Beruflich Dokumente
Kultur Dokumente
net/publication/303686258
CITATIONS READS
2 2,521
2 authors, including:
Miroslav Marence
IHE Delft Institute for Water Education
62 PUBLICATIONS 152 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Miroslav Marence on 31 May 2016.
ABSTRACT: The Ermenek hydro power plant, currently under construction, with numerous underground fa-
cilities represents a big challenge the rock mechanics and tunneling works, especially for the pressure tunnel
situated in the very heterogeneous rock mass with exchanging of weak and hard rock units. The tunnel is ex-
cavated by TBM, lined with concrete lining and loaded with internal pressure of up to 13 bar (130 m of wa-
ter). Design requirements and design considerations with selected solutions are presented.
Considering all of these data the possible failure − installation of the support in the region L1 imme-
mechanisms (ground behaviour types) can be de- diately after the head and in L2 behind the ma-
fined. The Austrian society for geomechanics (ÖGG, chine
2001) distinguishes eleven different ground behav- − application of shotcrete in the L1 region is re-
iour types. A unique calculation method covering all stricted to the support classes where immediate
ground behaviour types does not exist. The calcula- support and rock sealing is necessary
tion method, analytical and numerical, must be ap- − support with steel rings as an immediate support
propriate for the assumed behaviour type. Three fre- in weaker rock mass
quently encountered failure mechanisms are: block The support systems are grouped in 6 support
failure, local plastification and squeezing rock con- classes giving smooth transition from class to class.
ditions. A suitable model gives answer on suitability The first three classes, M1-M3, define the support in
of selected excavation process and support measures the blocky rock mass such as limestone and the last
and gives possibility for risk assessment (Marence, three, M4-M6, for the much weaker flysch rock. The
1998). In case of structurally controlled instabilities support class M5 (weak rock) is shown on Figure 3.
kinematic models are used for surface and under- The support consists of steel arches TH 36 on the
ground excavations. The condition of joints and their stroke distance of 1.70 m, systematic bolting in L1
orientation in relation to the designed structure are and additionally in L2 region with 3.60 m long
decisive for stability and several software products grouted bolts and 5 cm shotcrete in L1 and addi-
are available for such calculations. In case of ho- tional 10 cm shotcrete in L2 region reinforced with
mogenous and isotropic rock mass conditions con- two layers of wire mesh.
tinuous models like finite element or finite differ- On site, after each excavation cycle, the geologi-
ence models are used. cal conditions on face are compared with design
Based on the calculations the primary support values, the suitability of the designed system is
system is defined. Support is defined taking into checked and a decision about support class applica-
consideration requests of the TBM: tion is done. In case of over- or under-estimation of
the designed support system, the system can be eas- vourable loading and needs special treatment. Dif-
ily adopted to the actual circumstances. ferent methods to decrease, eliminate or overtake
tensile forces are developed. In the Ermenek pres-
sure tunnel two systems are selected: un-reinforced
and reinforced concrete lining.
The plane, un-reinforced, concrete lining, as the
most economic final lining, is adapted only for tun-
nels where only small tensile stresses in lining oc-
curs during operation. In pressure tunnels subject to
high internal pressures the plane concrete lining has
to be pre-stressed in order to keep it free from fis-
sures. The pre-stressing is made in form of grout in-
jection in the gap between the final lining and the
surrounding rock mass. In case that prestressing is
Figure 3. Primary support classes M5 for weak rock (flysch) not possible, tightening of the tunnel can be done by
thin foils (plastic or thin steel lining), reinforced
Geotechnical design gives possibility for under- concrete and by high internal water pressure by clas-
standable and comprehensive design with the option sical thick steel penstock. By the Ermenek project
of intervention and adaptation in each project stage, sections where full prestressing was not possible the
based on the new knowledge, and during the con- final lining is reinforced. A tight reinforced lining is
struction works according to the as found conditions. achieved by special design requirements on lining
and consolidation injections around the tunnel.
2.3 Pre-cast invert segment 2.4.2 Design based on Seeber theory
The pre-cast concrete segment is used as a TBM Seeber (1984) defines the design method for unrein-
sleeper. The segment is designed as a reinforced forced final linings of the pressure tunnels. The
concrete element. Based on the selected final lining grout is pumped under high pressure into the contact
technology the segment is made of two parts – bot- joint between primary and final lining, a circumfer-
tom and top part that are screwed together. The rein- ential gap is opened and filled with cement grout.
forcement design is made for separate parts (trans- With the grout pressure exerted in the circumferen-
port) and for the connected system (operation). tial gap, the concrete ring is pre-stressed against the
Five different segment types have been designed, rock and the deformations of both sides are fixed by
distinguishing the technology and additional geo- the hardened cement grout. To reduce adhesion be-
metric conditions from the support requirements – tween shotcrete and concrete and to achieve the
gaps for the still rings in bottom part. A simple circumferential gap opening the shotcrete separation
sketch of one invert segment type is shown in Figure layer is applied on the contact surface. In other to
4. maintain the pre-stressing effect permanently, the
rock mass has to be sufficiently firm and the rock
stresses around the tunnel must be high enough to
take the pre-stressing pressure. The final lining and
the surrounding rock mass take the internal water
pressure dependent on their stiffness. In the case that
the pre-stressing by the injection is high enough, the
lining will remain in compression during the opera-
tion and can be left unreinforced.
The selection of the injection pressure and opti-
mal lining thickness is based on the simple graphic
Figure 4. Two-part pre-cast concrete segment
load-line method (Figure 5). The method is based on
the assumption of the circular tunnel in homogene-
ous rock mass with full around radial pre-stressing.
2.4 Final lining design The injection pressure is limited to the concrete
compressive strength and a minimal primary stress
2.4.1 Reinforced or un-reinforced lining in the rock mass during the injection phases and by
Main loading for the pressure tunnels is internal wa- leaving the lining in compression during operation.
ter pressure – static and dynamic pressure caused by An additional design condition is the groundwater
maintenance of turbines and valves. The internal wa- pressure in case of an empty tunnel.
ter pressure causes tensile forces in the lining. This,
because of low concrete tensile strength, is an unfa-
shrinkage and creep of lining, contact and consolida-
tion grouting, cooling of the lining by filling and in-
ternal water pressure.
The numerical model cannot portray all nature
phenomenas, but should include the most important
parameters of influence. Detailed description of the
finite element modeling the pressure tunnels is de-
scribed in Marence (1996). The most important
model part is modeling of the gap between the lin-
ings and its behavior before and after grouting. The
calculations are performed by the finite element pro-
gram FINAL (Swoboda, 2004) simulating possible
loading cases and modelling phenomena that occurs.
In case of unreinforced final lining, the lining
must stay in compression and the stresses in lining
are checked. For reinforced lining the reinforcement
Figure 5. Load-line design method
design is performed on the results of the finite ele-
ment calculations. The reinforcement amount must
The same design philosophy as for the unrein-
satisfy following criteria:
forced concrete lining is used for the design of the
− higher than minimal reinforcement in compres-
reinforced lining. The reinforced lining is used
sion and tension
where full grouting is not possible, because of too
− designed for actual loadings with full safety
low overburden or too weak rock mass. The grouting
− crack width less than 0.30 mm
with maximal allowed pressure – minimal initial
The crack with width of 0.30 mm means not ab-
stress – is applied. Grouting with pressure of 10 bars
solutely tight lining, but technically tight system. In
guarantee a contact between final lining and the rock
case of crack width less than 0.30 mm no erosion by
mass after cooling the lining. The contact is neces-
wash out of fine particles in the rock joints is ex-
sary to achieve smooth and continuous force distri-
pected and self-cure process by filling with sedi-
bution between lining and rock and also to include
ments will occur (Schleiss, 1997). In case of water
the surrounding rock in the bearing of the internal
sensitive regions – tunnel situated near the surface or
pressure. Higher grouting pressures, applied if pos-
in a vicinity of potentially unstable slope the crack
sible, additionally reduce the reinforcement amount
width criterion is tightened up.
in the lining.
To achieve the continuous reinforcement in the
2.4.4 Grouting philosophy
lining, the pre-cast segment must be removed and
The grouting is performed in two steps: contact
replaced by reinforced concrete. The two-part pre-
grouting and consolidation grouting.
cast segment allows removing the upper part without
The contact grouting achieves the contact be-
demolishing the primary tunnel lining and endanger-
tween the final lining and surrounding rock in the
ing the tunnel stability.
tunnel crown. A gap in the crown is a result of self
The preliminary calculations by spreadsheet pro-
weight deformations and shrinkage of the concrete.
gram are suitable for parameter sensitivity analyses
Also, in the crown during concreting void (highest
in pre-design. The calculations are performed for
point) can occur. Because of all this effects for all
each geological unit with necessary division; de-
tunnels, independent of function (traffic or con-
pendent on overburden, groundwater and other im-
ducts), contact grouting is performed. The contact
portant parameters. The comparison of results shows
grouting is performed in the tunnel crown with low
good agreement between this spreadsheet program
pressure 2-3 bar in the crown.
and finite element calculations (Marence, 1996).
The consolidation grouting has a function to
achieve continuous contact between the final lining
2.4.3 Numerical model
and surrounding rock mass after shrinkage of lining
The spreadsheet calculations are based on the
by drying of concrete (draught in tunnel) and cool-
analytical solution with idealized assumptions that
ing of the lining by water (occurs by first filling of
are not fully satisfying in practice. The most influ-
the system). The consolidation grouting by radial
enced parameters rock mass anisotropy and primary
hole method is selected.
state of stress can be easily included in the finite
By the radial hole method the grouting is per-
element calculations. The calculations follow on the
formed through mostly radially arranged boreholes.
numerical modeling of the excavation and primary
During the grouting procedure the grout penetrates
support (Swoboda, et al. 1993) including the stresses
into the surrounding rock and the gap between the
around the tunnel after excavation: The model in-
final lining and the rock mass. A separation layer –
cludes all important influences such as self weight,
lime paint or thin plastic foil – installed in the gap
will easily activate the gap. The grouting injected in tions, not only to achieve a stable, safe and eco-
the gap between lining and the rock mass results in nomical solution, but also to collect additional data
the so-called pre-stressing effect on the final lining. necessary for the final lining design. In the pressure
To achieve the nearly constant pressure in the gap tunnels the final concrete lining and surrounding
and nearly continuous loading on the lining the dis- rock mass make an integrated bearing system. The
tance between grouting holes, in radial and longitu- better the rock mass behavior is known, more the fi-
dinal direction, should not be larger than 2-3 metres nal lining and the consolidation grouting can be op-
measured on the final lining extrados. In the rock timized.
mass around the tunnel open joints or plastified In the project, generally, two types of final lining
zones occur and must be filled with the consolida- are selected; unreinforced and reinforced concrete
tion grouting to achieve a continuous support for the lining. The unreinforced concrete lining is used in
final lining. rock mass that can be grouted by sufficient pressure.
In addition, the consolidation grouting decreases The main criterion is no tensile stress during the op-
the rock mass permeability and increases the rock eration in the lining. In case of reinforced lining the
mass stiffness and strength. Reduction of the perme- consolidation grouting is used to achieve continuous
ability up to 20 times can be achieved. The strength contact with the surrounding rock mass and reducing
and stiffness of the rock mass will not be changed the reinforcement amount.
with such effort, but in case of anisotropic rock the
minimal values of strength and stiffness will be in-
creased, which will cause a more uniform system REFERENCES
around the tunnel. The reduction of the permeability
is important to decrease the water loses by both solu- Austrian society for geomechanics (ÖGG) 2001, Richtlinie für
tions where technically tight lining is necessary. die Geomechanische Planung von Untertagebauarbeiten
(Recommendations for geomechanical design of under-
Technically tight means that the lining is not imper- ground works). Österreichische Gesellschaft für Geome-
meable, but the water losses can be neglected. Addi- chanik.
tionally, the leaked water in tight surrounding will Barla, G. 2001: Tunnelling under squeezing conditions. In
increase the water pressure outside resulting in less Tunnelling Mechanics, Eurosummerschool, Innsbruck, pp
loading on the lining. 169-268.
The length of the gap grouting holes is defined Bieniawski, Z.T. 1989: Engineering rock mass classification.
Wiley, New York.
based on the following criteria: Hoek, E. 1999: Support for very weak rock associated with
− Achieving the continuous support around the tun- faults and shear zones. Proc. Int. symposium on rock sup-
nel and continuous pre-stressing pressure on lin- port and reinforcement Practice in Mining., Kalgoorie,
ing, the length should be in order of the tunnel ra- Australia.
dius Hoek, E. & Marinos P. 2000. Predicting tunnel squeezing prob-
lems in weak heterogenous rock masses. Tunnels and Tun-
− In case of weak rock mass the plastified zone nelling. Nov. & Dec. 2000.
should be fully grouted Hoek, E., Carranza-Torres, C.T., and Corkum B. 2002. Hoek-
− In highly karstified regions with two and three Brown failure criterion – 2002 edition. Proc. North Ameri-
dimensional karst phenomena (open joints and can Rock Mechanics Society, Toronto, Canada.
caves) the pattern of longer boreholes (up to tun- Jung, G & Marence, M. 2004. Comparison of international and
nel diameter) for exploration is foreseen Austrian rock mechanical design procedures. EUROCK
2004 &53rd Geomechanics colloquium. Schubert (ed.), in
− The open joints, especially semi-parallel to the press.
tunnel axis, and caves that are encountered during Marence, M. 1996. Finite element modelling of pressure tun-
the excavation must be filled with concrete before nel. In. J.-A. Dèsidèri et al. (ed) Numerical Methods in En-
installation of the final lining. gineering ’96. Proc. of 2nd ECCOMASS Conf. Paris Sep-
Generally, the system of relatively short bore- tember 1996, Willey.
Marence, M. 2003. Geotechnical design of underground struc-
holes set with tight pattern is more efficient as long tures. In. Underground Construction, 563-572, London,
boreholes set in wide pattern. Hemming Group.
Schleiss, A. 1997. Design of reinforced concrete linings of
pressure tunnels and shafts. Hydropower and Dams, Vol.3,
3 CONCLUSION pp 88-94.
Seeber, G. 1984. Recent developments in the design and con-
struction of power conducts for storage power stations.
The design of pressure tunnel with the geotechnical Idraulica del territorio montano, Bressanone, Italy.
design, developed as a design of excavation and pri- Swoboda, G., Marence, M. & Mader. I 1993. Finite element
mary support of underground works, is extended on modelling of tunnel excavation. Engineering Modelling
the design of the final tunnel lining. The geotechni- Vol. 6, No. 1-4, pp 51.63
cal design represents a flexible procedure that can be Swoboda, G. 2004. Program FINAL – Finite element analyses
of linear and non-linear structures under static and dynamic
adopted to any project stage. During the excavation loadings – Version 7.2. University of Innsbruck.
the geotechnical design of the excavation and
primary support is adopted to the encountered condi-