% O.H. Charges except priming coat :
Cost for 5.760 Sqm.

Cost for 1 Sqm.

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
P/F angle iron door, window,clerestory window frame manufactured from steel iron section of 40x40x6mm,
thickness including hinges jamb, lock jamb,beed and if rerquired angle threshold of mild steel angle 50x25mm
welded or rigidly fixed by mechanical means, lugs with split end tails to each jamb including butt hinges 2.50mm
thick with provision for locking arrangement and shock as specified and applying a coat of approved steel
primer after pretreatment of the surface as directed by the Engineer-in-charge.
Detail of cost for 5 mtrs.
Sr.No. Description Unit Quantity
MATERIAL:
1 Size of frame : 2+2+1= 5mtrs.
Wt. Of angle iron =5x3.5=17.50Kg.
Wastage 5%= = 0.88 Kg.
Total : 18.38 Kg.
Wt. Per m= 18.38/5= 3.68 Kg.
Hinges : ( 107.5x6)/5= 0.128 Kg./m
Shock absorber= 0.02 Kg./m
Lugs(tail) 0.077Kg./m
Total wt. = 3.883Kg./m
For 5 m= 5x3.887= 19.345Kg. Qtl. 0.1944 Qtl.

Welding charges by Elect. Plant Cm. 16 Cm.

2 Carriage charges : L.S.

3 Labour :
Fitter Each 0.15 No.
Beldar Each 0.2 No.
Sundries : L.S.

Add 10% for contractor profit &


5% for over head charges : Cost of 5 mtrs. :
Cost of 1 Mtr.=

Say : Rs.
Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

Analysis of Rate
P/F in position collapsible steel shutters with vertical channels 20x10x2mm and braced with flat iron diagonals
20x5mm size with top and bottom rails of T-iron 40x40x6mm with 38mm dia steel pulley complete with bolts &
nuts, locking arrangements, stoppers,handles, including applying a priming coat of red lead paint.
Detail of cost for a gate 2.4mx1.5m= 3.6Sqm
Sr.No. Description Unit Quantity
Material :
MS channels 18 No. on both sides
20x10x2mm@ 0.56Kg./m=
2x18x2.4= 86.40m Quintal 0.53 Qtl.
Wastage @ 10%= 8.64
95.04m @ .56= 53.22 Kg. Or 0.53 Qtl.

MS Tee 40x40x6mm Quintal 0.13 Qtl.

20x 5mm flat iron diagonal Quintal 0.6 Qtl.

Applying priming coat of red lead Sqm 10.5 Sqm


paint to MS sheet :

Pulley 38mm dia Each 10 Nos.

Handle & locking arrangement LS

Rivets, hooks, washers LS

Carriage of steel :
Km.By mechanical transport Tonne 0.126 Tonne
Km.By head load Tonne 0.126 Tonne
LABOUR :
Fitter Each 3.6 No.
Black smith Ist class Each 7.2 No.
Black smith 2nd class Each 7.2 No.
Beldar Each 9.6 No.
Mason Ist Class Each 0.6 No.
Mason IInd class Each 0.6 No.
Sundries : LS
Total :
Add 1.5% water charges except priming coat :

Add 10% conttractor profit & 5% O.H. Charges except priming coat :
Cost for 3.60 Sqm.
Cost for 1 Sqm.

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE

Providing & laying cement concrete 1:1.5:3 (1 cement : 1.5 Sand 3 graded stone aggregate
20 mm nominal size ) and curing complete excluding cost of form work & reinforcement for RCC
work in : Stair cases (except spiral stair cases)excluding landing but including preparing of the surface
and finishing of nosing up to floor two level.

Detail of cost for a flight of 3.40m clear span including 1 metre landing ( cost of landing excluding)

Sr.No. Desciption Unit Quantity


1 C.C 1:1.5:3(Detail& rate as per
sub analysis of C.C 1:1.5:3,
in foundation & plinth) cum. 0.79

2 Labour( Extra for laying C.C in


RCC work)
(a) Beldar Each 0.1
(b) Bhisti Each 0.2
© Mason Ist. Class Each 0.04
(d) Mason 2nd. Class Each 0.04
(e) Mate Each 0.04
Extra for finishing
(a) Mason Ist. Class Each 0.5
(b) Mason 2nd. Class Each 0.5
Extra labour for lifting material :
Beldar Each 0.17

Total 1+2=
Add 1.5% water charges on 2:

Add 10%contractor profit and #REF!


5% O.H charges except 1:
Cost for 0.79 cum. =
Cost of 1 cum. =
Say Rs.
Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE
P/F precast concrete man hole cover and frame, conforming to IS-12593-Part-I 1888 and IS 12592-Part-II,199
560mm diameter , Heavy duty.

Sr.No. Desciption Unit Quantity

1 Material :
Precast concrete man hole cover &
frame heavy duty, 560 mm diameter. Each 1 No.
Add 4% HPST

2 Carriage : LS

3 Labour :
Labour for laying man hole
cover and frame :
Beldar Each 0.14 No.

Add 10% contractor profit and


5% over head charges

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

P/F precast concrete man hole cover and frame, conforming to IS-12593-Part-I 1888 and IS 12592-Part-II,199
560mm diameter , Medium duty.

Sr.No. Desciption Unit Quantity

1 Material :
Precast concrete man hole cover &
frame medium duty, 560 mm diameter. Each 1 No.
Add 4% HPST

2 Carriage : LS

3 Labour :
Labour for laying man hole
cover and frame :
Beldar Each 0.14 No.

Add 10% contractor profit and


5% over head charges

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE
Laying in trenches G.M.S tubes and tube fittings (Earth work in trenches to be measured and paid
seperataly).
Unit :
Sr.No. Desciption Unit Quantity
1 Carriage
Km.By mechanical transport tonne 0.02
Km.By head load tonne 0.02
15 mm and 20 mm nominal
Labour :
Plumber( Fitter) Each 0.1
Beldar Each 0.19

Add 10% C.P.& 5%O.H.charges :


Cost of 10 Rmtr. =
Cost of 1 Rmtr. =
Say Rs.
2 Carriage
Km.By mechanical transport tonne 0.02
Km.By head load tonne 0.02
25 mm and 32 mm nominal
Labour :
Plumber( Fitter) Each 0.14
Beldar Each 0.3

Add 10% C.P.& 5%O.H.charges :


Cost of 10 Rmtr. =
Cost of 1 Rmtr. =
Say Rs.
3 Carriage
Km.By mechanical transport tonne 0.02
Km.By head load tonne 0.02
40 mm and 50 mm nominal
Labour :
Plumber( Fitter) Each 0.19
Beldar Each 0.4

Add 10% C.P.& 5%O.H.charges :


Cost of 10 Rmtr. =
Cost of 1 Rmtr. =
Say Rs.
4 Carriage
Km.By mechanical transport tonne 0.02
Km.By head load tonne 0.02
65 mm and 80 mm nominal
Labour :
Plumber( Fitter) Each 0.3
Beldar Each 0.79

Add 10% C.P.& 5%O.H.charges :


Cost of 10 Rmtr. =
Cost of 1 Rmtr. =
Say Rs.
5 Carriage
Km.By mechanical transport tonne 0.02
Km.By head load tonne 0.02
100mm
Labour :
Plumber( Fitter) Each 0.4
Beldar Each 1.19

Add 10% C.P.& 5%O.H.charges :


Cost of 10 Rmtr. =
Cost of 1 Rmtr. =
Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE
Providing & Laying cement concrete 1:1.5:3 ( 1 cement : 1.5 sand : 3graded stone aggregate 20mm
nominal size) and curing complete excluding cost of form work & reinforcement for reinforced
concrete work in (a) Columns,pillars,posts & struts upto floor two level..
.
DETAIL OF COST FOR 1.00 CUM.
Sr.No. Desciption Unit Quantity
1
MATERIALS
1 Stone aggregate 20mm Cum 0.57 cum
2 Stone aggregate 10mm Cum 0.28 cum
3 Sand Cum 0.425 cum
4 Cement Tonne 0.4 Tonne

CARRIAGE
1 Carriage of aggrergate 20mm
Km.By mechanical transport 0 Cum 0.85 cum
Km.By head load 0.5 Cum 0.85 cum
2 Sand
Km.By mechanical transport 49 Cum 0.425 cum
Km.By head load 0.5 Cum 0.425 cum
3 Cement
Km.By mechanical transport 31 Tonne 0.4 Tonne
Km.By head load 0.5 Tonne 0.4 Tonne

LABOUR
1 Beldar Each 3.59 Nos.
2 Bhisti Each 0.29 Nos.
3 Mason Ist. Class Each 0.1 Nos.
4 Mason 2nd. Class Each 0.1 Nos.
5 Mate Each 0.04 Nos.
6 Beldar for extra ramming. Each 0.25 Nos.
7 Scaffolding L.S.
Extra labour for laying CC in RCC
Beldar Each 0.1 Nos.
Bhisti Each 0.2 Nos.
Mason Ist. Class Each 0.04 Nos.
Mason 2nd. Class Each 0.04 Nos.
Mate Each 0.04 Nos.
Extra labour for lifting of material: Each 0.17 Nos.
Sundries. L.S.

Total:- A+B+C
Add for water charges @1.5%
Total:-
Add 10% contracto's profit & 5% over head charges on 1159.4
all except cement .&Carriage

Cost per Cum. Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon
ANALYSIS OF RATE
Providing & laying cement concrete 1:5:10 (1 cement : 5 Sand 10 graded stone aggregate
40 mm nominal size ) and curing complete excluding cost of centring & shuttering in
foundation & plinth.
DETAIL OF COST FOR 1.00 CUM.
Sr.No. Desciption Unit Quantity

MATERIALS
1 Stone aggregate 40mm Cum 0.65
2 Stone aggregate 20mm Cum 0.24
3 Sand Cum 0.47
4 Cement Tonne 0.13

CARRIAGE
1 Carriage of aggrergate 40mm
Km.By mechanical transport 13 Cum 0.65
Km.By head load 0.5 Cum 0.65
2 Stone aggregate 20mm
Km.By mechanical transport 0 Cum 0.24
Km.By head load 0.5 Cum 0.24
3 Sand
Km.By mechanical transport 13 Cum 0.47
Km.By head load 0.5 Cum 0.47
4 Cement
Km.By mechanical transport 31 Tonne 0.13
Km.By head load 0.5 Tonne 0.13

LABOUR
1 Beldar Each 2.09
2 Bhisti Each 0.27
3 Mason Ist. Class Each 0.05
4 Mason 2nd. Class Each 0.05
5 Mate Each 0.04
6 Beldar for extra ramming. Each 0.25
Sundries. L.S.

Total:- A+B+C
Add for water charges @1.5%
Total:-
Add 10% contractor profit & 5% over head charges on
all except cement .& Carriage #REF!
G.Total:-
Cost per Cum Rs.
Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

ANLYSIS OF RATE

ANALYSIS OF RATE
Providing and laying cement concrete 1:5:10 (1Cement:5Sand:10 graded stone aggregate, 40 mm nominal
size) with 15% plum and curing complete excluding cost of form work in retaining walls/breast walls, the size
of plums shall usually be 150mm to 300 mm as per HP.PWD specifications.

DETAIL OF COST FOR 1.00 CUM.


Sr.No. Desciption Unit Quantity
MATERIAL
(I) Stone aggregate 40 mm (one size) Cum 0.6 Cum

(ii) Stone aggregate , 20mm nominal Cum 0.22 Cum


size.

(iii) Sand Cum 0.43 Cum

(iv) Cement Tonne 0.12 Tonne

(v) Selected hard stone plums Cum 0.15 Cum

CARRIAGE
(I) Stone aggrergate above 40mm
Km.By mechanical transport Cum 0.6 cum.
Km.By head load Cum 0.6 cum.
(ii) Stone aggregate below 40 mm
Km.By mechanical transport Cum 0.22 cum.
Km.By head load Cum 0.22 cum.
(iii) Sand
Km.By mechanical transport Cum 0.43 cum.
Km.By head load Cum 0.43 cum.
(iv) Cement
Km.By mechanical transport Tonne 0.12 Tonne
Km.By head load Tonne 0.12 Tonne
(v) Soling stone for filling crates
Km.By mechanical transport Cum 0.15 cum.
Km.By head load Cum 0.15 cum.

LABOUR
Beldar Each 1.07 No.
Beldar (For extra ramming) Each 0.98 No.
Bhisti ( For extra ramming ) Each 0.25 No.
Mason Ist class. Each 0.17 No.
Sundries : L.S.
Total:-
Add for water charges @1.5%
Total:-
Add 10% contractor profit & 5% over head charges on #REF!
all except cement .
G.Total:-
Cost per Cum Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATES
Random rubble masonry / polygonal rubble masonry ( uncoursed/ brought to courses) with hard stone of
approved quality in foundation and plinth including levelling up with cement concrete 1:6:12 (1 Cement :
6 sand : 12 graded stone aggregate , 20mm nominal size ) in cement mortar 1:6( 1cement:6 sand)
Sr.No. Description of items Unit Quantity

Stone at quarry Cum 1 Cum


Through & bond stone Each 7 100No.
Cement mortar 1:6 Cum 0.33 Cum
Cement concrete 1:6:12 L.S
Carriage of stones
Km.By mechanical transport #REF! Cum 1.16 Cum
Km.By head load 0 Cum 1.16 Cum

LABOUR :
Mason II nd class Each 1.77 No.
Beldar Each 2.12 No.
Bhisti Each 0.09 No.
Sundries LS

Add 1.5% for water charges except on mortar :

Add 10% C.P. & 5% O.H. charges


except (A+B) : #REF!
Cost for 1 cum metre
Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Kota slab 55 mm thick in risers of steps, skirting dado and pillars laid on 12mm (average) cement mortar
1:3 and jointed with gray cement slurry mixed with pigment to match the shade of slab including rubbing and
polishing complete .
Detail of cost for 10Sqm. Detail of cost for 1 Sqm.
Sr.No. Desciption Unit Quantity Rate

MATERIAL

25mm thick kota stone slab( polished) Sqm 11.5 250


including 15% wastage.

Cement mortar 1:3


(1cement : 3 sand) Cum 0.144

Cement for slurry :


Tonne 0.064

Pigment dark shade Kg. 4.5 50

Carriage of Kota stone :


Km.By mechanical transport Tonne 0.67
Km.By head load Tonne 0.67
Carriage of cement :
Km.By mechanical transport Tonne 0.064
Km.By head load Tonne 0.064

Labour :
Mason -2nd class Each 6.5
Beldar Each 10.8
Beldar (skilled ) for rubbing and polishing Each 10.8

Total :
Add 1.5% for water charges :

Add 10% for contractor profit and 5% over head charges


except cement mortar : Cost of 10 Sqm.
Cost of 1 Sqm.
Say Rs.
Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Kota stone slab flooring 20mm (average) thick base of cement mortar 1:4(1cement:4sand) laid over and jointed
with grey cement slurry mixed with pigment to match the sahde of the slab including rubbing and polishing
complete.
Detail of cost for 10Sqm. Detail of cost for 1 Sqm.
Sr.No. Desciption Unit Quantity Rate

MATERIAL

40mm thick kota stone slab( polished) Sqm 11.5 275


including 15% wastage.

Cement mortar 1:4


(1cement : 4 sand) Cum 0.224

Cement for slurry :


For bedding = 44 Kg. Tonne 0.076
For joints = 32 Kg.
Total : = 76 Kg.
Pigment = (76x3.5)/5=5.30 Kg. Kg. 5.3 50

Carriage of Kota stone :


Km.By mechanical transport Tonne 1.07
Km.By head load Tonne 1.07
Carriage of cement :
Km.By mechanical transport Tonne 0.076
Km.By head load Tonne 0.076

Labour :
Mason -2nd class Each 7
Beldar Each 10.8
Beldar (skilled ) for rubbing and polishing Each 10.8

Total :
Add 1.5% for water charges :

Add 10% for contractor profit and 5% over head charges


except cement mortar : Cost of 10 Sqm.
Cost of 1 Sqm.

Say Rs.
Junior Engineer, Assistant Engineer, Executive Engineer,
IPH Chirgaon. I P H Chirgaon I.P.H.Division Rohru

Analysis of Rate 485.30


White glazed tiles 6 mm thick in flooring , treads of steps and landing laid on a bed of 12mm thick cement mortar
1:3 ( 1 cement : 3 sand) finished with flush pointing in white cement.

Detail of cost for 1 Sqm.


Sr.No. Desciption Unit Quantity Rate

MATERIAL
Glazed tiles 152mmx152mmx6mm size= 44.4 Nos.
Add 2.5% for wastage & breakage: 1.1 Nos.
Total : 45.5 Nos.
Say : 46 Nos.
Sqm 1 530

12 mm thick cement mortar 1:3


(1cement : 3 sand) Cum 0.015

Cement for slurry overhead @


3.3Kg. Per square metre=3.3 Kg. Tonne 0.0033 2700
or 0.0033 Tonne.

Carriage of tiles/ cement L.S.

Labour :
Mason -1st class Each 0.7
Beldar Each 0.7

Total :
Add 1.5% for water charges :

Add 10% for contractor profit and 5% over head charges


except cement mortar :

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon
Analysis of Rate 516.30
White glazed tiles 6 mm thick in skirting , risers of steps and dado 12mm thick cement mortar
1:3 ( 1 cement : 3 sand) & jointed with cement slurry.

Detail of cost for 1 Sqm.


Sr.No. Desciption Unit Quantity Rate

MATERIAL
Glazed tiles 152mmx152mmx6mm size= 44.4 Nos.
Add 2.5% for wastage & breakage: 1.1 Nos.
Total : 45.5 Nos.
Say : 46 Nos.
100 Nos. 46 600

12 mm thick cement mortar 1:3


(1cement : 3 sand) Cum 0.015

Cement for slurry overhead @


3.3Kg. Per square metre=3.3 Kg. Tonne 0.0033 2700
or 0.0033 Tonne.

Carriage of tiles/ cement L.S.

Labour :
Mason -1st class Each 0.77
Beldar Each 0.77
Sundries L.S.

Total :
Add 1.5% for water charges :

Add 10% for contractor profit and 5% over head charges


except cement mortar :

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate 872.50


P/F wire gauge shutters using galvanised M.S. wire gauge of I.S. gauge designation 85 G. with wire
of dia 0.56mm for doors, windows and clerestory windows including bright finished black enamelled iron hinges
with necessary screws :40mm thick 2nd class Deodar wood :
Detail of cost for 200x108 cm. = 2.16 Sqm.
S.No. Desciption Unit Quantity Rate
MATERIAL :
2nd class deodar wood : Cum. 0.057 #REF!
Wire gauge Sqm. 1.41 90
Iron Hinges 100x58x1.90mm 10 Nos. 6 60
Iron hinges 50x37x1.5mm 10 Nos. 2 48
Screws 40mm 100 Nos. 48 20
Screws 20mm 100 Nos. 8 15

Carriage of wood :
Km.By mechanical transport 0 KM Cum 0.057 0
Km.By head load 0.5 KM Cum 0.057 0

Labour :
Carpenter Ist class Each 0.75 #REF!
Carpenter II class Each 0.75 #REF!
Beldar Each 0.57 #REF!
Sundries : LS

Add 10% C.P. & 5% O.H. Charges :


Cost of 2.16 Sqm.
Cost of 1 Sqm.
Say Rs. #REF!

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
P/F 12mm thick 150mm wide pelmet with 25mm diametre wooden curtain rods and brackets including fixing
25x3mm MS flat at 10cm. Long and plugs etc. complete.
2nd class deodar wood :
Detail of cost for a pelmet 2 meter long.
Sr.No. Desciption Unit Quantity Rate

MATERIAL :
2nd class deodar wood : Cum. 0.00847

Wooden plugs I/c cutting masonry; Each 2 7

MS flat 25x3mm and 10cm. Long LS

Carriage of wood :
Km.By mechanical transport Cum 0.00847
Km.By head load Cum 0.00847

Labour :
Carpenter Ist class Each 0.2
Carpenter II class Each 0.12
Beldar Each 0.2
Sundries : LS

Add 10% C.P. & 5% O.H. Charges :


Cost of 2.00 m
Cost of 1 m
Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Steel work welded in built up section,trusses and framed work i/c.in beam joist
channals ,angle tees ,flats with connection plates or angle cleets

Sr.No. Desciption Unit Quantity Rate


Detail of cost for 9.067 Qtl.
MATERIAL :

R.S. joist 350x200 mm @ 56.9Kg/M


6.0m X 56.9Kg =341.4 Kg
Add5% wastage =17.07 Kg
358.47Kgor 3.585 Qtl. Qtl. 3.585 2600
25 Cm wide X 12mm thick plate
4 X6 X 8.25 = 565.25Kg.
Add5% wastage =28.25 Kg
Total =593.5 Kg or 5.935 Qtl. Qtl. 5.935 2600
Priming coat same 150201 Sqr. 21.3 9.8
Welding Charges by electric paint CM 5000 2
Carriage :
Km.By mechanical transport Tonne 0.95
Km.By head load Tonne 0.95

Labour :
Black smith Ist class Each 3 121.33
Bandhani Each 3 75.83
Beldar Each 7 75.83
Sunderies L -S
Total:-
Add 10% CP & 5% O.H. Charges :
Cost for 9.067 Qtl
Cost for I Qtl
Says Rs 4602/- only.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Providing and laying 20cm. Thick composit stone masonry with stone facing of chisel dressed stones one
line dressed in cement mortar 1:6 (1cement :6sand) and concrete backing with cement concrete 1:3:6
(1cement:3sand:6graded stone aggregate,20mm nominal size)on inner face of walls including centring ,
shuttering and propping complete up to floor two level.

Detail of cost for 1 Square metre.


Description Unit Quantity Rate
Sr.No. MATERIAL :
1 S/R masonry coursed with hard stone of
approved quality in superstructure in Cum 0.15
CM 1:6

2 CC 1:3:6 in walls : Cum 0.05

3 Providing form work with steel plates


in vertical surfaces : Sqm 1

B Labour :
Extra labour for two line dressing :
Mason 1st class Each 0.54
Beldar Each 0.13
Blacksmith 2nd class Each 0.06
Extra labour for super structure :
Mason II nd class Each 0.25
Beldar Each 0.35
Scaffolding LS

Add 10% CP & 5% O.H. Charges on Rs.

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon
Analysis of rate

Excavation in earth work and filling in 15 cm.layers in foundation and plinth including ramming, .
watering and cnsolidating upto a lead of 20 mtres and lift upto a 1.5 mtres Pick work.

Detail of cost for 10cum


Sr.No. Description of items Unit Quantity Rate

Labour :
Beldar Each 6.11
Bhishti Each 0.29

Add 1.5% for water charges :

Add 10% for C.P. & 5% for overhead charges :


Cost of 10 Cum.
Cost of 1 cum

Say Rs. /- only.


LEAD.
Extra for a head of 20 metres or part thereof for.
Labour :
Beldar Each 0.5

Add 10% for C.P. & 5% for overhead charges :


Cost of 10 Cum.
Cost of 1 cum

Cost of one cum.

Boulder filling dry hand packed tightly under floors


Detail of cost for 1 cum
S.No. Description of items Unit Quantity Rate

MATERIAL :

Stone Cum 1

Carriage :
Km.By mechanical transport Cum 1
Km.By head load Cum 1

Labour :
Beldar Each 0.8

Add 10% for C.P. & 5% for overhead charges :


Cost of 1 Cum.

Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Conversion of timber

Detail of cost for 1 cum


Sr.No. Description of items Unit Quantity Rate
1 KAIL WOOD
MATERIAL :
Second class Kail wood
In sleepers to Planks 1 Cum 1.18 27930
Add waistage @18% 0.18
Total 1.18
Sawing Charges Of Wood: Cum 1.18 850
Total:
2 KAIL WOOD
MATERIAL :
Second class Kail wood
In sleepers to Scantling 1 Cum 1.15 27930
Add waistage @15% 0.15
Total 1.15
Sawing Charges Of Wood: Cum 1.15 600
Total:
3 DEODAR WOOD
MATERIAL :
Second class Kail wood
In sleepers to Planks 1 Cum 1.18 28760
Add waistage @18% 0.18
Total 1.18
Sawing Charges Of Wood: Cum 1.18 850
Total:
4 DEODAR WOOD
MATERIAL :
Second class Kail wood
In sleepers to Scantling 1 Cum 1.15 28760
Add waistage @15% 0.15
Total 1.15
Sawing Charges Of Wood: Cum 1.15 600
Total:

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Providing corrugated G.I Sheet rofing fixed with galvanised iron J.& L hocks bolts and nuts 8 mm
diametrs with bituman and G.I limpet washers fild with white lead complete excluding the cost of
of purlins rafters and trusses 0.63 mm thick Sheet.
Detail of cost for area of roof2x18.09 x 5.10=184.518 Sqrm.( considering roof with each sloping
side 8.09x5.10 m and the slopes being flater than 1 verticalto2.5 horizental)

Sr.No. Description of items Unit Quantity Rate


MATERIALS
Detail of length and breadth length
26 laps x 0.135 each lap=3.51 width of corrugated sheet with 10 corrugations, measures end
to end = 0.63 mm width of shet 27 (Nos of sheet)
21.6 Mtrs
Less lap 3.51 Mtrs
Net length 18.09 Mtrs
Breadth of one side
C.G.I sheet 1 No of 2.5 M. Length
C.G.I sheet 1 No of 2.8 M. Length
total:- 5.3 M. Length
Ded. End lap of 20 Cm (-) 0.2 M. Length
Breadth 5.1 M. Length
MATERIALS
C.G.I sheet 0.63 mm thick. 2x27 =54 Nos ,of 2.5x0.90@12.82 kg each=692.28
2.5 m x 0.90 is the size of plain G.I sheet which on being corrugated will become 2.5 x 0.80 m
( the size of plain sheet is taken because the wight is available only of plain sheets) 2x27=54 Nos
of size 2,80 x 0.90 m @ 14.36 Kg. each
775.44 Kg.
Total:- 1467.72 Kg.
Add for 5% wastage 73.39 Kg.
1541.11 Kg.
1541.11 QTL 1541.11 4550
G.I seam bolts and nuts 60 centimeteresto center zig i.e 30 cm center to center straight.
Breasth is 5.10 metres
Nos of bolts in one lap 5.10/0.3 17 Nos
2 x 26 lap x 17 884 10Nos 884 50
G.I J.& L hocks 8 mm dia ( Nos of purlins to be used = 5 Nos on either side)
2x5x27 (No of sheet) x 3 Nos of bolts in e 810 10Nos 810 60
Limpet Washer
Total of seam bolts and hocks 884+810 1694 100Nos 1694 35
Bitumen washers. 1694 100 Nos 1694 30
Carriage C.G I A
Km.By mechanical transport 31 tone 1.54 296.14
Km.By head load 0.5 tone 1.54 0.00
Nuts and bolts.
Km.By mechanical transport 31 tone 0.45 296.14
Km.By head load 0.5 tone 0.45 0.00
Labour :
Black smith 2nd class : Each 1.3 #REF!
Carpenter 2nd Class Each 14.75 #REF!
Beldar : Each 14.75 #REF!
Sundries : LS
B
TATAL A+B
Add 10% CP & 5% O.H. Charges :
Detail of cost for 184.518 Sqrm.
Detail of cost for ONE Sqrm.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of rates
Dressisng of Beds and prepration of sub-grade for CC lining
Detail of cost for 10 cu.m
Sr.No Description of Items Qty. Rate
1 Spade work
Beldar 1.28 Nos. #REF!

Add 10% C.P and 5% over head charges except on cement.

Total:-
Cost for 10sqmt.
Cost for 1sqmt.

2 Pick Work
Beldar 1.38 Nos. #REF!
Total:-

Add 10% C.P and 5% over head charges except on cement.

Total:-
Cost for 10sqmt.
Cost for 1sqmt.
Heance #REF! + #REF!
2
Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

Analysis of rates
Preparation of sub grade by dressing to chamber (earth work for the cuting involved making good.
Detail of cost for 100 Sqr.
Sr.No Description of Items Qty. Rate
1 Pick Work
Beldar 0.32 Nos.
Total:-

Add 10% C.P and 5% over head charges except on cement.

Total:-

Cost for 100sqmt.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of rates

Providing and Fixing 15 Cm wide 45 Cm. overall semicircular plain G.i Sheet Gutter with iron brackets 40x3mm
bolts and nuts and washers etc. including making necessary conection with rain water pipe complete as per d

Detail of cost for length of 9.04 m.


Sr.No Description of Items Qty.
1 Materials:-
Consider a length of 9.04 m Sheet.
used = 2.5 X 0.90m=2 Nos.
Weight =2X15.82=31.64 Kgor .3164 0.3164 Qtl.
Flat iron bracket with 40x3mm with bolts and nuts bitumen and G. 10 Nos

2 Carriege:-
C.G.Sheet.
31 Km by machenical transport 0.032 Tone
0.5 Km. by head load 0.032 Tone

3 Labour
Carpenter Ist Class 0.35 Nos.
Black Smith Ist Class 0.9 Nos.
Black Smith Iind Class 0.9 Nos.
Beldar 2.1 Nos.
Sundaries L

Add 10% C.P. profit and 5% over head charges except on steel.

Cost for 9.04 Mtr.


Cost for 1.00 Mtr.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of rates
Stone soling properly hand packed filling interestices with spalls and consollidating.
Detail of cost for one cu.m
Sr.No Description of Items Qty.
1 Materials
Soling Stone 1 cum.
Moorum/ Earth L-S

2 Carriage
#REF! Km by machenical transport 1.1 cum.
0 M. by head load 1.1 cum.

3 Labour
Mate 0.08 Nos.
Beldar 0.08 Nos
Bhisti 0.21 Nos

Add 10% C.P and 5% over head charges.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon
Analysis of rates
50mm thick cement concrete flooring 1:2:4
Detail of cost for 10 sqm.
Sr.No Description of Items Qty.
1 Materials
Stone ballast 20mm 0.334 cum.
Stone ballast 10mm 0.111 cum.
Sand 0.222 cum.
Cement 0.182 Tone

2 Carriage
Sand
Km by machenical transport 0.222 cum.
Km. by head load 0.222 cum.

Stone aggregate below 40mm:-


Km by machenical transport 0.445 cum.
Km. by head load 0.445 cum.

Cement
Km by machenical transport 0.182 Tone
Km. by head load 0.182 Tone

3 Labour
Mason 2nd class 1.35 Nos.
Beldar 2.16 Nos.
Bhisti 0.27 Nos.
Sundaries L.S.

Add 1.5% water charges.

Add 10% C.P and 5% over head charges.

Cost for 10 sqm.=

Cost per sqm.=


Junior Engineer, Assistant Engineer,
IPH Chirgaon. I P H Chirgaon

Analysis of rates
Providing CC Lining 15 cm. thick or less in c.c.1:3:6.
Detail of cost for 10 sqm.
Sr.No Description of Items Qty.
IN BED
1 Materials
CC 1:3:6 1.00 cum.

2 Labour for making slab up to 15cm thick or less


Mason 1stclass 0.17 Nos.
Beldar 0.17 Nos.

Add 1.5% water charges.

Add 10% C.P and 5% over head charges.

Cost for 1 cum..


Say Rs.

{ B }.C.C. Linning in side slope -460.65

Add. Additional labour i/c 10% C.P. & 5%O.H charges for carriage of material and difficalty of adjestment of si
laying & finishing upper surfaces..

Total
Say Rs.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of rates
Extra allounce for formwork in C.C Lining.
Detail of cost for 9.30Sqm. or 1.40.
Sr.No Description of Items Qty.
1 2 3
(A) IN BED
1 Material:
2nd class kail wood planks. (Quantity as per Analysis of 24.39 HPSR.1979

0.055 cum.
2 Carriage of Kail wood:
Km by machenical transport 0.055 cum.
Km. by head load 0.055 cum.

Add 10% C.P and 5% over head charges.

Assuming that Timber will become unreversable after being used 20 times
Cost using one
Sundaries.

3 Labour:
Detail of cost for 8.50cum.
Carpenter 2nd class 1 Nos.
Beldar 1 Nos.

Add 10% C.P and 5% over head charges.

Labor per block i.e 1.40cum.= (B


Labor
Total A+B =
Cost of 1.40cum.
Cost per cum.

(B) ON SIDE SLOPS:


1 Material same as in bed
2 (ii)Labour:
Detail of cost for 7.08mm.
Carpenter 2nd class 1 Nos.
Beldar 1 Nos.

Add 10% C.P and 5% over head charges.


Labour for 7.08cum.
Labour for block i.e. 1.40 cum.
Cost for 1.40cum. A+B
Cost for 1cum.

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Distempering with oil bound di laying & finishing upper surfaces.. 23.50
Detail of Cost for 10 Sqr.
Sr.No Description of Items Qty. Rate
Materials
Distempers 1 200
Chalk Whiting 1 15
Brush and Sand paper L-S
L-S

Carriage :-. L-S

Labour
Painter Ist Class 0.21 #REF!
Beldar 0.4 #REF!
Sundries

Total :-1+2+3=
Add 10% C.P and 5% over head charges.
Cosy for10 Sqr
Cosy for1 Sqr
Analysis of Rate
Finishing wall with water profing cement paint on decorated wall. ( Two Coat )
Detail of Cost for 10 Sqr.
Sr.No Description of Items Qty.
Materials
Paints 3
Brush and Sand paper

Carriage :-.

Labour
Painter Ist Class 0.4
Beldar 0.4
Bhisti 0.4
Sundries

Add 10% C.P and 5% over head charges.


Cosy for10 Sqr
Cosy for1 Sqr

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Wet well sinking in graval including all pumping shoring from spring level to 3 Mtr below S.L
S. No Description Qty.
Detail of cost for 31.57 cum.
Cost for tools &Plants
Pully( one pully can be used for 10 wall) 1/10
Caps rope 38mm dia (50Kg) used 5 walls 1/5*50
Sal Ballies can be used for 10 walls 5/10
Sleeper (16 sleeper can be used 10 walls 16/10 1.6
Dradger (one can be used 32 walls) 1/32
Add 10% C.P and 5% over head charges.
Cost for 9 Mtr.Sinking of well
Cost for3 Mtr.Sinking of well
Labour for eraction and subsquent
Beldar 4 Nos for 2 days=8 Nos 8
Mate 1/2 no. for 2 days 1

Add 10% C.P and 5% over head charges.

Labour and materials for loading/unlodding


Empty cement bags can be used twice 400/2
Baldar for filling bags with sand& loading 11
Sundries such as string etc.
Baldar for unloading of 400 bags after sin. 6

Add 10% C.P and 5% over head charges.

Labour tobe deployed for sinking of well


Beldar (11 Nosfor 15 days) 165
Well sinking (3 Nos for 15 days) 45
Mate 1 No. for 15 days 15

Add 10% C.P and 5% over head charges.

Vol. displaced=22/7*3.66*3.66*1/4*3= Labour for 31.57 Cum


Labour for Per Cum

Add working charges of Hoist taking


12 days to sink the well

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Wet well sinking in graval including all pumping shoring Exceeding 3mtrs but upto 6 Mtr below S.L
S. No Description Qty.
Detail of cost for 31.57 cum.
Cost for tools &Plants
Pully( one pully can be used for 10 wall) 1/10
Caps rope 38mm dia (50Kg) used 5 walls 1/5*50
Sal Ballies can be used for 10 walls 5/10
Sleeper (16 sleeper can be used 10 walls 16/10 1.6
Dradger (one can be used 32 walls) 1/32

Add 10% C.P and 5% over head charges.


Cost for 9 Mtr.Sinking of well
Cost for3 Mtr.Sinking of well
Labour for eraction and subsquent
Beldar 4 Nos for 2 days=8 Nos 8
Mate 1/2 no. for 2 days 1

Add 10% C.P and 5% over head charges.

Labour and materials for loading/unlodding


Empty cement bags can be used twice 600/2
Baldar for filling bags with sand& loading 22
Sundries such as string etc.
Baldar for unloading of 400 bags after sin. 8

Add 10% C.P and 5% over head charges.

Labour tobe deployed for sinking of well


Beldar (11 Nosfor 15 days) 180
Well sinking (3 Nos for 15 days) 60
Mate 1 No. for 15 days 15

Add 10% C.P and 5% over head charges.

Vol. displaced=22/7*3.66*3.66*1/4*3= Labour for 31.57 Cum


Labour for Per Cum

Add working charges of Hoist taking


12 days to sink the well

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of Rate
Wet well sinking in graval including all pumping shoring Exceeding 6mtrs but upto 9 Mtr below S.L
S. No Description Qty.
Detail of cost for 31.57 cum.
Cost for tools &Plants
Pully( one pully can be used for 10 wall) 1/10
Caps rope 38mm dia (50Kg) used 5 walls 1/5*50
Sal Ballies can be used for 10 walls 5/10
Sleeper (16 sleeper can be used 10 walls 16/10 1.6
Dradger (one can be used 32 walls) 1/32

Add 10% C.P and 5% over head charges.


Cost for 9 Mtr.Sinking of well
Cost for3 Mtr.Sinking of well
Labour for eraction and subsquent
Beldar 4 Nos for 2 days=8 Nos 8
Mate 1/2 no. for 2 days 1

Add 10% C.P and 5% over head charges.

Labour and materials for loading/unlodding


Empty cement bags can be used twice 1100/2
Baldar for filling bags with sand& loading 36
Sundries such as string etc.
Baldar for unloading of 400 bags after sin. 11

Add 10% C.P and 5% over head charges.

Labour tobe deployed for sinking of well


Beldar (11 Nosfor 15 days) 204
Well sinking (3 Nos for 15 days) 68
Mate 1 No. for 15 days 17

Add 10% C.P and 5% over head charges.

Vol. displaced=22/7*3.66*3.66*1/4*3= Labour for 31.57 Cum


Labour for Per Cum

Add working charges of Hoist taking


12 days to sink the well

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE
Earth work in foundation for digging well including excavation from ground level upto
the level where well curb is placed, including depositing sprils in 20mtr. Radius and
filling space out side the well after completion from NS level to 1.5mtrs. Depth in
pick and jumper work 20%,80% each.
DETAIL OF COST FOR 10 CUM
PICK WORK:
LABOUR:
Beldar. Each. 9.15
Bhishti. Each. 0.31
Add 1.5% water charges.
Add 15% C.P. & O.H charges.

Cost for 10 cum. 827.76


Cost for 1 cum. 82.78

JUMPER WORK:-
DETAIL OF COST FOR 10 CUM.

Drilling Equipment. Day. 0.045


MATERIAL:
Spl. Gelatine 80% Kg. 0.63
Detonator (ordinary). 100Nos. 3
Sefety fuse wire. Coil 0.25

LABOUR:
Driller. Each. 0.135
Balaster. Each. 0.09
Beldar. Each. 17.6

Add 15% C.P. & O.H charges.

Cost for 10 cum. 1943.91


Cost for 1 cum. 194.39

Average. 138.58

Say: 138.58

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE
Applying modrent solution on new GI sheet for preparation of surface for painting @
5 ltrs./100 Sqmt. of surface and rubbing the solution with brush including thoroughly
cleaning the surface of all oil grease dirt and other foreign mattter.

DETAIL OF COST FOR 10 SQMT.

MATERIAL:-
Modrent solution. 1ltr. 0.54

CARRIAGE:- L.S.

LABOUR:-
Painter 1st class. Each. 0.3
Beldar. Each. 0.3
Sundries. L.S.

Add 15% C.P. & O.H charges.

Cost for 10 Sqmt. 100.65


Cost for 1 Sqmt. 10.07

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE
20mm cement concrete topping 1:2 to 3 agg. Of size 4.75mm and below, by volume)
laid over and finished monolithic with base concrete.

DETAIL OF COST FOR 10 SQMT.

MATERIAL:
for cement concrete 0.200mm
stone chips 4.75mm noimnal size. 1cum 0.2

Stone dust. 1cum. 0.07


Cement. 1Tonne. 0.13

CARRIAGE:
Carriage of agg. Below 40mm. 1cum. 0.27
Cement. 1Tonne 0.13

LABOUR:-
Mason 2nd. Class. Each. 1
Beldar. Each. 1.2
Bhishti. Each. 0.5
Sundries. L.S.

Add 1.5% water charges.

Add 15% C.P. & O.H charges. 286.66


except A + B ie. Rs.

Cost for 10 Sqmt. 1160.27


Cost for 1 Sqmt. 116.03

Say. 116.03

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

ANALYSIS OF RATE

Providing ridges or hips 60mm over all in plain with galvanised iron GI sheet fixed J or L
hooks bolts and nuts 8mm dia GI limpet and bitumen washers complete.

0.63mm thick GI sheet


DETAIL OF COST FOR 10.35 MTRS. LONG RIDGE

MATERIAL:
GI plain sheet 0.63 thick 1.80x0.90 size 5No. 09.20Kg.
per sheet= 46.15 Kg.
Add 2% wastage= 0.92 Kg., Total 47.07 kg or 0.4 Qtl.

Qtl. 0.47
GI seam bolts and
25mmx6mm
there azre 19 joints=2x14=28Nos. 10No. 28
Bitumen washer. 100Nos. 28

CARRIAGE:
CGI sheet. 0.047
Carriage of washer. L.S.

LABOUR:
Carpenter 1st. Class. Each. 0.4
Black smith. Each. 1.04
Beldar. Each. 2.4
Sundries. L.S.
Total:-
Add 15% C.P. & O.H charges.
except on carriage:- 2583.12
Total:-

Cost for 10.35Rmt.


Cost for 1 Rmt.

Say 235.43

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon

Analysis of rates
Dressisng of Sides Slopes and prepration of sub-grade for CC lining
Detail of cost for 10 cu.m
Sr.No Description of Items Qty. Rate
1 Spade work
Beldar 1.66 Nos. 87.50

Add 10% C.P and 5% over head charges except on cement.

Total:-
Cost for 10sqmt.
Cost for 1sqmt.

2 Pick Work
Beldar 1.80 Nos. 87.50
Total:-

Add 10% C.P and 5% over head charges except on cement.

Total:-
Cost for 10sqmt.
Cost for 1sqmt.
Heance 16.704 + 18.11
2

Junior Engineer, Assistant Engineer,


IPH Chirgaon. I P H Chirgaon
ercial mild sheet of 1.25 mm .

Rate Amount

40 538.8

ercial mild sheet of 1.25 mm .


Rate Amount

3200 1590.4

3200 515.2

3200 2995.2
20 80
10 20

9.8 151.02
100
150
5601.82

40

Total:-
Executive Engineer,
I.P.H.Division Rohru

agonal braces of 40x40x 6mm


ey 40x40x6mm angle and T.iron
at of red lead paint.

Rate Amount

25 200

125

75

120

40
Executive Engineer,
I.P.H.Division Rohru

eel iron section of 40x40x6mm,


shold of mild steel angle 50x25mm
h jamb including butt hinges 2.50mm
plying a coat of approved steel

Rate Amount

2 32

/- only.
Executive Engineer,
I.P.H.Division Rohru

and braced with flat iron diagonals


a steel pulley complete with bolts &
coat of red lead paint.

Rate Amount

1900 1140

22 220

30

120

75
Executive Engineer,
I.P.H.Division Rohru

stone aggregate
inforcement for RCC
ng preparing of the surface

st of landing excluding)

Rate Amount

#REF! #REF!

#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

#REF! #REF!
#REF! #REF!

#REF! #REF!
Total : #REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
Executive Engineer,
I.P.H.Division Rohru

art-I 1888 and IS 12592-Part-II,1991

Rate Amount

725 725
29

100

Total :

Total :

Executive Engineer,
I.P.H.Division Rohru

art-I 1888 and IS 12592-Part-II,1991

Rate Amount
605 605
24.2

80

Total :

Total :

Executive Engineer,
I.P.H.Division Rohru

be measured and paid

10 Rmtr.
Rate Amount

Total :
G.Total:-

Total :

Total :

Total :
Total :

Total :

Total :

Total :

Total :

Total :

Executive Engineer,
I.P.H.Division Rohru

2139.20
d stone aggregate 20mm
ment for reinforced
OR 1.00 CUM.
Rate Amount

635.00 361.95
670.00 187.6
245.00 104.13
3400.00 1360
A 2013.68

1082.73 920.32
589.87 501.39

492.86 209.47
589.87 250.7

277.26 110.91
289.76 115.9
B 2108.69

87.50 314.13
87.50 25.38
111.40 11.14
111.40 11.14
87.50 3.5
87.50 21.88
50

87.50 8.75
87.50 17.5
111.40 4.46
111.40 4.46
87.50 3.5
87.50 14.88
15
C 505.72

4628.09
69.42
4697.51
173.91

Cum. Rs. 4871.42

Executive Engineer,
I.P.H.Division Rohru
1048.70
tone aggregate

OR 1.00 CUM.
Rate Amount

565.00 367.25
635.00 152.4
245.00 115.15
3400.00 442
A 1076.8

281.32 182.86
#REF! #REF!
0
617.10 148.1
0.00 0

281.32 132.22
#REF! #REF!
0
296.14 38.5
0.00 0
B #REF!

87.50 182.88
87.50 23.63
111.40 5.57
111.40 5.57
87.50 3.5
87.50 21.88
15
C 258.03

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
Executive Engineer,
I.P.H.Division Rohru

1011.30

tone aggregate, 40 mm nominal


aining walls/breast walls, the size

OR 1.00 CUM.
Rate Amount

565.00 339

635.00 139.7

245.00 105.35

3400.00 408

0 0
A 992.05

281.32 168.79
#REF! #REF!

617.10 135.76
0.00 0

281.32 120.97
#REF! #REF!

296.14 35.54
0.00 0

#REF! #REF!
#REF! #REF!
B #REF!

87.50 93.63
87.50 85.75
111.40 27.85
111.40 18.94
20
C 246.17
A+B+C #REF!
#REF!
#REF!
#REF!

#REF!
#REF!

Executive Engineer,
I.P.H.Division Rohru

1135.50
o courses) with hard stone of
concrete 1:6:12 (1 Cement :
ar 1:6( 1cement:6 sand)
Rate Amount

275 275
500 35
#REF! #REF! A
20
TATAL #REF!
#REF! #REF!
#REF! #REF!
total #REF! B

#REF! #REF!
#REF! #REF!
#REF! #REF!
15
Total : #REF!
G.Total : #REF!
#REF!
#REF!

#REF!
#REF!
Executive Engineer,
I.P.H.Division Rohru

mm (average) cement mortar


ade of slab including rubbing and

Amount

2875

225
Executive Engineer,
I.P.H.Division Rohru

cement:4sand) laid over and jointed'


ncluding rubbing and polishing

Amount

3162.5

265
Executive Engineer,
I.P.H.Division Rohru

12mm thick cement mortar

Amount

530

8.91

25

Executive Engineer,
I.P.H.Division Rohru
Amount

276

8.91

20

10

/- only.

Executive Engineer,
I.P.H.Division Rohru

signation 85 G. with wire


inished black enamelled iron hinges

Amount
#REF!
126.9
36
9.6
9.6
1.2
#REF!

0
0
0

#REF!
#REF!
#REF!
20
#REF!
#REF!
#REF!
#REF!
#REF!
/- only.

Executive Engineer,
I.P.H.Division Rohru

ods and brackets including fixing

Amount

14

5
1.5

/- only.

Executive Engineer,
I.P.H.Division Rohru

Amount

9321

15431
208.74
10000

363.99
227.49
530.81
20
Executive Engineer,
I.P.H.Division Rohru

g of chisel dressed stones one


with cement concrete 1:3:6
e of walls including centring ,

Amount

15

/- only.

Executive Engineer,
I.P.H.Division Rohru
including ramming, .

Amount

Amount
/- only.

Executive Engineer,
I.P.H.Division Rohru

Amount

32957.4

1003
33960

32119.5

690
32810

33936.8

1003
34940

33074

690
33764

Executive Engineer,
I.P.H.Division Rohru

312.10
bolts and nuts 8 mm
excluding the cost of

of with each sloping

Amount

ns, measures end

come 2.5 x 0.80 m


sheets) 2x27=54 Nos

7012050.5
nter straight.

4420

4860

592.9
508.2
76941.97
456.06
0

133.26
0

#REF!
#REF!
#REF!
20
#REF!
#REF!

#REF!
#REF!

Executive Engineer,
I.P.H.Division Rohru

Unit Amount

each #REF!

#REF!

#REF!
#REF!
#REF!

each #REF!

#REF!

#REF!
#REF!
#REF!
#REF!
Executive Engineer,
I.P.H.Division Rohru

volved making good.

Unit Amount

each

Executive Engineer,
I.P.H.Division Rohru

et Gutter with iron brackets 40x3mm size\


h rain water pipe complete as per design.

.80 mm Thick.
Rate Unit Amount

3200 Qtl. 1012.48


35 Each 350
296.14 Tone 9.48
0.00 Tone 0
Total:-

#REF! each #REF!


#REF! each #REF!
#REF! each #REF!
#REF! each #REF!
S 45

G Total:- #REF!
ges except on steel. #REF! #REF!
#REF!

#REF!
#REF!

Executive Engineer,
I.P.H.Division Rohru

292
Detail of cost for one cu.m
Rate Unit Amount

275 cum. 275


20

#REF! cum. #REF!


#REF! cum. #REF!
Total:- #REF!

#REF! each #REF!


#REF! each #REF!
#REF! each #REF!
#REF!
G. Total :- #REF!
#REF!

#REF!

Executive Engineer,
I.P.H.Division Rohru
113.00

Rate Unit Amount

500 cum. 167


500 cum. 55.5
210 cum. 46.62
3300 Tone 600.6
Total:- 869.72

617.10 cum. 137


0.00 cum. 0

617.10 cum. 274.61


0.00 cum. 0

296.14 Tone 53.9


0.00 Tone 0

Total:- 465.51

#REF! each #REF!


#REF! each #REF!
#REF! each #REF!
15
Total:- #REF!

Total:-1+2+3 #REF!

#REF!
Total:- #REF!
#REF!

#REF!

#REF!
Executive Engineer,
I.P.H.Division Rohru

452.60

Rate Unit Amount

#REF! cum. #REF!

#REF! each #REF!


#REF! each #REF!

Total:- #REF!
#REF!
G.Total #REF!

#REF!

Cost for 1 cum.. #REF!


Say Rs. #REF! (A)

rial and difficalty of adjestment of side slope

L. S. 35

A + 35 #REF!
#REF!

Executive Engineer,
I.P.H.Division Rohru

for 9.30Sqm. or 1.40.


Rate Unit Amount
4 5 6

f 24.39 HPSR.1979

cum.
cum.
cum.
Total:-

able after being used 20 times

L.S. 5
(A)

each
each
Total:-

Total:-
(B)

(A)

each
each
Total:-

(B)

Say Rs.

Executive Engineer,
I.P.H.Division Rohru

Units Amounts

Kg 200
Kg 15
2.5
5
222.5
5

Each #REF!
Each #REF!
L-S 2
#REF!
Total :-1+2+3= #REF!
#REF!
#REF!
#REF!

18.2

Rate Units Amounts

60 Kg 180
L-S 5
185
L-S 5

#REF! Each #REF!


#REF! Each #REF!
#REF! Each #REF!
L-S 2
#REF!
Total :-1+2+3= #REF!
% over head charges. #REF!
Cosy for10 Sqr #REF!
Cosy for1 Sqr #REF!

Executive Engineer,
I.P.H.Division Rohru

160
3 Mtr below S.L
Rate Units. Amounts.

1200 Each 120


55 Kg. 550
180 Each 90
2500 Each 4000
8800 Each 275
5035
% over head charges. 755.25
5790.25
A 1930.08

#REF! #REF!
#REF! #REF!
#REF!
% over head charges. #REF!
Total B #REF!

2 Each. 400
#REF! Each. #REF!
L-S 20
#REF! Each. #REF!
#REF!
% over head charges. #REF!
Total C #REF!

#REF! Each. #REF!


#REF! Each. #REF!
#REF! Each. #REF!
#REF!
% over head charges. #REF!
D #REF!
G. Total A+B+C+D #REF!
#REF!

L.S 200
G. Total #REF!

Executive Engineer,
I.P.H.Division Rohru

191
ut upto 6 Mtr below S.L
Rate Units. Amounts.

1200 Each 120


55 Kg. 550
180 Each 90
2500 Each 4000
8800 Each 275
5035
% over head charges. 755.25
5790.25
A 1930.08

#REF! #REF!
#REF! #REF!
#REF!
% over head charges. #REF!
Total B #REF!

2 Each. 600
#REF! Each. #REF!
L-S 20
#REF! Each. #REF!
#REF!
% over head charges. #REF!
Total C #REF!

#REF! Each. #REF!


#REF! Each. #REF!
#REF! Each. #REF!
#REF!
% over head charges. #REF!
D #REF!
G. Total A+B+C+D #REF!
#REF!

L.S 200
G. Total #REF!

Executive Engineer,
I.P.H.Division Rohru

236.20
ut upto 9 Mtr below S.L
Rate Units. Amounts.

1200 Each 120


55 Kg. 550
180 Each 90
2500 Each 4000
8800 Each 275
5035
% over head charges. 755.25
5790.25
A 1930.08

#REF! #REF!
#REF! #REF!
#REF!
% over head charges. #REF!
Total B #REF!

2 Each. 1100
#REF! Each. #REF!
L-S 20
#REF! Each. #REF!
#REF!
% over head charges. #REF!
Total C #REF!

#REF! Each. #REF!


#REF! Each. #REF!
#REF! Each. #REF!
#REF!
% over head charges. #REF!
D #REF!
G. Total A+B+C+D #REF!
#REF!

L.S 250
G. Total #REF!

Executive Engineer,
I.P.H.Division Rohru

24.12
87.5 800.63
87.5 27.13

Total:- 827.76

2054.69 92.46

45 28.35
157 4.71
12 3
Total:- 128.52

87.5 11.81
111.4 10.03
87.5 1540
Total:- 1561.84
G.Total:- 1690.36
253.55
Total:- 1943.91

Executive Engineer,
IPH Division,Rohru.

5.80
OR 10 SQMT.

25 13.5

111.4 33.42
87.5 26.25
5
Total: 83.17
12.48

100.65

Executive Engineer,
IPH Division,Rohru.

78

540 108

400 28
3400 442
Total:- 578 A

707.1 190.92
474.5 61.69
252.61 B

111.4 111.4
87.5 105
87.5 43.75
10
270.15
Total:- 1100.76
16.51
Total:- 1117.27
43
1160.27

Executive Engineer,
IPH Division,Rohru.

185.40

t fixed J or L

MTRS. LONG RIDGE

4550 2138.5

20 56
15 4.2
2198.7

841.45 39.55
5
Total 44.55 A

111.4 44.56
111.4 115.86
87.5 210
14
384.42
2627.67

387.468
2436.69

2436.69
235.43

Executive Engineer,
IPH Division,Rohru.

Unit Amount

each 145.25

21.79

167.04
167.04
16.704

each 157.5

23.63

181.13
181.13
18.11
17.41

Executive Engineer,
I.P.H.Division Rohru
LEAD CHART

CEMENT Mech. Tpt. (km) Head.Tpt. <1KM


IPH Store 31 2.5 0.0 Site of Work
1 Nogli

TOR STEEL
2
IPH Store 31 2.5 0.0 Site of Work
Nogli

3 SAND
49 2.5 0.0 Site of Work
Bithal

4 STONE AGGREGATE<40mm
0 2.5 0.0 Site of Work
#REF!

7 STONE
#REF! 0.0 Site of Work
Local Quarry #REF!

6 BRICKS
2.5 0.0 Site of Work
Chandigarh 0

7 TIMBER/M.S.PLATES
2.5 0.0 Site of Work
Rampur 0

8 G.I.Pipe
IPH Store 2.5 0.5 Site of Work
8
Nogli

9 STONE AGGREGATE>40mm
13 0.0 0.5 Site of Work
Local Quarry

* Certified that the lead has been taken throught shortiest & is economical , feasible route only.

Junior Engineer, Assistant Engineer, Executive Engineer,


I&PH NI-2 IPH Anni. IPH Division,Anni
:--------
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT
Sl.No.Lea Average No.of No.of Km. Litre of Costof Litres of Cost of Cost of 6 Hire Total cost Cost per Increase Average
d inK.M. speed Trips No. done diesel Diesel @ M.Oil M.Oil@ Beldar@ Charges Col.No6+8 trip in Cost per cost per
(L) Km/hour(s 2NL+6 consum- per Ltr. consum- per litre per day of Truk@ +9+10 Km over additional
) ed ed per day previous Km.after
Km. five Km.
35.75 110 116.67 1500
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 12 5.65 17.30 5.77 206.28 0.22 24.2 700.02 1500 2430.50 430.18
2 12.75 5.12 26.48 8.83 315.67 0.33 36.3 700.02 1500 2551.99 498.44 68.26
3 13.12 4.69 34.14 11.38 406.84 0.43 47.3 700.02 1500 2654.16 565.92 67.48
4 13.5 4.34 40.72 13.57 485.13 0.51 56.1 700.02 1500 2741.25 631.62 65.70
5 13.88 4.06 46.60 15.53 555.20 0.58 63.8 700.02 1500 2819.02 694.34 62.72
6 14.25 3.82 51.84 17.28 617.76 0.65 71.5 700.02 1500 2889.28 756.36 62.02
7 14.63 3.62 56.68 18.89 675.32 0.71 78.1 700.02 1500 2953.44 815.87 59.51
8 15.1 3.46 61.36 20.45 731.09 0.77 84.7 700.02 1500 3015.81 871.62 55.75
9 15.38 3.31 65.58 21.86 781.50 0.82 90.2 700.02 1500 3071.72 928.01 56.39
10 15.75 3.17 69.40 23.13 826.90 0.87 95.7 700.02 1500 3122.62 985.05 57.04 58.14
11 16.13 3.06 73.32 24.44 873.73 0.92 101.2 700.02 1500 3174.95 1037.57 52.52
12 16.5 2.96 77.04 25.68 918.06 0.96 105.6 700.02 1500 3223.68 1089.08 51.51
13 16.88 2.87 80.62 26.87 960.60 1.01 111.1 700.02 1500 3271.72 1139.97 50.89
14 17.25 2.78 83.84 27.95 999.21 1.05 115.5 700.02 1500 3314.73 1192.35 52.38
15 17.63 2.71 87.30 29.1 1040.33 1.09 119.9 700.02 1500 3360.25 1239.94 47.59
16 18 2.64 90.48 30.16 1078.22 1.13 124.3 700.02 1500 3402.54 1288.84 48.90
17 18.38 2.58 93.72 31.24 1116.83 1.18 129.8 700.02 1500 3446.65 1335.91 47.07
18 18.75 2.52 96.72 32.24 1152.58 1.21 133.1 700.02 1500 3485.70 1383.21 47.30
19 19.13 2.47 99.86 33.29 1190.12 1.25 137.5 700.02 1500 3527.64 1428.19 44.98
20 19.5 2.42 102.80 34.27 1225.15 1.29 141.9 700.02 1500 3567.07 1474.00 45.81 48.90
21 19.88 2.38 105.96 35.32 1262.69 1.32 145.2 700.02 1500 3607.91 1515.93 41.93
22 20.25 2.34 108.96 36.32 1298.44 1.36 149.6 700.02 1500 3648.06 1559.00 43.07
23 20.63 2.30 111.80 37.27 1332.40 1.4 154 700.02 1500 3686.42 1602.79 43.79
24 21 2.26 114.48 38.16 1364.22 1.43 157.3 700.02 1500 3721.54 1646.70 43.91
25 21.38 2.23 117.50 39.17 1400.33 1.48 162.8 700.02 1500 3763.15 1687.51 40.81
26 21.75 2.20 120.40 40.13 1434.65 1.51 166.1 700.02 1500 3800.77 1727.62 40.11
27 22.13 2.17 123.18 41.06 1467.90 1.54 169.4 700.02 1500 3837.32 1768.35 40.73
28 22.5 2.14 125.84 41.95 1499.71 1.57 172.7 700.02 1500 3872.43 1809.55 41.20
29 22.88 2.11 128.38 42.79 1529.74 1.6 176.00 700.02 1500 3905.76 1851.07 41.52
30 23.25 2.09 131.40 43.8 1565.85 1.64 180.4 700.02 1500 3946.27 1888.17 37.10 41.42
ANALYSIS OF RATE 982.10 Type of Pipe
P/L cement concrete 1:6:12 in foundation & plinth(40mm nominal size) & curing pipe dia
complete excluding cost of form work in foundation and plinth. Flange table
DETAILS OF COST FOR 1 CUM. wt.of joint
Description Unit Qty. Rate Amount Rate of flanges/Kg
Material Wt. Of pipe
Stone aggregate 40mm nominal s cum. 0.65 500.00 325.00 WELDING RATE
Stone aggregate 20 mm nominal cum 0.24 500.00 120.00 S.I.R.of Pipe
Sand cum 0.47 210.00 98.70 Random length
Cement Tonne 0.11 3300.00 363.00 Mech.Tpt.For Pipe
A 906.70 Head load For Pipe
Carriage of aggregate 40 mm MT Rate For Pipe
By Mechani #REF! Km cum 0.65 #REF! #REF! HL Rate For Pipe
By Head lo #REF! #REF! cum 0.65 #REF! #REF! O.Dia.
RUBBER GAKET
Carriage of aggreate 20 mm. CUTTING OF
By Mechani #REF! KM cum 0.24 #REF! #REF! THREADED ENDS
By Head lo #REF! #REF! cum. 0.24 #REF! #REF! M.Tpt.For H.Materi
H.load ForH.Materi
Carriage of sand MT Rate For H.Materia
By Mechani #REF! KM cum 0.47 #REF! #REF! HL Rate For Materi
By Head lo #REF! #REF! cum 0.47 #REF! #REF! PLUMBER/FITTER
A/FITTER
Carriage of cement. BELDAR
By Mechani #REF! KM tonne 0.11 #REF! #REF!
By Head lo #REF! #REF! tonne 0.11 #REF! #REF!
B #REF!
LABOUR
Beldar Each 2.09 #REF! #REF!
Bhisti Each 0.27 #REF! #REF!
Mason 1st class Each 0.05 #REF! #REF!
Mason 2nd class. Each 0.05 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar for extra ramming. Each 0.25 #REF! #REF!
Sundries. L.S. 10.00
C #REF!
Total A+B+C #REF!
Add 1.5% for water charges #REF!
Total #REF!
Add 10% contractor profit &5% over head charges
except cost of cement & carriage i 100 #REF! 15 #REF!
Total #REF!
Cost per cum #REF!
Say Rs. #REF! only

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru

ANALYSIS OF RATE 1181.80


P/L cement concrete 1:4:8 in foundation & plinth(40mm nominal size) & curing
complete excluding cost of form work in foundation and plinth.
DETAILS OF COST FOR 1 CUM.
Description Unit Qty. Rate Amount
Material
Stone aggregate 40mm nominal s cum. 0.65 #REF! #REF! PROV. & WELDING OF M
Stone aggregate 20 mm nominal cum 0.24 #REF! #REF! mm DIA.THE WELDING O
Sand cum 0.47 #REF! #REF! IS :816-1965 WITH EL
Cement Tonne 0.17 #REF! #REF! BOLTS & NUTS AS PER
A #REF! JOINTING GASKET SHEET
Carriage of aggregate 40 mm OF FLANGE SHOULD BE D
By Mechani #REF! Km cum 0.65 #REF! #REF! THE JOINTS AIR TIGHT &
By Head lo #REF! #REF! cum 0.65 #REF! #REF! IN- CHARGE.
S.NO.DESCRIPTION O
Carriage of 20 mm nominal size. 1) MATERIAL:-
By Mechani #REF! KM cum 0.24 #REF! #REF! 80
By Head lo #REF! #REF! cum. 0.24 #REF! #REF! 17

carriage of sand
By Mechani #REF! KM cum 0.47 #REF! #REF!
By Head lo #REF! #REF! cum 0.47 #REF! #REF! 2) MS FLANGE I/C N
No.of flanged joints:
Carriage of cement. Wt. Of one Joint
By Mechani #REF! KM tonne 0.17 #REF! #REF! Total wt. Of joints
By Head lo #REF! #REF! tonne 0.17 #REF! #REF!
B #REF!
LABOUR
Beldar Each 2.09 #REF! #REF!
Bhisti Each 0.27 #REF! #REF!
Mason 1st class Each 0.05 #REF! #REF! 3) WELDING WITH M
Mason 2nd class. Each 0.05 #REF! #REF! 2X2X2X22/7X
Mate Each 0.04 #REF! #REF!
Beldar for extra ramming. Each 0.25 #REF! #REF! 4) RUBBER JOINTIN
Sundries. L.S. 10.00
C #REF! 5) CUTTING OF THRE
Total A+B+C #REF! (NOT TAKEN DUE T
Add 1.5% for water charges #REF!
Total #REF! 6) CARRIAGE OF FLA
Add 10% contractor profit &5% over head charges BY MT
except cost of cement & carriage i 100 #REF! 15 #REF! BY H/L
Total #REF!
Cost per cum #REF! 7) LABOUR:-
Say Rs. #REF! only

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATE
P/L cement concrete 1:3:6 in foundation & plinth(20mm nominal size) & curing complete
excluding cost of form work in foundation and plinth. 1400.50
DETAILS OF COST FOR 1 CUM.
Description Unit Qty. Rate Amount Labour for Jointin
Material TYPE
Fitter-I
Stone aggregate 20mm nominal s cum. 0.70 #REF! #REF! Fitter-II
Stone aggregate 10 mm nominal cum 0.24 #REF! #REF! Beldar
Sand cum 0.47 #REF! #REF!
Cement Tonne 0.22 #REF! #REF!
A #REF!
CARRIAGE
Stone aggregate 20mm nominal size
By Mechani #REF! Km cum 0.94 #REF! #REF!
By Head lo #REF! #REF! cum 0.94 #REF! #REF!
SAND
By Mechani #REF! Km cum 0.47 #REF! #REF!
By Head lo #REF! #REF! cum 0.47 #REF! #REF!

CEMENT
By Mechani #REF! Km tonne 0.22 #REF! #REF!
By Head lo #REF! #REF! tonne 0.22 #REF! #REF!
B #REF!
LABOUR
Beldar Each 2.09 #REF! #REF!
Bhisti Each 0.27 #REF! #REF!
Mason 1st class Each 0.05 #REF! #REF!
Mason 2nd class. Each 0.05 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar for extra ramming. Each 0.25 #REF! #REF!
Sundries. L.S. 10.00
C #REF!
Total A+B+C #REF!
Add 1.5% for water charges #REF!
Total #REF!

Add 10% contractor profit &5% over head charges P/L,JOINTING & TE
except cost of cement & carriage i 100 #REF! 15 #REF! FLANGED WITH MS
Total #REF! RESPECT WITHIN A
Cost per cum #REF! S.No. DESCRIPTION
Say Rs. #REF! only 1) MATERIAL:-
ANALYSIS OF RATE 80
Providing plinth protection 50mm thick in cement concrete 1:3:6 ( 1: cement : 3 sand
: 6 graded stone aggregate 20mm N/S) 70.00
Detail of cost for 10 Sqm
Description Unit Qty. Rate Amount
Material
Cement concrete 1:3:6 2) MS FLANGE I/C N
( 1: cement : 3 sand : 6 graded s cum 0.50 #REF! #REF! No.of flanged joints:
20mm N/S ) 10 Sqmx0.50Sqm= 0.50 cum. Wt. Of one Joint
Rate same as per CC 1:3:6 Wt.Of one joints
Total #REF! Wt.Of 102/6=17 No
Cost per 10 Sqm #REF!
Cost per Sqm #REF!
Say Rs. #REF! only 3) WELDING WITH M
2X2X2X22/7X
4) RUBBER JOINTIN
Junior Engineer, AssistantExecutive Engineer,
IPHKharga. I P H Ni I.P.H.Division Rohru 5) CUTTING OF THRE
ANALYSIS OF RATE 2001.30 (NOT TAKEN DUE T
Providing and laying CC 1:1.5:3 (1cement: 1.5 sand : 3 graded stone aggregate 20mm N/S)
and curing complete excluding cost of form work & reinforcement in foundation and plinth. 6) LABOUR:-
DETAILS OF COST FOR 1 CUM. (a)Labour for laying
Description Unit Qty. Rate. Amount Type
MATERIALS Fitter-I
20 mm nominal size aggregate Cum. 0.57 #REF! #REF! Fitter-II
10mm nominal size aggregate Cum 0.28 #REF! #REF! Beldar
Sand Cum 0.425 #REF! #REF! Sunderies
Cement Tonne 0.40 #REF! #REF!
A #REF!
CARRIAGE
Stone aggregate 20mm nominal size (b)Labour for jointin
By Mechani #REF! Km Cum 0.850 #REF! #REF! TYPE
By Head lo #REF! #REF! Cum 0.850 #REF! #REF! Fitter-I
SAND Fitter-II
By Mechani #REF! Km Cum 0.425 #REF! #REF! Beldar
By Head lo #REF! #REF! Cum 0.425 #REF! #REF!
CEMENT
By Mechani #REF! Km Tonne 0.40 #REF! #REF!
By Head lo #REF! #REF! Tonne 0.40 #REF! #REF!
B #REF! 6) CARRIAGE OFMAT
LABOUR (a) FOR G.M.S.PIP
Beldar Each 2.09 #REF! #REF! BY MT
Bhishti Each 0.28 #REF! #REF! BY H/L
Mason Ist Class Each 0.05 #REF! #REF! (b) FOR MS FLANG
Mason 2nd Class Each 0.05 #REF! #REF! BY MT
Mate Each 0.04 #REF! #REF! BY HL
Beldar(For extra ramming) Each 0.25 #REF! #REF!
Sundries: L.S. 20.00
C #REF!
Total A+B+C #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% over head Charges
except cost of cement & carriage i 100 #REF! 15.00 #REF!
Cost for 1 cum #REF!
Say Rs. #REF! only
Junior Engineer, AssistantExecutive Engineer,
IPHKharga. I P H Ni I.P.H.Division Rohru

ANALYSIS OF RATE

Providing and laying CC 1:1.5:3 (1cement: 1.5 sand : 3 graded stone aggregate 20mm
2014.40 P/Laying, jointing and
nominal size) and curing complete excluding cost of form work & reinforcement in socketed i/c all type of
walls from top of foundation level up to floor two level. in trenches to be mea
DETAILS OF COST FOR 1 CUM. complete in all respect
Description Unit Qty. Rate. Amount
MATERIALS S.No. DESCRIPTION O
20 mm nominal size aggregate Cum. 0.57 #REF! #REF! S.No.
10mm nominal size aggregate Cum 0.28 #REF! #REF! 1) Material :-
Sand Cum 0.425 #REF! #REF! 150 mm
Cement Tonne 0.40 #REF! #REF!
A #REF!
CARRIAGE G.M.S.TUBES
Stone aggregate 20mm nominal size Add 2% for fitting e
By Mechani #REF! KM Cum 0.850 #REF! #REF!
By Head lo #REF! #REF! Cum 0.850 #REF! #REF! ADD FOR WHITE LE
OIL ETC.
Sand
By Mechani #REF! KM Cum 0.425 #REF! #REF! 2) CARRIAGE OF PIP
By Head lo #REF! #REF! Cum 0.425 #REF! #REF! BY MT
BY HL
Cement
By Mechani #REF! KM Tonne 0.40 #REF! #REF! 3) LABOUR:-
By Head lo #REF! #REF! Tonne 0.40 #REF! #REF! PLUBER/FITTER (G-
B #REF! BELDAR
LABOUR
Beldar Each 2.09 #REF! #REF!
Bhishti Each 0.28 #REF! #REF! ADD10% CP EXCEPT
Mason Ist Class Each 0.06 #REF! #REF! ADD 5 % O.H.C. ON
Mason 2nd Class Each 0.06 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar(For extra ramming) Each 0.25 #REF! #REF!
Sundries: L.S. 20.00
C #REF!
Total A+B+C #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% over head Charges
except cost of cement & carriage i 100 #REF! 15.00 #REF!
Cost for 1 cum #REF!

Detail of cost for 9.18 Cum


Cum 9.18 #REF! #REF! 'A'
Labour extra for laying C.C. in RCC work
Beldar Each 0.10 #REF! #REF!
Bhishti Each 0.20 #REF! #REF!
Mason Ist Class Each 0.04 #REF! #REF!
Mason 2nd Class Each 0.04 #REF! #REF!
Mate Each 0.04 #REF! #REF!
#REF!
9.18 #REF! #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% 100 #REF! 15.00 #REF!
except on 'A' #REF! ' B'
Grand Total ( A+ B) #REF!
Cost for 9.18 Cum #REF!
Cost for 1 Cum #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru

ANALYSIS OF RATES 1751.90


P/Lof Cement concrete 1:2:4 ( 1cement:2sand:4stone aggregate 20mm nominal size)
in flat surfaces such as suspended floor etc.
DETAIL OF COST FOR ONE CUM.
DESCRIPTION Unit Qty Rate. Amount
MATERIALS.
20mm stone aggregate Cum 0.67 #REF! #REF!
10mm stone aggregate Cum 0.22 #REF! #REF!
Sand Cum 0.445 #REF! #REF!
Cement Ton 0.32 #REF! #REF!
A #REF!
CARRIAGE OF AGGREGATE.
By Mechanical Transport.
By Head lo #REF! KM Cum 0.89 #REF! #REF!
By Hea #REF! #REF! Cum 0.89 #REF! #REF!
SAND
By Mechani #REF! KM Cum 0.445 #REF! #REF!
By Head lo #REF! #REF! Cum 0.445 #REF! #REF!
CEMENT
By Mechani #REF! KM Ton 0.32 #REF! #REF!
By Head lo #REF! #REF! Ton 0.32 #REF! #REF!
B #REF!
LABOUR
Belder Each 2.09 #REF! #REF!
Bhisti Each 0.27 #REF! #REF!
Mason Ist class. Each 0.05 #REF! #REF!
Mason 2nd class. Each 0.05 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar extra for ramming Each 0.25 #REF! #REF!
Sundries L.S. 20.00
Extra labour for slab:-
Belder Each 0.10 #REF! #REF!
Bhisti Each 0.20 #REF! #REF!
Mason Ist class. Each 0.04 #REF! #REF!
Mason 2nd class. Each 0.04 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar extra for ramming Each 0.17 #REF! #REF!
C #REF!
Total #REF!
Add 1.5% for water charges 100 #REF! 1.50 #REF!
Total #REF!
Add 10% contractor profit &5% o 100 #REF! 15 #REF!
except cost of cement & carriage Grant Total #REF!
Cost for 1 cum #REF!
Say Rs. #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATE
Providing and laying CC 1:2:4 (1cement:: 2 sand : 4 graded stone aggregate 20mm nominal
size) and curing complete excluding cost of form work in foundation and plinth.
DETAILS OF COST FOR 1 CUM. 1740.20
Description Unit Qty. Rate. Amount
MATERIALS
20 mm nominal size aggregate Cum. 0.67 #REF! #REF!
10mm nominal size aggregate Cum 0.22 #REF! #REF!
Sand Cum 0.445 #REF! #REF!
Cement Tonne 0.32 #REF! #REF!
A #REF!
CARRIAGE
Stone aggregate below 40mm
By Mechani #REF! KM Cum 0.89 #REF! #REF!
By Head lo #REF! #REF! Cum 0.89 #REF! #REF!

Sand
By Mechani #REF! KM Cum 0.445 #REF! #REF!
By Head lo #REF! #REF! Cum 0.445 #REF! #REF!

Cement
By Mechani #REF! KM Tonne 0.32 #REF! #REF!
By Head lo #REF! #REF! Tonne 0.32 #REF! #REF!
B #REF!
LABOUR
Beldar Each 2.09 #REF! #REF!
Bhishti Each 0.27 #REF! #REF!
Mason Ist Class Each 0.05 #REF! #REF!
Mason 2nd Class Each 0.05 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar(For extra ramming) Each 0.25 #REF! #REF!
Sundries: L.S. 20.00
C #REF!
Total A+B+C #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% over head Charges
except cost of mortar & carriage i. 100 #REF! 15.00 #REF!
Cost for 1 cum #REF!
Say Rs. #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATE
P/Lof Cement concrete 1:2:4 ( 1cement:2sand:4stone aggregate 20mm nominal size)
in Columns, pillar posts and struts up to floors two levels. 1889.60
DETAIL OF COST FOR ONE CUM.
DESCRIPTION Unit Qty Rate. Amount
MATERIALS.
20mm stone aggregate Cum 0.67 #REF! #REF!
10mm stone aggregate Cum 0.22 #REF! #REF!
Sand Cum 0.445 #REF! #REF!
Cement Ton 0.32 #REF! #REF!
A #REF!
CARRIAGE OF AGGREGATE.
By Mechanical Transport.
By Head lo #REF! KM Cum 0.89 #REF! #REF!
By Hea #REF! #REF! Cum 0.89 #REF! #REF!
SAND
By Mechani #REF! KM Cum 0.445 #REF! #REF!
By Head lo #REF! #REF! Cum 0.445 #REF! #REF!
CEMENT
By Mechani #REF! KM Ton 0.32 #REF! #REF!
By Head lo #REF! #REF! Ton 0.32 #REF! #REF!
B #REF!
LABOUR
Belder Each 3.59 #REF! #REF!
Bhisti Each 0.29 #REF! #REF!
Mason Ist class. Each 0.10 #REF! #REF!
Mason 2nd class. Each 0.10 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar extra for ramming Each 0.25 #REF! #REF!
Sundries L.S. 20.00
Scaffolding L.S. 38.00
Extra labour for slab:-
Belder Each 0.10 #REF! #REF!
Bhisti Each 0.20 #REF! #REF!
Mason Ist class. Each 0.04 #REF! #REF!
Mason 2nd class. Each 0.04 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar (Extra labour for lifting of m Each 0.17 #REF! #REF!
C #REF!
Total #REF!
Add 1.5% for water charges 100 #REF! 1.50 #REF!
Total #REF!
Add 10% contractor profit &5% o 100 #REF! 15 #REF!
except cost of cement & carriage Grant Total #REF!
Cost for 1 cum #REF!
Say Rs. #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATE
Providing and laying damp proof cource 38mm thick with CC 1:2:4 (1cement: 2 sand : 4 graded
stone aggregate 12.5mm nominal size) and curing complete.
DETAILS OF COST FOR 10 SQM.

Description Unit Qty. Rate. Amount


MATERIALS
C.C. 1:2:4 (12.5 mm nominal size)
10x0.038=0.38Cum.
Rate for 1:2:4 as per C.C.1:2:4 in Cum 0.38 #REF! #REF!
& plinth
Add for difference between 20 Cum 0.38 #VALUE! #VALUE!
size agg. I.e.0.67 cum x ( Rate of 20mm
aggregate ( - ) 12/12.5mm aggregate )

LABOUR ( EXTRA FOR FINISHING ) :


Mason Ist Class Each 0.05 #REF! #REF!
Mason 2nd Class Each 0.05 #REF! #REF!
Beldar Each 0.10 #REF! #REF!
Bhishti Each 1.00 #REF! #REF!
Sundries: L.S. 10.00
#REF!
Add 1.5% water charges except on 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% 100 #REF! 15.00 #REF!
except on 'A' #REF!
Cost for 10 Sqm #REF!
Cost per Sqm #REF!
Say Rs. #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATE
Applying a coat of hot bitumen ( Mexphalt 80/100 or equivalent) using 1.70 kg per Sqm on
damp proof course after cleaning the surface with piece of cloth lightly soaked with Kerosene.
DETAILS OF COST FOR 10SQM.

Description Unit Qty. Rate. Amount

MATERIALS
Mexphalt 80/100 Tonne 0.017 8250.00 140.25
SR-99
Kerosene oil Lit. 1.35 10.00 13.50
Fuel for heating L.S 7.00
CARRIAGE A 160.75
Tar Bitumen
By Mechani 1 KM Tonne 0.017 68.72 1.17
By Head lo 100 MT Tonne 0.017 23.24 0.40
B 1.56
LABOUR
Beldar Each 0.22 #REF! #REF!
Painter Ist class Each 0.18 #REF! #REF!
Sundries: L.S. 2.00
C #REF!
Total A+B+C #REF!
Add 10% contractor profit & 5% over head Charges
except cost of carriage 100 #REF! 15.00 #REF!
Cost for 10 Sqm #REF!
Cost per Sqm #REF!

ANALYSIS OF RATES 97.00


Cement concrete flooring CC 1:2:4 (1cement:: 2 sand : 4 graded stone aggregate 20mm
size) laid in one layer with floating coat neat cement. ( 40mm thick)and curing complete.
DETAILS OF COST FOR 10 SQM.
Description Unit Qty. Rate. Amount

MATERIALS
20 mm nominal size aggregate Cum. 0.267 #REF! #REF!
10mm nominal size aggregate Cum 0.089 #REF! #REF!
Sand Cum 0.178 #REF! #REF!
Cement Tonne 0.150 #REF! #REF!
A #REF!
CARRIAGE
Stone aggregate below 40mm
By Mechani #REF! KM Cum 0.356 #REF! #REF!
By Head lo #REF! #REF! Cum 0.356 #REF! #REF!

Sand
By Mechani #REF! KM Cum 0.178 #REF! #REF!
By Head lo #REF! #REF! Cum 0.178 #REF! #REF!
Cement
By Mecha #REF! KM Tonne 0.150 #REF! #REF!
By Head #REF! #REF! Tonne 0.150 #REF! #REF!
B #REF!
LABOUR
Mason 2nd Class Each 1.20 #REF! #REF!
Beldar Each 2.00 #REF! #REF!
Bhishti Each 0.50 #REF! #REF!
Sundries: L.S. 15.00
C #REF!
Total A+B+C #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% over head Charges
except cost of mortar & carriage 100 #REF! 15.00 #REF!
Cost for 10 Sqm #REF!
Cost per Sqm #REF!
Say Rs. #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATES 20.70
Providing Tor steel reinforcement for RCC work.
DETAILS OF COST FOR 1 QTL.
Description Unit Qty Rate. Amount.
Tor steel bars. = 1.00
Wastage 5% = 0.05
--------------
= 1.05 Qtl. Qtl. 1.05 #REF! #REF! A
CARRIAGE
By Mechani #REF! KM Ton. 0.11 #REF! #REF!
By Head lo #REF! #REF! Ton. 0.11 #REF! #REF!
#REF! B

LABOUR FOR BENDING BINDING


&PLACING IN POSITION
Beldar Each 1.00 #REF! #REF!
Black smith 2nd class Each 1.00 #REF! #REF!
Sundries L.S 35.00
#REF! C
Total A+B+C #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% CP & 5% O.H charges ex 100 #REF! 15.00 #REF!
and material. #REF!
Cost for one Qtl. #REF!
Cost for per K.G #REF!
Say Rs. #REF! only.
Junior Engineer, AssistantExecutive Engineer,
IPHKharga. I P H Ni I.P.H.Division Rohru
ANALYSIS OF RATES
Providing and laying No fine Cement Concrete1:4 (1cement: 4 graded stone
1160.70
aggregate 20mm N/S)and curing complete excluding cost of form work& reinforcement for
reinforced concrete work.
DETAILS OF COST FOR 1 CUM.
Description Unit Qty. Rate. Amount
MATERIALS
20 mm nominal size aggregate Cum. 0.89 #REF! #REF!
Cement Tonne 0.32 #REF! #REF!
A #REF!
CARRIAGE
Stone aggregate below 40mm
By Mechani #REF! KM Cum 0.89 #REF! #REF!
By Head lo #REF! #REF! Cum 0.89 #REF! #REF!
Cement
By Mechani #REF! KM Tonne 0.32 #REF! #REF!
By Head lo #REF! #REF! Tonne 0.32 #REF! #REF!
B #REF!
LABOUR
Beldar Each 2.09 #REF! #REF!
Bhishti Each 0.27 #REF! #REF!
Mason Ist Class Each 0.06 #REF! #REF!
Mason 2nd Class Each 0.06 #REF! #REF!
Mate Each 0.04 #REF! #REF!
Beldar(For extra ramming) Each 0.25 #REF! #REF!
Scafolding L.S. 20.00
Sundries L.S. 20.00
C #REF!
Total A+B+C #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% over head Charges
except cost of mortar & carriage i. 100 #REF! 15.00 #REF!
Cost for 1 cum #REF!
Say Rs. #REF!

Junior Engineer, AssistantExecutive Engineer,


IPHKharga. I P H Ni I.P.H.Division Rohru

Cement Mortar 1:4 (1cement:4sand)


DETAIL OF COST FOR 1 CUM.
DESCRIPTION UNIT QUANTITY RATE AMOUNT
cement Tonne 0.25 #REF! #REF!
Sand Cum. 1.07 #REF! #REF!
(A) #REF!
CARRIAGE OF CEMENT
By Mech #REF! KM Tonne 0.25 #REF! #REF!
By Hea #REF! #REF! Tonne 0.25 #REF! #REF!

CARRIAGE OF SAND
By Mechan #REF! KM Cum. 1.07 #REF! #REF!
By Hea #REF! #REF! Cum. 1.07 #REF! #REF!
(B) #REF!
LABOUR
Beldar Each 0.90 #REF! #REF!
Bhisti Each 0.08 #REF! #REF!
Sundries L.S. 15.00
(C) #REF!
Total (A+B+C) #REF!
Add 1.5% for water charges 100 #REF! 1.5 #REF!
Total #REF!
Add 10 % contractor profit &5% o 100 #REF! 15.00 #REF!
except cost of cement & carriage. Total #REF!
Cost for one cum #REF!

ANALYSIS OF RATES
402.90
P/F Chequrred terozo tiles 20mm thick with marble chips of specified size laid in floor, tread of steps,
landing on a bed of 25 mm average thickness cm 1:6 jointed with neets cement slurry mixed
with pigment to make the shade of tiles including in rubbing & polishing complete. (SILVER GREY)
DETAILS OF COST FOR 10 SQM.
Description Unit Qty. Rate. Amount
MATERIALS
Chequrred tile = 10 Sqm
wastage 10% = 01 Sqm Sqm 11.00 350.00 3850.00
= 11 Sqm
Cement mortor 1:6 Cum 0.255 #REF! #REF!
Grey cement for slurry over bedding
@ 4.40kg /Sqm = 0.044 tonne. Tonne 0.044 3400.00 149.60

Grey cement for cement grouting Tonne 0.044 3400.00 149.60

Carriage of tiles L.S. 50.00

LABOUR
Mason 2nd Class Each 2.16 #REF! #REF!
Beldar Each 2.16 #REF! #REF!
Bhishti Each 0.50 #REF! #REF!
Total #REF!
Add 1.5% water charges 100 #REF! 1.50 #REF!
#REF!
Add 10% contractor profit & 5% 100 #REF! 15.00 #REF!
except cost of mortar & carriage Cost for 10 Sqm #REF!
Cost per Sqm #REF!
Say Rs. #REF!
Junior Engineer, AssistantExecutive Engineer,
IPHKharga. I P H Ni I.P.H.Division Rohru

ANALYSIS OF RATES 429.30


GMS (M) GMS (H) PIPE DIABELDAR PLUMBER/ R
80 mm FIT.(G-I) LIGHT
17 15 mm 0.19 0.10 52.00
13.95 Kg 20 mm 0.19 0.10 70.00
56.00 /- 25 mm 0.30 0.14 103.00
10.51 Kg/m 32 mm 0.30 0.14 117.00
2.00 Per Cms. 40 mm 0.40 0.19 138.00
0.00 /- 50 mm 0.40 0.19 200.00
6.00 MTS. 65 mm 0.79 0.30 295.00
Km. Km 80 mm 0.79 0.30 362.00
Km. Km 100 mm 1.19 0.40 512.00
428.37 125 mm 1.79 0.54 0.00
0.00 150 mm 2.69 0.73 0.00
165.10 mm
38.00 Each
20.00 Each

Km. KM
Km. KM
0.00 MT
0.00 MT
148.15 Each
148.15 Each
116.65 Each
ANALYSIS OF RATE
& WELDING OF MS FLANGE ( IS:6392-1971 17 80
A.THE WELDING OF FLANGES WITH PIPE SHOULD CONFORM TO
6-1965 WITH ELECTODE AS PER IS :814-1967 I/c REQUIRED Nos. OF
& NUTS AS PER IS : 1369-1967 & 3mm THICK ASBESTOS FIBRE
NG GASKET SHEET CONFORMING TO IS :2712-1965.THE WELDING
NGE SHOULD BE DONE IN TWO LAYERS ON BOTH FACES TO MAKE
OINTS AIR TIGHT & TO ENTIRE SATISFACTION OF THE ENGINEER
(UNIT ONE PAIR)
DESCRIPTION OF ITEM QTY. RATE UNIT AMT.
MATERIAL:-
mm DIA.FLANGE TABLE OF
Pipe O.D 16.51 Cmts.

MS FLANGE I/C NUTS & BOLTS:-


No.of flanged joints: 1.00 No.
Wt. Of one Joint 13.95 Kg
Total wt. Of joints 13.95 Kg
13.950 56.00 EACH 781.20

Add 4 % HP Sale T 781.20 31.25


TOTAL 812.45 (a)
WELDING WITH MS FLANGE:-
2X2X2X22/7X 16.51 415.11 2.00 CMS. 830.22 (b)

RUBBER JOINTING GASKET 3 mm THICK:-


1.00 38.00 EACH 38.00 (c )
CUTTING OF THREADED ENDS:-
(NOT TAKEN DUE TO PLAIN ENDED PIPE)
2.00 20.00 EACH 40.00 (d)
CARRIAGE OF FLANGES:-
Km. KM 0.01395 0.00 MT 0.00
Km. KM 0.01395 0.00 MT 0.00
TOTAL 0.00 (e)
LABOUR:-

Labour for Jointing 10 Joints


QTY. RATE AMT.
0.18 148.15 26.67
0.18 148.15 26.67
0.96 116.65 111.98
TOTAL 165.32
Cost per16.53
1.00 16.53 EACH 16.53 (f)
TOTAL (a to f) 1737.20
Add 10% C.P. on Rs. 1737.20 173.72
Add 5% O.H.C. On Rs. 1737.20 86.86
TOTAL 1997.78
SAY Rs. 1997.80
ANALYSIS OF RATE
UNIT 102 RMT.
OINTING & TESTING OF BELOW MENTIONED GMS TUBE FULLY
GED WITH MS FLANGE (IS:6392-1971) COMPLETE IN ALL
ECT WITHIN ALL LEADS & LIFTS
DESCRIPTION OF IT QTY. RATE UNIT AMT.
MATERIAL:-
mm DIA. GMS TU 100.00
ADD 2% FOR FITT 0.20
0.00 RMT
TOTAL Total 0.00 RMT
TOTAL 102.00 0.00 RMT 0.00
TOTAL 0.00 (A)
MS FLANGE I/C NUTS & BOLTS (OF 17
No.of flanged joints: 1.00 No.
Wt. Of one Joint 0 Kg
Wt.Of one joints 13.950 Kg
Wt.Of 102/6=17 Nos.joints= 237.150 56.00 EACH 13280.40
Add 4 % HP Sale Tax 13280.40 531.22
TOTAL 13811.62 (B)
WELDING WITH MS FLANO.DIA. 16.51 Cmts.
2X2X2X22/7X 16.51 415.11 2.00 CMS. 830.22 (C )
RUBBER JOINTING GASKET 3 mm THICK
17.00 38.00 EACH 646.00 (D )
CUTTING OF THREADED ENDS:-
(NOT TAKEN DUE TO PLAIN ENDED PIPE)
34.00 20.00 EACH 680.00 (E)
LABOUR:-
(a)Labour for laying 514Kg pipe (BASED ON CI PIPE)
Qty Rate Amt.
0.20 148.15 29.63
0.20 148.15 29.63
1.60 116.65 186.64
Sunderies LS 31.75
TOTAL 277.65
Rate per Kg = 0.5402
1072.02 0.5402 kg 579.08 (I)
(b)Labour for jointing of 10 Nos.Joints.
QTY. RATE AMT.
0.18 148.15 26.67
0.18 148.15 26.67
0.96 116.65 111.98
TOTAL 165.32
Cost / Joint 16.53
1.00 16.53 EACH 16.53 (ii)
TOATL (i+ii) 595.61 (F)
CARRIAGE OFMATERIAL:-
(a) FOR G.M.S.PIPES:-
Km. KM 1.0720 428.37 MT 459.22
Km. KM 1.0720 0.00 MT 0.00
(b) FOR MS FLANGES:-
Km. KM 0.2372 428.37 MT 101.59
Km. KM 0.2372 0.00 MT 0.00
TOTAL 560.81 (G)
TOTAL (A to G) 17124.25
ADD 10 % CONTRACTOR'S PROFIT EXCEPT THE COST
OF PIPE & FLAN 3312.64 (+) 331.26
ADD 5.00 % OVER HEAD CHARGES
ON ALL AMOUNT 17124.25 (+) 856.21
TOTAL 18311.73
COST FOR 100 RMT 18311.73
COST PER 1.00 RMT 183.12
SAY Rs. 183.10

ANALYSIS OF RATE
ng, jointing and testing of below mentioned GMS Tubes screwed &
ted i/c all type of fitting such as bends,tees.air valves etc.(Earth work
nches to be measured & paid for separately) within all leads & lifts
ete in all respect as per entire satisfaction of Engineer-in-charge.
(Details of 10 Rmt.)
DESCRIPTION OF ITEM QTY. RATE UNIT AMT.
Description Qty.
Material :-
mm dia.
10.00 RMT
0.20 RMT
G.M.S.TUBES 10.00
Add 2% for fitting etc. 0.20
TOTAL 10.20 585.00 RMT 5967.00
ADD FOR WHITE LEAD & HUMP
OIL ETC. LS 25.00
T0TAL 5992.00 (A)
CARRIAGE OF PIPES:-
Km. KM 10.200 428.37 100 Rmt 43.69
Km. KM 10.200 0.00 100 Rmt 0.00
TOTAL 43.69 (B)
LABOUR:- (LABOUR FOR JOINTING OF PIPE)
PLUBER/FITTER (G-I) 0.73 148.15 EACH 108.15
2.69 116.65 EACH 313.79
TOTAL 421.94 (C )
TOTAL (A+B+C) 6457.63
ADD10% CP EXCEPT COST OF PIPE ON Rs. 490.63 49.06
ADD 5 % O.H.C. ON ALL AMOUNT ON Rs. 6457.63 322.88
COST OF10.00 RMT 6829.58
COST OF1.00RMT 682.96
SAY Rs. 683.00

-
RATE /RMT WT.OF GMS TUBES
MEDIUM HEAVY LIGHT MEDIUMHEAVY
0.00 0.00 1.03 1.29 1.52
0.00 0.00 1.50 1.67 1.99
0.00 0.00 2.13 2.56 3.09
0.00 0.00 2.74 3.29 3.99
102.00 135.00 3.43 3.79 4.63
140.00 167.00 4.36 5.35 6.42
178.00 244.00 6.16 6.84 8.23
245.00 280.00 7.29 8.89 10.51
362.00 395.00 10.51 12.72 15.02
500.00 639.00 0.00 17.09 18.69
585.00 726.00 0.00 20.27 22.27
Rate Unit Amt.
CARRIAGE OF MATERIAL BY MANUAL LABOUR INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
S.No MATERIALS CAPACITY NET UNITS COST COST OF CARRIGE INCLUDING LOADING
QTY.TO OF 8 AND STACCKING
BE PAID HOURS FOR FOR FOR FOR 1 BEYON
AFTER FIRST EVERY 100 KM. D1
DEDUC 50 MTR ADD. MTR KM./EVE
TION LEAD RY 1/2
OF OF 50 KM.
VOIDS. MTRS
OR
1 2 3 4 5 6 7 8 9 10 11

LIGHT MATERIAL : A = ( 7.67 BELDAR @ 116.67 = 626.41 ) B= (626.41/2)+(626.41*1.40)/2=751.7


Lime, moorum and building rubish. 35 cu.m 35 1 cu.m 0.00 0.00 0.00 0.00 0.00
1
2 .Earth work. 35 cu.m 28 1 cu.m 0.00 0.00 0.00 0.00 0.00
3 Manure or sludge 35cu.m 32.2 1 cu.m 0.00 0.00 0.00 0.00 0.00
4 Excavated rock. 35 cu.m 17.5 1 cu.m 0.00 0.00 0.00 0.00 0.00
5 Sand,stone agg.below 40mm size. 28 cu.m 28 1 cu.m 0.00 0.00 0.00 0.00 0.00

Stone agg.40mm & above,build. 28 cu.m 25.9 1 cu.m 0.00 0.00 0.00 0.00 0.00
6
Stones.
7 Soling stone, stone block & stone 28 cu.m 28 1 cu.m 0.00 0.00 0.00 - 0.00
for filling crates
8 Bricks. 15000 Nos 15000 1000 Nos. 0.00 0.00 0.00 0.00 0.00
Bricks tiles. 24000 Nos. 24000 1000 Nos. 0.00 0.00 0.00 0.00 0.00
9

10 Slates. 80000 Nos. 80000 1000 Nos. 0.00 0.00 0.00 0.00 0.00
Terrazzo Tiles. 15000 Nos 15000 1000 Nos. 0.00 0.00 0.00 0.00 0.00
11

HEAVY MATERIAL. A= (9.2 Beldar @ Rs.116.67 =751.36) B= (751.36/2)+(751.36*1.4)/2 =901.63


Stone blocks G.I,C.C. pipes below
1 100mm dia & other heavy 46 Tonne 46 1 Tonne 0.00 0.00 0.00 0.00 0.00
materials.
2 cement 57 Tonne 57 1 Tonne 0.00 0.00 0.00 0.00 0.00
Steel including C.G.I & asbestos
3 27 Tonne 27 1 Tonne 0.00 0.00 0.00 0.00 0.00
sheet.
4 Timber 42 cu.m 42 1 cu.m 0.00 0.00 0.00 0.00 0.00
5 Tar Bitumen etc. 46 Tonne 46 1 Tonne 0.00 0.00 0.00 0.00 0.00
1 2 3 4 5 6 7 8 9 10 11
Concrete, R.C.C. Hume, steel
6 1702m 1702 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 100mm dia
Concrete, R.C.C. Hume, steel
7 1391m 1391 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 125mm dia
Concrete, R.C.C. Hume, steel
8 1208m 1208 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 150mm dia
Concrete, R.C.C. Hume, steel
9 805m 805 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 200mm dia
Concrete, R.C.C. Hume, steel
10 458m 458 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 250mm dia
Concrete, R.C.C. Hume, steel
11 366m 366 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 300mm dia
Concrete, R.C.C. Hume, steel
12 256m 256 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 350mm dia
Concrete, R.C.C. Hume, steel
13 220m 220 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 400mm dia
Concrete, R.C.C. Hume, steel
14 165m 165 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 450mm,500mm dia
15 Concrete, R.C.C. Hume, steel 150m 150 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:- 600,700,750&800mm
dia
Concrete, R.C.C. Hume, steel
16 125m 125 100m 0.00 0.00 0.00 0.00 0.00
C.I.Pipes:-
900,1000,1100&1200mm dia
Asbestes cement pipes: - 50mm
17 10064m 10064 100m 0.00 0.00 0.00 0.00 0.00
dia =5032 pipes of 2m length
10064m
As bestes cement pipes: - 80mm
18 3660m 3660 100m 0.00 0.00 0.00 0.00 0.00
dia 1620 pipes of 2m length=3660
19 As bestes cement pipes:- 100mm 2562m 2562 100m 0.00 0.00 0.00 0.00 0.00
dia 1281 pipes of 2m
length=2562m
As bestes cement pipes:- 125mm
20 dia 1100 pipes of 2m length= 2200m 2200 100m 0.00 0.00 0.00 0.00 0.00
2200m
As bestes cement pipes:- 150mm
21 dia 915 pipes of 2m length =1830m 1830m 1830 100m 0.00 0.00 0.00 0.00 0.00
22 As bestes cement pipes:- 200mm 1600m 1600 100m 0.00 0.00 0.00 0.00 0.00
dia 800 pipes of 2m length= 1600m
23 As bestes cement pipes:- 250mm 1400m 1400 100m 0.00 0.00 0.00 0.00 0.00
dia 700 pipes of 2m length= 1400m
As bestes cement pipes:- 300mm
24 1200m 1200 100m 0.00 0.00 0.00 0.00 0.00
dia 600 pipes of 2m length= 1200m
ABSTRACT OF COST AND DETAIL OF MEASUREMENT

Name of wok :-Providing.W.S.S. to PC Habitation Urtoo of G.P.Rahnoo in Tehsil Nirmand


Sr. Description Of Items / Sub Head No
1 Excavation in foundation and trenches etc. in earth work lift up to 1.5 mtr.
Stacking the excavated earth not more than 3 mtr. Clear from the edge of
excavation and then returning the stacked soil in 15 cm layer when required
into plinth, sides of foundation etc. consolidating each deposited layer by
ramming and watering and then disposing of aii surplus earth with in a lead
as directed by the Engineer in charge in P/J work 50% each
1*1
2 Providing and laying G.I.Pipes (LG) in trenches etc i/c necessary fitting. Earth
work to be measured and paid separately.
1)15 mm 1*1
11)20mm 1*1
III)25 mm 1*1
iv)32mm 1*1
v)40mm 1*1
MEASUREMENT

noo in Tehsil Nirmand


L B H/D Qty Rate Unit Amount

7800 0.55 0.75 3217.5 #REF! cum #REF!


0

2800 - - 2800 58.93 Rmt 165004


600 - - 600 80.13 Rmt 48078
700 - - 700 107.87 Rmt 75509
3000 - - 3000 128.36 Rmt 385080
700 - - 700 164.2 Rmt 114940
Total 0
#REF!

Assistant Engineer Executive Engineer


I&PH.Sub Division I&PH.Division
Nirmand Ani

Das könnte Ihnen auch gefallen