Contract No.

: 148/10 – Al Ras Al Akhdar and Baynoonah Street Upgrading and Traffic


Improvement (Packages 1 & 2)

METHOD STATEMENT
FOR
CONSTRUCTION OF CHAMBERS

Designation Signature Date

Prepared by Site Engineer

Checked by QA/QC Engineer

Approved by Project Manager

Page No. 1 of 5
MACE CONTRACTORS CO. LIMITED
Ref.: MACE-MS-WL-106
Rev.: 0
Date of Issue: 21 April. 2011
CONTENTS

1.0 Purpose

2.0 Definitions

3.0 Responsibilities

4.0 Actions

5.0 Appendices

1.0 PURPOSE
Page No. 2 of 6
MACE CONTRACTORS CO. LIMITED
Ref.: MACE-MS-WL-106
Rev.: 0
Date of Issue: 21 April. 2011
The purpose and scope of this method statement is to ensure that the construction of
chambers is done in accordance with the correct methods and procedures.
2.0 DEFINITIONS
ADDC Abu Dhabi Distribution Company
TEBODIN Tebodin Middle East Limited
MACE MACE Contractors Company Limited
RE Resident Engineer
PM Project Manager
SE Site Engineer
SO Safety Officer
QA/QC Quality Assurance / Quality Control Engineer
RFI Request for Inspection
Utilities All services, such as gas, water, oil , sewage, chilled lines, cables, etc.
ADM Abu Dhabi Municipality
3.0 RESPONSIBILITIES
PM/DPM shall ensure that all necessary tools & Instruments, safety protective equipments
are provided along with properly trained and qualified surveyors and made
available sufficiently in advance to the commencement of the work.

Safety Officer has to implement and enforce all safety precautions. He will also inspect the work
site regularly, and report deficiencies to the DPM / PM.

Site Engineer is responsible for the construction work and shall delegate a named Site
Supervisor who shall ensure that this procedure is fully implemented including
documentation till completion.

Surveyor is responsible to ensure that all surveying instrument being used are calibrated
and having valid calibration certificate and he shall ensure that all information,
data etc. required is to be taken and recorded on his Field Book.
4.0 ACTIONS
4.1 Prior to commencement, approval for all mechanical fittings, valves D.I. covers, steel
reinforcement, water stop and concrete to be obtained.
4.2 Excavation will be started, considering that excavation will be done as open-cut to safe
angle of repose for stable soil condition.
4.3 Getting the required formation level, proper compaction will be applied. Any soil test
is required will be carried out according to Engineer’s instruction.

Page No. 3 of 6
MACE CONTRACTORS CO. LIMITED
Ref.: MACE-MS-WL-106
Rev.: 0
Date of Issue: 21 April. 2011
Page No. 4 of 6
MACE CONTRACTORS CO. LIMITED
Ref.: MACE-MS-WL-106
Rev.: 0
Date of Issue: 21 April. 2011
Page No. 5 of 6
MACE CONTRACTORS CO. LIMITED
Ref.: MACE-MS-WL-106
Rev.: 0
Date of Issue: 21 April. 2011