Project: Example

ETAP Page: 1
19.5.0D
Location: Irvine, California Date: 05-08-2020
Contract: OTI-12345678 SN: DLRPTILTDA
Engineer: Operation Technology, Inc. Revision: Base
Study Case: ANSI-Max
Filename: Example-ANSI Config.: Normal

This info is printed on every output report, 1st remark line. (120 characters)
Second line of remarks for "ANSI - Max" study case.

SHORT-CIRCUIT REPORT

3-phase fault at bus: Bus1

Prefault voltage = 0.490 kV = 102.00 % of nominal bus kV (0.480 kV)


= 102.00 % of base (0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Bus1 Total 0.00 3.827 -29.022 7.6 29.274

Bus2 Bus1 0.00 0.000 0.000 999.9 0.000

Sub 3 Bus1 93.29 3.827 -29.022 7.6 29.274

Sub3 Swgr Sub 3 93.33 0.023 -0.083 3.7 0.086

Bus3 Sub 3 93.62 0.161 -1.107 6.9 1.119

#T1~ Sub 3 100.67 0.258 -2.158 8.4 2.174

Bus9 Sub3 Swgr 93.98 0.006 -0.021 3.7 0.022

LVBus Sub3 Swgr 93.77 0.004 -0.008 1.9 0.009

MCC1 Sub3 Swgr 97.20 0.006 -0.029 4.6 0.030

Pump 1 Sub3 Swgr 106.08 0.007 -0.025 3.8 0.026

WTG1 Bus3 102.00 0.161 -1.107 6.9 1.119

#Main Bus T1~ 100.77 0.029 -0.250 8.5 0.251

#Sub2B T1~ 100.97 0.002 -0.011 6.6 0.011

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer.


* Indicates a fault current through a tie circuit breaker.
If the faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these protective devices will not be reported.
Project: Example
ETAP Page: 2
19.5.0D
Location: Irvine, California Date: 05-08-2020
Contract: OTI-12345678 SN: DLRPTILTDA
Engineer: Operation Technology, Inc. Revision: Base
Study Case: ANSI-Max
Filename: Example-ANSI Config.: Normal

This info is printed on every output report, 1st remark line. (120 characters)
Second line of remarks for "ANSI - Max" study case.

3-phase fault at bus: Bus3

Prefault voltage = 4.243 kV = 102.00 % of nominal bus kV (4.160 kV)


= 102.00 % of base (4.160 kV)

Contribution 1/2 Cycle 1.5 to 4 Cycle


From Bus To Bus %V kA kA Imag. kA Symm. %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude From Bus Real Imaginary /Real Magnitude

Bus3 Total 0.00 2.115 -38.035 18.0 38.094 0.00 1.744 -33.090 19.0 33.136

Sub 3 Bus3 7.86 1.715 -24.515 14.3 24.575 7.71 1.566 -24.073 15.4 24.123

WTG1 Bus3 102.00 0.400 -13.520 33.8 13.526 102.00 0.178 -9.018 50.7 9.019

Sub3 Swgr Sub 3 8.22 0.196 -0.915 4.7 0.936 7.90 0.059 -0.461 7.8 0.465

Bus1 Sub 3 7.86 0.000 0.000 999.9 0.000 7.71 0.000 0.000 999.9 0.000

#T1~ Sub 3 87.51 1.519 -23.600 15.5 23.649 87.40 1.507 -23.611 15.7 23.659

Bus9 Sub3 Swgr 15.14 0.048 -0.230 4.8 0.235 12.69 0.025 -0.160 6.5 0.162

LVBus Sub3 Swgr 12.39 0.039 -0.088 2.2 0.096 9.88 0.009 -0.042 4.8 0.043

MCC1 Sub3 Swgr 23.82 0.051 -0.320 6.3 0.325 14.89 0.013 -0.145 10.8 0.146

Pump 1 Sub3 Swgr 106.08 0.057 -0.276 4.9 0.282 106.08 0.012 -0.114 9.5 0.115

Bus2 Bus1 7.86 0.000 0.000 999.9 0.000 7.71 0.000 0.000 999.9 0.000

#Main Bus T1~ 88.59 0.172 -2.730 15.9 2.736 88.49 0.172 -2.740 15.9 2.745

#Sub2B T1~ 90.73 0.011 -0.115 10.3 0.116 90.39 0.010 -0.107 11.2 0.107

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer.


* Indicates a fault current through a tie circuit breaker.
If the faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these protective devices will not be reported.
Project: Example
ETAP Page: 3
19.5.0D
Location: Irvine, California Date: 05-08-2020
Contract: OTI-12345678 SN: DLRPTILTDA
Engineer: Operation Technology, Inc. Revision: Base
Study Case: ANSI-Max
Filename: Example-ANSI Config.: Normal

This info is printed on every output report, 1st remark line. (120 characters)
Second line of remarks for "ANSI - Max" study case.

3-phase fault at bus: Main Bus

Prefault voltage = 35.190 kV = 102.00 % of nominal bus kV (34.500 kV)


= 102.00 % of base (34.500 kV)

Contribution 1/2 Cycle 1.5 to 4 Cycle


From Bus To Bus %V kA kA Imag. kA Symm. %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude From Bus Real Imaginary /Real Magnitude

Main Bus Total 0.00 0.572 -22.737 39.7 22.744 0.00 0.529 -22.294 42.2 22.301

Sub2A Main Bus 12.76 0.022 -0.309 14.3 0.310 9.17 0.012 -0.222 18.0 0.222

#T1~ Main Bus 0.78 0.096 -1.950 20.4 1.952 0.64 0.061 -1.594 26.0 1.595

Utility Main Bus 102.00 0.455 -20.478 45.0 20.483 102.00 0.455 -20.478 45.0 20.483

Bus7 Sub2A 12.88 0.044 -0.462 10.6 0.464 9.26 0.023 -0.340 14.7 0.341

Syn1 Sub2A 106.64 0.010 -0.310 30.0 0.310 106.64 0.008 -0.215 27.9 0.215

#Sub2B T1~ 23.33 0.041 -0.808 19.7 0.809 21.41 0.032 -0.744 22.9 0.745

#Sub 3 T1~ 33.13 0.055 -1.142 20.9 1.144 24.68 0.029 -0.850 29.5 0.850

Sub22 Bus7 27.29 0.044 -0.462 10.6 0.464 19.85 0.023 -0.340 14.7 0.341

Bus6 Sub2B 23.34 0.021 -0.076 3.7 0.079 21.41 0.001 -0.013 23.5 0.013

Gen1 Sub2B 102.00 0.068 -1.525 22.3 1.527 102.00 0.074 -1.562 21.0 1.564

Mtr2 Sub2B 106.64 0.013 -0.418 31.1 0.418 106.64 0.006 -0.286 46.2 0.286

Sub3 Swgr Sub 3 33.37 0.108 -0.669 6.2 0.677 24.82 0.032 -0.376 11.7 0.377

Bus3 Sub 3 35.56 0.345 -8.805 25.5 8.812 26.53 0.206 -6.672 32.3 6.675

Bus1 Sub 3 33.13 0.000 0.000 999.9 0.000 24.68 0.000 0.000 999.9 0.000

NACD Ratio = 0.97

# Indicates a fault current contribution from a three-winding transformer.


* Indicates a fault current through a tie circuit breaker.
If the faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these protective devices will not be reported.
Project: Example
ETAP Page: 4
19.5.0D
Location: Irvine, California Date: 05-08-2020
Contract: OTI-12345678 SN: DLRPTILTDA
Engineer: Operation Technology, Inc. Revision: Base
Study Case: ANSI-Max
Filename: Example-ANSI Config.: Normal

This info is printed on every output report, 1st remark line. (120 characters)
Second line of remarks for "ANSI - Max" study case.

3-phase fault at bus: Sub2A

Prefault voltage = 14.076 kV = 102.00 % of nominal bus kV (13.800 kV)


= 102.00 % of base (13.800 kV)

Contribution 1/2 Cycle 1.5 to 4 Cycle


From Bus To Bus %V kA kA Imag. kA Symm. %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude From Bus Real Imaginary /Real Magnitude

Sub2A Total 0.00 0.296 -6.448 21.8 6.455 0.00 0.265 -6.167 23.3 6.173

Bus7 Sub2A 0.16 0.052 -0.528 10.2 0.530 0.11 0.026 -0.374 14.5 0.375

Main Bus Sub2A 91.87 0.232 -5.566 24.0 5.570 91.72 0.230 -5.557 24.1 5.562

Syn1 Sub2A 106.64 0.013 -0.354 27.0 0.355 106.64 0.009 -0.236 27.0 0.236

Sub22 Bus7 16.61 0.052 -0.528 10.2 0.530 11.74 0.026 -0.374 14.5 0.375

#T1~ Main Bus 91.95 0.013 -0.193 15.1 0.194 91.79 0.009 -0.160 17.7 0.161

Utility Main Bus 102.00 0.080 -2.033 25.5 2.034 102.00 0.083 -2.062 24.8 2.064

LUMP2 Sub22 106.64 0.207 -2.111 10.2 2.121 106.64 0.103 -1.496 14.5 1.499

#Sub2B T1~ 94.19 0.005 -0.080 14.7 0.080 93.88 0.005 -0.075 16.2 0.075

#Sub 3 T1~ 95.16 0.007 -0.113 15.4 0.114 94.21 0.004 -0.086 19.3 0.086

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer.


* Indicates a fault current through a tie circuit breaker.
If the faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these protective devices will not be reported.
Project: Example
ETAP Page: 5
19.5.0D
Location: Irvine, California Date: 05-08-2020
Contract: OTI-12345678 SN: DLRPTILTDA
Engineer: Operation Technology, Inc. Revision: Base
Study Case: ANSI-Max
Filename: Example-ANSI Config.: Normal

This info is printed on every output report, 1st remark line. (120 characters)
Second line of remarks for "ANSI - Max" study case.

3-phase fault at bus: Sub2B

Prefault voltage = 14.076 kV = 102.00 % of nominal bus kV (13.800 kV)


= 102.00 % of base (13.800 kV)

Contribution 1/2 Cycle 1.5 to 4 Cycle


From Bus To Bus %V kA kA Imag. kA Symm. %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude From Bus Real Imaginary /Real Magnitude

Sub2B Total 0.00 0.352 -10.367 29.5 10.373 0.00 0.310 -10.083 32.5 10.088

Bus6 Sub2B 0.03 0.028 -0.098 3.5 0.102 0.00 0.001 -0.017 21.0 0.017

#T1~ Sub2B 86.48 0.198 -7.751 39.1 7.753 86.24 0.196 -7.729 39.4 7.731

Gen1 Sub2B 102.00 0.104 -1.976 19.0 1.979 102.00 0.104 -1.976 19.0 1.979

Mtr2 Sub2B 106.64 0.022 -0.542 25.0 0.542 106.64 0.010 -0.361 37.5 0.362

Sub23 Bus6 3.19 0.028 -0.098 3.5 0.102 0.52 0.001 -0.017 21.0 0.017

#Main Bus T1~ 87.65 0.070 -2.925 42.0 2.926 87.42 0.073 -2.959 40.6 2.960

#Sub 3 T1~ 91.44 0.010 -0.175 18.3 0.175 89.98 0.005 -0.132 24.1 0.132

Bus23A Sub23 21.48 0.111 -0.393 3.5 0.408 3.49 0.003 -0.066 21.0 0.066

Sub2A Main Bus 89.44 0.003 -0.043 14.1 0.044 88.73 0.002 -0.032 17.4 0.032

Utility Main Bus 102.00 0.067 -2.882 43.2 2.882 102.00 0.071 -2.928 41.2 2.929

Sub3 Swgr Sub 3 91.48 0.017 -0.102 5.9 0.104 90.00 0.005 -0.058 10.8 0.059

Bus3 Sub 3 91.81 0.062 -1.350 21.8 1.351 90.26 0.040 -1.037 25.9 1.038

Bus1 Sub 3 91.44 0.000 0.000 999.9 0.000 89.98 0.000 0.000 999.9 0.000

NACD Ratio = 0.80

# Indicates a fault current contribution from a three-winding transformer.


* Indicates a fault current through a tie circuit breaker.
If the faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these protective devices will not be reported.
Project: Example
ETAP Page: 6
19.5.0D
Location: Irvine, California Date: 05-08-2020
Contract: OTI-12345678 SN: DLRPTILTDA
Engineer: Operation Technology, Inc. Revision: Base
Study Case: ANSI-Max
Filename: Example-ANSI Config.: Normal

This info is printed on every output report, 1st remark line. (120 characters)
Second line of remarks for "ANSI - Max" study case.

3-phase fault at bus: Sub 3

Prefault voltage = 4.243 kV = 102.00 % of nominal bus kV (4.160 kV)


= 102.00 % of base (4.160 kV)

Contribution 1/2 Cycle 1.5 to 4 Cycle


From Bus To Bus %V kA kA Imag. kA Symm. %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude From Bus Real Imaginary /Real Magnitude

Sub 3 Total 0.00 1.462 -39.358 26.9 39.386 0.00 0.973 -34.609 35.6 34.623

Sub3 Swgr Sub 3 0.40 0.171 -0.988 5.8 1.003 0.20 0.044 -0.496 11.3 0.498

Bus3 Sub 3 4.17 0.658 -13.031 19.8 13.047 2.82 0.300 -8.801 29.3 8.806

Bus1 Sub 3 0.00 0.000 0.000 999.9 0.000 0.00 0.000 0.000 999.9 0.000

#T1~ Sub 3 86.45 0.632 -25.339 40.1 25.347 86.36 0.629 -25.312 40.3 25.320

Bus9 Sub3 Swgr 8.01 0.042 -0.249 5.9 0.252 5.44 0.020 -0.173 8.7 0.174

LVBus Sub3 Swgr 6.01 0.038 -0.096 2.5 0.103 2.69 0.007 -0.045 6.0 0.046

MCC1 Sub3 Swgr 17.96 0.041 -0.345 8.4 0.348 8.08 0.008 -0.156 18.7 0.156

Pump 1 Sub3 Swgr 106.08 0.049 -0.298 6.1 0.302 106.08 0.008 -0.122 15.1 0.123

WTG1 Bus3 102.00 0.658 -13.031 19.8 13.047 102.00 0.300 -8.801 29.3 8.806

Bus2 Bus1 0.00 0.000 0.000 999.9 0.000 0.00 0.000 0.000 999.9 0.000

#Main Bus T1~ 87.62 0.069 -2.931 42.4 2.932 87.53 0.070 -2.937 41.9 2.938

#Sub2B T1~ 89.91 0.007 -0.124 17.5 0.124 89.56 0.006 -0.115 19.8 0.115

LUMP6 Bus9 102.00 0.042 -0.249 5.9 0.252 102.00 0.020 -0.173 8.7 0.174

LUMP1 LVBus 106.43 0.332 -0.831 2.5 0.895 106.43 0.065 -0.390 6.0 0.395

Mtr6 MCC1 109.16 0.089 -0.595 6.7 0.602 109.16 0.018 -0.271 15.2 0.271

Mtr4 MCC1 181.28 0.170 -1.705 10.1 1.713 181.28 0.035 -0.766 22.0 0.767

Mtr3 MCC1 109.16 0.049 -0.369 7.5 0.372 109.16 0.010 -0.167 17.0 0.167

Mtr5 MCC1 109.16 0.041 -0.250 6.0 0.253 109.16 0.008 -0.114 13.9 0.114

Sub2A Main Bus 89.42 0.003 -0.044 14.2 0.044 88.83 0.002 -0.032 17.6 0.032

Utility Main Bus 102.00 0.066 -2.888 43.7 2.889 102.00 0.068 -2.906 42.6 2.907

Bus6 Sub2B 89.91 0.003 -0.012 3.6 0.012 89.56 0.000 -0.002 20.2 0.002

Gen1 Sub2B 102.00 0.012 -0.234 19.5 0.235 102.00 0.013 -0.241 18.4 0.241

Mtr2 Sub2B 106.64 0.002 -0.064 25.9 0.064 106.64 0.001 -0.044 35.1 0.044

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer.


* Indicates a fault current through a tie circuit breaker.
If the faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these protective devices will not be reported.