Flowsheet of Portland Cement
MANUFACTURE PROCESS
It involves the following steps:-
1.Crushing
2.Mixing wet process
3.Grinding
4.Kiln
5.Grinding
6. Storage and packaging
1.Crushing:-
This is the first step in the manufacturing of Portland
cement.
Jaw crushers of various sizes are use for the crushing
process.
Raw materials are crushed by crushers till the size of the
raw material reduces to ¾ of an inch.
It is then send for either wet process or dry process.
2.Mixing wet process:-
calcareous materials are crushed , powdered and stored
in bins.
Argillaceous materials is mixed with water and washed.
Then it removes any adhering organic impurities.
Powdered, calcareous and washed argillaceous materials
are mixed in proper proportions to get a slurry.
This slurry is then fed into a rotary kiln.
3.Grinding:-
Grinding can be done by the two stages.
1.Ball mill
2.Tube mill
4.Kiln:-
Slurry is brunt in rotary kiln.
kiln is divided into three zones
1.Drying zone – 200-500°c
2.Calcinating zone – 1000°c
3.Clinkering zone – 1400-1600°c
1.Drying Zone :-
This is the upper part of the kiln.
Temperature is maintained about 200-500°c.
Most of water gets evaporated from the slurry by means
of hot gases.
2.Calcinating Zone:-
This process is done in the middle portion of the kiln.
The temperature is maintained about 1000°c
Here in organic matter burns away and 𝐶𝑎𝐶𝑂3decomposes
to quick lime and 𝐶𝑂2 escapes away.
Materials forms small lumps formed.
𝐶𝑎𝐶𝑂3 CaO + 𝐶𝑂2
Lime Quick
stone lime
3.Clinkering Zone:-
This is the lower portion of the kiln.
The temperature is between 1400-1600°c.
Here lime and clay nodules melts with chemical fusion and
gives calcium aluminates and silicates.
And then forms small hard stones called clinkers and then
cooled to form crystals.
2CaO + 𝑆𝑖𝑂2 𝐶𝑎2 4
3CaO+ 𝑆𝑖𝑂2 𝐶𝑎3 𝑆𝑖𝑂5
3Cao+𝐴𝑙2 3 𝐶𝑎3𝐴𝑙2𝑂6
4CaO+𝐴𝑙2 3 +𝐹𝑒2 𝑂3 𝐶𝑎4𝐴𝑙2𝐹𝑒2𝑂12
5.Grinding:-
Clinkers are finally grinded in the ball mill and tube mill
to a fine powder.
6.Packing:-
Cement is stored in bins from which it is fed to automatic
packing machines.Each bag usually contains 50 Kg of
cement.
Major Engineering Problems:-
1.Grinding
2.Kiln design
3.Heat economy
4.Quality control