LAGB CHECK LIST - 001 1. Licences and documents of Bullets and Barge
THE FERTILISERS AND CHEMICALS TRAVANCORE LTD. 2. Licences of crew members
PD - AMMONIA HANDLING SECTION 3. Safety training certificates
CHECK LIST FOR AMMONIA BARGE LOADING/UNLOADING 4. Details of PPE's kept in Barge
Ensure and fill the following details before releasing Ammonia Barge

Sl.No. CREW MEMBERS


Name of Barge : FACT - PRAGATIYAN / HAILMARY 1 Master -1
Date & Time of Departure : 2. Master -2
ICGP No. : 3. Engine Driver -1
Authorized carrying capacity 4. Engine Driver - 2

of the Barge (MT) : 192 T (6 x 32 MT) 5. Deck Hand -1


6. Deck Hand -2
Total loaded quantity (MT) :
7 Fact Personnel -1
8. Fact Personnel -2
Status of Valves / Levels / Temperatures / Pressures in Barge at the time of Despatch
AB1 AB2 AB3 AB4 AB5 AB6 Remarks
Initial Final Initial Final Initial Final Initial Final Initial Final Initial Final
Level (cm)
Temp. (C)
Bullet / Header (Loaded) Pressure (Kg/cm2)
Quantity (MT)
Confirm Liquid Eduction Valve - I is closed
Confirm Liquid Eduction Valve II is closed
Confirm Vapour Eduction valve is closed
Confirm Liq. line to Bullet Isol. Valve closed
Confirm Vap. line to Bullet Isol. Valve closed
Relief Valve Status
Lid Status
Level Indicator
SAFETY DEPARTMENT
Confirm By -pass valve in liquid line, between liquid line 1 & 2 closed
Confirm Working of the Sprinkler system and Fire water system by switching on pumps in the barge.
Confirm vapour & liquid hoses of each bullet disconnected (12 Nos) after
loading / unloading operations. (Pragatiyan) Confirm availability of PPE's (Mask, Goggles, Helmets, PVC suite, SCBA, Ammonia Mask with canister, Gloves) in the barge
Confirm By -pass valve in liquid line, between liquid line 2 & 3 closed Confirm availability of Fire Fighting Equipment in the barge.
Confirm shore side 3 nos liquid and 2 nos vapour hoses disconnected Confirm availability of diesel for sprinkler pump
from the barge after loading / unloading operations
Confirm that waters is filled in the ballast tank to required level.
Confirm 3 nos Drain Valves and 2 nos Vapour Vent Valves are closed after
loading / unloading operations Check Tremcard, First Aid Box and Emergency Telephone nos. are kept in the cabin.
Any minor leaks from valve flanges / glands? Do not release the barge if any Whether mobile phone available in barge: Mob.No:
leak is detected
The Consignment Received After Safety Check.
Signed by EMERGENCY CONTACT NUMBER Name Signature
Engineer / Assistant Safety Officer 1. 0484 - 2568308, 25683692 (PD) Barge Master
Manager (Production) 2. 0484 - 2667720 (W.I.) FACT Technical
Person(Process)
3. 0484 - 2723488 (CD) Date : Time