Beruflich Dokumente
Kultur Dokumente
GAS TRANSMISSION
AND DISTRIBUTION
PIPING SYSTEMS
The 1995 Edition of this Code is being issued with an automatic update service
that includes Addenda, Interpretations, and Cases. The next Edition is scheduled for
publication in 1998.
The use of an Addenda allows revisions made in response to public review com-
ments or committee actions to be published on a regular basis; revisions published
in Addenda will become effective 6 months after the Date of issuance of theAddenda.
ASME issues written replies to inquiries concerning interpretations of technical
aspects of the Code. The Interpretations are not partof the Code or the Addenda and
and are published in a separate supplement.
' Periodically certainactions of the ASME 831 Committee will be published as Cases.
While these Cases do not constitute formal revisions of the Code, they may be used
in specifications, or otherwise, as representing considered opinions
of the Committee.
The Cases are not part of the Code or the Addenda and are published in a separate
supplement.
This code was developed under procedures accreditedas meeting the criteria for American
National Standards. The Consensus Committee that approvedthe code or standard was balanced
to assure that individuals from competent and concerned interests have had an opportunity to
participate. The proposed code or standard was made available for public review and comment
which provides an opportunity for additional public input from industry, academia, regulatory
agencies, and the public-at-large.
ASME does not "approve," "rate," or "endorse" any item, construction, proprietary device,
or activity.
ASME does not take any position with respect to the validity of any patent rights asserted in
connection with any items mentioned in this document, and does not undertake to insure anyone
utilizing a standard againstliability for infringement of any applicable Letters Patent, nor assume
any such liability. Users of a code or standard are expressly advisedthat determination of the
validity of any such patent rights, and the risk of infringement of such rights, is entirely their
own responsibility.
Participation by federalagency representative(s1or person(s) affiliated with industry is not to
be interpreted as government or industry endorsement of this code or standard.
ASME acceptsresponsibilityfor only those interpretationsissuedin accordancewith governing
ASME procedures and policies which preclude the issuance of interpretations by individual
volunteers.
Copyright Q 1995 by
THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS
All Rights Reserved
Printed in USA.
The needfor a national code for pressure piping American Standards Association and the sponsor to
becameincreasinglyevidentfrom 1915 to 1925. To reorganize the sectional committee and its several sub-
meet this need, the American Engineering Standards committees and to invite the various interested bodies
Committee (later changed to the American Standards to reaffirm their representatives or to designate new
Association, now the American National Standards In- ones.
stitute) initiated Project B31 in March 1926 at the re- Because of the wide field involved, some 30 to 40
quest of the American Societyof Mechanical Engineers differentengineeringsocieties,government bureaus,
and with that Society as sole sponsor. After several trade associations, institutes, and similar organiza-
years’ work by Sectional Committee B31 and its sub- tions havehad one or more representatives on the
committees, a first Edition was published in 1935 as an sectional committee, plus a few “members at large”
American Tentative Standard Code for Pressure Pip- to representgeneral interests. Codeactivitieshave
ing. been subdivided according to the scope of the several
A revision of the original tentative standard was sections. General direction of Codeactivitiesrested
begun in 1937. Several more years’ effort was given to with the Standards Committee officers and an execu-
securing uniformity between sections and to eliminat- tive committee, membership of which consisted prin-
ing divergent requirements and discrepancies as well cipally of Standards Committee officers and section
as to keeping the Code abreast of current develop- chairmen.
ments in welding technique,calculating stress compu- Following its reorganization in1948, Standards
tations, and includingreference to new dimensional Committee B31 made an intensive review of the 1942
and material standards. During this period, a new sec- Code which resulted in:
tion was added on refrigerationpiping,preparedin (a) a general revision and extension of requirements
cooperation with the American Society of Refrigera- to agree with present day practice;
tionEngineers and complementing the American (6) the revision of references to existing dimensional
Standard CodeforMechanicalRefrigeration. This standards and material specifications and the addition
work culminated in the 1942 American Standard of references to the new ones; and
Code for Pressure Piping. (c) the clarification of ambiguous or conflicting re-
Supplements 1 and 2 of the 1942 Code which ap- quirements.
peared in 1944 and 1947, respectively, introduced new A revision was prepared which was presented for letter
dimensional and material standards, a new formula for ballot vote of Standards Committee B31. Following
pipe wall thickness, and more comprehensive require- approval by this body, the project was next approved
ments for instrument and control piping. Shortly after by the sponsor organization and by the American Stan-
the 1942 Code was issued, procedures were established dards Association. It was finallydesignated as an
for handling inquiries requiring explanation or inter- American Standard in February 1951, with the desig-
pretation of Code requirementsand for publishingsuch nation B31.1-1951.
inquiries and answers inMechanical Engineering mag- Standards Committee B31 at its annual meeting of
azine for the information of all concerned. November 29, 1951, authorized the separate publica-
By 1948, continuing increases in the severity of ser- tion of a section of the Code forPressure Piping dealing
vice conditions, with concurrent developments of new with gas transmissionand distribution piping systems,
materials and designsequal to meeting these higher to be complete with the applicable parts of Section 2,
requirements, had pointed to the need for more exten- Gas and Air PipingSystems,Section6, Fabrication
sive changes in the Code than could be provided from Details, and Section 7, Materials - Their Specifica-
supplements alone. The decision was reached by the tions and Identification. The purpose was to provide an
...
111
iv
OFFICERS
L. E. Hayden, Jr., Chairman
D. R. Frikken, Vice Chairman
J. Yarmush, Secretary
COMMITTEE PERSONNEL
P. A. Bourquin, Pleasantville. New York
J. D. Byers, Mobil Research & Development, Princeton, New Jersey
L. F. Clynch, CONOCO, Ponca City, Oklahoma
D. M. Fischer, Sargent & Lundy, Naperville, Illinois
P. D. Flenner, Consumers Power Co., Covert, Michigan
D. R. Frikken, Monsanto Co., St. Louis, Missouri
P. H. Gardner, Wilmington, Delaware
R. W. H a u p t Pressure Piping Engineering Associates Inc., Foster City, California
L. E. Hayden, Jr., Victaulic Company of America, Easton, Pennsylvania
R. R. Hoffrnann, Federal Energy Regulatory Commission, Washington, District of Columbia
B. P. Holbrook, Riley Stoker Corp., Worcester, Massachusetts
G. A. Jolly, Henry Vogt Machine Co., Louisville, Kentucky
K. Kaye, Ministry of Municipal Affairs, Vancouver, British Columbia, Canada
W. B. McGehee, Houston, Texas
E. Michalopoulos, Hartford Steam Boiler Inspection and Insurance Co., Hartford, Connecticut
A. P. Povilonis, ABB Combustion Engineering Inc., Windsor, Connecticut
W. V. Richards, William V. Richards Inc., Lincolnshire, Illinois
G. W. Spohn, 111, Colejon Spohn Corp., Cleveland, Ohio
L. G. Vetter, Sargent & Lundy Engineers, Chicago, Illinois
vi
vii
...
Vlll
...
Foreword ................................................................................ 111
Personnel ................................................................................ V
...
Introduction ............................................................................ x111
Chapter I MaterialsEquipment
and
810 Materials and Equipment ................................................. 11
81 1 Qualification of Materials and Equipment ................................... 11
812 Materials for Use in Cold Climates ......................................... 12
813 Marking ............................................................... 12
814 Material Specifications ................................................... 12
815 Equipment Specifications ................................................. 13
816 Transportation of Line Pipe ............................................... 13
817 Conditions for the Reuse of Pipe .......................................... 13
Chapter I1 Welding
820 Welding ............................................................... 15
82 1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
822 Preparation for Welding .................................................. 15
823 Qualification of Procedures and Welders .................................... 16
824 Preheating ............................................................. 16
825 Stress Relieving ......................................................... 17
826 Welding and Inspection Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
827 Repair or Removal of Defective Welds in Piping Intended to Operate at
20% or More of the Specified Minimum Yield Strength ..................... 18
Chapter
I11 Piping System Components
and
Fabrication Details
830 Piping System Components and Fabrication Details ........................... 19
831 Piping System Components ............................................... 19
832 Expansion and Flexibility ................................................. 25
833 Combined Stress Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
834 Supports and Anchorage for Exposed Piping ................................. 27
835 Anchorage for Buried Piping .............................................. 28
ix
Tables
841.114A BasicDesign Factor F ................................................... 33
841.114B Design Factor for Steel Pipe Construction ................................... 33
841.115A Longitudinal Joint Factor E .............................................. 34
841.1 16A Temperature Derating Factor T for Steel Pipe ............................... 34
841.322(f) Test Requirements for Pipelines and Mains to Operate at Hoop Stresses
of 30% or More of the Specified Minimum Yield Strength of the Pipe . . . . . . . . . 40
841.33 Maximum Hoop Stress Permissible During Test .............................. 40
842.214 Standard Thickness Selection Table for Ductile Iron Pipe ...................... 42
842.32(c) Wall Thickness and Standard Dimension Ratio for Thermoplastic Pipe . . . . . . . . . . 43
842.33(c) Diameter and Wall Thickness for Reinforced Thermosetting Plastic Pipe ......... 44
842.396(c) Nominal Values for Coefficients of Thermal Expansion of Thermoplastic
PipeMaterials ........................................................ 46
Table
854.1(c) Location Class .......................................................... 78
xi
Table
A842.22 Design Factors for Offshore Pipelines. Platform Piping. and Pipeline
Risers ............................................................... 97
Appendices
A References ............................................................. 109
B List of Numbers and Subjects of Those Standards and Specifications
WhichAppear in AppendixA ........................................... 111
C List of Numbers and Subjects of Those Standards and Specifications
Which Do Not Appear in the Code or Appendix A but May Be of
Informational Benefit .................................................. 113
D ...................................................................... 115
E Flexibility and Stress Intensification Factors ................................. 117
F ...................................................................... 123
G Test of Welders Who Are Limited to Work on Lines Operating at Hoop
Stresses ofLess Than 20% of the Specified Minimum Yield Strength .......... 129
H Flattening Test for Pipe .................................................. 131
I ...................................................................... 133
J ...................................................................... 145
K Criteria for Cathodic Protection ........................................... 149
L Determination of Remaining Strength of Corroded Pipe ....................... 151
M Gas Leakage Control Criteria ............................................. 153
N Recommended Practice for Hydrostatic Testing of PipelinesinPlace ............ 163
0 Preparation of Technical Inquiries to the ASME Code for Pressure
Piping.
B31 .......................................................... 165
xii
The ASME Code for Pressure Piping consists of a latest Edition and addenda issued at least 6 months
number ofindividuallypublishedSections,each an prior to the original contract date for the first phase of
American National Standard. Hereafter, in this Intro- activity coveringa piping systemor systems shallbe the
duction and in the text of this Code Section B31.8, governing document, unless agreement is specifically
when the word “Code” is used without specific identi- made between contracting parties to use another issue,
fication, it means this Code Section. or the regulatory body havingjurisdiction imposes the
The Code sets forth engineeringrequirements use of another issue, or different requirements.
deemed necessary for safe design and construction of Users of this Codeare cautioned against making use
pressure piping. While safetytheisbasic consideration, of revisions without assurancethat they are acceptable
this factor alone will not necessarily govern the final to any authorities of jurisdiction where the piping isto
specifications of anypipingsystem. The designeris be installed.
cautioned that the Code is not a design handbook; it The Code is underthe direction of ASME Commit-
does not do away with the need for the designer or for tee B3 1, Code for Pressure Piping, which is organized
competent engineering judgment. and operates under procedures of The American Soci-
To the greatest possible extent, Code requirements ety of Mechanical Engineers which have been accred-
for designare stated in terms of basic designprinciples ited by the American National Standards Institute. The
andformulas.These are supplemented as necessary Committee is a continuing one, and keeps all Code
with specific requirements to assure uniform applica- Sections current with new developments in materials,
tion of principles andto guide selection and application construction, and industrial practice. Addenda are is-
of piping elements. The Code prohibits designs and sued periodically. New editionsare published at inter-
practices known to be unsafe and contains warnings vals of 3 years to 5 years.
where caution, but not prohibition, is warranted. When no Section of the ASME Code for Pressure
This Code Section includes: Piping specifically coversa piping system, the user has
(a) references to acceptable material specifications discretion to select any Section determined to be gener-
and component standards, including dimensional and ally applicable. However, it is cautioned that supple-
mechanical property requirements; mentary requirements to the Section chosen may be
(b) requirements for design of components and as- necessary to provide for a safe piping system for the
semblies; intended application. Technical limitations of the vari-
(c) requirements anddata for evaluation and limita- ous Sections, legal requirements, and possible applica-
tion of stresses, reactions, and movements associated bility of other Codes or Standards are some of the
with pressure, temperature changes, and other forces; factors to be considered by the user in determiningthe
(d) guidanceandlimitationson the selectionand applicability of any Section of this Code.
application of materials,components,andjoining
methods;
(e) requirements for the fabrication, assembly, and
installation of piping;
Interpretations and Revisions
# requirements for examination,inspection,and
testing of piping; The Committee has established an orderly procedure
(g) procedures for operation and maintenance that to consider requests for interpretation and revision of
are essential to public safety; and Code requirements.To receive consideration, inquiries
(h) provisions for protecting pipelines fromexternal must be in writing and must give full particulars (see
and internal corrosion. Appendix 0 covering preparation of technical inqui-
It is intendedthat this Edition of Code SectionB31.8 ries).
and any subsequent addenda not be retroactive. The The approved replyto aninquiry willbe sent directly
...
x111
xiv
GENERAL
801 ation and maintenance of gas transmission and distribu-
tion systems, including gas pipelines, gas compressor
801.1
Standards
and
Specifications
stations, gas metering and regulation stations, gas
801.11 Standards and specifications approved for use mains, and service lines up to the outlet of the cus-
under the Code and the names and addresses of the tomer’s meter set assembly. Included within the scope of
sponsoring organizations are shown in Appendices A this Code are gas transmission and gathering pipelines,
and B. It is not considered practicable to refer to a including appurtenances, that areinstalled offshore for
specific edition of each of the standards and specifica- the purpose of transporting gas from production facili-
tions in the individual Code paragraphs. Instead, the ties to onshore locations; gas storage equipment of the
specific edition references are included in Appendices closedpipetype, fabricated or forged from pipe or
A and B, which will be revised at intervals as needed. fabricatedfrompipe and fittings, and gas storage lines.
(See Figs. 18, 19, and 110.)
801.12 Useof Standards and Specifications Incorpo-
rated by Reference. Some standards and specifications
cited in Appendices A and B are supplemented by spe- 802.12 The requirements of this Code also cover the
cific requirements elsewhere inthis Code. Users of this conditions of use of the elements of the piping systems
Code are advised against attempting direct application described in para. 802.11, including, but not limited to,
of any of these standards without carefully observing pipe, valves, fittings, flanges, bolting, gaskets, regula-
the Code’s reference to that standard. tors, pressure vessels, pulsation dampeners, and relief
valves.
801.2
Standard
Dimensions 802.13 This Code does not apply to:
(a) design and manufacture of pressure vessels cov-
Adherence to American National Standard dimen-
ered by the BPV Code I ;
sions is strongly recommended wherever practicable.
(b) piping with metal temperatures above 450°F or
However, paragraphs or notations specifying these and
below -20°F. (For low temperatures within the range
other dimensional standards in this Code shall not be
covered by this Code, see para. 812.)
mandatory, provided that otherdesigns of at least equal
(c) piping beyond the outlet of the customer’s meter
strengthand tightness, capable of withstanding the
set assembly (refer to ANSI 2223.1 and NFPA 54);
same test requirements, are substituted.
(d) piping in oil refineriesor naturalgasoline extrac-
tion plants, gas treating plant piping other than the
main gas stream piping in dehydration, and all other
801.3 SI (Metric) Conversion
processing plants installed as part of a gas transmission
For factors used in converting English units to SI system, gas manufacturing plants, industrial plants, or
units, see Appendix J. mines. (See other applicable sections of the ASME
Code for Pressure Piping, B31.)
(e) vent piping to operateat substantially atmo-
spheric pressures for waste gases of any kind;
802 SCOPE
AND
INTENT &J wellheadassemblies, including control valves,
flow lines between wellhead and trap orseparator, off-
Scope
802.1
802.11 This Code covers the design, fabrication, in- ‘BPV Code references here and elsewhere In this Code are to the
stallation, inspection, testing, and safety aspects of oper- ASME Boiler and Pressure Vessel Code.
shore platform production facility piping,or casing and 802.25 Qualification of Those Performing Inspec-
tubing in gasor oil wells (for offshore platformproduc- tions.Individualswhoperforminspections shall be
tion facility piping, see API RP 14E); qualified by training or experience, or both, to imple-
(g) the design and manufacture of proprietary items ment the applicable requirements and recommenda-
of equipment, apparatus, or instruments; tions of this Code.
(h) the design and manufacture of heat exchangers
(refer to appropriate TEMA' Standard);
(i) liquidpetroleum transportation pipingsystems
(refer to ANSI/ASME B31.4);
803 PIPING SYSTEMS DEFINITIONS
0) liquid slurry transportation piping systems (refer
to ASME B3 1.1 1); 803.1 General Terms
(k) carbon dioxide transportation piping systems; 803.11 Gus, as used in this Code, is any gas or mix-
(I) liquefied natural gaspipingsystems(refer to
ture of gases suitable for domestic or industrial fuel and
NFPA 59A and ASME B31.3).
transmitted or distributed to theuser through a piping
system. The common types are natural gas, manufac-
802.2 Intent tured gas, and liquefied petroleum gasdistributed as a
802.21 The requirements of this Code are adequate vapor, with or without the admixture of air.
for safety under conditions usually encountered inthe 803.12 Operating company, as usedherein,is the
gas industry. Requirements for all unusual conditions individual, partnership, corporation, public agency, or
cannot be specifically provided for,nor are all detailsof other entity that operates the gas transmissionor distri-
engineeringand construction prescribed. Therefore, ac- bution facilities.
tivities involvingthe design, construction, operation, or
maintenance of gas transmission or distribution pipe- 803.13 Private rights-of-way, as used in this Code, are
lines should be undertaken using supervisory personnel rights-of-way not located on roads, streets, or highways
having the experience or knowledge to make adequate used by the public, or on railroad rights-of-way.
provision for such unusual conditionsand specific engi- 803.14 Parallel encroachment, as used in this Code,
neering and construction details. All work performed pertains to that portion of the route of a pipeline or
within the scope of this Code shall meetor exceed the mainwhichlieswithin, runs in a generally parallel
safety standards expressed or implied herein. direction, and does not necessarily cross, the rights-of-
802.22 This Code is concerned with: way of a road, street, highway, or railroad.
(a) safety of the general public; 803.15 Hot taps are branch pipingconnections
(6) employee safety to the extent that it is affected made to operating pipelines, mains, or other facilities
by basic design, quality of
materials and workmanship, whilethey are in operation. The connection of the
and requirements for testing, operations, and mainte- branch piping to the operating line and the tapping
nance of gas transmission and distribution facilities. of the operating line is done while it is under gas
Existing industrial safetyprocedurespertaining to pressure.
work areas, safety devices,and safe work practicesare
not intended to be supplanted by this Code. 803.16 Vault is an underground structure which
may be entered, and which is designed to contain pip-
802.23 It is not intended that this Code be applied ing and piping components (such as valves or pressure
retroactively to existing installations insofar as design, regulators).
fabrication, installation, and testing at thetime of con-
struction are concerned. Further, it isnot intended that
this Code be applied retroactivelyto established operat- 803.2 Piping
Systems
ing pressures of existing installations, except as pro- 803.21 Pipeline or transmission lineis a pipe installed
vided for in Chapter V. for the purpose of transmitting gas from a source or
802.24 Provisions of this Codeshall be applicable to sources of supply to one or more distribution centers or
operating and maintenance procedures of existing in- to one or more large volume customers, or a pipe in-
stallations, and when existinginstallations are uprated. stalled to interconnect sources of supply. In typical
cases, pipelines differ from gas mainsthat in they oper-
*Tubular Exchanger Manufacturers Association, 25 N Broadway, ate at higher pressures, are longer, and have greater
Tarrytown, NY 10591 distances between connections.
803.24 Gas service lineis the piping installed between 803.324 Pressure limiting station consists of equip-
a main, pipeline, or other source of supply, and the ment which under abnormal conditions will act to re-
meter set assembly [(see para. 802.13(c)]. duce, restrict, or shut off the supply of gas flowing into
a system in order to prevent the gas pressure from
803.25 Gas storage line is a pipeline usedfor convey- exceeding a predetermined value. While normal pres-
ing gas between a compressor station and a gas well sure conditions prevail, the pressure limiting station
used for storing gas underground. may exercise somedegree of control of the flow of the
gas or may remain in the wide open position. Included
803.26 Miscellaneous Systems
in the station are piping and auxiliary devices, such as
803.261 Instrument piping is all piping,valves, valves, control instruments, control lines, the enclo-
and fittings used to connect instruments tomain piping, sure, andventilating equipment installed in accordance
to other instruments and apparatus, or to measuring with the pertinent requirements of this Code.
equipment.
803.33 Pressure Relief
803.262 Control piping is all piping, valves, and
803.331 Pressure relief station consists of equip-
fittings used to interconnect air, gas, or hydraulically
ment installed to vent gas from a system being pro-
operated control apparatus or instrument transmitters
tected in order toprevent the gas pressure from exceed-
and receivers.
ing a predetermined limit. The gas may be vented into
803.263 Sample piping is all piping, valves, and the atmosphere or into a lower pressure system capable
fittings used for the collection of samples of gas, steam, of safely absorbing the gas being discharged. Included
water, or oil. in the station are piping and auxiliary devices, such as
valves, control instruments, control lines, the enclo-
sure, and ventilating equipment, installed in accord-
ance with the pertinent requirements of this Code.
803.3 Meters,Regulators, and PressureRelief
Stations
803.31 Meters 803.4 Valves
803.311 Customer’s meter is a meter which mea- 803.41 Stop valve is a valve installed for the purpose
sures gas delivered to a customer for consumption on of stopping the flow of gas in a pipe.
the customer’s premises.
803.42 Service line valveis a stop valve readily opera-
803.312 Meter set assembly is the piping and fit- ble and accessible, located in the service line ahead of
tings installed to connect the inlet side of the meter to the service regulator or ahead of the meter, if a regula-
the gas service line and the outlet side of the meter to tor is not provided, for the purpose of shutting off the
the customer’s fuel line. supply of gas to the customer’s fuel line. The valve is
also known as a service line shutoff, a service line cock,means of chemistry and a ferritizing heat treatment of
or a meter stop. the castings.
803.43 Curb valve isa stop valveinstalledbelow 804.13 The unqualified term cast iron shall apply to
grade in a service line at or near the property line, gray castiron, which is a cast
ferrous material in which
accessible through a curb box or standpipe, and opera- a majorpart of the carbon content occurs as free carbon
ble by a removable key or wrench, for the purpose of in the form of flakes interspersed through the metal.
shutting off the gas supply to a building. This valve is 804.14 Proprietary items are items made and mar-
also known as a curb shutoff or a curb cock. keted by a company havingthe exclusive or restricted
803.44 Check valve is a valve designed
to permit flow right to manufacture and sell them.
in one direction and to close automatically to prevent 804.15 Pipe container is a gas-tightstructure assem-
flow in the reverse direction. bled in ashop or in the field from pipe and end closures.
803.5 Gas
Storage 804.2 Pipe
803.51 Pipe-type holder is anypipe container or 804.21 Pipe and Piping Terms
group of interconnected pipecontainers installed at one 804.211 Pipe is a tubular product made as a pro-
location and used for the sole purpose of storing gas. duction item for sale as such. Cylinders formed from
plate inthe course of the fabrication of auxiliary equip-
803.52 Bottle, asusedin this Code,isagas-tight
ment are not pipe as defined herein.
structure completely fabricated from pipe with
integral
drawn, forged, or spun end closures and tested in the 804.212 Cold expandedpipe is seamlessor welded
manufacturer’s plant. pipe which is formed and then expanded in the pipe
millwhilecold so that the circumference is perma-
803.53 Bottle-type holder is any bottle or group of nently increased by at least 0.50%.
interconnectedbottlesinstalled in onelocationand
used for the sole purpose of storing gas. 804.22 Dimensional Terms
804.221 Length is a piece of pipe of the length
delivered from the mill. Each piece is called a length,
regardless of its actual dimension. This is sometimes
804 PIPING SYSTEMS COMPONENT called “joint,” but “length” is preferred.
DEFINITIONS 804.222 Nominal wall thickness t is the wall thick-
804.1 General ness computed by or used in the design equation in
para. 841.11or A842.221 in Chapter VIII. Under this
804.11 Plastic Terms Code, pipe may be ordered to this computed wall thick-
804.111 Plastic (noun) is a material which con- ness without adding allowance to compensate for the
tains as an essential ingredientan organic substanceof underthickness
tolerance
permitted in approved
high to ultrahigh molecular weight, is solid in its fin- specifications.
ished state, and at some stage of its manufacture or
804.223 NPS (nominalpipe size)is a dimensionless
processing, can be shaped byflow. The two general
designator of pipe. It indicates a standard pipesize
types of plastic referredto in this Code are thermoplas-
when followed by the appropriate number (e.g., NPS
tic and thermosetting.
1 1/2, NPS 12).
804.112 Thermoplastic is a plastic which is capa-
804.23 Mechanical Properties
ble of being repeatedly softened by increase
of tempera-
804.231 Yield strength is the strength at which a
ture and hardened by decrease of temperature.
material exhibits a specified limiting permanent set or
804.113 Thermosetting plastic is plastic which is produces a specified total elongation under load. The
capable of being changed into a substantially infusible specified limiting setor elongation is usually expressed
or insoluble product when cured under application of as a percentage of gage length. Its values are specified
heat or chemical means. in the various material specifications acceptableunder
this Code (psi).
804.12 Ductile iron (sometimes called nodular iron)
is a cast ferrous material in which the free graphite 804.232 Tensile strength is the highest unit tensile
present is in a spheroidal form,
rather than a flake form. stress (referred to the original cross section) a material
The desirable propertiesof ductile iron are achieved by can sustain before failure (psi).
ASTMA134
ASTMA139Buttjoint
API 5L
ASTMA211Butt joint, lap joint, or lockseam joint 805.12 For definitions of leakage investigation terms,
(d) Electric-flash-weldedpipe is pipe havinga longi- see Appendix M.
tudinal butt joint, whereincoalescenceisproduced
simultaneously overthe entire area of abutting surfaces
by the heat obtained from resistance to the flow of
electric current between the two surfaces, and by the 805.13 Plastic Terms
application of pressure after heating is substantially 805.131 Plastic Joint Nomenclature
completed. Flashing and upsetting are accompanied by (a) Solvent cement joint is a joint made in thermo-
expulsion of metal from the joint. A typical specifica- plastic pipingby the use of a solvent or solvent cement
tion is: which forms a continuous bond between the mating
API 5L surfaces.
(bl Heat fusionjoint is a joint made in thermoplastic
(e) Double submerged-arc-welded pipe is pipe hav- piping by heating the parts sufficientlyto permit fusion
ing a longitudinal butt joint produced by at least two of the materials when the parts are pressed together.
passes, oneof which is onthe inside of the pipe. Coales- (c) Adhesivejoint is a joint made in plastic piping by
cence is produced by heating withan electric arc orarcs the use ofan adhesive substance which forms a continu-
between the bare metal electrodeor electrodes and the ous bond between the mating surfaceswithout dissolv-
work. The welding is shielded by a blanket of granular, ing either one of them.
fusible material onthe work. Pressure is not used and
filler metalfor the inside and outside welds is obtained 805.132 Standard dimension ratio is the ratio of
from the electrode or electrodes. Typical specifications outside pipediameter to wall thickness of thermoplas-
are: tic pipe. It is calculated by dividing the specified outside
diameter of the pipe by the specified wall thickness in
ASTM A 381 inches.
API 5L
805.133 Long term hydrostatic strength is the es-
03 Seamless pipe is a wrought tubular product
timated hoopstress in psi in a plastic pipe wall
that will
made without a welded seam. It is manufactured by
cause failure of the pipe at an average of 100,OOO hr
hot-working steel and, if necessary, by subsequently
when subjected to a constant hydrostatic pressure (see
cold-finishing the hot-worked tubular product to pro-
Appendix D).
duce the desiredshape,dimensions, and properties.
Typical specifications are:
ASTM A 53
ASTMA106
API 5L 805.15 Fabrication
805.151 Cold-springing, where used in the Code,
is the fabrication of piping to an actual length shorter
804.25 For plastic pipe, see para. 805.13. than its nominal length and forcing it into position so
CHAPTER I
MATERIALS AND EQUIPMENT
810 MATERIALS AND EQUIPMENT 811.21 Items which conformto standards or specifi-
cations referenced inthis Code [para.81 l.l(a)] may be
810.1
usedfor appropriate applications, as prescribedand
It is intended that all materials and equipment that limited by this Code without further qualification (see
willbecome a permanent part of any piping system para. 8 14).
constructed under this Code shallbe suitable and safe
for the conditions under which theyare used. All such 811.22 Important items of a type for which standards
materials and equipment shall be qualified for the con- or specifications are referenced in this Code, such as
ditions of their use by compliance withcertain specifi- pipe, valves, and flanges,but which do not conform to
cations, standards, andspecialrequirements of this standards or specificationsreferencedin this Code
Code, or otherwise as provided herein. [para. 8 11.1 (b)] shallbe qualified as described inpara.
811.221 or 811.222.
11
MARKING
813 (b) Thermoplastic pipe,tubing,fittings, and ce-
ments conforming to ASTM D 25 13 shall be produced
813.1
in accordance with the in-plant quality control pro-
All valves, fittings, flanges, bolting, pipe,and tubing gram recommended in Appendix A4 of that specifica-
shall be marked in accordance with the marking sec- tion.
tions of the standards and specifications to which the 814.14 Qualification of Plastic Piping Materials
items were manufactured or in accordance with the (a) In addition to theprovisions of para. 8 14.13,the
requirements of MSS SP-25. specific plastic pipe, tubing, or fitting to be used shall
be thoroughly investigated by the user and material
813.2 serviceabilitydetermined for the conditions antici-
pated. The selected material shall be adequately resist-
Die stamping, if used, shall be done with dies having
ant to the liquids and chemical atmospheres which may
blunt or rounded edges to minimize stress concentra-
be encountered.
tions. (b) When plastic pipe, tubing,or fittings of different
material specifications are joined together, a thorough
investigation shall be made to determine that the mate-
814 MATERIAL SPECIFICATIONS
rials are compatible with each other. See para. 842.39
For a listing of all referenced material specifications, for joining requirements.
see AppendicesA and B. For a listing of standards for
other commonly usedmaterials that arenot referenced,
814.2 Steel, CastIron, and DuctileIronPiping
see Appendix C.
Components
12
815 EQUIPMENT SPECIFICATIONS split seams or other defects that would cause leakage,
and provided further that, if the pipe is to be welded
Except for the piping components and structuralma-
and is of unknown specification, it shall satisfactorily
terials listed in Appendices A, B, and C, it is not in-
pass weldability tests prescribed in para. 817.13(e).
tended to include in this Code complete specifications
for equipment. However, certain details of design and 817.13 Used steel pipe and unidentified new steel
fabrication necessarily refer to equipment, such aspipe pipe may be qualifiedfor use at stress levels above 6000
hangers, vibration dampeners, electrical facilities, en- psi or for service involving close coiling or close bend-
gines, compressors, etc. Partial specifications for such ing by the procedures and within the limits outlined in
equipment items are given herein, particularly if they the table below.
affect the safety of the piping system in which they are The letters in the table refer to the corresponding
to be installed. In other cases where the Code gives no paragraphs following.
specifications for the particular equipment item, the New or Used
intent is that the safety provisions of the Code shall Pipe,
govern, insofar as they are applicable, and in any case Unknown Used
Pipe, Known
the safety of equipment installed in a piping system Specification
Specification
Inspection (a) (a)
shall be equivalent to that of other parts of the same
Bending and coiling
system. properties (b) ...
Thickness (c) (C)
Joint longitudinal (4 (d)
Weldability (e) ...
816
TRANSPORTATION OF LINE PIPE
Defects (f) (0
Any pipe having an outer diameter to wall thickness Yield strength (8) ...
S value (para. 841.11) (h) ...
ratio of 70 to 1 or more, that is to be used in a pipeline Test (i) (i)
at a hoop stress of 20% or more of the specified mini-
mum yield strength, that has been or willbe trans- (a) Inspection. All pipe shall be cleaned inside and
ported by railroad, inland waterway, or by marine outside, if necessary, to permit good inspection and
transportation, must have been or shall be loaded in shall be visuallyinspected to insure that it is reasonably
accordance with API RP5Ll or APIRPSLW, respec- round and straight and to discover any defects which
tively. Where it is not possible to establish that pipe was might impair its strength or tightness.
transported in accordance with the appropriaterecom- (b) Bending Properties. For pipe NPS 2 and smaller,
mended practice, the pipe must be hydrostatically a sufficient length of pipe shall be bent cold through 90
tested for at least 2 hr to at least 1.25 times the maxi- deg. arounda cylindrical mandrel, thediameter of
mum allowable operating pressure if installed in a Class which is12 times the nominal diameter of the pipe,
1 location, or to at least 1.5 times the maximum allowa- without developing cracks at any portion and without
ble operating pressure if installed in a Class 2, 3, or 4 opening the weld.
location. For pipe larger than NPS 2, flattening tests as pre-
scribed in Appendix H shall be made. The pipe shall
meet the requirements in this test, except that thenum-
817 CONDITIONS FOR THE REUSE OF ber of tests required to determine flattening properties
PIPE shall be the same as required in (g) below to determine
yield strength.
817.1
Reuse of Steel Pipe (c) Determination of Wall Thickness. Unless the
817.11 Removal of a portion of an existing steel line nominal wall thickness is known with certainty, it shall
and reuse of the pipe in the same line, or in a line be determined by measuring the thickness at quarter
operating at the same or lower pressure, is permitted, points on one end of each piece of pipe. theIf lotof pipe
except for subsea application, subject only to the re- is known to beof uniform grade, size, and nominal
strictions of paras. 817.13(a), (9, and (i). thickness, measurement shall be made on not less than
10% of the individual lengths, but not less than 10
817.12 Used steel pipe and unidentified new steel lengths; thickness of the other lengths may be verified
pipe may be used for low-stress (hoop stress less than by applying a gage set to the minimum thickness. Fol-
6000 psi) level service where no close coiling or close lowing such measurement, the nominal wall thickness
bending is to be done, provided careful visual examina- shall be taken as the next commercial wall thickness
tion indicates that it is in goodcondition and free from below the average of all the measurements taken, but
13
in no case greater than 1.14 times the least measured (h) S Value. For pipe of unknown specification, the
thickness for all pipe smaller than NPS 20, and no yield strength, to be used as S in the formula of para.
greater than 1.11 times the least measured thickness for 84 1.1 1, in lieu ofthe specified minimum yield strength,
all pipe NPS 20 and larger. shall be 24,000 psi, or determined as follows.
(d) Longitudinal Joint Factor. If the type of longi- Determine the averagevalue of allyield strength
tudinal joint canbedeterminedwith certainty, the tests for a uniform lot. The value of S shall then be
correspondingLongitudinal Joint Factor E (Table taken as the lesser of the following:
841.1 15A) may be used. Otherwise, the factor E shall (1) 80% of the average valueof the yield strength
be takenas 0.60 for pipeNPS 4 and smaller, or 0.80 for tests;
pipe larger than NPS 4. (2) the minimum valueof any yield strength test,
(e) Weldability. Weldability shall be determined as provided however, that in no case shall S be taken as
follows. A qualified welder shall make a girth weld in greater than 52,000 psi.
the pipe. The weld shall then be tested in accordance (i) Hydrostatic Test. New or used pipe of unknown
with requirements of API 1104. The qualifying weld specification and all used pipe,the strength of which is
shall be made under the most severe conditions under impaired by corrosion or other deterioration, shall be
which welding will be permitted in the field and using retested hydrostaticallyeither length by length ina mill
the same procedureas to be used in the field. The pipe type test or in the field after installation before being
shall be considered weldable if the requirements set placed in service. The test pressure used shall establish
forth in API 1104 are met. At least one such test weld the maximum allowableoperating pressure, subject to
shall be made for each 100 lengths ofpipe in sizes limitations described in para. 841.111.
larger than NPS 4. On sizes NPS 4 and smaller, one
test will be required for each 400 lengths of pipe. If in
testing the weld, the requirements of API 1104 cannot 817.2 Reuse of Ductile Iron Pipe
be met, the weldability may be established by making
chemical tests for carbon and manganese(seepara. 817.21 The removal of a portion of an existing line
823.23), and proceeding in accordance with the provi- of unknown specifications and the reuse of the pipe in
sions of the ASME Boiler and Pressure Vessel Code, the same lineor in a line operatingat the same or lower
Section IX.The number of chemical tests shall be the pressure is permitted, provided careful inspectionindi-
same as required for circumferential weld tests stated cates that the pipe issound, permits the makeup of tight
above. joints, and has an actual net wall thickness equal to or
cf) Surface Defects. All pipe shall be examined for exceeding the requirements of para. 842.214. The pipe
gouges, grooves, and dents, and shall be qualified in shall be leak-tested in accordance with para. 841.34 or
accordance with the provisions of para. 841.24. 841.35.
(g) Determination of YieldStrength. When the 817.23 Usedpipeofknownspecificationsmaybe
manufacturer’s specified minimum yieldstrength, ten- reused in accordance with the provisions and specifica-
sile strength, or elongation for the pipe is unknown, and tions of para. 842.2 provided a careful inspection indi-
no physical testsare made, the minimum yieldstrength cates the pipe issound and permitsthe makeup of tight
for purposes of design shall be taken as not more than joints.
24,000 psi. Alternatively, the tensile properties may be
established as follows.
Perform all tensile tests prescribed by API 5L except
817.3 Reuseof Plastic Piping
that the number of such tests shall be as follows.
Used plastic pipeand tubing of known specifications
Number of Tensile Tests, All Sizes
Lot of: and dimensions that has been used in natural gas ser-
10 lengths or less 1 set of tests from each length vice only may be reused, provided that:
11 to 100 lengths 1 set of tests for each 5 lengths, but (a) it meets the requirements of ASTM D 2513 for
not less than 10 new thermoplasticpipe or tubing, or ASTM D 2517 for
Over 100 lengths 1 set of tests for each 10 lengths, new thermosetting pipe;
but not less than 20
(b) a careful inspection indicates that it is free of
All test specimens shall be selected at random. visible defects;
If the yield-tensile ratio exceeds 0.85, the pipe shall (c) it is installed and tested in accordance with the
not be used, except as provided in para. 817.12. requirements of this Code for new pipe.
14
CHAPTER I1
WELDING
WELDING
820 mum yield strength as established in API 1104 shall be
used.
GENERAL
821
821.1
821.5
This Chapter concerns the welding of pipe joints in
both wrought and cast steel materials and covers butt All welding done under this Code shall be performed
and filletwelded joints inpipe,valves,flanges, and under a standard referenced in para. 823.11 or 823.21,
fittings and fillet weld joints in pipe branches, slip-on whichever is applicable.
flanges, socket weld fittings,etc., as applied in pipelines
and connections to apparatusor equipment. When 821.6
valves or equipment are furnished with welding ends
suitable for welding directly into a pipeline, the design, Prior to welding in or around a structure or area
composition, welding, and stress relief procedures must containing gas facilities, a thorough check shall be
be such that no significant damage will result from the made to determine the possible presence of a combusti-
welding or stress relieving operation. This Chapter ble gas mixture. Welding shall begin only when safe
does not apply to thewelding of the seam in the manu- conditions are indicated.
facture of pipe.
821.7
Welding
Terms
821.2
Definitions pertaining to welding as used in this
The welding may be done by any process or combi- Code conform to the standard definitions established
nation of processes which produce welds that meet the by the American Welding Society and contained in
procedure qualification requirements of this Code. The ANSI/AWS A3.0.
weldsmaybe produced by position welding or roll
welding, or a combination of position and roll welding.
822
PREPARATION FOR
WELDING
821.3
822.1 Butt Welds
Prior to welding of any pipe, piping components, or
related equipment covered by this Code, a welding pro- (a) Some acceptable end preparations are shown in
cedure shall be established and qualified. Each welder Fig. 14.
or welding operator shall be qualified for the estab- (b) Fig. I5 shows acceptable end preparations for
lished procedure before performing any welding on any butt welding of pieces having either unequal thickness
pipe,piping components, or related equipment in- or unequal yield strength, or both.
stalled in accordance with this Code.
822.2 Fillet Welds
821.4
Minimum dimensions for filletweldsused in the
The standards of acceptability for welds of piping attachment of slip-on flanges, and for socket welded
systems to operate at 20% or more of specified mini- joints, are shown in Fig. 16. Similar minimum dimen-
15
sions for fillet welds used in branch connections are terials, and although not an essential variable to welder
shown in Figs. I1 and 12. qualification, may require separate procedure qualifi-
cation in accordance with para. 823.21 above.
822.3
Seal
Welds
Seal welding shall be done by qualified welders. Seal
823.3 Welder
Requalification
Requirements
welding of threaded joints is permitted, but the seal
welds shall not be considered as contributing to the Welder requalification tests shall be required if there
strength of joints. is some specific reason to question a welder’s ability or
if the welder is not engaged in a given process of weld-
ing for a period of 6 months or more. All welders shall
823
QUALIFICATION OF PROCEDURES be requalified at least once each year.
AND WELDERS
823.1
Requirements for Qualification of
Procedures and Welders on Piping 823.4
Qualification
Records
Systems Operating at Hoop Stresses of
Records of the tests that establish the qualification of
Less Than 20% of the Specified Minimum
a welding procedure shall be maintained as long as that
Yield Strength
procedure is in use.The operating companyor contrac-
823.11 Welders whose work is limited to piping oper- tor shall, during the construction involved, maintain a
ating at hoopstress levelsofless than 20%of the record of the welders qualified, showing the dates and
specified minimum yield strength shall be qualified results of tests.
under any of the references given in para. 823.21 or in
accordance with Appendix G.
PREHEATING
824
823.2
Requirements for Qualification of
Procedures and Welders on Piping 824.1
Systems to Operate at Hoop Stresses of
Carbon steels having a carbon content in excess of
0.32% (ladle analysis) or a carbon equivalent (C +
20% or More of the Specified Minimum
Yield Strength
Y4Mn) in excess of0.65% (ladle analysis) shall be pre-
823.21 Welding procedures and welders performing heated to thetemperature indicated by the welding
work under this classification shall be qualified under procedure. Preheating shall also be required for steels
BPV Code, Section IX, or API 1104. having lower carbon content or carbon equivalents
when the welding procedure indicates that chemical
823.22 When welders qualified under API 1104 are
composition, ambient and/or metal temperature, mate-
employed on compressor station piping, their qualifi- rial thickness, or weld-end geometry require such treat-
cation shall have beenbased on the destructive me-
ment to produce satisfactory welds.
chanical test requirements of API 1104.
823.23 Variables for the Separate Qualification of
Welders. The references given in para. 823.21 contain
824.2
sections entitled “Essential Variables,” applicable to
welder qualification. These shall be followed, except When welding dissimilar materials having different
that for the purposes of this Code all carbon steels preheating requirements, the material requiring the
which have a carbon content not exceeding 0.32% by higher preheat shall govern.
+
heat analysis, and a carbon equivalent (C Y4Mn) not
exceeding 0.65% by heat analysis, are considered to
come under material grouping P-No. 1. Alloy steels
824.3
having weldability characteristics demonstrated to be
similar to these carbon steels shall be welded, pre- Preheating maybe accomplished by any suitable
heated, and stress relieved as prescribed herein for such method, provided that it is uniform and that the tem-
carbon steel. There may be significant differences inthe perature does not fall below the prescribed minimum
base metal strength encompassed by these P-No. 1 ma- during the actual welding operations.
16
17
checked by the use of thermocouple pyrometers or (4) 75% of welds in Location Class 4;
other suitable equipment toassurethatthe proper (5) 100% of the welds in compressor stations,
stress relieving cycle has been accomplished. and at major or navigable river crossings, major high-
way crossings, and railroad crossings, if practical, but
in no case less than 90%. All tie-in welds not subjected
to a pressure proof test shall be examined.
826 WELDING AND INSPECTION TESTS
(c) All welds which are inspected must either meet
826.1Inspection of Welds on Piping Systems the standardsof acceptability of API 1104or be appro-
Intended to Operate at Less Than 20% of priately repaired and reinspected. The results of the
the Specified Minimum Yield Strength inspection shall be used to control the quality of weld-
ing.
The quality of welding shall be checked visually on
(d) When radiographic examination is employed, a
a sampling basis and defective welds shall be repaired
procedure meeting the requirements of API 1104 shall
or removed from the line.
be followed.
(e) When pipe size is less than NPS 6, or when the
826.2InspectionandTests for Quality Control construction project involves such a limited number of
of Welds on Piping Systems Intended to welds that nondestructive inspection would be imprac-
Operate at 20% or More of the Specified tical, and the pipe is intended to operate at40% or less
Minimum Yield Strength of the specified minimum yield strength, then provi-
sions (a), (b), and (c) above are not mandatory, pro-
(a) The quality of welding shall be checked by non-
vided the welding is inspected visually and approved by
destructive inspection. Nondestructive inspection may
a qualified welding inspector.
consist of radiographic examination, magnetic particle
(jlIn addition to the nondestructive inspection re-
testing, or other acceptable methods. The trepanning
quirements outlined above, the quality of welding shall
method of nondestructive testing is prohibited.
be continually controlled by qualified personnel.
(6) The following minimum number offield butt
welds shall be selectedon a random basis by the operat-
ing company from each day’s construction for exami-
827
REPAIR
OR
REMOVAL OF
nation. Each weld so selected shall be examined over its DEFECTIVE WELDS IN PIPING
entire circumference or else the equivalent length of
INTENDED TO OPERATE AT 20% OR
welds shall be examined if the operating company MORE OF THE SPECIFIED
chooses to examine only a part of the circumference of MINIMUM YIELD STRENGTH
each. The same minimum percentages shall be exam-
ined for double ending at railhead or yard: Defective welds shall be repaired or removed. If a
( I ) 10% of welds in Location Class 1; repair is made, it shall be in accordance with API 1104.
(2) 15% of welds in Location Class 2; Welders performing repair shall be qualified inaccord-
(3) 4 0% of welds in Location Class 3; ance with para. 823.2.
18
CHAPTER I11
PIPING SYSTEM COMPONENTS AND
FABRICATION DETAILS
19
831.13 Pressure reducing devices shall conform to threaded companion cast iron flangeshaving 1/16 in.
the requirements of this Code for valves in comparable raised faces, the bolting shall be of carbon steel equiva-
service conditions. lent to ASTM A 307 Grade B, without heat treatment
other than stress relief.
0) Class 150 steelflangesmaybebolted to Class
Flanges
831.2 125 cast iron flanges. When such construction is used,
the 1/16 in.raisedface on the steel flange shall be
831.21 Flange Types and Facings removed. When bolting such flanges together using a
(a) The dimensions and drilling for all line or end flat ring gasket extending to the inner edge of the bolt
flanges shall conform to one of the following standards: holes, the bolting shall be of carbon steel equivalent to
ANSI B16SerieslistedinAppendixA (for Ironand ASTM A 307 Grade B, without heat treatment other
Steel) than stress relief. When bolting such flanges together
MSS S P 4 i Steel Pipe LineFlanges using a full-face gasket, the bolting may be alloy steel
Appendix I Light-Weight Steel
Flanges (ASTM A 193).
ANSI B16.24 Brass or Bronze FlangesandFlanged Fit- (k) Class 300 steel flanges may be bolted to Class
tings
250 cast iron flanges. Where such construction is used,
Flanges cast or forged integral with pipe, fittings, or the bolting shall be ofcarbon steel, equivalentto ASTM
valves will bepermitted in sizesand the pressure classes A 307 Grade B, without heat treatment other than
covered by the standards listed above, subject to the stress relief. Good practice indicates that the raised face
facing, bolting,and gasketing requirements of this par- on the steel flange should be removed, but also in this
agraph and paras. 831.22 and 831.23. case,bolting shall beof carbon steel equivalent to
(b) Threaded companion flanges which comply with ASTM A 307 Grade B.
the B 16 group of American National Standards will be (1) Forged steel welding neck flanges havingan out-
permitted in sizesand pressure classes covered by these side diameter and drilling the same as ANSI B 16.1,but
standards. with modified flange thicknesses, hub dimensions, and
(c) Lappedflangeswillbe permitted insizes and special facing details, may be used to bolt against flat
pressure classes established in ANSI B16.5. faced cast iron flanges and may operate at the pressure-
(d) Slip-on welding flanges will be permitted in sizes temperature ratings given in ANSI B 16.1for Class 125
and pressure classes established ANSI
in B 16.5. Slip-on cast iron pipe flanges, provided:
flanges of rectangular section may be substituted for (1) the minimum flange thickness T is not less
hubbed slip-on flanges, provided the thickness is in- thanthat specifiedinAppendix I for lightweight
creased as required to produce equivalent strength as flanges;
determined by calculations made in accordance with (2) flanges are used with nonmetallic full-face gas-
Section VI11 of the BPV Code. kets extending to the periphery of the flange;
(e) Welding neck flanges will be permitted in sizes (3) the joint design has been proven by test to be
and pressure classes established in ANSI B 16.5 and suitable for the ratings.
MSS SP-44. The bore of the flange should correspond (m)Flanges made of ductile iron shall conform to
to theinside diameter of the pipe used. For permissible the requirements of ANSI B16.42. Bolting require-
welding end treatment, see Fig. 15. ments for ductile iron flange joints shall be the same as
cr) Cast iron, ductile iron, and steelflanges shall those for carbon and low alloy steel flangesas specified
have contact faces finished in accordance with MSS in para. 831.22.
SP-6.
(g) Nonferrous flanges shall have contact faces fin- 831.22 Bolting
ished in accordance with ANSI B16.24. (a) For all flange joints, the bolts or studbolts used
(h) Class 25 and 125 cast iron integral or threaded shall extend completely through the nuts.
companion flanges may be used with a full-face gasket (6) For all flange joints other than those described
or with a flat ring gasket extending to theinner edge of in paras. 83 1.21(h), (i),(i), and (k), the bolting shall be
the bolt holes. When using a full-face gasket, the bolt- made of alloy steel conforming to ASTM A 193, A 320,
ing may be of alloy steel (ASTM A 193). When using or A 354, or of heat treated carbon steel conforming to
a ring gasket,the bolting shall be of carbon steel, equiv- ASTMA449,except that bolting for ANSI B16.5
alent to ASTM A307 Grade B, without heat treatment Class150 and 300flanges at temperatures between
other than stress relief. -20°F and 450°F may be made of Grade B of ASTM
(i) When bolting together two Class 250 integral or A 307.
20
(c) Alloy-steel bolting material conforming to also be used with steel flanges with lapped, large male
ASTM A 193 or A 354 shall be used for insulating and female, large tongue and groove, or raised face
flanges if such bolting is made YE in. undersized. facings.
(d) The materials used for nuts shall conform with (e) Full-face gaskets shall be used with all bronze
ASTM A 194 and A 307. A 307 nuts may be used only flanges, and may be used with Class 25 or 125 cast iron
with A 307 bolting. flanges. Flat ring gaskets with an outside diameter ex-
(e) All carbon and alloy-steel bolts, studbolts, and tending to theinside of the bolt holes may be usedwith
their nuts shall be threaded in accordance with the cast iron flanges, with raised face steel flanges, or with
following thread series and dimension classes as re- lapped steel flanges.
quired by ANSI B1.1. fl In order to secure higher unit compression on
(I) Carbon Steel. All carbon-steel bolts and stud- the gasket, metallic gaskets of a width less than thefull
bolts shall have coarse threads, Class 2A dimensions, male face of the flange may be used with raised face,
and their nuts Class 2B dimensions. lapped, or large male and female facings. The width of
(2) AIIoy Steel. All alloy-steel bolts and studbolts the gasket for small male and female or for tongue and
of 1 in. and smaller nominal diameter shall be of the groovejoints shall be equal to thewidth of the male face
coarse-thread series; nominal diameters 1'/s in. and or tongue.
larger shall be of the 8-thread series. Bolts and stud- (g) Rings for ring joints shall be of dimensions es-
bolts shall have a Class 2A dimension; their nuts shall tablished in ANSI B 16.20. The material for these rings
have Class 2B dimension. shall be suitable for the service conditions encountered
fl Bolts shall have American NationalStandard and shall be softer than the flanges.
regular square heads or heavy hexagonal heads and (h) The insulating material shall be suitable for the
shall have American National Standard heavy hexa- temperature, moisture, and other conditions where it
gonal nuts conforming tothe dimensions of ANSI will be used.
B18.2.1 and B18.2.2.
(g) Nuts cut from bar stock in such a manner that
the axis will be parallel to the direction of rolling of the
831.3 Fittings Other Than Valves and Flanges
bar may be used in all sizes for joints in which one or
both flanges are cast ironand for joints with steel 831.31 Standard Fittings
flanges where the pressure does not exceed 250 psig. (a) The minimum metal thickness of flanged or
Such nuts shall not be used for joints in which both threaded fittings shall not be less than specified for the
flanges are steel and the pressure exceeds250psig, pressures and temperaturesin the applicable American
except that for nut sizes '/2 in. and smaller, these limita- National Standards or the MSS Standard Practice.
tions do not apply. (b) Steel buttwelding fittings shall comply with ei-
ther ANSI B16.9 or MSS SP-75, and shall have pres-
831.23 Gaskets sure and temperatureratings based on stresses for pipe
(a) Material for gaskets shall be capable of with- of the same or equivalent material. To insureadequacy
standing themaximum pressure and of maintaining its of fitting design, the actual bursting strengthof fittings
physical and chemical properties at any temperature to shall at least equal the computed bursting strength of
which it might reasonably be subjected in service. pipe of the designated material and wall thickness. Mill
(6) Gaskets used under pressure and at tempera- hydrostatic testing of factory made steel buttwelding
tures above 250°F shall be of noncombustible material. fittings is not required, but all such fittings shall be
Metallic gaskets shall not be used with Class 150 stan- capable of withstanding a field test pressure equal to the
dard or lighter flanges. test pressure established by the manufacturer, without
(c) Asbestos composition gaskets may be used as failure or leakage, and without impairment of their
permitted in ANSI B16.5. This type of gasket may be serviceability.
used with any of the various flanged facings except (c) Steel socket-welding fittings shall comply with
small male and female or small tongue and groove. ANSI B16.11.
(d) The useof metal or metal-jacketed asbestos (d) Ductile iron flanged fittings shall comply with
gaskets (either plain or corrugated) is not limited as to the requirements of ANSI B16.42 or ANSI A21.14.
pressure, provided that the gasket material is suitable (e) Thermoplastic fittings shall comply with ASTM
for the service temperature. These types of gaskets are D 2513.
recommended for use with the small male and female Ir) Reinforced thermosetting plastic fittings shall
or the small tongue and groove facings. They may comply with ASTM D 2517.
21
831.32 Special Fittings. When special cast, forged, tions listed in this Code, shall be designed, constructed,
wrought, or welded fittings are required to dimensions and tested under requirements of the BPV Code. BPV
differing from those of regular shapes specified in the Code requirements are not intended to apply to such
applicable American National and MSS Standards, the partial assemblies as split rings or collars or to other
provisions of para. 831.36 shall apply. field welded details.
(e) Every prefabricated unit produced underthis
831.33 Branch Connections section of the Code shall successfully withstand a pres-
(a) Welded branch connections on steel pipe must sure test without failure, leakage, distress, or distortion
meet the design requirements of paras. 83 1.4and 83 1.5. other than elastic distortion at a pressure equal to the
(6) Threaded taps in cast iron pipe for branch con- test pressure of the system in which it is installed, either
nections are permitted without reinforcement to a size before installation or duringthe system test. When
not more than 25% of the nominal diameter of the such units are to be installed in existing systems, they
pipe. However, where climate service conditions or soil shall be pressure tested before installation, if feasible;
, conditions create abnormal or unusual external load- otherwise, they shall withstand aleak test at the operat-
ings on cast iron pipe, unreinforced threaded taps for ing pressure of the line.
branch connections are permittedonly on cast iron pipe
NPS 8 and larger in diameter, provided that the tap
size 831.36 Pressure Design of Other Pressure Contain-
is no greater than 25% of the nominal pipe diameter. ing
Components. Pressure containing components
(c) Existing threaded taps in cast iron pipe may be which are not covered by the standards listed in Ap-
used for replacement branch connections when careful pendix A and for which design equations or proce-
inspection shows there are no cracks or other deteriora- dures are not given herein may be used where the de-
tion in the main immediately surrounding the opening. signof similarly shaped, proportioned,and sized
(d) Threaded taps in ductile iron pipe are permitted components has been proven satisfactory by success-
without reinforcement to a size not more than 25% of ful performance under comparable service conditions.
the nominal diameter of the pipe, except that 1 Y4 in. (Interpolation may be made between similarly shaped
taps arepermitted in NPS 4pipe having a nominal wall proved components with small differencesin size or
thickness of not less than 0.380 in. proportion.)Inthe absence of such service experi-
(e) Mechanical fittings may be used for making hot ence, the pressure design shall be based on an analy-
taps on pipelines and mains provided they are designed sis consistent with the general design philosophy em-
for the operating pressure of the pipeline or main, and bodied in this Code, and substantiated by at least one
are suitable for the purpose. of the following:
(a) proof tests (as are described in UG-101 of Sec-
831.34 Openings for Gas Control Equipment in Cast tion VIII, Division 1, of the BPV Code);
Iron Pipe. Threaded taps used for gas control equip- (6) experimental stress analysis (such as described in
ment in cast iron pipe (i.e.,bagging off a section of Appendix 6 of Section VIII, Division 2, of the BPV
main) are permitted without reinforcement, to a size Code);
not more than 25% of the nominal diameter of the (c) engineering calculations.
pipe, except that 1 '/i in. taps are permitted in NPS 4
pipe. Larger taps than those permitted above shall be
covered by a reinforcing sleeve. 831.37 Closures
831.371 Quick Opening Closures. A quick open-
831.35 Special Components Fabricated by Welding ing closure is a pressure containing component (see
(a) This section covers piping system components para. 831.36) used for repeated access to theinterior of
other than assemblies consisting of pipe and fittings a piping system. It is not the intent of this Code to
joined by circumferential welds. impose the requirements of a specific design method on
(b) All welding shall be performed using procedures the designer or manufacturer of a quick opening clo-
and operators that arequalified in accordance with the sure.
requirements of para. 823. Quick opening closures shall have pressure and tem-
(c) Branch connections shall meet the designre- perature ratings equal to or inexcess of the design
quirements of paras. 831.4, 831.5, and 831.6. requirements of the piping system to which they are
(d) Prefabricated units, other than regularly manu- attached.
factured buttwelding fittings, which employ plate and Quick opening closures shall be equipped with safety
longitudinal seams ascontrasted with pipe thathas locking devices in compliance with Section VIII, Divi-
been produced and tested under one of the specifica- sion 1, UG-35(b) of the BPV Code.
22
Weld end preparation shall be in accordance with shall be equal to or greater than the required area as
Fig. 14. defined in this paragraph as well as in Fig. F5.
(c) The required cross-sectional area A , is defined
831.372 Closure Fittings. Closure fittings com-
as the product of d times t:
monly referred to as “weld caps” shall be designed and
manufactured in accordance with ANSI B16.9 or MSS
AR = dt
SP-75 [see para. 831.31(b)].
831.373ClosureHeads. Closure heads such as where
flat,ellipsoidal (other than in para. 831.372above), d = the greater of the length of the finished open-
spherical, or conical heads are allowed for use under ing in the header wall measured parallel to the
this Code. Such items may be designed in accordance axis of the run or the inside diameter of the
with Section VIII, Division 1, of the BPV Code. The branch connection
maximum allowable stresses for materials used in these t = the nominal header wall thickness required by
closure heads shall be established under the provisions para. 841.11 for the design pressure and tem-
of para. 841 not exceeding 60% SMYS. perature
If welds are used in the construction of these heads, When the pipe wall thickness includes an allowance
they shall be inspected in accordance with the provision for corrosion or erosion, all dimensions used shall be
of Section VIII, Division 1. those that will result after the anticipated corrosion or
Closure heads shall have pressure and temperature erosion has taken place.
ratings equal to or in excess of the design requirement (d) The area available for reinforcement shall be the
of the piping system to which they are attached. sum of:
(1) the cross-sectional area resulting from any ex-
831.374FabricatedClosures. Orange-peel bull
cess thickness available in the header thickness [over
plugs and orange-peel swagesare prohibited on systems
the minimum required forthe header as defined in
operating at stress levels of 20% or more of the specified
para. 831.41(c), and which lies within the reinforce-
minimum yield strength of the pipe material. Fish tails
ment area as defined in para. 831.41(e);
and flat closures are permitted on pipe NPS 3 and
(2) the cross-sectional area resulting from any ex-
smaller operating at less than 100 psi.Fish tails on pipe
cess thickness available in the branch wall thickness
larger than NPS 3 are prohibited. Flat closures on pipe
over the minimum thickness required for the branch
larger than NPS3 shall be designed according to Section
and which lieswithin the reinforcement area asdefined
VIII, Division 1, of the BPV Code (see para. 831.373).
in para. 831.41(e);
831.375 Bolted Blind Flange Connections.Bolted (3) the cross-sectional area of all added reinforc-
blind flange connections shall conform to para. 831.2. ing metal which lies within the reinforcement area, as
defined in para. 831.41(e), including that of solid weld
metal which isconventionally attached to theheader or
831.4 Reinforcement of Welded
Branch
branch, or both.
Connections
(e) The area of reinforcement is shown in Fig. F5,
831.41 GeneralRequirements. All welded branch and is defined as a rectangle whose length shall extend
connections shall meet the following requirements. a distance d on each side of the transverse center line
(a) When branch connections are made to pipe in of the finished opening and whose width shall extend
the form of a single connection or in a header or mani- a distance of 2‘/2 times the header wall thickness on
fold as a series of connections, the design must be ade- each side of the surface of the header wall, except that
quate tocontrol the stress levels in the pipe within safe in no case shall it extend more than 2 % times the
limits. The construction shall take cognizance of the thickness of the branch wall from the outside surface
stresses in the remaining pipe wall due to the opening of the header or of the reinforcement, if any.
in the pipe or header, the shear stresses produced by the cf) The material of any added reinforcement shall
pressure acting on the area of the branch opening, and have an allowable working stress at least equal to that
any external loadings due tothermal movement, of the header wall, exceptthat material of lower allowa-
weight, vibration, etc. The following paragraphs pro- ble stress may be used if the area is increased in direct
videdesign rules for the usual combinations of the ratio of the allowable stresses for header and reinforce-
above loads, except for excessive external loads. ment material, respectively.
(6) The reinforcement required in the crotchsection (9) The material used for ring or saddle reinforce-
of a welded branch connection shall be determined by ment may be of specifications differing from those of
the rule that themetal area available for reinforcement the pipe, provided the cross-sectional area is made in
23
24
smoothly contoured wrought steel tee of proven design the outlet intersects and is perpendicular to theaxis of
may be used. the run.
(i) The reinforcement may be of any type meeting (d) Figures F1 through F4 define the pertinent di-
the requirements of para. 831.41. mensions and limiting conditions.
(e) Required Area. The required area is defined as
25
26
21
835
ANCHORAGE FOR BURIED PIPING support of the pipe in the trench is essential. Unequal
settlements may produce added bending stresses in the
General
835.1
pipe. Lateral thrusts at branch connections may greatly
Bends or offsets in buried pipe cause longitudinal increase the stresses in the branch connection itself,
forces which must be resisted by anchorage at the bend, unless the fill isthoroughly consolidated or other provi-
by restraint due to friction of the soil, or by longitudinal sions made to resist the thrust.
stresses in the pipe. Rock shield shall not be draped over the pipe unless
suitable backfill and padding are placed in the ditch to
provide a continuous and adequate support of the pipe
835.2 Anchorage Bends
at
in the trench.
If the pipe is anchored by bearing at the bend, care
shall be taken to distribute the load on the soil so that
835.51 When openings are made in a consolidated
the bearing pressure is within safe limits for the soil
backfill to connect new branches to an existing line,
involved.
care must be takento provide firm foundation forboth
the header and the branch, to prevent both vertical and
835.3RestraintDue to Soil Friction lateral movements.
Where there is doubt as to the adequacy of restraint
friction, calculations shall be made and indicated an-
choring installed.
835.6
Interconnection of Underground Lines
835.4
Forces on Pipe Joints
Underground lines are subjected to longitudinal
If anchorage is not provided at the bend (see para. stresses due to changes in pressure and temperature.
835.2), pipe joints which are close to the points of For long lines, the friction of the earth will prevent
thrust origin shall be designedto sustain the longitudi- changes in length from these stresses, except for several
nal pullout force. If such provision is not made in the hundred feet adjacent to bends or ends. At these loca-
manufacture of the joints, suitable bracingor strapping tions, the movement, if unrestrained, may be ofconsid-
shall be provided. erable magnitude. If connections are made at such a
location to a relatively unyielding line or other fixed
object, itis essential that theinterconnection shall have
835.5
Supports for Buried
Piping ample flexibilityto care for possible movement,or that
In pipelines,especiallythosewhich are highly the line shall be provided with an anchor sufficient to
stressed from internal pressure, uniform and adequate develop the forces necessary to limit the movement.
28
CHAPTER IV
DESIGN, INSTALLATION, AND TESTING
840 DESIGN,
INSTALLATION,
AND damage. One of the measures required by this Code
TESTING is to lower the stress level in relation to increased
public activity. This activity is quantified by deter-
840.1 General Provisions
mining Location Class and relating the design of the
(a) The design requirements of this Code are in- pipeline to the appropriate design factor.
tended to be adequate for public safety under all condi- (c) Previous editions of this Code used the term
tions encountered in the gas industry. Conditions that population density index to determine design, con-
may cause additional stress in any part of a line or its struction, testing, and operation requirements. It also
appurtenances shall be provided for, using good engi- used the term location class in prescribing design pres-
neering practice. Examples of such conditions include sure, type of construction and maximum allowable op-
long self-supported spans, unstable ground, mechanical erating pressure. To simplify useof this Code, the term
or sonic vibration, weight of special attachments, earth- population density index has been eliminated by this
quake induced stresses, stresses caused by temperature Edition. This Edition of the Code also eliminated the
differences, and the soil and temperature conditions term Construction Types, A, ByC and D and replaced
found in the Arctic. Temperature differences shall be it with the same terminology used for design-location
taken as the difference between the lowest and highest class.
expected metal temperature during pressure test and/ The requirements based on Location Class are such
or operating services having due regard to past re- that there are no significant changes in the design, in-
corded temperature data and the possible effects of stallation, testing and operation of piping systems be-
lower or higher air and ground temperature. tween this Edition of the Code and the 1986 Edition
(b) The most significant factor contributing to the that are due to change in terminology.
failure of a gas pipeline is damage to theline caused by Pipelines constructed prior to the publication of this
the activities of peoplealong the routeof the line. Dam- Edition and designedin accordance with location
age will generally occur during construction of other classes established in compliance with previous editions
facilities associated with providing the servicesas- of this Code may continue to use the location classes so
sociated with human dwellings, and commercial or in- determined, provided that when observed increases in
dustrial enterprises. These services, such as water, gas the number of buildings intended for human occupancy
and electrical supply, sewage systems, drainage lines occur, the Location Class determination shall be as set
and ditches, buried power and communication cables, out in para. 840.2.
streets and roads, etc., become more prevalent and ex-
tensive, and the possibility of damage to the pipeline
becomes greater with larger concentrations of buildings
840.2 Buildings Intended for
intended for human occupancy. Determining the Loca-
Human Occupancy
tion Class provides a method of assessing the degree of
exposure of the line to damage. (a) General
A pipelinedesigned, constructed, and operated in (1) To determine the number of buildings in-
accordance with the requirements of Location Class tended for human occupancy foran onshore pipe-
1 [see para. 840.2(b)(l)] is basically safe for pressure line, lay out a zone '/4 mile wide along the route of
containment in any location; however, additional the pipelinewith the pipeline on the center line of
measures are necessary to protect the integrity of the this zone, and divide the pipeline into random sec-
line in the presence of activities which might cause tions 1 mile in length such thatthe individual
29
lengths will include the maximum number of build- tended for human occupancy except when a Loca-
ings intended for human occupancy. Count the num- tion Class 4 prevails. A Location Class 3 is intended
ber
of buildings intended for human occupancy to reflect areas such as suburban housing develop-
within each 1 mile zone. For this purpose, each sep- ments, shopping centers, residential areas, industrial
arate dwelling unit in a multiple dwelling unit build- areas, and other populated areas not meeting Loca-
ing is to be counted as a separate building intended tion Class 4 requirements.
for human occupancy. (4) LocationClass 4. Location Class 4 includes
It is not intended here that a full mile of lower stress areas where multistory buildings are prevalent, and
level pipeline shall be installed if there are physical where traffic is heavy or dense and where there may be
barriers or other factors that will limit the further ex- numerous other utilities underground. Multistory
pansion of the more densely populated area to a total means 4 or more floors above ground including the first
distance of less than 1 mile. It is intended, however, or ground floor. The depth of basements or number of
that where nosuchbarriers exist, ample allowance basement floors is immaterial.
shall be made in determining the limits of the lower
stress design to provide for probable further develop-
840.3
Considerations
Necessary for
ment in the area.
Concentrations of People in Location
(2) When a cluster of buildings intended for
Class 1 or 2
human occupancy indicates that a basic mile of pipeline
should be identified as a Location Class 2 or Location (a) In addition tothe criteria contained in para.
Class 3, the Location Class 2 or Location Class 3 may 840.2, additional consideration must begiven to the
be terminated 660 ft from the nearest building in the possible consequences of a failure near a concentration
cluster. of people, such as found in a church, school, multiple
(3) For pipelines shorter than 1 mile in length, a dwelling unit, hospital, or recreational area of an orga-
Location Class shall be assigned which istypical of the nized character in Location Class 1 or 2.
Location Class which would be required for 1 mile of If the facility is used infrequently, the requirements
pipeline traversing the area. of (b) below need not be applied.
(b) Location Classes for Design and Construction (b) Pipelines near places of public assembly or con-
(1) Location Class I. A Location Class 1 is any 1 centrations of people such as churches, schools, multi-
mile section that has 10 or fewer buildings intended for ple dwelling unit buildings, hospitals, or recreational
human occupancy. A Location Class 1 is intended to areas of an organized nature in Location Class 1 or 2
reflect areas suchas wasteland, deserts, mountains, shall meet requirements for Location Class 3.
grazing land, farmland, and sparsely populated areas. (e) Concentrations of people referred to in (a) and
(a) Class 1 Division I. A Location Class 1 (b) above are not intended to include groups of fewer
where the design factor of the pipe is greater than 0.72 than 20 peopleper instance or location but areintended
but equal to or less than 0.80, and which has been to cover people in an outside area as well as in a build-
hydrostatically tested to 1.25 times the maximum oper- ing.
ating pressure. (See Table 841.114B for exceptions to
design factor.)
Intent
840.4
(b) Class 1 Division 2. A Location Class 1
where the design factor of the pipe is equal to or less 840.41 It should be emphasized that Location
than 0.72, and which has been tested to 1.1 times the Class (1,2, 3, or 4) as described in the foregoing
maximum operating pressure. (See Table 841.1 14B for paragraphs is defined as the general description of a
exceptions to design factor.) geographic area having certain characteristics as a
(2) Location Class 2. A Location Class 2 is any basis for prescribing the types of design, construc-
1 mile section that has more than 10 but fewer than tion, and methods of testing to be used in those lo-
46 buildings intended for human occupancy. A Loca- cations or in areas that are respectively comparable.
tion Class 2 is intended to reflect areas where the de- A numbered Location Class, such as Location Class
gree of population is intermediate between Location 1, refers only to the geography of that location or a
Class 1 and Location Class 3 such as fringe areas similar area, and does not necessarily indicate that a
around cities and towns, industrial areas, ranch or design factor of 0.72 will suffice for all construction
country estates, etc. in that particular location or area, e.g., in Location
(3) Location Class 3. A Location Class 3 is any Class 1, all aerial crossings require a design factor of
1 mile section that has 46 or more buildings in- 0.6 (see para. 841.122).
30
840.42 When classifying locations for the purpose of (c) Fracture Control and Arrest. A fracture tough-
determining the design factor for pipeline construction ness criteria or other method shall be specified to con-
and testing that should be prescribed, due considera- trol fracture propagation when a pipeline is designed to
tion shall be given to the possibility of future develop- operate either at ahoop stress over 40% through 80%
ment of the area. If at the time of planning a new of SMYS in sizes NPS 16 or larger, or at a hoop stress
pipeline this future development appears likely to be over 72% through 80% of SMYS in sizes smaller than
sufficient to change the Class Location, this shall be NPS 16.
taken into consideration in the design and testing of the When a fracture toughness criteria is used, control
proposed pipeline. can be achieved by assuring that the pipe has adequate
ductility and either specifying adequate toughness or
installing crack arrestorson the pipeline to stoppropa-
STEEL
841 PIPE gation.
841.1 Steel PipingSystemsDesign Requirements (1) Brittle Fracture Control. To assure that the
pipe has adequate ductility, fracture toughness testing
841.11 Steel Pipe Design Formula shall be performed in accordance with the testing pro-
(a) The design pressure for steel gas piping systems cedures of the supplementary requirements SR5 or SR6
or the nominal wall thickness for a given design pres- of API 5L, or other equivalent alternatives. If the oper-
sure shall be determined by the following formula (for ating temperature is below 32"F, an appropriate lower
limitations, see para. 841.111): test temperature shall be used. The appropriate lower
test temperature for notch toughness purposes shall be
2st taken to be at or below the lowest expected metal tem-
P = --ET
D
perature duringpressure testing (if with air or gas) and
where during service, having regard to past recorded tempera-
P = design pressure, psig (see also para. 841.111) ture data and possible effects of lower air and ground
S = specified minimum yield strength, psi, stipu- temperatures. The average shear value of the fracture
lated in the specificationsunder which the pipe appearance of the test specimens from each heat shall
was purchased from the manufacturer or de- not be less than 35% and the all heat average shall not
termined in accordance with paras. 817.13(h) be less than 50% shear when Charpy V-notch testing,
and 841.112. The specified minimum yield based on full-sized Charpy specimens, is specified, or,
strengths of some of the more commonly used at least 80% of the heats shall exhibit a fracture shear
piping steels, whose specificationsare incorpo- appearance of 40% or more when drop-weight tear
rated by reference herein, are tabulated for testing is specified.
convenience in Appendix D. (2) Ductile Fracture Arrest. To assurethatthe
D = nominal outside diameter of pipe, in. pipeline has adequatetoughness to arrest a ductile frac-
t = nominal wall thickness, in. ture, the pipe shall be tested in accordance with the
F = design factor obtained from Table 841.114A. procedures of supplementary requirement SR5 of API
In setting the values of the design factor E: due 5L.The all-heat average of the Charpy energy values
consideration has beengiven and allowance shall meet or exceed the energy value calculated using
has been made for the various underthickness one of the following equations that have been devel-
tolerances provided for in the pipe specifica- oped in various pipeline research programs.
tions listed and approved for usage in this (a) Battelle Columbus Laboratories (BCL)
Code. (AGA)
E = longitudinal joint factor obtained from Table
841.115A [see also para. 8 17.13(d)] CVN = 0.0108~2R'/3t'/3
T = temperaturederatingfactor obtained from
Table 84 1.1 16A (b) American Iron and Steel Institute (AISI)
(b) The design criterion for pipelines in Location
Class 1, Division 1 isbased upon gas pipeline opera-
CVN = 0.0345~
3/2R
tional experience at operation levels in excess of those
previously recommended by this Code.
It should be noted that the user may be required to (c) British Gas Council (BGC)
change out such pipe or reduce pressure to 0.72 SMYS
maximum in accordance with 854.2. CVN = 0.031S~R/t'/*
31
(d)British Steel Corporation (BSC) ( I ) S value for new pipe qualified under para.
811.221 or 811.222;
CVN = 0.00119~~R (2) S value for reuse of steel pipe qualified under
one of the provisions of para. 8 17.1;
where (3) S value for pipe of unknown specification as
CVN = full-size Charpy V-notch absorbed energy, ft- determined by para. 8 17.13(h).
lb (6) When pipe that has been cold worked for the
u = hoop stress, ksi purpose of meeting the specified minimum yield
R = pipe radius, in. strength is subsequently heated to a temperature higher
t = wall thickness, in. than 900°F for any period of time or over 600°F for
(3) Mechanical
Crack
Arrestors. Mechanical more than 1 hr, the maximum allowable pressure at
crack arrestors consisting of sleeves, wire-rope wrap, which it can be used shall not exceed 75% of the value
heavy-wall pipe, or othersuitable types have been obtained by use of the steel pipe design formula given
shown to provide reliable methods of arresting ductile in para. 841.11.
fracture. The mechanical crackarrestors shall be (c) In no case where the Code refers to the specified
placed at intervals along the pipeline. minimum value of a mechanical property shall the
higher actual value of a property be substituted in the
CAUTION:The requirements specifiedin (2) above assume the steel pipe design formula given in para. 841.1 1. If the
pipeline is transporting essentially pure methane. The presence of
heavier hydrocarbons can cause the gas to exhibit two phase behavior actual value is lessthan thespecified minimum value of
on sudden decompression and thus requires a greater Charpy energy a mechanical property, the actual value may be used
to arrest propagating pipe fracture. Calculations must be performed where it is permitted by the Code, suchas in para. 817.1
to determine if the decompression exhibits two phase behavior where
additional toughness is required; otherwise mechanical crack arres- regarding the reuse of steel pipe.
tors, [see (3) above], should be installed or the Charpy toughness
requirement for arrest be verified through experiments. 841.113AdditionalRequirements For Nominal
Wall Thickness t in Para. 841.11
841.111Limitations on DesignPressure P in (a) The minimum wall thickness t required for pres-
Para. 841.11. The design pressure obtained by the for- sure containment as determined by para. 841.11 may
mula in para. 841.1 1 shall be reduced to conform to the not be adequate for other forces to which the pipeline
following. may be subjected [see para. 840.l(a)]. Consideration
(a) P for furnace butt welded pipe shall not exceed shall also be given to loading due to transportation or
the restrictions of para. 841.11 or 60% ofmill test handling of the pipe duringconstruction, weightof
pressure, whichever is the lesser. water during testing, and soil loading and othersecond-
(b) P shall not exceed 85% of the mill test pressure ary loads during operation.Consideration should also
for all other pipes provided; however, that pipe, mill begiven to welding or mechanical joining require-
tested to a pressure less than 85% of the pressure re- ments. Standard wall thickness, as prescribed in ASME
quired to produce a stress equal to the specified mini- B36.10M, shall be the least nominal wall thickness used
mum yield, may be retested with a mill type hydro- for threaded and grooved pipe.
static test or tested in place after installation. In the (6) Transportation, installation, or repair of pipe
event the pipe is retested to a pressure in excess of the shall not reduce the wall thickness at any point to a
mill test pressure, then P shall not exceed 85% of the thickness less than 90% of the nominal wall thickness
retest pressure rather than the initial mill test pres- as determined by para. 841.11 for the design pressure
sure. It is mandatory to use a liquid as the test me- to which the pipe is to be subjected.
dium in all tests in place after installation where the
test pressure exceeds the mill test pressure. This para- 841.114 Design Factors F and Location Classes
graph is not to be construed to allow an operating (a) The design factor in Table 841.1 14A shall be
pressure or design pressure in excess of that provided used for the designated Location Class. All exceptions
for by para. 841.11. to basic design factors to be used in the design formula
are given in Table 841.1 14B.
841.112 Limitations on Specified Minimum Yield
Strength S in Para. 841.11 841.115 The longitudinal joint factor shall be in
(a) If the pipe under consideration is not new pipe accordance with Table 841.115A.
purchased under a specification approved and listed in
this Code, the value of S may be determined in accord- 841.116 The temperature derating factor shall be
ance with one of the following: in accordance with Table 841.116A.
32
TABLE 841.114A
BASIC DESIGN FACTOR F
~~ ~~
TABLE 841.114B
DESIGNFACTORS FOR STEEL PIPE CONSTRUCTION
Location Class
1
Facility Div. 1 Div. 2 2 3 4
Pipelines, mains, and service lines [see para. 840.2(b)1 0.80 0.72 0.60 0.50 0.40
Fabricated assemblies (see para. 841.121) 0.60 0.60 0.60 0.50 0.40
Pipelines on bridges (see para. 841.122) 0.60 0.60 0.60 0.50 0.40
Near concentration o f people in Location Classes 1 and 2 [See para. 840.3(b)I 0.50 0.50 0.50 0.50 0.40
841.12Additional Design Information or Instruc- outthe assembly and for a distance equal to the lesser
tions of 5 diameters or 10 ft in each direction beyond the last
fitting. A shorter distance 'may be used provided that
841.121 FabricatedAssemblies. When fabricated combined stresses are considered in the design of the
assemblies, such as connections for separators, main installation. Transition pieces at the end of an assembly
line valve assemblies, cross connections, river crossing and elbows used in place of pipe bends are not consid-
headers, etc., are to be installed in areas definedin ered fittings under the requirements of thisparagraph.
Location Class 1, design factor 0.6 is required through- Also see para. 822.
33
TABLE 841.115A
LONGITUDINAL JOINT FACTOR E
Spec. No. Pipe Class E Factor Spec. No. Pipe Class E Factor
GENERALNOTE:
Definitions for the variousclasses of welded pipe are given in para. 004.243.
841.13Protection of Pipelines and Mains From 841.14 Cover, Clearance, and Casing Requirements
Hazards for Buried Steel Pipelines and Mains
(a) When pipelines and mains must be installed 841.141 CoverRequirements for Mains. Buried
where they will be subject to natural hazards, such as mains shall be installed with a cover not less than 24
washouts, floods, unstable soil, landslides, earthquake in. Where this cover provision cannot be met, or where
related events (such as surface faulting, soil liquefac- external loads may be excessive, the main shall be en-
tion, soil and slope instability characteristics), or other cased, bridged, or designed to withstand any such an-
conditions which may cause serious movement of, or ticipated external load. Where farming or other opera-
34
tions might result in deep plowing or in areas subject casing shall be sealed. Ifthe end sealing is of a typethat
to erosion or in locations where future grading is likely, will retain the maximum allowable operating pressure
such as road, highway, railroad and ditch crossings, of the carrier pipe, the casing shall be designed for this
additional protection shall be provided. pressure and at least to thedesign factor of 0.72. Vent-
ing of sealed casings is not mandatory; however, if
841.142 CoverRequirementsfor Pipelines. Ex- vents are installed they should be protected from the
cept for offshore pipelines, buried pipelines shall be weather to prevent water from entering the casing.
installed with a cover not less than that shown in the (Requirements for crossings within casing of rail-
following table: roads and highways are shown in Table 841.114B.)
Cover. in.
841.15 Design factors are summarized in Table
For Rock1
Excavation 841.1 14B.
Pipe Size Pipe Size
For Normal NPS 20 and Larger Than
Location Excavation Smaller NPS 20 841.2Installation of Steel Pipelines and Mains
Class 1 24 12 18
Class 2 30 18 18
841.21 Construction Specifications. All construction
Classes 3 and 4 30 24 24 work performed on piping systems in accordance with
Drainage ditch at 24 36 24 the requirements of this Code shall be done undercon-
public roads and struction specifications.The construction specifications
railroad crossings shall cover all phases of the work and shall be in suffi-
(all locations)
cient detail to cover the requirements of this Code.
NOTE: 841.22 Inspection Provisions
(1) Rock excavation is excavation that requires blasting. 841.221 The operating company shall provide
Where these cover provisions cannot be met or suitable inspection. Inspectors shall be qualified either
where external loads may be excessive, the pipeline by experience or training. The inspector shall have the
shall be encased, bridged, or designed to withstand any authority to order the repair or removal and replace-
such anticipated external load. In areas where farming ment of any component found that fails to meet the
or other operations might result in deep plowing, or in standards of this Code.
areas subject to erosion, or in locations where future
841.222 The installation inspection provisions for
grading is likely, such as at roads and highway, rail-
pipelines and other facilities to operate at hoop stresses
road, and ditchcrossings, additional protection shall be
of 20% or more of the specified minimum yield
provided.
strength shall be adequate to make possible at least the
841.143 ClearanceBetweenPipelines or Mains following inspections at sufficiently frequent intervals
and Other Underground Structures to assure good quality of workmanship.
(a) There shall be at least 6 in. clearance wherever (a) Inspect the surface of the pipe for serious surface
possiblebetween any buried pipeline and any other defects just prior to the coating operation [see para.
underground structure not usedin conjunction with 84 1.242(a)].
the pipeline. When such clearance cannot be attained, (b) Inspect the surface of the pipe coating as it is
precautions to protect the pipe shall be taken, such as lowered into the ditch to find coating lacerations that
the installation of casing, bridging, or insulating mate- indicate the pipe might have been damaged after being
rial. coated.
(b) There shall be at least 2 in. clearance wherever (c) Inspect the fitup of the joints before the weld is
possible between any buried gas main and any other made.
underground structure not usedin conjunction with (d) Visually inspect the stringer beads before subse-
the main. When such clearance cannot be attained, quent beads are applied;
precautions to protect the main shall be taken, such as (e) Inspect the completed welds before they are cov-
the installation of insulating material or casing. ered with coating.
cfl Except for offshore pipelines, inspect the condi-
841.144Casing RequirementsUnderRailroads, tion of the ditch bottom just before the pipe is lowered
Highways, Roads,or Streets. Casings shall be designed in.
to withstand the superimposed loads. Where there is a (g) Except for offshore pipelines, inspect the fit of
possibility of water entering the casing, the ends of the the pipe to the ditch before backfilling.
35
(h) Inspect all repairs, replacements, or changes or- not be permitted. Wrinkles shall have
a spacing not less
dered before they are covered up. than the distance equal to the diameter of the pipe
(i) Perform such special testsand inspections as are measured alongthe crotch. On pipeNPS 16 and larger,
required by the specifications, such as nondestructive the wrinkle shall not produce an angle of more than
testing of welds and electrical testingof the protective 15'2 deg. per wrinkle.
coating.
841.232 Mitered bends are permitted subject to
0;)Inspectbackfill material prior to use and ob-
the following limitations.
serve backfillprocedure to assure no damageoccurs to
(a) In systems intended to operate at 4 0% or more
the coating in the process of backfilling.
of the specified minimum yieldstrength, mitered bends
841.23 Bends, Elbows, AndMiters in Steel Pipelines are not permitted. Deflections causedby misalignment
and Mains. Changes in direction may be made by the up to 3 deg. are not considered as miters.
useof bends,elbows, or miters under the following (b) In systems intended to operate at 10% but less
limitations. than 40% of the specified minimum yieldstrength, the
841.231 total deflection angle at each miter shall not exceed
(a) A bend shall be free from buckling, cracks, or 1295 deg.
other evidence of mechanical damage. (c) In systems intended to operate at less than 10%
(6) The maximum degree of bending on a field cold of the specified minimum yield strength, the total de-
bend may be determined by either method in the table flection angle at each miter shall not exceed 90 deg.
below. The first column expresses the maximum de- (d) In systems intended to operate at 10% or more
flection in an arc length equal to the outside diameter, of the specified minimum yieldstrength, the minimum
and the second column expressesthe minimum radius distance between miters measured at the crotch shall
as a function of the outside diameter. not be less than one pipe diameter.
(e) Care shall be taken in making mitered joints to
Deflection of Minimum Radius of
Nominal Longitudinal Axis,
Bend
in Pipe Diameters provide proper spacing and alignment and full Ipenetra-
deg. Pipe Size [See 841.231(c)] tion.
Smaller than 12 841.231(d) 180
12 180 841.233 Factory-made, wrought-steel welding el-
14 2.1 210 bows or transverse segmentscut therefrom may be used
16 2.4 240 for changes in direction, provided that the arc length
18 2.1 210 measured alongthe crotch is at least 1 in. on pipe sizes
20 and larger 1.9 300 NPS 2 and larger.
(c) A fieldcoldbendmaybemade to a shorter
841.24PipeSurfaceRequirementsApplicableto
minimum radius than permitted in (b) above, provided
Pipelines and Mains to Operate at a Hoop Stress of
the completed bend meets all other requirements of this
20% or More of the Specified
Minimum Yield
section, andthe wall thickness after bending is not less
Strength. Gouges,grooves, and notcheshavebeen
than the minimum permittedby para. 841.1 1. This may
found to be an important cause of pipeline failuresand
be demonstrated through appropriate testing. all harmful defects of this nature must be prevented,
(d) For pipe smallerthan NPS 12, the requirements
eliminated or repaired. Precautions shall be takendur-
of (a) above must be met and the wall thickness after
ing manufacture, hauling, and installation to prevent
bending shall not be less than the minimum permitted
the gouging or grooving of pipe.
by para. 841.11. This maybe demonstrated through
appropriate testing. 841.241 Detection of Gouges and Grooves
(e) Except for offshore pipelines, when a circumfer- (a) The field inspection provided on each job shall
ential weld occurs in a bend section, it shall be sub- be suitable to reduce to an acceptable minimum the
jected to radiography examination after bending. chances that gouged or grooved pipe will get into the
cfl Hot bends made on cold worked or heat treated finished pipeline or main. Inspection for this purpose
pipe shall be designedfor lower stress levels in accord- just ahead of the coating operation and during the low-
ance with para. 841.112(b). ering-in and backfill operation is required.
(g)Wrinkle bends shall be permitted only on sys- (6) When pipe iscoated, inspection shall be made to
tems operating at less than 30% of the specified mini- determine that the coating machine does not cause
mum yield strength. When wrinkle bendsare made in harmful gouges or grooves.
welded pipe, the longitudinal weld shall be located as (c) Lacerations of the protectivecoating shall be
nearly to 90 deg. with the top of the wrinkle as condi- carefully examinedprior to the repair of the coating to
tions will permit. Wrinkle bends with sharp kinks shall see if the pipe surface has been damaged.
36
841.242 Field Repair of Gouges and Grooves as a cylinder and replaced with a good piece. Insert
(a) Injurious gouges or grooves shall be removed. patching is prohibited. Care shall beexercised that
(b) Gouges or grooves may be removedby grinding the heat of grinding does not produce a metallurgi-
to a smooth contour, provided thatthe resulting wall cal notch.
thickness is not less than the minimum prescribed by
this Code for the conditions of usage[see para. 841.25 Miscellaneous Operations Involved in theIn-
.
841.113(b)l. I.,
stallation of SteelMains
Pipelines and
(e) When the conditions outlined in para. 841.251 Handling, Hauling, and Stringing. Care
841.242(b) cannot be met, the damaged portion of pipe shall be taken in the selection of the handling equip-
shall be cut out as a cylinder and replaced with a goo& ment and in handling, hauling, unloading, and placing
piece. Insert patching is prohibited. the pipe so as not to damage the pipe.
841.252 Installation of Pipe in the Ditch. On pipe-
841.243 Dents lines operating Bt stresses of 20% or more of the speci-
(a) A dent may be defined as a depression which fied minimum yield strength, it is importantthat
produces a gross disturbance in the curvature of the stresses induced into the pipeline by construction be
pipe wall (as opposed to a scratch or gouge,which minimized. Except for offshore pipelines,the pipe shall
reduces the pipe wall thickness). The depth of a dent fit the ditch without the use of external force to hold
shall be measured as the gap between the lowest point it in place until the backfill is completed. When long
of the dent and a prolongation of the original contour sections of pipe that have been welded alongside the
of the pipe in any direction. ditch are lowered in, care shall be exercised so as not
(b) A dent,as defined in para. 841.243(a),which to jerk the pipe or impose any strains that may kink or
contains a stress concentrator such as a scratch, gouge, put a permanent bend in the pipe. Slack loops are not
groove, or arc burn shall be removed by cutting out the prohibited by this paragraph where laying conditions
damaged portion of the pipe as a cylinder. render their use advisable.
(c) All dents which affect the curvature of the pipe
at the longitudinal weld or any circumferential weld 841.253 Backfilling
shall be removed. All dents which exceed a maximum (a) Backfilling shall be performed in a manner to
depth of '/4 in. in pipe NPS 12 and smaller or 2% of provide firm support under the pipe.
the nominal pipe diameter in all pipe greater than NPS (6) If there arelarge rocks in the material to be used
12 shall not be permitted in pipelines or mains intended for backfill, care shall be usedto prevent damage to the
to operate at 40% or more of the specified minimum coating by such means as the use of rock shield mate-
yield strength. When dents are removed, the damaged rial, or by making the initial fill with rock-free material
portion of the pipe shall be cut out asa cylinder. Insert sufficient to prevent damage.
patching and pounding out of the dents is prohibited. (e) Where flooding of the trench is done to consoli-
date the backfill, care shall be exercised to see that the
841.244 Arc Burns. Arc burns have been found to pipe is not floated from its firm bearing on the trench
cause serious stress concentration in pipelinesand shall bottom.
be prevented or eliminated in all lines intended to oper-
ate at 40% or more of the specified minimum yield 841.26 Hot Taps. All hot taps shall be installed by
strength. trained and experienced crews.
841.245 Elimination of Arc Burns. The metallur- 841.27 Precautions to Avoid Explosions of Gas-Air
gical notch caused by arc burns shall be removed by Mixtures or Uncontrolled Fires During Construction
grinding, provided the grinding does not reduce the Operations
remaining wall thickness to less than the minimum
prescribed by this Code for the conditions ofuse. ' 841.271 Operations such as gas or electric welding
and cutting with cutting torches can besafely per-
In all other cases, repair is prohibited and the por-
formed on pipelines and mains and auxiliary equip-
tion of pipe containing the arc burn must be cut out
ment, provided that they are completely full of gas or
of air thatis free from combustible material. Steps shall
be taken to prevent a mixture of gas and air at all points
'Complete removal of the metallurgical notch created by an arc burn where such operations are to be performed.
can be determined as follows: After visible evidence of the arc bum
has beenremovedby grinding, swab the ground areawitha 20% 841.272 When a pipeline or main can be kept full
solution of ammonium persulfate. A blackened spot is evidence of a
metallurgical notch and indicates that additional grinding is neces- Of gas during a Or 'peration, the
sary. ing procedures are recommended.
37
(a) Keep a slight flowof gas moving toward the (6) In cases where gas in a pipeline or main is to be
point where cutting or welding is being done. displaced with air and the rate at which air can be
(b) The gas pressure at the site of the work shall be supplied to the line is too small to make a procedure
controlled by suitable means. similar to, but the reverse of, that described in (a) above
(c) After a cut is made, immediately close all slots feasible, a slug of inert gas should be introduced to
or open ends with tape, tightly fitted canvas, or other prevent the formation of an explosive mixture at the
suitable materials. interface between gas and air. Nitrogen or carbon diox-
(d) Do not permit two openings to remain uncov- ide can be used for this purpose.
ered at the same time. This is doubly important if the (c) If a pipeline or main containing gas is to be
two openings are at different elevations. removed, the operation may be carried out in accord-
ance with para.-841.272, or theline may befirst discon-
841.273 Welding, cutting, or otheroperations that
nected from all sources of gas and then thoroughly
could be a source of ignition shall not be done on a
purged with air, water, or inert gas before any further
pipeline, main, or auxiliary apparatus that contains air,
cutting or welding is done.
if it is connected to a source of gas, unless a suitable
(d) If a gas pipeline, main, or auxiliary equipment
means has been provided to prevent the formation of an
is to be filled with air after having been in service and
explosive mixture in the work area.
there is a reasonable possibility that the inside sur-
841.274 In situations where welding orcutting faces of the facility are wetted with volatile inflamm-
must be done on facilities which are filled with air and able liquid, or if such liquids might have accumulated
connected to a source of gas, and the precautions rec- inlowplaces, purging procedures designed to meet
ommended above cannot be taken, one or more of the this situation shall be used. Steaming of the facility
following precautions, depending upon circumstances until all combustible liquids have been evaporated and
at the job, are suggested: swept out is recommended. Filling of the facility with
(a) purging of the pipe or equipment upon which an inert gas and keeping it full of such gas during the
welding or cutting is to be done with an inert gas or progress of any work that might ignite an explosive
continuous purging with air in such a manner that a mixture in the facility is an alternative recommenda-
combustible mixture does not form inthe facility at the tion. The possibility of striking staticsparks within
work area; the facility must not be overlooked as a possible
(b) testing of the atmosphere in the vicinity of the source of ignition.
zone to be heated before the work is started and at
841.276 Whenever the accidental ignition in the
intervals as thework progresses with a combustible gas
open air of gas-air mixture might be likely to cause
indicator or by other suitable means;
personal injury or property damage, precautions shall
(c) careful verification before and during the work
be taken, for example:
that the valves that isolate the work from a source of
(a) prohibit smoking and open flames in the area;
gas do not leak.
(b) install a metallic bond around the location of
cuts in gas pipes to be made by other means than cut-
841.275 Purging of Pipelines and Mains
ting torches;
(a) When a pipeline or main is to be placed in ser-
(c) take precautions to prevent static electricity
vice, the air in it shall be displaced. The following are
sparks; and
some acceptable methods.
(d) provide a fire extinguisher of appropriate size
( I ) Introduce a moderately rapid and continuous
and type, in accordance with ANSI/NFPA 10.
flow of gas into one end of the line and vent the air out
the other end. The gas flow shall be continued without
interruption until the vented gas is free of air.
841.3 Testing
After
Construction
(2) If the vent is in a location where the release of
gas into the atmosphere may cause a hazardous condi- 841.31 General Provisions. All piping systems shall
tion, then a slug of inert gas shall be introduced be- be tested after construction to therequirements of this
tween the gas and air. The gas flow shall then be con- Code except for pretested fabricated assemblies, pre-
tinued without interruption untilall of the air and inert tested tie-in sections, and tie-in connections.
gas have been removed from the facility. The vented The circumferential welds of welded tie-in connec-
gases shall be monitored and the vent closed beforeany tions not pressure tested after construction shall be
substantial quantity of combustible gas is released to inspected by radiographic orother accepted nonde-
the atmosphere. structive methods in accordance with para. 826.2.
38
Nonwelded tie-in connections not pressure tested 841.323 Other provisions of this Code notwith-
after construction shall be leak tested at not less than standing, pipelines and mains crossing highways and
the pressure available when the tie-in is placed into railroads may betested in each case in the same manner
service. and to the same pressure as the pipeline on each side
of the crossing.
841.32 Test Required to Prove Strength of Pipelines
and Mains to OperateatHoop Stresses of 30% or 841.324 Other provisions of this Code notwith-
More of the Specified Minimum Yield Strength of the standing, fabricated assemblies, including main line
Pipe valveassemblies, cross connections, river crossing
841.321 All pipelines and mains to be operated at headers, etc., installed in pipelines in Location Class 1
a hoop stress of 30% or more of the specified minimum and designed inaccordance with a design factor of 0.60
yield strength of the pipe shall be givena test for at least as required in para. 841.121, may be tested as required
2 hr to prove strength after construction and before for Location Class 1.
being placed in operation.
841.325 Notwithstandingthe limitations on air
841.322
testing imposed on para. 841.322(d), air testing may be
(a) Pipelines located in Location Class 1 Division 1
usedin Location Class 3 and Location Class 4, pro-
shall be tested hydrostatically to 1.25 times design pres-
vided that all of the following conditions apply:
sure if the maximum operating pressure is greater than
(a) the maximum hoop stress during test is less than
72% SMYS(see para. 841.36).
50% of the specified minimum yield strength in Loca-
(6) Pipelines located in Location Class 1 Division 2
tion Class 3, and less than 40% of the specified mini-
shall be tested either with air or gas to 1.1 times the
mum yield strength in Location Class 4;
maximum operating pressure or hydrostatically to at
(b) the maximum pressure at which the pipeline or
least 1.1 times the maximum operating pressure if the
main is to be operated does not exceed 80% of the
maximum operating pressure is 72% SMYS or less (see
maximum field test pressure used;
para. 841.36).
(c) the pipe involved is new pipe having a longitudi-
(c) Pipelines and mains in Location Class 2 shall be
nal joint factor E in Table 841.115A of 1.00.
tested either with air to 1.25 times the maximum oper-
ating pressure or hydrostatically to at least 1.25 times 841.326 Records. The operating company shall
the maximum operating pressure (see para. 841.36). maintain, in its file for the useful life of each pipeline
(d) Pipelines and mains in Location Class 3 and 4 and main, records showing the procedures used and the
shall be tested hydrostatically to a pressure notless data developed in establishing its maximum allowable
than 1.4 times the maximum operating pressure. This operating pressure.
requirement does not apply if, at the time the pipeline
or main is first ready for test, one or both of the follow- 841.33 Tests Required to Prove Strength for Pipe-
ing conditions exist: lines and Mains to Operate at Less Than 30% of the
( I ) the ground temperature at pipe depth is 32°F Specified Minimum Yield Strengthof the Pipe, but in
or less, or might fall to that temperature before the Excess of 100psi. Steel piping that is to operate at
hydrostatic test could be completed; or stresses less than 30% of the specified minimum yield
(2) water of satisfactory quality is not available in strength in Class 1 Locations shall at least be tested in
sufficient quantity. accordance with 841.34. In Class 2,3, and 4 Locations,
In such cases an air test to 1.1 times the maximum such piping shall be tested in accordance with Table
operating pressure shall be made, and the limitations 841.322(f),except that gas or air may be usedas thetest
on operating pressure imposed by Table 841.322(f) do medium within the maximum limits setin Table
not apply. 841.33.
(e) The test requirement given in paras. 841.322(a),
(b), (c), and (d) are summarized in Table 841.322(f) 841.34 Leak Tests for Pipelines or Mains to Operate
(see also para. 816). at 100 psi or More
cfl In selecting the test level, the designer or operat- 841.341 Each pipeline and main shall be tested
ing company should be aware of the provisions of para. after construction and before being placed in operation
854 and the relationship between test pressure and op- to demonstrate thatit does not leak. If the test indicates
erating pressure when the pipeline experiences a future that a leak exists, the leak or leaks shall be located and
increase in the number of dwellings intended for eliminated, unless it can be determined that no undue
human occupancy. hazard to public safety exists.
39
TABLE 841.322(f)
TEST REQUIREMENTS FOR PIPELINES AND MAINS TO OPERATE AT HOOP STRESSES OF 30%
OR MORE OF THE SPECIFIED MINIMUM YIELD STRENGTH OF THE PIPE
1 2 3 4 5
Maximum Allowable
Pressure Test Prescribed
Location Permissible Operating Pressure,
Class Minimum
Test Fluid Maximum the Lesser of
1 Water x m.0.p.
1.25 None t.p. + 1.25
Division 1
m.0.p. = maximum operating pressure (not necessarily the maximum allowable operating pressure)
d.p. = designpressure
t.p. = test pressure
GENERAL NOTE:
This Table brings out the relationship between test pressures and maximum allowable operating pressures subsequentt o the test. If an operating
company decidesthat the maximum operating pressure will be less than thedesign pressure, a corresponding reduction inprescribed test pressure
maybemadeas indicated in the Pressure Test Prescribed, Minimum, column.However, if this reduced test pressure is used, the maximum
operating pressure cannot later be raised t o the design pressure without retesting the line t o the t e s t pressure prescribed in the Pressure Test
Prescribed, Maximum, column. See paras. 805.214, 845.213, and 845.214.
NOTE:
(1) For exceptions, see para. 841.322(d).
TABLE 841.33 fied minimum yield strength of the pipe, and gas or
MAXIMUM HOOP STRESS PERMISSIBLE air is the test medium, a leak test shall be made at a
DURING TEST pressure in the range from 100 psi to that required to
produce a hoop stress of 20% of the minimum speci-
Class Location,
% of Specified
fied yield, or the line shall be walked while the hoop
Minimum Yield Strength stress is held at approximately 20% of the specified
minimum yield.
Test Medium 2 3 4
Air 75 50 40 841.35 Leak Tests for Pipelines and Mains to Oper-
Gas30 30 ate at Less Than 100 psi
841.351 Each pipeline, main, and related equip-
ment which will operate at less than 100 psi shall be
tested after construction and beforebeing placed in
operation to demonstrate that it does not leak.
841.342 The test procedure used shall be capable
of disclosing all leaks in the section being tested and 841.352 Gas may be usedas thetest medium at the
shall be selected after giving due consideration to the maximum pressure available in the distribution system
volumetric content of the section and to its location. at the time of the test. In this case, the soapbubble test
This requires the exercise of responsible and experi- may be used to locate leaks if all joints are accessible
enced judgement, rather than numerical precision. during the test.
841.343 In all cases where a line is to be stressed 841.353 Testing at available distribution system
in a strength proof test to 20% or more of the speci- pressures as provided for in 841.352 may not be ade-
40
quate if substantial protective coatings are used that ANSI A21.52 and ANSI/AWWA C111/A21.11. Me-
would seal a split pipe seam. If such coatings are used, chanical joints shall be assembled in accordance with
&the leak test pressure shall be 100 psi. “Notes on Installation of Mechanical Joints” in ANSI/
AWWA C111/A21.11.
841.36 Safety During Tests. All testing of pipelines (b) Other Joints. Ductile iron pipe may be furnished
and mains after construction shall be done with due
with other types of joints provided they are properly
regard for the safety of employees and thepublic during qualified and meet the appropriate provisions of this
the test. When air or gas is used, suitable steps shall be Code. Such joints shall be assembled in accordance
taken to keep persons not working on the testing opera-
with applicable standards or in accordance with the
tions out of the testing area during the period in which manufacturer’s written recommendations.
the hoop stress is first raised from 50% of the specified (c) Threaded Joints. The useof threaded joints to
minimum yield to the maximum test stress, and until couple lengths of ductile iron pipe is not recommended.
the pressure is reduced to the maximum operating pres-
sure. 842.22 Installation of Ductile Iron Pipe
842.221 Laying. Ductile iron pipe shall be laid in
accordance with the applicable field conditions de-
OTHER
842
MATERIALS
scribed in ANSI/AWWA C150/A21.50.
842.2Ductile IronPipingSystemsRequirements
842.222 Underground ductile iron pipe shall be
842.21 Ductile Iron Pipe Design installed with a minimum cover of 24 in. unless pre-
842.211 Determination of Required Wall Thick- vented by other underground structures. Where suffi-
ness. Ductile iron pipe shall be designed in accordance cient cover cannot be provided to protect the pipe from
with the methods set forth in ANSI/AWWA C150/ external loads or damage and the pipe is not designed
A2 1S O . to withstand such external loads, the pipe shall be cased
or bridged to protect the pipe.
842.212 Allowable Values of s and f. The values
of design hoop stress s and design bending stress f at 842.223JointRestraint. Suitable harnessing or
bottom of pipe, to be used in the equations given in buttressing shall be provided at point where the main
ANSVAWWA C150/A21.50, are deviates from a straight line and the thrust, if not re-
strained, would separate the joints.
s = 16,800 psi
f = 36,000 psi 842.224 Making Ductile Iron Field Joints. Duc-
tile iron pipe joints shall conform to para. 842.215 and
shall be assembled according to recognized American
842.213 Standard Ductile Iron Strength and Con- National Standards or in accordance with the manufac-
formance to ANSI A21.52. The ductile iron pipe shall turer’s written recommendations.
be (60-42-10) grade and shall conform to all require-
ments of ANSI A21.52. Grade (60-42-10) ductile iron 842.23TestingDuctileIronFieldJoints. Ductile
iron pipe joints shall be leak tested in accordance with
has the following mechanical properties:
para. 841.34 or 841.35.
Minimum tensile strength, 60,000 psi
Minimum yield strength, 42,000 psi
Mintmum elongation, 10%
842.3
Design
of
Plastic
Piping
842.214 AllowableThicknessforDuctileIron General Provisions. The design requirements of this
Pipe. The least ductile iron pipe thicknesses permitted section are intended to limit the use of plastic piping
are the lightest standard class for each nominal pipe primarily to mains and service lines in typical distribu-
size as shown in ANSI A21.52. Standard wall thick- tion systems operating at a pressure of 100 psi or less.
nesses for 250 psi maximum working pressure and stan- For other applications in Class 1 or 2 locations, plastic
dard laying conditions at several depths of cover are piping may be used within the limitations prescribed in
shown in Table 842.214. this Code.
842.215 Ductile Iron Pipe Joints 842.31 Plastic Pipe andTubing DesignFormula.
(a) Mechanical Joints. Ductile iron pipe with me- The design pressure for plastic gas piping systems or
chanical joints shall conform to the requirements of the nominal wall thickness for a given design pressure
41
TABLE 842.214
STANDARD THICKNESS SELECTION TABLE FOR DUCTILE IRON PIPE
Thickness, in.
Nominal
Depth of Cover, ft
Pipe Laying
Size Condition 21/2 3% 5 8 12 16 20 24
GENERAL NOTES:
(a) This Table is taken from ANSI A21.52.
(b) Laying Condition A flat-bottom trench without blocks, untamped backfill.
(c) Laying Condition B: flat-bottom trench without blocks, tamped backfill.
(d) The thicknesses in this Table are equal t o or in excess of those required t o withstand 250 psi working pressure.
(e) All thicknesses shown in this Table for the depths of cover indicated are adequate for trench loads including truck superloads.
(f) For the basis of design,see A N S I l A W A C150/A21.50.
(g) Thread engagement in taps for service connections and bag holes may require consideration in selecting pipe thicknesses. See Appendix of
ANSI A21.52.
42
TABLE 842.32k)
WALL THICKNESS AND STANDARD DIMENSION RATIO FOR
THERMOPLASTIC PIPE
1
4
la
1.050
1.315
1.660
0.090
0.090
0.090
0.090
0.090
0.090
0.090
0.090
0.098
r 0.090
0.097
0.123
0.095
0.119
0.151
If 1.900 0.090 0.090 0.112 0.141 0.173
2 2.375 0.091 0.113 0.140 0.176 0.216
2; 2.875 0.110 0.137 0.169 0.213 ...
3 3.500 0.135 0.167 0.206 0.259 ...
3f 4.000 0.154 0.190 0.236 0.296 ...
4 4.500 0.173 0.214 0.264 0.333 ...
5 5.563 0.224 0.265 0.328 0.413 ...
6 6.625 0.255 0.316 0.390 0.491 ...
GENERAL NOTES:
(a) Standard Dimension Ratio. The Standard Dimension Ratio System enables the user to select a number
of differentsizes of pipe for a piping system, all of which will have the same design pressure.When plastic
materials of the same design strengths are used, the same Standard Dimension Ratio may be used for
all sizes of pipe instead of calculating a value of t for each size.
(b) Wall thicknesses above line are minimums and are not a function of Standard Dimension Ratio.
(subject to the limitations in para. 842.32) shall be de- para. 842.31 is determined except that in no case shall
termined by the following formula: the temperature exceed 140°F.
(c) t for thermoplastic pipe shall not beless than
1 that shown in Table 842.32(c).
P = 2s- (' - t) x 0.32 (d) t for thermoplastic tubing shall not be less than
0.062 in.
where (e) For saddle type service connections made by
P = design pressure, psig heat fusion techniques, it may be necessary for some
S = for thermoplastic pipe and tubing, long term materials which are intended for use at high operating
hydrostatic strengthdetermined in accordance pressures to require heavier wall thicknesses than de-
with the listed specification at a temperature fined by pressure design formula for sizes 2 in. and
equal to 73"F, 100"F, 120"F, or 140°F for rein- smaller. Manufacturers of the specificpipe material
forced thermosetting plastic pipe, 11,OOO psi should be contacted for recommendations or a qualified
t = specified wall thickness, in. procedure shall be used.
D = specified outside diameter, in.
NOTE: Long termhydrostatic strength at 73°F for the plastic materi- 842.33ReinforcedThermosettingPlasticDesign
als whose specifications are incorporated by reference herein are Limitations
given in Appendix D.
(a) P for reinforced thermosetting plastic mains and
842.32 Thermoplastic Design Limitations service lines in distribution systems in all class loca-
(a) The design pressure shall not exceed 100 psig. tions, and for other applications in Class 3 and 4 loca-
(b) Thermoplastic pipe, tubing, and fittings shall not tions, shall not exceed 100 psig.
be used where the operating temperatures of the mate- (b) Reinforced thermosetting plastic pipe and fit-
rials will be: tings shall not be used where operating temperatures
( I ) below-20°F; or will be below -20°F or above 150°F.
(2) above the temperature at which the long-term (c) t for reinforced thermosetting plastic pipe shall
hydrostatic strength used in the design formula under not be less than that shown in Table 842.33(c).
43
TABLE 842.33k) 842.39 Plastic Pipe and Tubing Joints and Connec-
DIAMETER AND WALL THICKNESS FOR tions
REINFORCED THERMOSETTING PLASTIC PIPE 842.391 General Provisions. Plastic pipe, tubing,
Minimum
and fittings maybe joined by the solvent cement
Nominal Pipe Outside Diameter, Thickness, method, adhesive method, heat-fusion method, or by
in. Size in. means of compression couplings or flanges. The
method used must be compatible with the materials
0.060 2 2.375 being joined. The recommendations of the manufac-
3 3.500 0.060
4 4.500 0.070 turer shall be considered when determining the method
6 6.625 0.100 to be used.
842.36 Protection From Hazards. Plastic piping 842.393 Solvent Cement Joints
shall conform to the applicable provisions of 841.13. (a) Square cut ends free of burrs are required for a
proper socket joint.
842.37 Cover and Casing Requirements Under Rail- (b) Proper fit betweenthe pipe or tubing and mating
roads, Roads, Streets, or Highways. Plastic piping socket or sleeve is essential to a good joint. Sound joints
shall conform to the applicable requirements of paras. cannot normally be made between loose or very tight
841.141 and 841.144. Where plastic piping must be fitting components.
cased or bridged suitable precautions shall be taken to (c) The mating surfaces must be clean, dry, and free
prevent crushing or shearing of the piping. (See also of material which might be deterimental to the joint.
para. 842.43.) (d) Solvent cements which conform to ASTM D
25 13 and are recommended by the pipe or tubing
842.38 Clearance Between Mains and OtherUnder- manufacturer shall be used to make cemented joints.
ground Structures. Plastic piping shall conform to the (e) A uniform coating of the solvent cement is re-
applicable provisions of para. 841.143. Sufficient clear- quired on both mating surfaces. After the jointis made,
ance shall be maintained between plastic piping and excess cement shall be removedfrom the outside of the
steam, hot water, or power lines and other sources of joint. The jointshall not be disturbed until it has prop-
heat to prevent operating temperatures in excess of the erly set.
limitations of para. 842.32(b) or 842.33(b). fl The solvent cement and piping components to be
44
joined may be conditioned prior to assembly by warm- (b) The tubular stiffener required to reinforce the
ing if done in accordance with the manufacturer’s rec- end of the pipe or tubing shall extend at least under that
ommendations. section of the pipe being compressed by the gasket or
(g) A solvent cement joint shall not be heated to gripping material. The stiffener shall be free of rough
accelerate the setting of the cement. or sharp edges and shall not be a force fit in the pipe
(h) Safety requirements in Appendix A of ASTM D or tube. Split tubular fittings shall not be used.
2513 shall be followed when solvent cements are used. (c) Since pull-out resistance of compression type
fittings varies with type and size, all mechanical joints
842.394 Heat-Fusion Joints
shall be designed and installed to effectively sustain the
(a) Sound butt heat-fusion joints require the use of
longitudinal pull-out forces caused by contraction of
a jointing device that holds the heater element square
the piping or by maximum anticipated external load-
to the ends of the piping, can compress the heated ends
ing. The installation shall be designed and made to
together, and holds the piping in proper alignment
minimize these forces as follows.
while the plastic hardens.
( I ) In the case of direct burial when the pipe is
(b) Sound socket heat-fusion joints require the use
sufficiently flexible,the pipe may be snaked in the ditch.
of a jointing device that heats the mating surfaces of the
(2) In the case of pipe installed by insertion in
joint uniformly and simultaneously to essentially the
casing, the pipe shall be pushed rather than pulled into
same temperature. The completed joint must not be
place so as to place it in compression rather than ten-
disturbed until properly set.
sion.
(c) Care must be used in the heating operation to
(3) Allowance shall be made for thermal expan-
prevent damage to the plastic material from overheat-
sion and contraction due to seasonal changes in tem-
ing or having the material not sufficiently heated to
perature of installed pipe. The importance of this allow-
assure a sound joint. Direct application of heat with a
ance increases as the length of the installation
torch or other open flame is prohibited.
increases. Such allowance is of paramount importance
(dl When connecting saddle-type fittings to pipe
when the plastic pipe is used for insertion renewal in-
NPS 2 and smaller, see para. 842.32(e) to minimize the
side another pipe, because it is not restrained by earth
possibility of failures.
loading. This allowance may be accomplished by ap-
842.395 Adhesive Joints propriate combinations of:
(a) Adhesives which conform to ASTM D 25 17 (a) offsets;
and are recommended by the pipe, tubing, or fitting (b) anchoring;
manufacturer shall be used to make adhesive bonded (c) aligning the pipe and fitting;
joints. (d) in the case of compression fittings by the use
(b) When dissimilar materials are bonded together, of long-style types and placing the pipe in slight axial
a thorough investigation shall be made to determine compression;
that the materials and adhesive used are compatible (e) expansion-contraction devices; or
with each other. cfl fittings designed to prevent pull-out.
(c) An adhesive bonded joint may be heated in ac- Typical coefficients of thermal expansion, which may
cordance with the pipe manufacturer’s recommenda- be used to make calculations, are givenin Table
tion in order to accelerate cure. 842.396(c).
(d) Provision shall be made to clamp or otherwise
prevent the joined materials from moving until the ad-
hesive is properly set.
842.4 Installation of PlasticPiping
842.396 Mechanical Joints *
(a) When compression type mechanical joints are 842.41 Construction Specifications. All construction
used, the elastomeric gasket material in the fitting shall work performed on piping systems in accordance with
be compatible with the plastic, i.e., the plastic and the the requirements of this Code shall be done undercon-
elastomer shall not cause deterioration in one another’s struction specifications.The constructionspecifications
chemical and physical properties over a long period. shall cover the requirements of this Code, and shall be
in sufficient detail to assure proper installation.
’Refer to the current editions of the American GasAssmiation 842.42 Inspection and Handling Provisions. Plastic
Plastic Pipe Manualfor Gas Service, ASTM D 2513, the ASME
Guide for Gas Transmission and Distribution Piping Systems, and piping components are to damage by
technical publications of plastic pipeand fitting manufacturkrs. handling. Gouges, cuts, kinks, or otherforms of dam-
45
46
(d) When long sections of piping that have been volume of water changing to ice will be insufficient to
assembled alongside the ditch arelowered in, careshall crush the carrier pipe;
be exercised to avoid any strains which may overstress (2) provide adequate draining for the casing; or
or buckle the piping or impose excessive stress on the (3) insert filler such as foam into the annulus be-
joints. tween the casing and the carrier pipe.
(e) Backfilling shall be performed in amanner to
842.44 Bendsand Branches. Changes in direction of
provide firm support around the piping. The material
plastic piping may be made with bends, tees, or elbows
used for backfilling shall be free of large rocks, pieces
under the following limitations.
of pavement, or any other materials that might damage
(a) Plastic pipe and tubing may be deflected to a
the pipe. radius not less than theminimum recommended by the
(JlWhere flooding of the trench is done to consoli-
manufacturer for the kind, type, grade, wall thickness,
date the backfill, care shall be exercised to see that the
and diameter of the particular plastic used.
piping is not floated from its firm bearing on the trench
(b) The bends shall be free of buckles, cracks, or
bottom. other evidence of damage.
(g) An electrically conductive wire should be in- (c) Changes in direction thatcannot be made in
stalled with the piping to facilitate locating it with an accordance with (a) above shall be made with elbow-
electronic pipe locator. Other suitable material may be type fittings.
employed. (d) Miter bends are not permitted.
(e) Branch connections shall be made only with
socket-type tees or other suitable fittings specifically
842.432 Insertion of Casing designed for the purpose.
(a) The casing pipe shall be prepared to the extent
necessary to remove any sharp edges, projections, or 842.45 FieldRepairs of Gouges and Grooves. Injuri-
abrasive material which could damage the plastic dur- ous gouges or grooves shall be removed by cutting out
ing and after insertion. and replacing the damaged portion as a cylinder or
(b) Plastic pipe or tubing shall be inserted into the repaired in accordance with para. 852.7.
casing pipe in such a manner so as toprotect the plastic 842.46 Hot Taps. All hot taps shall be installed by
during the installation. The leading end of the plastic trained and experienced crews.
shall be closed before insertion. Care shall be taken to
prevent the plastic piping from bearing on the end of 842.47 Purging.Purging of plastic mains and service
the casing. lines shall be done in accordance with the applicable
(c) That portion of the plastic piping exposed due to provisions of paras. 841.275 and 841.276.
the removal of a section of the casing pipe shall be of
sufficient strength to withstand the anticipatedexternal 842.5Testing Plastic PipingAfterConstruction
loading, or it shall be protected with a suitable bridging
842.51 General Provisions. All plastic piping shall be
piece capable of withstanding the anticipated external
pressure tested afterconstructionand before being
loading.
placed in operation to prove its strength and to demon-
(d) That portion of the plastic piping which spans
strate that it does not leak.
disturbedearth shall be adequately protected by a
Tie-Zns. Because it is sometimes necessary to divide
bridging piece or other means from crushing or shear-
a pipeline or main into sections for testing, and to
ing from external loading or settling of backfill.
install test heads, connecting piping, and other neces-
(e) The piping shall be installed to provide for possi-
sary appurtenances, itis not required that the tie-in
ble contraction. Cooling may be necessary before the
sections of piping be tested. The tie-in joints, however,
last connection is made when the pipe has been in-
shall be tested for leaks.
stalled in hot or warm weather. (See para. 842.396.)
cfl If water accumulates between the casing and the 842.52 Test Requirements
carrier pipe where it may be subjected to freezing tem- (a) The test procedure used, including the duration
peratures, the carrier pipe can be constricted to the of the test, shall be capable of disclosing all leaks in the
point where the capacity is affected or the pipe wall section being tested and shall be selected after giving
could be crushed and leak. To avoid this, one or more due consideration to the volumetric content of the sec-
of the following steps shall be taken: tion and its location.
( I ) the annulus between the carrier pipe and cas- (b) Thermoplastic piping shall not be tested at mate-
ing shall be kept to a minimum so that the increased rial temperatures above 140"F, and reinforced thermo-
47
setting plastic piping shall not be tested at material type coupling or a brazed or soldered lap joint. The
temperatures above 150°F. The duration of the test of filler material used for brazing shall be a copper-phos-
thermoplastic piping above l W F , however, shall not phorous alloy or silver base alloy. Butt welds are not
exceed 96 hr. permissible for joining copper pipe or tubing. Copper
(c) Sufficient time for joints to “set” properly must tubing shall not be threaded, but copper pipe with wall
be allowed before the test is initiated. thickness equivalent to the comparablesize of Schedule
(d) Plastic pipelines and mains silall be tested at a 40 steel pipe may be threaded and used for connecting
pressure not less than 1.5 times the maximum operat- screw fittings or valves.
ing pressure or 50 psig, whichever is greater, except
842.615ProtectionAgainstGalvanicCorrosion.
that:
Provision shall be made to prevent harmful galvanic
(2) the test pressure for reinforced thermosetting
action where copper is connected underground to steel
plastic piping shall not exceed 3.0 times the design
[see para. 862.1 14(a)].
pressure of the pipe;
(2) the test pressure for thermoplastic piping shall 842.62 Testing of Copper Mains After Construction
not exceed 3.0 times the design pressure of the pipe at 842.621 All copper mains shall be tested after con-
temperatures upto andincluding 100°F or 2.0 times the struction in accordance with the provisions of para.
design pressure at temperatures exceeding 100°F. 841.35.
(e) Gas, air, or water may be used as the test me-
dium.
COMPRESSOR
843 STATIONS
842.53 Safety During Tests. All testing after con-
struction shall be done with due regard for the safety 843.1
Compressor
Station
Design
of employees and the public during the test. 843.11 Locationof Compressor Building. Except for
offshore pipelines, the main compressor building for
842.6 Copper
Mains gas compressor stations shouldbe located at such clear
distances from adjacent property not under control of
842.61 Design of Copper Mains the company as tominimize the hazard of communica-
842.611 When used for gas mains, copper pipe or tion of fire to the compressor building from structures
tubing shall conform to the following requirements. on adjacent property. Sufficient open space should be
(a) Copper pipe or tubing shall not beused for provided around the building to permit the free move-
mains where the pressure exceeds 100 psig. ment of firefighting equipment.
(b) Copper pipe or tubing shall not beused for
843.12 Building Construction. All compressor sta-
mains where the gas carried contains more than an
tion buildings which house gas piping in sizes larger
average of 0.3 grains of hydrogen sulfide per 100 stan-
than NPS 2, or equipment handling gas (except equip-
dard cubic feet of gas. This is equivalent to a trace as
ment for domestic purposes) shall be constructed of
determined by the lead acetate test. (See para. 863.4.)
noncombustible or limited combustible materials as de-
(c) Copper tubing or pipe for mains shall have a
fined in ANSI/NFPA 220.
minimum wall thickness of 0.065 in. and shall be hard
drawn. 843.13 Exits. A minimum of two exits shall be pro-
(d) Copper pipe or tubing shall not beused for vided for each operating floor of a main compressor
mains where strain or external loading may damage the building, basements, and any elevated walkway or plat-
piping. form 10 ft or more above ground or floor level. Individ-
ual engine catwalks shall not require two exits. Exits of
842.612 Valves in Copper Piping.Valves installed each such building may be fixedladders, stairways, etc.
in copper lines may be made of any suitable material The maximum distance from any point on an operating
permitted by this Code. floor to an exit shall not exceed 75 ft, measured along
842.613Fittings inCopperPiping. It is recom- the center line ofaisles or walkways. Exits shall be
mended that fittings in copper piping and exposed to unobstructed doorways located so as toprovide a con-
the soil, such as service tees, pressure control fittings, venient possibility of escape and shall provide unob-
etc., be made of bronze, copper, or brass. structed passage to a place of safety. Door latches shall
be of a type which can be readily opened from the inside
842.614 Joints in Copper Pipe and Tubing. Cop- without a key. All swinging doors located in an exterior
per pipe shall be joined by using either a compression wall shall swing outward.
48
843.14 Fenced Areas. Any fence which may hamper 843.42FireProtection. Fire protection facilities
or prevent escape of persons from the vicinity of a should be provided in accordance with the American
compressor station in an emergency shall be provided Insurance Association’s recommendations. If the fire
with a minimum oftwo gates. These gates shall be pumps are a partof such facilities, their operation shall
located so as to provide a convenient opportunity for not be affected by emergency shutdown facilities.
escape to a place of safety. Any such gates located
within 200 ft of any compressor plant building shall 843.43 Safety Devices
open outward and shall be unlocked (or capable of 843.431 Emergency Shutdown Facilities
being opened from the inside without a key) when the (a) Each transmission compressor station shall be
area within the enclosure is occupied. Alternatively, provided with an emergency shutdown system by
other facilities affording a similarly convenient exit means of which the gas can be blocked out of the
from the area may be provided. station and the station gas piping blown down. Opera-
tion of the emergency shutdown system also shall cause
the shutdown of all gas compressing equipment and all
843.2
Electrical
Facilities gas fired equipment, and shall de-energize the electrical
All electrical equipment and wiring installed in gas facilities located in the vicinity of gas headers and in the
compressor room, except those that provide emergency
transmission and distribution compressor stations shall
lighting for personnel protection and those that are
conform to the requirements of ANSI/NFPA 70, inso-
far as the equipment commercially available permits. necessary for protection of equipment. The emergency
Electrical installations in hazardous locations as de- shutdown system shall be operable from any one of at
fined in ANSI/NFPA 70 and which are to remain in least two locations outside the gas area of the station,
operation during compressor station emergency shut- preferably near exit gates in the station fence, but not
down as provided in para. 843.43l(a) shall be designed more than 500 ft from the limits of the stations. Blow-
to conform to ANSI/NFPA 70 for Class I, Division I down piping shall extend to a location where the dis-
requirements. charge of gas is not likely to create a hazard to the
compressor station or surrounding area. Unattended
field compressor stations of lo00 hp and less are ex-
843.4 Compressor Station Equipment cluded from the provisions of this paragraph.
(b) Each compressor station supplying gas directly
843.41 Gas Treating Facilities to a distribution system shall be provided with emer-
843.411 LiquidRemoval. When condensable va- gency shutdown facilities located outside the com-
pors are present in the gas stream in sufficient quantity pressor station buildings by means of which all gas
to liquefy under the anticipated pressure and tempera- can beblocked out of the station, provided there is
ture conditions, the suction stream to each stage of anotheradequate source of gas for the distribution
compression (or to each unit for centrifugal compres- system. These shutdown facilities can be either auto-
sors) shall be protected against the introduction of dan- matic or manually operated as local conditions desig-
gerous quantities of entrained liquids into thecompres- nate. When no other gas source is available, no shut-
sor. Every liquid separator used for this purpose shall down facilities shall be installed that might function
be provided with manually operated facilities for re- at the wrong time and cause an outage on the distri-
moval of liquids therefrom. In addition, automatic liq- bution system.
uid removal facilities or an automaticcompressor shut-
down device or a high liquid level alarm shall be used 843.432 Engine Overspeed Stops. Every compres-
where slugs of liquid might be carried into thecompres- sor prime mover, except electrical induction or syn-
sors. chronous motors, shall be provided with an automatic
device which is designed to shut down the unit before
843.412 LiquidRemovalEquipment. Liquid the speed of the prime mover or of the driven unit
separators, unless constructed of pipe and fittings and exceeds the maximum safe speed of either as estab-
no internal welding is used, shall be manufactured in lished by the respective manufacturers.
accordance with Section VI11 of the ASME Boiler and
Pressure Vessel Code. Liquid separators when con- 843.44 Pressure Limiting Requirements in Compres-
structed of pipe and fittings without internal welding sor Stations
shall be in accordance with Location Class 4 require- 843.441 Pressure relief or other suitable protective
ments. devices of sufficient capacity and sensitivity shall be
49
installed and maintained to assure that the maximum 843.5 Compressor Station
Piping
allowable operating pressure of the station piping and
843.51 Gas Piping. The following are general provi-
equipment is not exceeded by more than 10%.
sions applicable to all gas piping.
843.442 A pressure relief valve or pressure lim-
843.511 Specifications for Gas Piping. All com-
iting device, such as a pressure switch or unloading
pressor station gas piping, other than instrument, con-
device, shall be installed in the discharge line of each
trol and sample piping, to andincluding connections to
positive displacement transmission compressor be-
the main pipeline, shall be ofsteel and shall use a design
tween the gas compressor and the first discharge block
factor F per Table 841.114B. Valveshaving shell com-
valve. If a pressure relief valve is the primary overpro-
tection device, then therelieving capacity shall be equal ponents made of ductile iron may be used subject to the
limitations in para. 831.1 l(b).
to orgreater than thecapacity of the compressor. If the
relief valves on the compressor do not prevent the pos- 843.512 Installationof Gas Piping.The provisions
sibility of overpressuring the pipeline as specified in of para. 841.2 shall apply where appropriateto gas
para. 845, a relieving or pressure limiting device shall piping in compressor stations.
be installed on the pipeline to prevent it from being
overpressured beyond the limits prescribed by this 843.513Testing of GasPiping. All gas piping
Code. within a compressor station shall be tested after in-
stallation in accordance with the provisions of para.
843.443 Vent lines provided to exhaust the gas 841.3 for pipelines and mains in Class 3 locations, ex-
from the pressure relief valves to atmosphere shall be cept that small additions to operatingstations need
extended to a location where the gas may be discharged not be tested where operating conditions make it im-
without undue hazard. Vent lines shall have sufficient practical to test.
capacity so that they will not inhibit the performance
of the relief valve. 843.514 Identification of Valves and Piping. All
emergency valves and controls shall be identified by
843.45 Fuel Gas Control. An automatic device de- signs. All important gas pressure piping shall be identi-
signed to shut off the fuel gas when the engine stops fied by signs or color codes as to their function.
shall be provided on each gas engine operating with
pressure gas injection. The engine distribution mani- 843.52 Fuel Gas Piping. The following are specific
fold shall be automatically vented simultaneously. provisions applicable to fuel gas piping only.
843.46Cooling and LubricationFailures. All gas 843.521 All fuel gas lines within a compressor
compressor units shall be equipped with shutdown or station, serving the various buildings and residential
alarm devices to operate in the event of inadequate areas, shall be provided with master shutoff valves
cooling or lubrication of the units. located outside of any building or residential area.
843.47 Explosion Prevention 843.522 The pressure regulating facilities for the
843.471 Mufflers. The external shell of mufflers fuel gas system for a compressor station shall be pro-
for engines using gas as fuel shall be designed in accord- vided with pressure-limiting devices to prevent the nor-
ance with good engineering practice and shall be con- mal operating pressure of the system from being ex-
structed of ductile materials. It is recommended that all ceeded by more than 25%, or the maximum allowable
compartments of the mufflerbe manufactured with operating pressure by more than 10%.
vent slots or holes in the baffles to prevent gas from
being trapped in the muffler. 843.523 Suitable provision shall be made to pre-
vent fuel gas from entering the power cylinders of an
843.472 Building Ventilation.Ventilation shall be engine and actuating moving parts while work is in
ampleto assure that employees are not endangered progress on the engine or on equipment driven by the
under normal operating conditions (or such abnormal engine.
conditions as a blown gasket, packing gland, etc.) by
accumulations of hazardous concentrations offlam- 843.524 All fuel gas used for domestic purposes at
mable or noxious vapors or gasesin rooms, sumps, a compressor station which has an insufficient odor of
attics, pits, or similarly enclosed places, or in any por- its own to serve as a warning in the event of its escape
tion thereof. shall be odorized as prescribed in para. 871.
50
51
(c) Minimum Clearance Between Pipe Containers or installation shall be made, and no damaged bottleshall
Bottles. The minimum distance in inches between pipe be used.
containers or bottles shall be determined by the follow- (e) Such bottles and connecting piping shall be
ing formula: tested for tightness after installation using air or gas at
a pressure of 50 psi above the maximum operating
c = - 3DPF pressure.
loo0
844.5 General ProvisionsApplicabletoBoth
where
Pipe-Type and Bottle-Type Holders
C = minimum clearance between pipe containers
or bottles, in. (a) No gas containing more than 0.1 grain of hydro-
D = outside diameter of pipe container or bottle, gen sulfide per 1 0 0 standard cubic feet shall be stored
in. when free water is present or anticipated without em-
P = maximum allowable operating pressure, psig ploying suitable means to identify, mitigate, or prevent
F = design factor [see para. 844.32(a)] detrimental internal corrosion (see para. 863).
(d) Pipe containers shall be buried with the top of (b) Provision shall be made to prevent the formation
each container not less than 24 in. below the ground or accumulation of liquids in the holder, connecting
surface. piping, and auxiliary equipment that might cause cor-
(e) Bottles shall be buried with the top of each con- rosion or might interfere with the safe operation of the
tainer below the normal frost line but in no case closer storage equipment.
than 24 in. to the surface. Relief valves shall be installed in accordance with
Pipe-type holders shall be tested in accordance provisions of this Code which will have relieving capac-
with the provisions of para. 841.32 for a pipeline ity adequate to limit the pressure imposed on the filling
located in the same class location as the holder site, line and thereby on the storage holder to 1 0 0 % of the
provided, however, that in any case where the test pres- design pressure of the holder, or to thatpressure which
sure will produce a hoop stress of 80% or more of the produces a hoop stress of 75% of the specified mini-
specified minimum yield strength of the pipe, water mum yield strength of the steel, whichever is the lesser.
shall be used as the test medium.
845
CONTROL AND LIMITING OF GAS
844.4 Special
Provisions Applicable to PRESSURE
Bottle-Type Holders Only
845.1Basic Requirement for ProtectionAgainst
844.41 A bottle-type holder may be manufactured Accidental Overpressuring
from steel which is not weldable under field conditions,
subject to all of the following limitations. Every pipeline, main, distribution system, customer’s
(a) Bottle-type holders made from alloy steel shall meter and connected facilities, compressor station,
meet the chemical and tensile requirements for the vari- pipe-type holder, bottle-type holder, container fab-
ous grades of steel in ASTM A 372. ricated from pipe and fittings, and all special equipment,
(6) In no case shall the ratio of actual yield strength ifconnected to a compressor or toa gas source where the
to actual tensile strength exceed 0.85. failure of pressure control or other causes might result
(c) Welding shall not be performed on such bottles in a pressure which would exceedthe maximum allowa-
after they have been heat treated and/or stress relieved, ble operating pressure of the facility (refer to para.
except that it shall be permissible to attach small cop- 805.214), shall be equipped with suitable pressure re-
per wires to thesmall diameterportion of the bottleend lieving or pressure limiting devices. Special provisions
closure for cathodicprotection purposes using a local- for service regulators are set forth in para. 845.24.
ized thermit welding process. (Charge not to exceed 15
g.) 845.2 ControlandLimiting of GasPressure
(d) Such bottles shall be given a hydrostatic test in
the mill and need not be retested hydrostatically at the 845.21ControlandLimiting of GasPressure in
time of installation. The mill test pressure shall not be Holders, Pipelines, andAll Facilities ThatMightat
less than that required to produce a hoop stress equal Times Be Bottle Tight
to 85% of the specified minimum yield strength of the 845.212 Suitable types of protective devices to pre-
steel. Careful inspection of the bottles at the time of vent overpressuring of such facilities include:
52
(a) spring-loaded relief valves of types meeting the 845.214 Qualification of a Steel Pipelineor Main
provisions of BPV Code, Section VIII; to Establish the MAOP
(6) pilot-loaded back-pressure regulators used as re- (a) Pipelines Operating at I O 0 psig or More. This
lief valves, so designed that failure of the pilot system paragraph applies to existing natural gas pipelines or to
or control lines will cause the regulator to open; existing pipelines being converted to naturalgas service
(c) rupture disks of the type meeting the provisions where one or more factors of the steel pipe design for-
of BPV Code, Section VIII, Division 1. mula (see para. 841.1 1) isunknown, and the pipeline is
to be operated at 100psig or more. The maximum
845.213 Maximum Allowable Operating Pressure allowable operating pressure shall be determined by
for Steel or Plastic Pipelines or Mains. This pressure hydrostatic testing of the pipeline.
isby definition the maximum operating pressure to ( I ) The maximum allowable operating pressure
which the pipeline or main may besubjected in accord- shall be limited to the pressure obtained by dividing the
ance with the requirements of this Code. For a pipeline pressure to which the pipeline or main is tested by the
or main, the maximum allowable operating pressure appropriate factor for the Location Class involved as
shall not exceed the lesser of either: follows:
(a) the design pressure (defined in para. 805.212) of
the weakest element of the pipeline or main. Assuming Location Maximum Allowable
that all fittings, valves, and other accessories in the line Class Pressure
Operating
1 Division 1 Test pressure
have an adequate pressure rating, the maximum allow-
1.25
able operating pressure of a pipeline or main shall be
the design pressure determined in accordance with 1 Division 2 Test pressure
para. 841.1 1 for steel or para. 842.3 for plastic; or 1.39
(b) the pressure obtained by dividing the pressure to
2 Testpressure
which the pipeline or main is tested after construction 1.67
by the appropriate factor for the Location Class in-
volved, as follows: 3 Test pressure
2.0
Pressure
Location Pressure
Class For Steel ’ For Plastic 4 Test pressure
1 Division 1 Test pressure N.A. 2.5
1.25
(2) The test pressure to be used in the maximum
1 Division 2 Test pressure Test pressure
allowable operating pressure calculation shall be the
1.10 1S O
test pressure obtained at the high elevation point of the
2 Test pressure Test pressure minimum strength test section and shall not be higher
1.25 1S O than the pressure required to produce a stress equal to
the yield strength as determined by testing. Only the
3 Test pressure’ Testpressure first test to yield can be used to determine maximum
1.40 1.50
allowable operating pressure.
4 Test pressure’ Test pressure (3) Records of hydrostatic pressure tests and line
1.40 1.50 repairs shall be preserved as long as the facilities in-
volved remain in service.
NOTES: (4) Determine that all valves, flanges, and other
(1) See para. 845.214 fortest factors applicable to conversion of pressure rated components have adequate ratings.
pipelines with unknown factors.
(2) Other factors should beusedif the line was tested under the (5) While the maximum pressure of a test utilized
specla1 conditions described in paras. 841.322(d), 841.325, and to establish the maximum allowable working pressure
841.33. In such cases, use factors thatare consistent with the is not limited by this paragraph except by (2) above,
applicable requirements of these sections.
due caution should be exercised in selecting the maxi-
(c) the maximum safe pressure to which the pipeline mum test pressure.
or main should be subjected based on its operating and (6) Pipelines Operating at Less than I O 0 psig. This
maintenance history (for pipelines, see para. 851.1); paragraph applies to existing natural gas pipelines or to
(dl when service lines are connected to the pipeline existing pipelines beingconverted to naturalgas service
or main, the limitations set forth in paras. 845.223(b) where one or more factors of the steel pipe design for-
and (e). mula (see para. 841.1 1) isunknown, and the pipeline is
53
to be operated at less than 100psig. The maximum shall be provided to prevent accidental overpressuring
allowable operating pressure shall be determined by of a high-pressure distribution system.
pressure testing the pipeline. Suitable types of protective devices to prevent over-
( I ) The maximum allowable operating pressure pressuring of high pressure distribution systems in-
shall be limited to thepressure obtained by dividing the clude:
pressure to which the pipeline or main is tested by the (a) reliefvalves as prescribed in para. 845.212(a)
appropriate factor for the Location Class involved as and (b);
follows: fb) weight-loaded relief valves;
(c) a monitoring regulator installed in series with
Location Allowable
Maximum the primary pressure regulator;
Class Operating Pressure (d) a series regulator installed upstream from the
1 Pressure Test primary regulator, and set to limit the pressure on the
1.25 inlet of the primaryregulator continuously to the maxi-
2 Test Pressure
mum allowable operating pressure of the distribution
1.25 system or less;
(e) anautomatic shutoff device installed in series
3 Test Pressure with the primary pressure regulator and set to shut off
1.5 when the pressure on the distribution system reaches
4 Test Pressure
the maximum allowable operating pressure or less.
1.5 This device must remain closed until manually reset. It
should not be usedwhere it might cause an interruption
(2) The test pressure to be used in the maximum in service to a large number of customers.
allowable operating pressure calculation shall be the 67 spring-loaded, diaphragm type relief valves.
test pressure obtained at thehigh elevation point of the
minimum strength test section and shall not be higher 845.223 Maximum Allowable Operating Pressure
than the pressure required to produce a stress equal to for High-pressure Distribution Systems.This pressure
the yield strength as determined by testing. Only the shall be the maximum pressure to which the system can
first test to yield can be used to determine maximum be subjected in accordance with the requirements of
allowable operating pressure. this Code. It shall not exceed:
(3) Records of pressure tests and line repairs shall (u) the design pressure of the weakest element of the
be preserved as long as thefacilities involved remain in system as defined in para. 805.212;
service. (b) 60 psig if the service lines in the system are not
(4) Determine that all valves, flanges, and other equipped with series regulators or other pressure lim-
pressure rated components have adequate ratings. iting devices as prescribed in para. 845.243;
(5) While the maximum pressure of a test utilized (c) 25 psig in cast iron systems having caulked bell
to establish the maximum allowable working pressure is and spigot joints, which have not been equipped with
not limited by this paragraph except by (2) above, due bell joint clamps or other effective leak sealing
caution should be exercised in selecting the maximum methods;
test pressure. (d) the pressure limits to which any joint could be
subjected without possibility of parting;
845.22 ControlandLimiting of GasPressurein (e) 2 psigin high-pressure distribution systems
High-pressure Steel, Ductile Iron, Cast Iron, or Plas- equipped with service regulators not meeting the re-
tic Distribution Systems quirements of para. 845.241 and which do not have an
845.221 Each high-pressure distribution system or overpressure protective device as required in para.
main, supplied from a sourceof gas which is at a higher 845.242;
pressure than the maximum allowable operating pres- 67 the maximum safe pressure to which the system
sure for the system, shall be equipped with pressure should be subjected, based on its operation and mainte-
regulating devices of adequate capacity and designed to nance history.
meet the pressure, load, and other service conditions 845.23 ControlandLimiting of GasPressure in
under which they will operate or to which they may be Low-Pressure Distribution Systems
subjected.
845.231 Each low-pressure distribution system or
845.222 In addition to the pressure-regulating de- low pressure main supplied from a gas source which is
vices prescribed in para. 845.221, a suitable method at a higher pressure than the maximum allowable oper-
54
ating pressure for the low-pressure system, shall be (5) At bends or offsets in coupled or bell and
equipped with pressure regulating devices of adequate spigot pipe, reinforce or replace anchorages determined
capacity, designed to meet the pressure, load, and other to be inadequate for the higher pressures.
service conditions under which they will have to oper- (c) The pressure in the system being converted shall
ate. be increased by steps, with a period to check the effect
of the previous increase before making the next in-
845.232 In addition to the pressure-regulating de- crease. The desirable magnitude of each increase and
vices prescribed in para. 845.23l, a suitabledevice shall the length of the check period will vary depending upon
be provided to prevent accidental overpressuring. Suit- conditions. The objective of this procedure is to afford
able types of protective devices to prevent overpressur- an opportunity to discover any unknown open and un-
ing of low-pressure distribution systems include: regulated connections to adjacent low-pressure systems
(a) a liquid seal relief device that can be set to open or to individual customers before excessive pressures
accurately and consistently at the desired pressure; are reached.
(b) weight-loaded relief valves;
(c) an automatic shutoff device as described in para. 845.24 Control and Limiting of the Pressure of Gas
845.222(e); Delivered to Domestic, Small Commercial, and Small
(d) a pilot-loaded, back-pressureregulatorasde- IndustrialCustomersFrom High-pressure Distribu-
scribed in para. 845.212(b); tion Systems
(e) amonitoringregulatoras described in para. NOTE: When the pressure of the gas and the demand by the cus-
845.222(c); tomer are greater than that applicable under the provisionsof para.
cfl a series regulator as described in para. 845.24, the requirements for control and limiting of the pressure of
gas delivered are included in para. 845.1.
845.222(d).
845.241 If the maximum allowable operating pres-
845.233 Maximum Allowable Operating Pressure sure of the distribution system is 60 psig or less and a
forLow-PressureDistribution Systems. The maxi- service regulator having the characteristicslisted below
mum allowable operating pressure for a low-pressure is used, no other pressure-limiting device is required:
distribution system shall not exceed either: (a) a pressure regulator capable of reducing distri-
(a) a pressure which would cause the unsafe opera- bution line pressure, psi, to pressures recommended for
tion of any connected and properly adjusted low-pres- household appliances, inches of water column;
sure gas burning equipment; or (b) a single port valve with orifice diameter no
(b) a pressure of 2 psig. greater than that recommended by the manufacturer
for the maximum gas pressure at the regulator inlet;
845.234 Conversion of Low-Pressure Distribution
(c) the valve seat shall be made of resilient mate-
Systems to High-pressure Distribution Systems
rial designed to withstand abrasion of the gas, im-
(u) Before converting a low-pressure distribution
purities in gas, and cutting by the valve, and to resist
system to a high-pressure distribution system, it is re-
permanent deformation when it is pressed against the
quired that the following factors be considered:
valve port;
( I ) the design of the system including kinds of
(d) pipe connections to the regulator shall not ex-
material and equipment used;
ceed 2 in. in diameter;
(2) past maintenance records including results of
(e) the regulator must beof a type that is capable
any previous leakage surveys.
under normal operating conditions of regulating the
(b) Before increasing the pressure the following
downstream pressure within the necessary limits of ac-
steps(not necessarily in sequence shown) shall be
curacy and of limiting the buildup of pressure under
taken.
no-flow conditions to no more than 50%over the nor-
( I ) Make a leakage survey and repair leaks found.
mal discharge pressure maintained under flow condi-
(2) Reinforce or replace parts of the system found
tions;
to be inadequate for the higher operating pressures.
cf) a self-contained service regulator with no exter-
(3) Install a service regulator on each service line,
nal static or control lines.
and test each regulator to determine that it is function-
ing. In some cases it may be necessary to raise the 845.242 If the maximum allowable operating pres-
pressure slightly to permit proper operation of the ser- sure of the distribution system is 60 psig or less, and a
vice regulator. service regulator not having all of the characteristics
(4) Isolate the system from adjacent low-pressure listed in para. 845.241 is used, or if the gas contains
systems. materials that seriously interfere with the operation of
55
service regulators, suitable protectice devices shall be tion of the device will not normally be impaired by
installed to prevent unsafe overpressuring of the cus- corrosion of external parts by the atmosphere or inter-
tomer’s appliances, should the service regulator fail. nal parts by gas;
Some of the suitable types of protective devices to pre- (b) have valves and valve seats that aredesigned not
vent overpressuring of the customers’ appliances are: to stick in a position that will make the device inopera-
(a) a monitoring regulator; tive and result in failure of the device to perform in the
(b) a relief valve; manner for which it was intended;
(c) an automatic shutoff device. (c) be designed and installed so that they can be
These devices may be installed as anintegral part of readily operated to determine if the valve isfree, can be
the service regulator or as a separate unit. tested to determinethe pressure at which they will
operate,and can be tested for leakage when in the
845.243 If the maximum allowable operating pres- closed position.
sure of the distribution system exceeds 60 psig, suitable
methods shall be used to regulate and limit the pressure 845.311 Rupture discs shall meet the requirements
of the gas delivered to the customer to the maximum for design as set out in Section VIII, Division 1, BPV
safe value. Such methods may include: Code.
(a) a service regulator having thecharacteristics
845.32 The discharge stacks, vents, or outlet portsof
listed in para. 845.241 anda secondary regulator
all pressure relief devices shall be located where gas can
located upstream from the service regulator. In no case
be discharged into the atmosphere without unduehaz-
shall the secondary regulator be set to maintain a pres-
ard. Consideration should be given to all exposures in
sure higher than 60 psi. A device shall be installed
the immediate vicinity. Where required to protect de-
between the secondary regulator and theservice regula-
vices, the discharge stacks or vents shall be protected
tor to limit the pressure on the inlet of the service
with rain caps to preclude the entry of water.
regulator to 60 psi or less in case the secondary regula-
tor fails to function properly. This device may be either 845.33 The size of the openings, pipe, and fittings
a relief valve or an automatic shutoff that shuts if the located between the system to be protected and the
pressure on theinlet of the service regulator exceeds the pressure-relieving device and the vent line shall be of
set pressure (60 psi or less) and remains closed until adequate size to prevent hammering of the valve and to
manually reset. prevent impairment of relief capacity.
(6) a service regulator and a monitoring regulator
set to limit to a maximum safe value the pressure of the 845.34 Precautions shall be taken to prevent unau-
gas delivered to the customer; thorized operation of any stop valve which will make
(c) a service regulator with a relief valve vented to a pressure relief valve inoperative. This provision shall
the outside atmosphere, with the relief valveset to open not apply to valves which will isolate the system under
so that the pressure of gas going to the customer shall protection from itssource of pressure. Acceptable
not exceed a maximum safe value. The relief valvemay methods for complying with this provision are as fol-
be either built into the service regulator or may be a lows.
separate unit installed downstream fromthe service (a) Lock the stopvalve inthe open position. Instruct
regulator. This combination may be used alone only in authorized personnel of the importanceof not inadver-
those cases where the inlet pressure on the service regu- tently leaving the stopvalve closed and of being present
lator does not exceed the manufacturer’s safe working during the entireperiod that the stopvalve is closed so
pressure rating of the service regulator, and is not rec- that they can lock it in the open position before they
ommended for use where the inlet pressure on the ser- leave the location.
vice regulator exceeds 125 psi. For higher inlet pres- (b) Install duplicate relief valves, each having ade-
sures, the method in para. 845.243(a) or (b) should be quate capacity by itself to protect the system, and ar-
used. range the isolating valves or three-way valve so that
mechanically it is possible to render only one safety
device inoperative at a time.
845.3 RequirementsforDesignofPressure
845.35 Precautions shall be taken to prevent unau-
Relief and Pressure Limiting Installations
thorized operation of any valve which will make pres-
845.31 Pressure relief or pressure limiting devices, sure-limiting devices inoperative. This provision ap-
except rupture disks, shall: plies to isolating valves, bypass valves, and valves on
(a) be constructed of materials such that the opera- control or float lines which are located between the
56
pressure limiting device and the system which the de- the capacity of the piping system to transmit gas to the
vice protects. A method similar to para. 845.34(a) shall remote location or to the capacity of the remote relief
be considered acceptable in complying with this provi- device, whichever is less.
sion.
845.42 Proof of Adequate Capacity and Satisfactory
845.36 Performance of Pressure Limiting and Pressure Relief
(a) When a monitoring regulator, series regulator, Devices
system relief, or system shutoff is installed at a district 845.421 Wherethe safety device consists of an
regulator station to protect a piping system from over- additional regulator which is associated with or func-
pressuring, the installation shall be designed and in- tions in combination with one or more regulators in a
stalled to prevent any single incident, such as anexplo- series arrangement to control or limit the pressure in a
sion in a vault or damage by a vehicle, from affecting piping system, suitable checks shall be made to deter-
the operationofboth theoverpressure protective device mine that the equipment will operate in a satisfactory
and the district regulator (see paras. 846 and 847). manner to prevent any pressure in excess of the estab-
(6) Special attention shall be given to control lines. lished maximum allowable operating pressure of the
All control lines shall be protected from falling objects, system, shouldanyone of the associated regulators
excavations by others, or other foreseeable causes of malfunction or remain in the wide-open position.
damage and shall be designed and installed to prevent
damage to any one control line from making both the 845.5 Instrument,
Control,
andSample
Piping
district regulator and the overpressure protective de-
vice inoperative. (a) Scope
( I ) The requirements given in this section apply
to the design of instrument, control, and sampling pip-
845.4 CapacityofPressureRelievingand ing for safe and proper operationof the piping itself and
Pressure Limiting Station and Devices do not cover design of piping to secure proper function-
845.41 Required Capacity of Pressure Relieving and ing of instruments for which the piping is installed.
Pressure Limiting Stations (2) This section does not apply to permanently
closed piping systems, such as fluid-filled, temperature-
845.411 Each pressure relief station or pressure
responsive devices.
limiting station or group of such stations installed to
(6) Materials and Design
protect a piping system or pressure vessel shall have
(1) The materials employed for valves, fittings,
sufficient capacity and shall be set to operateto prevent
tubing, and piping shall be designed to meet the partic-
the pressure from exceeding the following levels.
ular conditions of service.
(a) Systems With Pipe or Pipeline Components Oper-
ating Over 72% of the SMYS. The maximum allowable (2) Takeoff connections and attaching bosses, fit-
operating pressure plus 4%. tings, or adapters shall be made of suitable material and
(b) Systems With Pipe or Pipeline Components Oper- shall be capable of withstanding the maximum service
ating at or Below 72% of the SMYS Other Than in pressure and temperature of the piping or equipment to
Low-Pressure Distribution Systems. The lesser of: which they areattached. They shall be designed to
( I ) the maximum allowable operating pressure satisfactorily withstand all stresses without failure by
plus 10%; or fatigue.
(2) the pressure which produces a hoop stress of (3) A shutoff valve shall be installed in each take-
75% of the specified minimum yield strength. off line as near as practicable to the point of takeoff.
(c) Low-Pressure Distribution Systems. A pressure Blowdown valves shall be installed where necessary for
which would cause the unsafe operation of any con- the safe operation of piping, instruments, and equip-
nected and properly adjusted gas burning equipment. ment.
(4) Brass pipe or copper pipe or tubing shall not
845.412 When more than one pressure regulating be used for metal temperatures greater than 400°F.
or compressor station feeds into the pipeline or distri- (5) Piping subject to clogging from solids or
bution system and pressure relief devices are installed deposits shall be provided with suitable connections for
at such stations, the relieving capacity at the remote cleaning.
station may be taken into account in sizing the relief (6) Pipe or tubing required under this section may
devices at each station. However, in doing this, the be specified by the manufacturers of the instrument,
assumed remote relieving capacity must be limited to control apparatus, or sampling device, provided that
57
the safety of the pipe or tubing as installed is at least (6) A plan shall be prepared for uprating which
equal to that otherwise required under the Code. shall include a written procedure that will ensure com-
(7) Piping which may contain liquids shall be pro- pliance with each applicable requirement of this sec-
tected by heating or other suitable means from damage tion.
due to freezing. (c) Before increasing the maximum allowable oper-
(8) Piping in which liquids may accumulate shall ating pressure of a segment that has been operating at
be provided with drains or drips. a pressure less than that determined by para. 845.213,
(9) The arrangement of piping and supports shall the following investigative and corrective measures
be designed to provide not only for safety under operat- shall be taken.
ing stresses, but also to provide protection for the pip- (I) The design, initial installation, method,and
ing against detrimental sagging, external mechanical date of previous testing, Location Classes, materials,
injury, abuse, and damage due to unusual service con- and equipment shall be reviewed to determine that the
ditions other than thoseconnected with pressure, tem- proposed increase is safe and consistent with the re-
perature, and service vibration. quirements of this Code.
(ZO) Suitable precautions shall be taken to protect (2) The condition of the line shall be determined
against corrosion (see para. 863). by leakage surveys, other field inspections, and by ex-
(II) Joints between sections of tubing or pipe, or amination of maintenance records.
both, and between tubing or pipe, or both, and valves (3) Repairs, replacements, or alterations disclosed
or fittings shall be made in a manner suitable for the to be necessary by (c)( 1) and (c)(2) above shall be made.
pressure and temperatureconditions, such as by means (d) A new test according to the requirements of this
of flared, flareless, and compression type fittings, or Code should be considered if satisfactory evidence is
equal, or they may beof the brazed, screwed, or socket- not available to assure safe operation at the proposed
welded type. If screwed-end valves are to be used with MAOP.
flared, flareless, or compression type fittings, adapters (e) When gas upratings are permitted under paras.
are required. 845.62, 845.63, 845.64, and 845.65, the gas pressure
Slip type expansion joints shall not be used; expan- shall be increased in increments, with a leak survey
sion shall be compensated for by providing flexibility performed after each incremental increase. The num-
within the piping or tubing system itself. ber of increments shall be determined by the operator
(12) Plastic shall not beused where operating after considering the total amount of the pressure in-
temperatures exceed limitations shown in paras. crease, the stress level at the final MAOP, the known
842.32(b) and 842.33(b). condition of the line, and the proximity of the line to
(13) Plastic piping shall not be painted. If identi- other structures. The number of increments shall be
fication other than that already provided by the manu- sufficient to assure that any leaks are detected before
facturer’s marking is required, it shall be accomplished they can create a potential hazard. Potentially hazard-
by other means. ous leaks discovered shall be repaired before further
increasing the pressure. A final leak survey shall be
conducted at the higher maximum allowable operating
pressure.
845.6 Uprating
cfl Records for uprating, including each investiga-
This section of theCode prescribes minimum re- tion required by this section, corrective action taken,
quirements for uprating pipelines or mains to higher and pressure test conducted, shall be retained as long
maximum allowable operating pressures. as the facilities involved remain in service.
845.61 General
(a) A higher maximum allowable operating pres- 845.62 Uprating Steel Pipelines or Mains to a Pres-
sure established under this section may not exceed the sure ThatWill Produce aHoop Stress of 30% or More
design pressure of the weakest element in the segment of SMYS. The maximum allowable operating pressure
to be uprated. It is not intended that the requirements may be increased after compliance with para. 845.61(c)
of this Code be applied retroactively to such items as and one of the following provisions.
road crossings, fabricated assemblies, minimum cover, (a) If the physical condition of the line as deter-
and valve spacings. Instead, the requirements for these mined by para. 845.61(c) indicates the line is capable of
items shall meet the criteria of the operating company withstanding the desired higher operating pressure, is
performing the uprating. in general agreement with the design requirements of
58
this Code, and the line has previously been tested to a of the specified minimum yield strength of the pipe, the
pressure equal to or greater than that required by this provisions of para. 845.62 shall apply.
Code for a new line for the proposed maximum allowa- (6) Before increasing the maximum allowable oper-
ble operating pressure, the line may be operated at the ating pressure of a system that has been operating at
higher maximum allowable operating pressure. less than the applicable maximum pressure to a higher
(6) If the physical condition of the line as deter- maximum allowable operating pressure, the following
mined by para. 845.61(c) indicates that the ability of factors shall be considered:
the line to withstand the higher maximum operating (1) the physical condition of the line as deter-
pressure has not been satisfactorily verified or that the mined by para. 845.61(c); and
line has not been previously tested to thelevels required (2) information from themanufacturer or sup-
by this Code for a new line for the proposed higher plier determining that each component of a plastic sys-
maximum allowable operating pressure, the line may tem is capable of performing satisfactorily at thehigher
be operated at the higher maximum allowable operat- pressure.
ing pressure if the line shall successfully withstand the (c) Before increasing the pressure, the following
test required by this Code for a new line to operate steps shall be taken.
under the same conditions. (1) Install suitable devices on the service lines to
(c) If the physical condition of the line asdeter- regulate and limit the pressure of the gas in accordance
mined by para. 845.61(c) verifies its capability of oper- with para. 845.243 if the new maximum allowable oper-
ating at a higher pressure, a higher maximum allowable ating pressure is to be over 60 psi.
operating pressure may be established according to (2) Adequately reinforce or anchor offsets, bends,
para. 845.213 using as a test pressure the highest pres- and dead ends in coupled pipe to avoid movement of
sure to which the line has been subjected, either in a the pipe should the offset, bend, or dead end be exposed
strength test or in actual operation. in an excavation.
(d) If it is necessary to test a pipeline or main before (3) Increase pressure in increments as provided in
it can be uprated to ahigher maximum allowable oper- para. 845.61(e).
ating pressure, and if it is not practical to test the line
either because of the expense or difficulties created by 845.64 Uprating a DuctileIron High-pressure Main
taking it out of service, or because of other operating or System to a New and Higher Maximum Allowable
conditions, a higher maximum allowable operating Operating Pressure
pressure maybe established in Location Class 1 as (a) The maximum allowable operating pressure of a
follows. ductile iron main or system shall not be increased to a
( I ) Perform the requirements of para. 845.61(c). pressure in excess of that permitted in para. 842.21 1.
(2) Select a new maximum allowable operating Where records are not complete enough to permit the
pressure consistent with the condition of the line and direct application of para. 842.2 1 1, the following proce-
the design requirements of this Code, provided: dures shall be used.
(a) in no such case shall the new maximum (I) Laying Condition. Where the original laying
allowable operating pressure exceed 80% of that per- conditions cannot be ascertained, it shall be assumed
mitted for a new line to operate under the same condi- that Condition D (pipe supported on blocks, tamped
tions; and backfill) exists for cast iron pipe and Condition B(pipe
(6) the pressure is increased in increments as laid without blocks, tamped backfill) exists for ductile
provided in para. 845.61(e). iron pipe.
(2) Cover. Unless theactual maximum cover
depth is known with certainty, it shall be determined
845.63 Uprating Steel or Plastic Pipelines to a Pres- by exposing the main or system at three or more points
sure That Will Produce a HoopStress Less Than 30% and making actual measurements. The main or system
of SMYS shall be exposed in those areas where the cover depth
(a) This applies to high-pressure steel mains and is most likely to be greatest. The greatest measured
pipelines where the higher maximum allowable operat- cover depth shall be used for computations.
ing pressure is lessthan that required to produce a hoop (3) Nominal Wall Thickness. Unless the nominal
stress of 30% of the specified minimum yield strength thickness is known with certainty, it shall be deter-
of the pipe and to all high-pressure plastic distribution mined with ultrasonic measuring devices. The average
systems. If the higher maximum allowable operating of all measurements taken shall be increased by the
pressure of a steel pipeline or main is more than 30% allowance indicated in the following table:
59
Allowance. in.
~~~~ ~~
(b) Low-Pressure Distribution Systems. Valves may tions, etc., shall be designed and constructed in accord-
be used on low-pressure distribution systems, but are ance with the following provisions.
not required except as specified in para. 846.22(a). (a) Vaults and pits shall be designed and con-
structed in accordance with good structural engineer-
ing practice to meet the loads which may be imposed
846.2 Location of Valves upon them.
(b) Sufficient working space shall be provided so
846.21 Transmission Valves
that all of the equipment required in the vault can be
(a) Sectionalizing blockvalves shall be accessible properly installed, operated, and maintained.
and protected from damage and tampering. If a blow- (c) In the design of vaults and pits for pressure lim-
down valve isinvolved, it shall be located where the gas iting, pressure relieving, and pressure regulating equip-
can be blownto the atmospherewithout undue hazard. ment, consideration shall be given to the protection of
(b) Sectionalizing valvesmay be installed above the installed equipment from damage, such as that re-
ground, in a vault, or buried. In all installations an sulting from an explosion within the vault or pit which
operating device to open or close the valve shall be may cause portions of the roof or cover to fall into the
readily accessible to authorized persons. All valves vault.
shall be suitably supported to prevent settlement or (d) Pipe entering and within regulator vaults or pits
movement of the attached piping. shall be steel for NPS 10 and smaller sizes, except that
(c) Blowdown valves shall be provided so that each control and gage piping may be copper. Where piping
section of pipeline betweenmain line valves can be extends through the vault or pit structure, provision
blown down. The sizes and capacity of the connections shall be made to prevent the passage of gases or liquids
for blowing down the line shall be such that under through the opening and to avert strains in the piping.
emergency conditions the section of line can be blown Equipment and piping shall be suitably sustained by
down as rapidly as is practicable. metal, masonry, or concrete supports. The control pip-
(d) This Code does not require the use of automatic ing shall be placed and supported in the vault or pit so
valves, nor does the Code imply that the use of auto- that its exposure to injury or damage is reduced to a
matic valves presently developed will provide full pro- minimum.
tection to a piping system. Their use and installation (e) Vault or pit openings shall be located so as to
shall be at the discretion of the operating company. minimize the hazards of tools or other objects falling
upon the regulator, piping, or other equipment. The
846.22 Distribution System Valves
control piping and theoperating parts of the equipment
(a) A valve shall be installed on the inlet piping of
installed shall not be located under a vault or pit open-
each regulator station controlling the flow or pressure
ing where workmen can step on them when entering or
of gas in a distribution system. The distance between
leaving the vault or pit, unless such parts are suitably
the valve and the regulator or regulators shall be suffi-
protected.
cient to permit the operation of the valve during an
cf) Whenever a vault or pit opening is to be located
emergency, such as a large gas leak or a firein the
above equipment which could be damaged by a falling
station.
cover, acircular cover should be installed or other
(b) Valves on distribution mains, whether for oper-
ating or emergency purposes, shall be located in a man- suitable precautions taken.
ner that will provide ready access and facilitate their
operation during an emergency. Where a valve is in- 847.2 Accessibility
stalled in a buried box or enclosure, only ready access
Consideration shall be given to accessibility in select-
to theoperating stem or mechanism is implied. The box
ing a site for a vault. Some of the important factors to
or enclosure shall be installed in a manner to avoid
consider in selecting the location of a vault are as fol-
transmitting external loads to the main.
lows.
(a) Exposure to Trafic. The location of vaults in
street intersections or at points where traffic is heavy or
847 VAULTS dense should be avoided.
(6) Exposure to Flooding. Vaults should not be
847.1
Structural
Design
Requirements
located at points of minimum elevation, near catch
Underground vaults or pits for valves, pressure re- basins, or where the access cover will be in the course
lieving, pressure limiting or pressure regulating sta- of surface waters.
61
62
turer’s rating for the meter. New tinned steel case me- 848.4 Installation of Meters and Regulators
ters shall not be used at a pressure in excess of 50% of
All meters and regulators shall be installed in such
the manufacturer’s test pressure; rebuilt tinned steel
a manner as to prevent undue stresses upon the con-
case meters shall not be used at a pressure in excess of
necting piping or the meter, or both. Lead (Pb) connec-
50% of the pressure used to test the meter after rebuild-
tions or other connections made of material which can
ing.
be easily damaged shall not be used. The use of stan-
dard weight close (all thread) nipples is prohibited.
848.3 Protection of Customers’ Meterand
Regulator Installations from Damage 849 GAS SERVICE
LINES
848.31 Meters and service regulators shall not be 849.1 General Provisions Applicable to Steel,
installed where rapid deterioration from corrosion or Copper, and Plastic Service Lines
other causes is likely to occur, unless proven measures
are taken to protect against such deterioration. 849.11 Installation of Service Lines
(a) Service lines shall be installed at a depth which
848.32 A suitable protective device, such as a back- will protect them from excessive external loading and
pressure regulator or a check valve, shall be installed local activities, such as gardening. It is required that a
downstream of the meter if and as required under the minimum of 12 in. of cover be provided in private
following conditions. property and a minimum of 18 in. of cover be provided
(a) If the nature of the utilization equipment is such in streets and roads. Where these cover requirements
that it may induce a vacuum at the meter, install a cannot be met due to existing substructures, less cover
back-pressure regulator downstream from the meter. is permitted provided such portions of these service
(b) Install a check valve or equivalent if: lines that are subject to excessive superimposed loads
( I ) the utilization equipment might induce a are cased or bridged or the pipe is appropriately
back-pressure; strengthened.
(2) the gas utilization equipment is connected to (b) Service lines shall be properly supported at all
a source of oxygen or compressed air; points on undisturbed or well compacted soil so that
(3) liquefied petroleum gas or other supplemen- the pipe will not be subject to excessive external loading
tary gas is used as standby and might flow back into the by the backfill. The material used for the backfill shall
meter. A three-way valve, installed to admit the be free of rocks, building materials, etc., that might
standby supply and at the same time shut off the regu- cause damage to the pipe or the protective coating.
lar supply, can be substituted for a check valve if (c) Where there is evidence of condensate in the gas
desired. in sufficient quantities to cause interruptions in the gas
supply to the customer, the service line shall be graded
848.33 All service regulator vents and relief vents,
so as to drain into themain or to dripsat thelow points
where required, shall terminate in the outside air in rain in the service line.
and insect resistant fittings. The open end of the vent 849.12 Types of Valves Suitable for Service Line
shall be located where the gas can escape freely into the Valves
atmosphere and away from any openings into thebuild- (a) Valves used as service line valves shall meet the
ings if a regulator failure resulting in the release of gas applicable requirements of paras. 8 10 and 83 1,l.
occurs. At locations where service regulators might be (b) The useofsoft seat service line valvesis not
submerged during floods, either a special antiflood type recommended when the design of the valves is such
breather vent fitting shall be installed or the vent line that exposure to excessive heat could adversely affect
shall be extended above the height of the expected flood the ability of the valve to control the flow of gas.
waters. (c) A valve incorporated in a meter bar which per-
mits the meter to be bypassed does not qualify under
848.34 Pitsand vaults housing customers’ meters this Code as a service line valve.
and regulators shall be designed to support vehicular (d) Service line valves of high-pressure service lines,
traffic when installed in the following locations: installed either inside buildings or in confined locations
(a) travelled portions of alleys, streets, and high- outside buildings where the blowing of gas would be
ways; hazardous, shall be designed and constructed to mini-
(b) driveways. mize the possibility of the removal of the core of the
63
valve accidentally or willfully with ordinary household (6) Service lines to operate at a pressure of less than
tools. 1 psig, which have a protective coating which might
(e) The operating company shall make certain that temporarily seal a leak, and all service lines to operate
the service line valves installed on high-pressure service at a pressure of 1 psig or more, shall be givena standup
lines are suitable for this use either by making their own air or gas pressure test for at least 5 min at theproposed
tests or by reviewing the tests madeby the manufactur- maximum operating pressure or 90 psig, whichever is
ers. greater, except that service lines of steel stressed to
fl On service lines designed to operate at pressures 20% or more of the specified minimum yield strength
in excess of 60 psig, the service line valves shall be the shall be tested in accordance with the requirements for
equivalent of a pressure lubricated valve or a needle testing mains (see para. 841.3).
type valve. Other types of valves may be used where (c) The requirements of (a) and (b) above shall
tests by the manufacturer or by the user indicate that apply to plastic service lines, except that plastic service
they are suitable for this kind of service. lines shall be tested to at least 1.5 times the maximum
operating pressure, and the limitations on maximum
849.13 Location of Service Line Valves
test pressure, temperature, and duration set forth in
(a) Service line valves shall be installed on all new
para. 842.52 shall be observed.
service lines (including replacements) in a location
readily accessible from the outside.
(b) Valves shall be located upstream of the meter if
there is no regulator, or upstream of the regulator, if 849.2
Steel
Service
Lines
there is one. 849.21 Design of Steel Service Lines
(c) All service lines operating at a pressure greater (a) Steel pipe, when used for service lines, shall con-
than 10 psig, and allservice lines NPS 2 or larger, shall form to the applicable requirements of Chapter I.
be equipped with a valve located on the service line (b) Steel service pipe shall be designed in accordance
outside of the building, except that whenever gas is with the requirements of paras. 841.11 and 841.121.
supplied to a theatre, church, school, factory, or other Where pressure is less than 100 psig, the steel service
building where large numbers of persons assemble, an pipe shall be designed for at least 100 psig pressure.
outside valve will be required, regardless of the size of (c) Steel pipe used for service lines shall be installed
the service line or of the service line pressure. in such a mannerthatthe piping strain or external
(d) Underground valves shall be located in a covered loading shall not be excessive.
durable curb box or standpipe which is designed to (d) All underground steel service lines shall be
permit ready operation of the valve. The curb box or joined by threadedand coupled joints, compression
standpipe shall be supported independently of the ser- type fittings, or by qualified welding or brazing meth-
vice line. ods, procedures, and operators.
849.14Location of ServiceLineConnectionsto
Main Piping. It is recommended that service lines be 849.22 Installation of Steel Service Lines
connected to either the topor the side of the main. The 849.221Installationof Steel ServiceLines in
connection to the topof the main is preferred, in order Bores
to minimize the possibility of dust and moisture being (a) When coated steel pipe is to be installed as a
carried from the main into the service line. service line in a bore, care shall be exercised to prevent
damage to the coating during installation.
849.15 Testing of Service Lines After Construction
(b) When a service line is to be installed by boring
849.151GeneralProvisions. Each service line or driving and coated steel pipe is to be used, it shall
shall be tested after constructionand before being not be used as thebore pipe or drive pipe and left in the
placed in service to demonstrate that it does not leak. ground as part of the service line unless it has been
The service line connection to the main need not be demonstrated that thecoating is sufficientlydurable to
included in this test if it is not feasible to do so. withstand the boring or driving operation in the type
849.152 Test Requirements of soil involved without significant damage to the coat-
(a) Service lines to operate at a pressure of less than ing. Where significant damage to thecoating may result
1 psig, which do not have a protective coating capable from boring or driving, the coated service line should
of temporarily sealing a leak, shall be given a standup be installed in an oversized bore or casing pipe of suf-
air or gas pressure test at not less than 10 psig for at ficient diameter to accommodate the service pipe.
least 5 min. (c) In exceptionally rocky soil, coated pipe shall not
64
be inserted through an open bore if significant damage ing from the thermal expansion or contraction. (See
to the coating is likely. paras. 842.431 and 842.432.)
(b) Notwithstandingthe limitations imposed in
849.222Installation of ServiceLinesInto or
para. 842.43, a plastic service line may terminate above
Under Buildings
ground and outside the building, provided that:
(a) Underground steel service lines, when installed
(1) the above ground portion of the plastic service
below grade through the outer foundation wall of a
line is completely enclosed in a conduit or casing of
building, shall be either encased in a sleeve or otherwise
sufficient strength to provide protection from external
protected against corrosion. The service line or sleeve,
damage and deterioration. Where a flexible conduit is
or both, shall be sealed at the foundation wall to pre-
used, the top of the riser must be attached to a solid
vent entry of gas or water into the building.
support. The conduit or casing shall extend a minimum
(b) Steel service lines, where installed underground
of 6 in. below grade.
under buildings, shall be encased in a gas tight conduit.
(2) the plastic service line is not subjected to ex-
When such a service line supplies the building it sub-
ternal loading stresses by the customer’s meter or its
tends, the conduit shall extend into a normally usable
connecting piping.
and accessible portion of the building. At the point
where the conduit terminates, the space between the 849.421 Installation of Plastic Service Lines Into
conduit and the service line shall be sealed to prevent or Under Buildings
the possible entrance of any gas leakage. The casing (u) An underground plastic service line installed
shall be vented at a safe location. throughtheouterfoundation or wallof a building
shall be encased in a rigid sleeve with suitable protec-
tion from shearing action or backfill settlement. The
849.3
Ductile Iron Service
Lines sleeve shall extend past the outside face of the founda-
849.31Use of Ductile Iron ServiceLines. When tion a sufficient distance to reach undisturbed soil or
used for service lines, ductile iron pipe shall meet the thoroughly compacted backfill. Atthe point where
applicable requirements of para. 842. Ductile iron pipe the sleeve terminates inside thefoundation or wall,
may be used for service lines except for that portion of the space between the sleeve and the service line shall
the service line which extends throughthe building be sealed to prevent leakage intothe building. The
wall. Ductile iron service lines shall not be installed in plastic service line shall not be exposed inside the
unstable soils or under buildings. building.
(b) A plastic service line installed underground
under a building shall be encased in a gastight conduit.
849.4
Plastic
Service
Lines When such a service line supplies the building it sub-
849.41 Design of Plastic Service Lines tends, the conduit shall extend into a normally usable
fa) Plastic pipe and tubing shall be used for service and accessible portion of the building. At the point
lines only where the piping strain or external loading where the conduit terminates, the space between the
will not be excessive. conduit and the service line shall be sealed to prevent
fb) Plastic pipe, tubing, cements, and fittings used leakage into the building. The plastic service line shall
for service lines shall conform to theapplicable require- not be exposed inside the building. The casing shall be
ments of Chapter I. vented at a safe location.
(c) Plastic service lines shall be designed in accord-
ance with the applicable requirements of para. 842.3. 849.5 Copper Service
Lines
(d) Plastic service lines shall be joined in accordance 849.51 Design of Copper Service Lines
with the applicable requirements of para. 842.39.
849.511 Copper pipe or tubing, when used for ser-
849.42 Installation of Plastic Service Lines vice lines, shall conform to thefollowing requirements.
(u) Plastic service lines shall be installed in accord- (a) Copper pipe or tubing shall not be used for ser-
ance with the applicable requirements of paras. 842.4 vice lines where the pressure exceeds 100 psig.
and 849.11. Particular care must be exercised to pre- (b) Copper pipe or tubing shall not be used for ser-
vent damage to plastic service line piping at theconnec- vice lines where the gas carried contains more than an
tion to the main or other facility. Precautions shall be average of 0.3 grains of hydrogen sulfide per 100 stan-
taken to prevent crushing or shearing of plastic piping dard cu ft of gas. This is equivalent to a trace as deter-
due to external loading or settling of backfill and to mined by the lead-acetate test (see para. 863.4).
prevent damage or pull out from the connection result- (c) The minimum wall thickness for copper pipe or
65
tubing used for service lines, shall be not less than type (b) using a service line clamp or saddle;
"L" as specified in ASTM B 88. (c) compression fittings using rubber or rubber-like
(d) Copper pipe or tubing shall not be used for ser- gaskets or welded connections may be used to connect
vice lines where strain or external loading may damage the service line to the main connection fitting. Gaskets
the piping. used in a manufactured gas system shall be of a type
849.512 Valves in Copper Piping. Valves installed that effectively resists that type of gas.
in copper service lines may be made of any suitable (d) welding a steel service line directly to the main
material permitted by this Code. (see para. 83 1.42and Table 83 1.42).
66
CHAPTER V
OPERATING AND MAINTENANCE PROCEDURES
850
OPERATING AND MAINTENANCE tions. The training shall be comprehensive and shall be
PROCEDURES AFFECTING THE designed to prepare employees for service in their area
SAFETY OF GAS TRANSMISSION of responsibility.
AND DISTRIBUTION FACILITIES Ifl keep records to administer the plans and training
properly.
850.1
(a) Because of many variables, it is not possible to
prescribe in a code a detailed set of operating and main-
tenance procedures that will encompass all cases. It is 850.3EssentialFeatures of theOperatingand
possible, however, for each operating company to de- Maintenance Plan
velop operating and maintenance procedures based on The plan prescribed in para. 850.2(a) shall include:
the provisions of this Code, its experience, and its (a) detailed plans andinstructions for employees
knowledge of its facilities and conditions under which covering operating and maintenance procedures for gas
they are operated which willbe adequate from the facilities during normal operations and repairs;
standpoint of public safety. For operating and mainte- (6) items recommended for inclusion in the plan for
nance procedures relating to corrosion control, see specific classes of facilities which are given in paras.
Chapter VI. 851.2, 851.3, 851.4, 851.5, 851.6, and 861(d):
(6) Upon initiating gas service in a pipeline designed (c) plans to give particular attention to those por-
and constructed or converted to gas service in accord- tions of the facilities presenting the greatest hazard to
ance with this Code, the operating company shall de- the public in the event of an emergency or because of
termine the Location Class in accordance with Table construction or extraordinary maintenance require-
854.1(c). ments;
(d) provisions for periodic inspections along the
route of existing steel pipelines or mains, operating at
a hoop stress in excess of 40% of the specified mini-
850.2
Basic Requirements mum yield strength of the pipe material in order to
Each operating company having gas transmission or consider the possibility of Location Class changes. It is
not intended that these inspections include surveys of
distribution facilities within the scope of this Code
the number of buildings intended for human occupancy
shall:
(see para. 854).
(a) have a written plan covering operating and
maintenance procedures in accordance with the pur-
pose of this Code;
(b) have a written emergency plan covering facility 850.4 EssentialFeatures of theEmergency Plan
failure or other emergencies;
(c) operateand maintain its facilities in confor- 850.41 Written Emergency Procedures
mance with these plans; 850.411 Each operating company shall establish
(d) modify the plans from time to time as experience written procedures which will provide the basis for
dictates and as exposure of the public to the facilities instructions to appropriate operating and maintenance
and changes in operating conditions require; personnel which will minimize thehazard resulting
(e) provide training for employees in procedures es- from a gas pipeline emergengy. At a minimum, the
tablished for their operating and maintenance func- procedures shall provide for the following:
67
(a) a system for receiving, identifying, and classify- type of pipeline operation and the environment tra-
ing emergencies which require immediate response by versed by the pipeline and should be conducted in each
the operating company; language that is significant in the community served.
(b) indicating clearly the responsibility for instruct- Operators of distribution systems should communicate
ing employees in the procedures listed in the emergency their programs to consumers and the general public in
plans and for training employees in the execution of their distribution area. Operators of transmission sys-
those procedures; tems should communicate their programs to residents
(c) indicating clearly those responsible for updating along their pipeline right-of-way. The programs of op-
the plan; erators in the same area should be coordinated to prop-
(d) establishing a plan to insure prompt and ade- erly direct reports of emergencies and to avoid inconsis-
quate handling of all calls which concern emergencies tencies.
whether they are from customers, the public, company
employees, or other sources;
(e) establishing a plan to insure the prompt and ef- 850.5
Pipeline
Failure
Investigation
fective response to a notice of each type of emergency;
# controlling emergency situations, including the Each operating company shall establish proce-
action to be taken by the first employee arriving at the dures to analyze all failures and accidents for the
scene; purpose of determining the cause andto minimize
(g) the dissemination of information to the public; the possibility of a recurrence. This plan shall in-
(h) the safe restoration of service to all facilities af- clude a procedure to select samples of the failed fa-
fected by the emergency after proper corrective mea- cility or equipment for laboratory examination when
sures have been taken; necessary.
(i) reporting and documenting the emergency.
850.6
Prevention of Accidental
Ignition
850.42 Training Program. Each operating company Smoking and all open flames shall be prohibited in
shall have a program for informing, instructing, and and around structures or areas under the control of the
training employees responsible for executing emer- operating company containing gas facilities (such as
gency procedures. The program shall acquaint the em- compressor stations, meter and regulator stations, and
ployee with the emergency procedures and how to other gas handling equipment) where possible leakage
promptly and effectively handle emergency situations. of gas constitutes a hazard of fire or explosion. Each
Said program may beimplemented by oral instruction, operating company shall take steps to minimize the
written instruction, and, in some instances, group in- danger of accidental ignition of gas.
struction, followed by practice sessions. The program (a) When a hazardous amountof gas is to be vented
shall be established and maintained on a continuing into open air, each potential source of ignition shall first
basis with provision for updating as necessitated by be removed from the area and adequate fire extinguish-
revision of the written emergency procedures. Program ers shall be provided. All flashlights, lighting fixtures,
records shall be maintained to establish what training extension cords, and tools shall be of a type approved
each employee has received and the dateof such train- for hazardous atmospheres. Blowdown connections
ing. must be installed or used that will direct the gas away
from any electrical transmission lines.
(b) Suitable signs and flagmen or guards, if neces-
850.43 Liaison.Each operating company shall estab- sary, shall be posted to warn others approaching or
lish and maintain liaison with appropriate fire, police, entering the area of the hazard.
and other public officials and public communications (c) To prevent accidental ignition by electric arcing,
media. an adequate bonding cable should be connected to each
side of any piping that is to be parted or joined, and any
cathodic protection rectifiers in the area shall be turned
850.44 EducationalProgram. An educational pro- off. When plastic pipe is beingparted or joined, a spray
gram shall be established to enable customers and the of water or useofwet rags isadvised to cover the
general public to recognize and reporta gas emergency surface to prevent static arcing.
to the appropriate officials. The educational program (d) When cutting by torch or welding is to be per-
called for under this section should be tailored to the formed, a thorough check shall first be made for the
68
presence of a combustible gas mixture in the area out- the maximum allowable operating pressure shall be
side of the pipeline. Iffound, the mixture shall be elimi- reduced commensurate with the requirements de-
nated before starting welding or cutting. Monitoring of scribed in para. 845.213(c).
air mixture should continue throughout progress of
work.
851.2
Pipeline
Patrolling
(e) Should welding beanticipated on a pipeline filled
with gas and thesafety checkunder (d) above has been Each operating company shall maintain a periodic
completed satisfactorily, the gas pressure must be con- pipeline patrol program to observe surface conditions
trolled by a suitable 'means to keep a slight positive on and adjacent to the pipeline right-of-way, indica-
pressure in the pipeline at thewelding area before start- tions of leaks, construction activity otherthanthat
ing work. Precautions should be taken to prevent a performed by the company, natural hazards, and any
backdraft from occurring at the welding area. other factors affecting the safety and operation of the
If) Before cutting by torch or welding on a line pipeline. Patrols shall be performed at least once each
which may contain a mixture of gas and air, it shall be year in Locations Class 1 and 2, at least once each 6
made safe by displacing the mixture with gas, air, or an months in Location Class 3, and at least once each 3
inert gas. Caution must be taken when using an inert months in Location Class 4. Weather, terrain, size of
gas to provide adequate ventilation for all workers in line, operating pressures, and other conditions will be
the area. factors in determining the need for more frequent pa-
trol. Main highways and railroad crossings shall be
inspected with greater frequency and more closely than
850.7
Blasting
Effects
pipelines in open country.
Each operating company shall establish procedures
851.21 Maintenanceof Cover at Road Crossings and
for protection of facilities in the vicinity of blasting
Drainage Ditches. The operating company shall deter-
activities. The operating company shall:
mine by periodic surveys if the cover over the pipeline
(a) locate and mark its pipeline when explosivesare
at road crossings and drainage ditches has been re-
to be detonated within distances as specified in com-
duced below the requirements of the original design. If
pany plans. Consideration should be givento themark-
the operating company determines thatthenormal
ing of minimum blasting distances from the pipelines
cover provided at the time of pipeline construction has
depending upon the type of blasting operation.
become unacceptably reduced due to earth removal or
(6) determine the necessity and extent of observing
line movement, the operating company shall provide
or monitoring blasting activities based upon the prox-
additional protection by providing barriers, culverts,
imity of the blast with respect to the pipelines, the size
concrete pads, casing, lowering the line, or other suit-
of charge, and soil conditions;
able means.
fc) conduct a leaksurveyfollowingeachblasting
operation near its pipelines. 851.22 Maintenanceof Cover inCross-country Ter-
rain. If the operating company learns as a result of
patrolling that the cover over the pipeline in cross-
851 PIPELINE MAINTENANCE country terrain does not meet the original design, it
shall determine whether the cover has been reduced to
851.1 Continuing Surveillance of Pipelines
an unacceptable level.If unacceptable, the operating
As a means of maintaining the integrity of its pipe- company shall provide additional protection by replac-
line system, each operating company shall establish ing cover, lowering the line, or other suitable means.
and implement procedures for continuing surveillance
of its facilities. Studies shall be initiated and appropri-
851.3 Leakage
Surveys
ate action taken where unusual operating and mainte-
nance conditions occur, such as failures, leakage his- Each operating company of a transmission line shall
tory, drop in flow efficiency due to internal corrosion, provide for periodic leakage surveys of the line in its
or substantial changes in cathodic protection require- operating and maintenance plan. The types of surveys
ments. selected shall be effective for determining if potentially
When such studies indicate the facility is in unsatis- hazardous leakage exists. The extent and frequency of
factory condition, a planned program shall be initiated the leakage surveys shall be determined by the operat-
to abandon, replace, or recondition and proof test. If ing pressure, piping age, class location, and whether the
such a facility cannot be reconditioned or phased out, transmission line transports gas without an odorant.
69
851.4 RepairProceduresfor Steel Pipelines or soil environment will be kept out of the area under the
Mains Operating at or Above 40% of the 'sleeve.
Specified Minimum Yield Strength
851.41 Permanent Field Repairs of Injurious
If at any time a defect mentioned in the following Gouges, Grooves, and Dents
subsections of para. 85 1.4 is evident on a pipeline oper- (a) Injurious gouges, grooves, anddentsshall be
ating at or above 40% of the specified minimum yield removed or reinforced, or the operating pressure re-
strength of the pipe, temporary measures shall be em- duced.
ployed immediately to protect thepropertyandthe (1) Iffeasible,gouges, grooves, anddents shall
public. If it is not feasible to make permanent repairs be removed by taking the pipeline out of service and
at the. time of discovery, permanent repairs shall be cutting out a cylindrical piece of pipe and replacing
made as soon as feasible as described herein. The use same with pipe of equal or greater design pressure.
of a welded patch as a repair method is prohibited, (2) If not feasible to take the pipeline out of ser-
except as provided in para. 85 1,43(e). If the pipeline is vice or operate at a reduced pressure, repairs may be
not taken out of service, the operatingpressure shall be made:
at a level which will provide safety during the repair (a) with a full encirclement welded split sleeve
operations. with or without circumferential fillet welds;
Gouges and grooves are defined as injurious when (b) by removing the defect by hot tapping, pro-
thedepth of the defect is greaterthan 10% of the vided the entire defect is removed; or
nominal wall thickness of the pipe. See para. 841.113(b) (e) if the defect is not a dent, by grinding as
for additional limitations. Smooth dents in existing provided for in para. 841.242. If afterthe defectis
pipelines do not require repair unless they: removed by grinding not enough wall thickness re-
(a) contain a stress concentrator, such as a scratch, mains [see para. 841.113(b)], a full encirclement welded
gouge, groove, or arc burn; split sleeve, with or without circumferential fillet welds,
(b) affect the curvature of the pipe at the longitudi- shall be installed.
nal weld or a circumferential weld; or (3) If a dent is repaired with a sleeve and circum-
(e) exceed a maximum depth of 6% of nominal pipe ferential fillet welds are not made, the dentshall first be
diameter. filled with a hardenable filler. If fillet welds are made,
Nonleaking corroded areas that must be repaired or the dent may be protected either by the filler just men-
replaced are defined in para. 826.213. Longitudinal tioned or by intentionally pressurizing the sleeve by hot
weld seams are commonly identified by visual inspec- tapping the pipeline under it.
tion, etchants, and ultrasonics. (b) All repairs under para. 851.41(a) shall pass non-
A full encirclement welded split sleeve shall have a destructive inspections and tests as provided in para.
851.5.
design pressure at least equal to that required for the
maximum allowable operating pressure of the pipe 851.42 PermanentFieldRepairofWeldsHaving
being repaired. If conditions require that the sleeve Injurious Defects
carry the full longitudinal stresses, the sleeve shall be (a) All circumferential butt welds found to have un-
at least equal to the design strength of the pipe being acceptable defects (according to API 1104) shall be
repaired. Full encirclement sleeves shall not beless repaired in accordance with requirements of para. 827,
than 4 in. in width. provided the pipeline can be taken out of service. Re-
If the defect is not a leak, the circumferential fillet pairs on welds may be made while the pipeline is in
welds are optional in certain cases as described in the service, provided the weld is not leaking, the pressure
following subsections of para. 851.4. If circumferential in the pipeline has been reduced to a pressure which
fillet welds are made, the sleeve's longitudinal welds will not produce a stress in excess of20% of the speci-
should be butt welds. The welding procedures for the fied minimum yield of the pipe, and grinding of the
circumferential fillet welds shall be suitable for the ma- defective area can be limited so that there will remain
terials and shall consider the potential for underbead at least YE in. thickness in the pipe weld.
cracking. Backup strips are not required. If the circum- (b) Defective welds mentioned in (a) above, which
ferential filletwelds are not made, the longitudinal cannot be repaired under (a) above and where it is not
welds may be butt welds or fillets to a side bar. The feasible to remove the defect from the pipeline by re-
circumferential edges, which would have been sealed, placement, may be repaired by the installation of a full
had the fillet welds been made, should be sealed with encirclement welded split sleeve using circumferential
a coating material such as enamel or mastic, so that the fillet welds.
71
851.4 and any of its subsections, the welding shall be deflection; diameter, wall thickness, and grade of pipe;
examined in accordance with para. 826. pipeline pressure, type of girth welds, test and operat-
ing history, presence of defects, existing curvature,
851.6 Pipeline Leak
Records bends, valves and fittings; terrain and soil conditions;
personnel safety considerations; and additional stresses
Records shall be made covering all leaks discovered caused by repositioning of the pipeline.
and repairs made. All pipeline breaks shall be reported
in detail. These records along with leakage survey rec-
ords, line patrol records, and other records relating to 852 DISTRIBUTION PIPING
routine or unusual inspections shall be kept in the file MAINTENANCE
of the operating company,as long as thesection of line
remains in service. Patrolling
852.1
Distribution mains shall be patrolled in areas where
851.7
Pipeline
Markers necessary to observe factors which may affect safe oper-
ation. The patrolling shall be considered in areas of
(u) Signs or markers shall be installed where it is
construction activity, physical deterioration of exposed
considered necessary to indicate the presence of a pipe-
piping andsupports, or any natural causes, which
line at road, highway, railroad, and stream crossings.
could result in damage to thepipe. The frequency of the
Additional signs and markers shall be installed along
patrolling shall be determined by the severity of the
the remainder of the pipeline at locations where there
conditions which could cause failure or leakage and the
is a probability of damage or interference.
subsequent hazards to public safety.
(b) Signs or markers and the surrounding right-of-
way shall be maintained so markers can be easily read
and are not obscured. 852.2
Leakage
Surveys
(c) The signs or markers shall include the words
Each operating company having a gas distribution
“Gas (or name of gas transported) Pipeline,” the name
system shall set up in its operating and maintenance
of the operating company, and the telephone number
plan a provision for the making of periodic leakage
(including area code) where the operating company can
surveys on the system.
be contacted.
852.21 The types of surveys selected shall be effective
851.8 Abandoning of Transmission Facilities for determining if potentially hazardous leakage exists.
The following are some procedureswhich may be em-
Each operating company shall have a plan in its ployed:
operating and maintenanceprocedures for abandoning (a) surface gas detection surveys;
transmission facilities. The plan shall include the fol- (6) subsurface gas detector survey (including bar
lowing provisions. hole surveys);
(a) Facilities to be abandoned shall be disconnected (c) vegetation surveys;
from all sources and supplies of gas such as otherpipe- (d) pressure drop test;
lines, mains, crossover piping, meter stations, control (e) bubble leakage test;
lines, and other appurtenances. cf) ultrasonic leakage test.
(b) Facilities to be abandoned in place shall be A detailed description of the various surveys and
purged of gas with an inert material andthe ends leakage detection procedures is shown in Appendix M.
sealed, except that:
(c) if precautions are taken to insure that no liquid 852.22 The extent and frequency of the leakage sur-
hydrocarbons remain in the facilities to be abandoned, veys shall be determined by the characterof the general
then suchfacilities may be purged with air. If the facili- service area, building concentration, piping age, system
ties are purged with air, then precautionsmust be taken condition, operating pressure, andanyother known
to insure that a combustible mixture is not present after condition (such as surface faulting, subsidence, flood-
purging. (See para. 841.275.) ing, or an increase in operating pressure) which has
significant potential to either initiate a leak or tocause
leaking gas to migrate to an area where it could result
851.9RepositioningaPipeline in Service in a hazardous condition. Special one-time surveys
When repositioning a pipeline in service, the follow- should be considered following exposure ofthe gas
ing are some of the factors that shall be considered: distribution system to unusual stresses (such as those
72
resulting from earthquakes or blasting). The leakage shutting off the flow of gas to thefacility, shall be taken
survey frequencies shall be based on operating experi- to eliminate the potential hazard.
ence, sound judgment, and a knowledge of the system. 852.34 Followup Inspections. While the excavation
Once established, frequencies shall be reviewed periodi- is open, the adequacy of leak repairs shall be checked
cally to affirm that they are still appropriate. The fre- by using acceptable methods. The perimeter of the leak
quencies of the leakage survey shall at least meet the area shall be checked with a gas detector. In the case
following. of a Grade 1 leak repair as defined in Appendix M,
(0) Distribution systems in a principal business dis-
where there is residual gas in the ground, a followup
trict should be surveyed at least annually. Such surveys inspection should be made as soon as practicable after
shall be conducted using a gas detector and shall in- allowing the soil atmosphere to vent and stablize, but
clude tests of the atmosphere which will indicate the in no case later than 1 month following the repair. In
presence of gas in utility manholes, at cracks in the the case of other leak repairs, the need for a followup
pavement and sidewalks, and at otherlocations provid- inspection should be determined by qualified personnel.
ing opportunity for finding gas leaks.
(b) The undergrounddistribution system outside
852.4 Requirements for Abandoning,
the areas covered by (a) above should be surveyed as
Disconnecting, and Reinstating
frequently as experience indicates necessary, but not
Distribution Facilities
less than once every 5 years.
852.41 Abandoning of Distribution Facilities. Each
operating company shall have a plan for abandoning
852.3 Leakage
Investigation
and Action
inactive facilities, such as service lines, mains, control
852.31 Leakage Classification and Repair. Leaks lines, equipment, and appurtenances forwhich there is
located by surveys or investigation, or both, should be no planned use.
evaluated, classified, and controlled in accordance with The plan shall also include the following provisions.
the criteria set forth in para. M5 of Appendix M. (a) If the facilities are abandoned in place, they shall
Prior to taking any repair action, leaks should be be physically disconnected from the piping system. The
pinpointed but only after it has been established that an open ends of all abandoned facilities shall be capped,
immediate hazard does not exist or has been controlled plugged, or otherwise effectively sealed. The need for
by such emergency actions as evacuation, blocking an purging the abandoned facility to prevent the develop-
area off, rerouting traffic, eliminating sources of igni- ment of a potential combustion hazard shall be consid-
tion, ventilating, or stopping the flow of gas. The pin- ered and appropriate measures taken. Abandonment
pointing guidelines provided in para. M6 of Appendix shall not be completed until it has been determined that
M should be followed. the volume of gas or liquid hydrocarbons contained
within the abandoned section poses no potential haz-
852.32 Investigation of Reports From
Outside
ard. Air or inert gas may be used for purging, or the
Sources. Any notification from an outside source(such
facility may be filled with water or other inert material
as police or fire department, other utility, contractor,
(see para. 841.275). If air is used for purging, the oper-
customer, or general public) reporting a leak, explo-
ating company shall insure that a combustible mixture
sion, or fire, which may involve gas pipelines or other
is not present after purging. Consideration shall be
gas facilities, shall be investigated promptly. If the in-
given to any effects the abandonment may have on an
vestigation reveals a leak, the leak should be classified
active cathodic protection system and appropriate ac-
and action taken in accordance with thecriteria in
tion taken.
para. M5 of Appendix M.
(b) In cases where a main is abandoned, together
852.33 Odor or Indications From Foreign Sources. with the service lines connected to it, insofar as service
When potentially hazardous leak indications (such as lines are concerned, only the customer’s end of such
gasoline vapors, natural, sewer, or marsh gas) are service lines need be sealed as stipulated above.
found to originate from a foreign source or facility or (c) Service lines abandoned from the active mains
customer-owned piping, they shall be reported to the should be disconnected as close to themain as practica-
operator of the facility and, where appropriate, to the ble.
police department, fire department, or other govern- (d) All valves left in the abandoned segment should
mental agency. When the company’s pipeline is con- be closed. If the segment is long and there are few line
nected to a foreign facility (such as thecustomer’s pip- valves, consideration should be given to plugging the
ing), necessary action, such as disconnecting or segment at intervals.
13
(e) All above-grade valves, risers, and vault and (b) After compliance with (a) above, whenever ther-
valve box covers shall be removed. Vault and valve box moplastic pipe or tubing is pinched and reopened, it is
voids shall befilled with suitable compacted backfill required that:
material. (1) the work be done with equipment and proce-
dures that have been established and proven by test to
852.42 Temporarily Disconnected Service. When- be capable of performing the operation safely and ef-
ever service to a customer is temporarily discontinued, fectively;
one of the following shall be complied with. (2) the pinched and reopened area of the pipe or
(a) The valve that is closed to prevent the flow ofgas tubing be reinforced in accordance with the appropri-
to thecustomer shall be provided with a locking device ate provisions of para. 852.52, unless it has been deter-
or other means designed to prevent the opening of the mined by investigation and test that pinching and re-
valve by persons other than those authorized by the opening does not significantly affect the long-term
operating company. properties of the pipe or tubing.
(6) A mechanical service or fitting that will prevent
the flow of gas shall be installed in the service line or 852.52 Repair of Plastic Pipe or Tubing. If at any
in the meter assembly. time an injurious defect, groove, gouge, or dentis found
(c) The customer’s piping shall be physically dis- in plastic pipe or tubing, the damaged or defective sec-
connected from the gas supply and the open pipe ends tion shall be replaced unless satisfactory repairs are
sealed. made.
Repairs shall be made in accordance with qualified
852.43 Test RequirementsforReinstatingAban- procedures which have been established and proven by
doned Facilities andTemporarily Disconnected Ser- test and in accordance with the following.
viceLines. Facilities previously abandoned shall be (a) The recommendations of the plastic manufac-
tested in the same manner asnew facilities before being turer shall be taken into consideration when determin-
reinstated. ing the type of repair to be made. Special consideration
Service lines previously abandoned shall be tested in shall be given to the extent of fiber damage in the case
the same manner as new service lines before being rein- of thermosetting plastic pipe.
stated. (6) If a patch or full encirclement sleeve is used, it
Service lines temporarily disconnected because of shall extend at least Y2 in. beyond the damaged area.
main renewals or other planned work shall be tested (c) If a full encirclement split sleeveis used, the
from the point of disconnection to theservice line valve joining line between the halves of the sleeve shall be as
in the same manner as new service lines before recon- far as possible from the defect, but in no case closer
necting, except: than 5” in. Suitable precautions shall be taken to assure
(0) when provisions to maintain continuous service a proper fit at the longitudinal seam.
are made, such as by installation of a bypass, any por- (d) The patch or sleeve material shall be the same
tion of the original service line used to maintain contin- type and grade as the pipe or tubing being repaired.
uous service need not be tested; or Wall thickness of the patch or sleeve shall be at least
(b) when the service line has been designed, in- equal to that of the pipe or tubing.
stalled, tested, and maintained in accordance with the (e) The method of attachment of the patch or sleeve
requirements of this Code. shall be compatible with the material and shall conform
to the applicable provisions of para. 842.392. Precau-
tions shall be taken to assure a proper fit and acomplete
bond between the patch or sleeve and the pipe being
852.5 Plastic Pipe Maintenance repaired. The patch or sleeve shall be clamped or held
852.51 pinching andReopening of Thermoplastic in-place by other suitable means during the setting or
Pipe and Tubing for Pressure Control Purposes curing of the bonding material or during the hardening
(a) Before thermoplastic pipe and tubing is pinched Of a heat-fusion bond. ExcessSolventCement shall be
and reopened, it is required that investigations and tests removed from the edges Of the Patch Or
be made to determine that the particular type, grade,
size, and wall thickness of pipe or tubing of the same
852.6 Piping
Maintenance
Records
manufacture can be pinched and reopened without
causing failure under the conditions which will prevail 852.61 Whenever any portion or section of an exist-
at the time of the pinching and reopening. ing underground distribution piping system is uncov-
14
ered for operating or maintenance purposes or for the compressor units shall be established by the operating
installation of new facilities, the following information company. The operating company shall take appropri-
shall be recorded: ate steps to see that the approved practices are fol-
(a) the condition of the surface of bare pipe, if pitted lowed.
or generally corroded;
853.12 Inspection and Testing of Relief Valves. All
(b) the condition of the pipe surface and of the pro-
pressure relieving devices in compressor stations shall
tective coating where the coating has deteriorated to
be inspected or tested, or both, in accordance with para.
the extent that the pipe is corroding underneath;
853.3 and all devices except rupture disks shall be oper-
(c) any damaged protective coating;
ated periodically to determine that they open at the
(d) any repairs made.
correct set pressure. Any defective or inadequate equip-
852.62 Whenever broken cast iron facilities are un- ment found shall be promptly repaired or replaced. All
covered, the cause of breakage, such as thermal effect, remote control shutdowndevices shall be inspected and
backfill, or construction by others, shall be recorded if tested at least annually to determine that they function
it can be determined. properly.
852.63 Distribution piping condition records shall be 853.13 Repairs to Compressor Station Piping. All
analyzed periodically. Any indicated remedial action scheduled repairs to compressor station piping operat-
on the piping system shall be taken and recorded. ing at hoop stresslevels at or above 40% of the specified
minimum yield strength shall be done in accordance
852.7 Cast
Iron
Pipe
Maintenance with para. 851.3, except that the use of a welded patch
is prohibited. Testing repairs shall be done in accord-
852.71 Each cast iron caulked bell and spigot joint ance with para. 851.4.
operating at pressures of 25 psig or more which is
exposed for any reason must be sealed with a mechani- 853.14 Isolation of Equipment for Maintenance or
cal leak clamp or a material or device which does not Alterations. The operating company shall establish
reduce the flexibility ofthe joint andpermanently seals procedures for isolation of units or sections of piping
and bonds. for maintenance, and for purging priortoreturning
units to service, and shall follow these established pro-
852.72 Each cast iron caulked bell and spigot joint cedures in all cases.
operating at pressures of less than 25 psig which is
exposed for any reason must be sealed by a means other 853.15 Storage of Combustible Materials. All
than caulking. flammable or combustible materials in quantities
beyond those required for everyday use or other than
852.73 When a section of cast iron pipe is exposedfor those normally used in compressor buildings shall be
any reason, an inspection shall be made to determine stored in a separate structure built of noncombustible
if graphitization exists. If detrimental graphitization is material located a suitable distance from the compres-
found, the affected segment must be replaced. sor building. All aboveground oil or gasoline storage
852.74 When an operating company has knowledge tanks shall be protected in accordance with ANSI/
that the support for a segment of a buried cast iron NFPA 30.
pipeline is disturbed:
(a) that segment of the pipeline must be protected as 853.2 Procedures for Maintaining Pipe-Type and
necessary against damage during the disturbance; Bottle-Type Holders in Safe Operating
(b) as soon as possible, appropriate steps must be Condition
taken to provide permanentprotection for the dis-
turbed segment from damage that might result from 853.21 Each operating company having a pipe-type
external loads. or bottle-type holder shall prepare and place in its files
a plan for the systematic, routine inspection and testing
of the facilities which has the following provisions.
853 MISCELLANEOUS
FACILITIES
853.211 Procedures shall be followed to enable the
MAINTENANCE
detection of external corrosion before the strength of
853.1 Compressor Station
Maintenance the container has been impaired.
853.11 Compressors and Prime Movers. The start- 853.212 Periodic sampling and testing of gas in
ing, operating,andshutdownprocedures for all gas storage willbe made to determine the dew point of
75
vapors contained in the stored gas that might cause relief devices on a piping system or facility is adequate
internal corrosion or interfere with the safe operations to limit the pressure at all times to values prescribed by
of the storage plant. the Code. This review should be based on the operating
853.213 The pressure control and pressure lim- conditions that create the maximum probable require-
iting equipment will be inspected and tested periodi- ment for relief capacity in each case, even though such
cally to see if it is in a safe operating condition and has operating conditions actually occurinfrequently, or for
adequate capacity. only short periods of time, or both. If it is determined
that the relieving equipment is of insufficient capacity,
853.22 Eachoperating company, having prepared steps shall be taken to install new or additional equip-
such a plan as prescribed in para. 853.21, shall follow ment to provide adequate capacity.
the plan and keep records which detail the inspection
and testing work done and the conditions found.
853.32 Whenever abnormal conditions are imposed
on pressure or flow control devices, the incident shall
853.23 All unsatisfactory conditions found shall be be investigated and a determination made as to theneed
promptly corrected. for inspection or repairs, or both. Abnormalconditions
may include regulator bodies which are subjected to
853.3 Maintenance of Pressure Limiting and erosive service conditions or contaminants from up-
Pressure Regulating Stations stream construction and hydrostatic testing.
853.31 All pressure limiting stations, relief devices, 853.33
and other pressure regulating stations and equipment (a) An inspection or test, or both, of stop valves
shall be subject to systematic, periodic inspections and shall be made to insure that thevalves willoperate and
suitable tests, or reviewed to determine that they are: are correctly positioned. (Caution shall be usedto avoid
(a) in good mechanical condition. Visual inspec- any undesirable effect on pressure during operational
tions shall be made to determine that equipment is checks.) The following shall be included in the inspec-
properly installed and protected from dirt, liquids, or tion or test, or both:
other conditions that might prevent proper operation. (1) station inlet, outlet, and bypass valves;
The following shall be included in the inspection where (2) relief device isolating valves;
appropriate: (3) control, sensing, and supply line valves.
(1) station piping supports, pits, andvaults for (b) The final inspection procedure shall include the
general condition and indications of ground settlement. following:
See para. 853.5 for vault maintenance. (1) a check for proper position of all valves. Spe-
(2) station doors andgates and pit vault covers to cial attention shall be given to regulator station bypass
insure that they are functioning properly and that ac- valves, relief device isolating valves, and valves in con-
cess is adequate and free from obstructions; trol, sensing, and supply lines.
(3) ventilating equipment installed in station (2) restoration of all locking and security devices
buildings or vaults for proper operation and for evi- to proper position.
dence of accumulation of water, ice, snow, or other 853.34
obstructions; (a) Every distribution system supplied by more than
(4) control, sensing, and supply lines for condi- onedistrict pressure regulating station shall be
tions which could result in a failure; equipped with telemetering or recording pressure gages
(5) all locking devices for proper operation; to indicate the gas pressure in the district.
(6) station schematics for correctness. (b) On distribution systems supplied by a single dis-
(b) adequate from the standpoint of capacity and trict pressure regulating station,theoperating com-
reliability of operation for the service in which they are pany shall determine the necessity of installing such
employed and set to function at the correct pressure. gages in the district. In making this determination, the
(1) If acceptable operation is not obtained during operating company shall take into consideration the
the operational check, the cause of the malfunction operating conditions such as the number of customers
shall be determined and the appropriate components supplied, the operating pressures, the capacity of the
shall be adjusted, repaired, or replaced as required. installation, etc.
After repair, the component shall again be checked for (c) If there are indications of abnormal high or low
proper operation. pressure, theregulatorandthe auxiliary equipment
(2) at least once each calendar year, a review shall shall be inspected and the necessary measures shall be
be made to ensure that the combined capacity of the employed to rectify any unsatisfactory operating condi-
76
tions. Suitable periodic inspections of single district Unsatisfactory conditions encountered shall be cor-
pressure regulation stations not equipped with teleme- rected.
tering or recording gages shall be made to determine
853.44 Valve Records. A record shall be maintained
that the pressure regulating equipment is functioning
for locating valves covered by paras. 853.41 and 853.42.
properly.
These records may be maintained on operating maps,
separate files, or summary sheets, and the information
853.4 Valve
Maintenance on these records shall be readily accessible to personnel
required to respond to emergencies.
853.41 Pipeline valves that would be required to be
operated during an emergency shall be inspected peri- 853.45 Preventionof Accidental Operation.Precau-
odically and partially operated at least once a year to tions shall be taken to prevent accidental operation of
provide safe and proper operating conditions. any valve covered by paras. 853.41 and 853.42. Acci-
(a) Routine valve maintenance procedures shall in- dental valve operation by gas company personnel and
clude, but not be limited to, the following: the general public should be considered in taking these
(1) servicing in accordance with written proce- precautions. Some recommended actions to be taken,
dures by adequately trained personnel; where applicable, are as follows.
(2) accurate system maps for use during routine (a) Lock valves in aboveground settings readily ac-
or emergency conditions; cessible to the general public, that are not enclosed by
(3) valve security to prevent service interruptions, a building or fence.
tampering, etc., as required; (b) Lock valves located in vaults, if accessible to the
(4) employee training programs to familiarize general public.
personnel with the correct valve maintenance proce- (c) Identify the valve by tagging, color coding, or
dures. any other suitable means of identification.
(b) Emergency valve maintenance procedures in-
clude:
853.5
Vault
Maintenance
(1) written contingency plans to be followed dur-
ing any type emergency; Each vault housing a pressure limiting, pressure re-
(2) training personnel to anticipate all potential lief, or pressure regulating station shall be inspected to
hazards; determine its condition each time the equipment is in-
(3) furnishing tools and equipment as required, spected and tested in accordance with para. 853.3. For
including auxiliary breathing equipment, to meet antic- any vault which personnel enter, the atmosphere shall
ipated emergency valve servicing and/or maintenance be tested for combustible gas. If the atmosphereis haz-
requirements. ardous, the cause shall be determined. The vault shall
be inspected for adequate ventilation. The condition of
853.42 Distribution System Valves. Valves, the use
the vault covers shall be carefully examined for haz-
of which may be necessary for the safe operation of a
ards. Unsatisfactory conditions disclosed shall be cor-
gas distribution system, shall be checked and serviced,
rected. The applicable provisions of para. 821.6 shall be
including lubrication where necessary, at sufficiently
met before any welding isperformed in the vault. Main-
frequent intervals to assure their satisfactory operation.
tenance work performed in the vault shall be in accord-
Inspection shall include checking of alignment to per-
ance with procedures developed per para. 850.2(a), giv-
mit use of a key or wrench and clearing from the valve
ing particular consideration to the monitoring of the
box or vault any debris which would interfere with or
atmosphere and safety protection for personnel in the
delay the operation of the valve. System maps showing
vault.
valve location should be available.
853.43 Service Line Valves. Outside shutoff valves
installed in service lines supplying places of public as- 854 LOCATION
CLASS AND CHANGES
sembly, such as theatres, churches,schools, and hospi- IN NUMBER OF BUILDINGS
tals, shall be inspected and lubricated where required INTENDED FOR HUMAN
at sufficiently frequent intervals to assure their satisfac- OCCUPANCY
tory operation. The inspection shall determine if the
854.1
valve is accessible, if the alignment is satisfactory, and
if the valve box or vault, if used, contains debris which (a) A continuing surveillance of existing steel pipe-
would interfere with or delay the operation of the valve. lines or mains operating in excess of 40% of specified
TABLE 854.U~)
LOCATION CLASS
Original
[Note (113 Current
Location Number of Location Number of Maximum Allowable
Class Buildings Class Buildings Operating Pressure
1 Division 1 0-10 11-25 Previous MAOP but not greater than 80% SMYS
1 Division 2 0-10 11-25 Previous MAOP but not greater than 72% SMYS
1 0-10 26-45 0.800 X test pressure but not greater than 72% SMYS
1 0-1 0 46-65 0.667 X test pressure but not greater than 60% SMYS
1 0-10 66 + 0.667 x t e s t pressure but not greater than 60% SMYS
1 0-10 Note (2) 0.555 x t e s t pressure but not greater than 50% SMYS
2 1145 2 46-65 Previous MAOP but not greater than 60% SMYS
2 1145 3 66 + 0.667 X t e s t pressure but not greater than 60% SMYS
2 1145 4 Note (2) 0.555 x t e s t pressure but not greater than 50% SMYS
3 46 + 4 Note (2) 0.555 x t e s t pressure but not greater than 50% SMYS
NOTES:
(1) At time of design and construction.
(2) Multistory buildings become prevalent.
minimum yield strength shall be maintained to deter- (3) operatingandmaintenance history of the
mine if additional buildings intended for human occu- pipeline or main;
pancy have been constructed.Thetotalnumber of (4) the maximum operating pressure and the cor-
buildings intended for human occupancy shall be responding operating hoop stress. The pressure gradi-
counted to determine the current Location Class in ent may be taken into account in the section of the
accordance with the procedures specifiedin paras. pipeline or main directly affected by the increasing
840.2(a) and (b). number of buildings intended for human occupancy.
(b) In accordance with the principles stated in para. (5) the actual area affected by the increase in the
840.l(c), and with the knowledge that the number of number of buildings intended for human occupancy
buildings intended for human occupancy is not an and physical barriers or other factors which may limit
exact or absolute means of determining damage-caus- the further expansion of the more densely populated
ing activities, judgment must be used to determine the area.
changes that should be made to items, such as operat-
ing stress levels, frequency of patrolling and cathodic
protection requirements, as additional buildings in-
854.2
tended for human occupancy are constructed.
(c) When there is an increase in the number of If the study described in para. 854.1 indicates that
buildings intended for humanoccupancy to or near the the established maximum allowable operating pressure
upper limit of the Location Class listed in Table of a section of pipeline or main is not commensurate
854.1(c) to the extent that a change in Location Class with existing Location Classes 2, 3, or 4, andsuch
is likely, a studyshall be made to determine thefollow- section is in satisfactory physical condition, the maxi-
ing: mum allowable operating pressure of that section shall
( I ) the design, construction,and testing proce- be confirmed or revised within 18 months following the
dures followed in the original construction and a com- Location Class change as follows.
parison of such procedures with the applicable provi- (a) If the section involved has been previously tested
sions of this Code; in place for aperiod of not less than 2 hr, themaximum
(2) the physical conditions of the pipeline or main allowable operating pressure shall be confirmed or re-
to the extent that this can be ascertained from current duced so that it does not exceed that allowed in Table
tests and evaluation records; 854.1(c).
78
(b) If the previous test pressure was not high enough allowable operating pressure, para. 854.2(a), or testing,
to allow the pipeline to retain its MAOP or to achieve para. 854.2(b), no additional valves will normally be
an acceptable lower MAOP in the Location Class ac- required.
cording to (a) above, the pipeline may either retain its (b) Where a segment of pipeline must be replaced to
MAOP or become qualified for an acceptable lower maintain the established maximum allowable operating
MAOP if it is retested at a higher test pressure for a pressure as provided in para. 854.2(d), consideration
period of not less than 2 hr in compliance with the should be given to valve spacing as follows.
applicable provisions of this Code. If the new strength ( I ) Where a short section of line is replaced, addi-
test is not performed during the 18 month period fol- tional valves will normally not be required.
lowing the Location Class change, the MAOP must be (2) Where the replacement section involves a mile
reduced so as to not exceed the design pressure com- or more of transmission line, additional valve installa-
mensurate with the requirements of Chapter IV at the tion shall be considered to conform to the spacing re-
end of the 18 month period. However, if the test is quirements in para. 846.11.
performed any time after the 18 month period has ex-
pired, the MAOPmay be increased to the level it would
have achieved if the test had been performed during 855
CONCENTRATIONS OF PEOPLE IN
that 18 month period. LOCATION CLASSES 1 AND 2
(c) An MAOP that has been confirmed or revised
855.1
according to (a) or (b) above shall not exceed that
established by this Code or previously established by (a)(l) Where a facility such as a hospital, school,
applicable editions of the B31.8 Code. Confirmation or motor hotel, or recreational area of an organized char-
revision according to para. 854.2 shall not preclude the acter such as a sportsfacility, fairground or amusement
application of para. 845.6. park, is built near an existing steel pipeline in Location
(d) Where operating conditions require that the ex- Classes 1 or 2, consideration shall be given to the possi-
isting maximum allowable operating pressure be main- ble consequence of a failure, even though the probabil-
tained, and thepipeline cannot be brought into compli- ity of such an occurrence is very unlikely if the line is
ance as provided in (a), (b), or (c) above, the pipe within designed, constructed, and operated in accordance with
the areaof the Location Class change shall be replaced this Code. Where such a facility results in frequent
with pipe commensurate with the requirements of concentrations of people, the requirements of (b) below
Chapter IV, using the design factor obtained from shall apply.
Table 841.114A for the appropriate Location Class. (2) However, (b) below need not be applied if the
facility is used infrequently, and the lesser usage com-
bined with the very remote possibility of a failure at
854.3
that particularpoint on the pipeline virtually eliminates
Where the maximum allowable operating pressure of the possibility of an occurrence.
a section of pipeline or main is revised in accordance (6) Pipelines near place of public assembly as out-
with para. 854.2 and becomes less than the maximum linedin (a) above shall have a maximum allowable
allowable operating pressure of the pipeline or main of hoop stress not exceeding50% of SMYS, or the operat-
which it is a part, a suitable pressure relieving or pres- ing company may make the study described in para.
sure limiting device shall be installed in accordance 854.1(c) and determine that compliance with the fol-
with provisions of paras. 845.1, 845.2, and 845.212. lowing will result in an adequate level of safety.
( I ) The segment is hydrostatically retested for at
least 2 hr to a minimum stress level of:
854.4
(a) 100% of SMYS if the pipeline is operating
Where the study required in para. 854.1 indicates over 60% and up to 72% of SMYS;
that the established maximum allowable operating (6) 90% of SMYS if the pipeline is operating
pressure of a transmission pipeline is not commensu- over 50% and up to 60%of SMYS, unless the segment
rate with that permitted by this Code for the new loca- was tested previously to a pressure of at least 1.5 times
tion class, the sectionalizing valve spacing shall be re- the MAOP.
viewed and revised as follows. If the segment contains pipe of various operating
(a) If the section of pipe is qualified for continued stress levels, the minimum test stress levels stated above
service because of a prior test, para. 854.2(a), or can be should bebasedon the SMYS of the pipe with the
brought into compliance by lowering the maximum highest operating stress level.
79
(2) Patrols and leakage surveys are conducted at (a) Review historical records of the pipeline as indi-
intervals consistent with those established by the oper- cated in para. 856.2.
ating company for Location Class 3. (6) Inspect all above ground segments of the pipe-
(3) When the maximum allowable hoop stress ex- line for physical condition. During theinspection, iden-
ceeds 60% SMYS, adequate periodic visual inspections tify the material where possible for comparison with
are conductedby an appropriate sampling technique or available records.
insrumented inspections capable of detecting gouges (c) Operating Stress LeveI Study
and corrosion damage are madeto confirm the contin- (I) Establish the numberof buildings intended for
uing satisfactory physical condition of the pipe. human occupancy and determine the design factor for
(4) If the nearby facility islikely to encourage each segment in accordance with para. 840.2 and Table
additionalconstruction activity, provide appropriate 841.1 14A.
pipeline markers. (2) Conduct a study to compare the proposed op-
erating stress levels with those allowed for the Location
Class.
856 PIPELINE SERVICE
CONVERSIONS (3) Make the necessary replacements to insure
that theoperating stress level iscommensurate with the
General
856.1
Location Class.
The intent of this section is to set out requirements (d) If necessary, make inspections of appropriate
to allow an operator of a steel pipeline previously used sections of underground piping to determine thecondi-
for service not covered by this Code to qualify that tion of the pipeline.
pipeline for service under this Code. For a dual service (e) Make replacements, repairs, or alterations
pipeline used alternately to transport liquids in confor- which in the operatingcompany’sjudgment are advisa-
mance with an appropriate Code, such as ASME ble.
B31.4, and gas under this Code, only the initial conver- cf) Perform a strength test in accordance with this
sion to gas service requires qualification testing. Code to establish the maximum allowable operating
pressure of the pipeline, unless the pipeline has been so
tested previously.
856.2
Historical
Records
Study
(g) Perform a leak test in conformance with this
Review the following historical data and make an Code.
evaluation of the pipeline’s condition. (h) Within 1 year of thedatethatthe converted
(a) Study all available information on the original pipeline is placed in gas service, provide cathodic pro-
pipeline design, inspection, and testing. Particular at- tection as set out in para. 862.2, except that wherever
tention should be paid to welding procedures used and feasible, replacement sections andother new piping
other joining methods, internal and external coating, shall be cathodically protected as required for new
pipe, and other material descriptions. pipelines.
(b) Study available operating and maintenance data
including leak records, inspections, failures, cathodic
856.4 Conversion
Procedure
protection, and internal corrosion control practices.
(c) The age of the pipeline and the length of time it Prepare awritten procedure outlining thesteps to be
may have been out of service should alsobe considered followed during the study and conversion of the pipe-
in preparing a final evaluation to convert the pipeline line system. Note any unusual conditions relating to
to gas service. this conversion.
80
CHAPTER VI
CORROSION CONTROL
CORROSION
860 CONTROL lines, and pipe-type and bottle-type holders installed
under this Code shall, except as permitted under para.
861 SCOPE
862.113, be externally coated and cathodically pro-
(a) ThisChaptercontainsthe minimum require- tected unless it can be demonstrated by test or experi-
ments and procedures for corrosion control of exposed, ence that the materials are resistant to corrosion in the
buried, and submerged metallic piping and compo- environment in which they are installed. Consideration
nents. (See Chapter VI11 for special offshore require- shall be givento the handling, shipping, storing, instal-
ments.) This Chapter containsminimum requirements lation conditions, and the service environment and ca-
and procedures for controlling external (including at- thodic protection requirements when selecting the
mospheric) and internal corrosion. This Chapter is ap- coating materials. The Corrosion Data Survey, pub-
plicable to the design and installation of new piping lished by the National Association of Corrosion Engi-
systems and to theoperation and maintenance of exist- neers (NACE), is a source of information on materials
ing piping systems. performance in corrosive environments.
(6) The provisions of this Chaptershould be applied
under the direction of competent corrosion personnel.
Every specificsituation cannotbe anticipated; therefore, 862.112 Coating Requirements
the application and evaluation of corrosion control (a) The surface preparation should be compatible
practices require a significant amount of competent with the coating to be applied. The pipe surface shall
judgment in order tobe effective mitigating
in corrosion. be free of deleterious materials, such as rust, scale,
(c) Deviations from the provisions of this Chapter moisture, dirt, oils, lacquers, and varnish. The surface
are permissible in specific situations, provided the oper- shall be inspected for irregularities which could pro-
ating company can demonstrate that theobjectives ex- trude through thecoating. Any suchirregularities shall
pressed herein have been achieved. be removed. Further information can be obtained from
(d) Corrosion control requirements and procedures NACE RP-02-75.
may in many instances require measures in addition to (b) Suitable coatings, including compatible field
those shown in this Chapter. Each operatingcompany joint and patch coatings, shall be selected, giving con-
shall establish procedures to implement its corrosion sideration to handling, shipping, storing, installation
control program, including the requirements of this condition, moisture adsorption,operating tempera-
chapter, to achieve the desired objectives. Procedures, tures of the pipeline, environmental factors (including
including those for design, installation, and mainte- thenature of the soil in contact with the coating),
nance of cathodic protection systems, shall be prepared adhesion characteristics, and dielectric strength.
and implemented by or under the direction of persons (c) Coatings shall be applied in a manner that en-
qualified by training or experience, or both, in corro- sures effective adhesion to the pipe. Voids, wrinkles,
sion control methods. holidays, and gas entrapment should be avoided.
(d) The coating shall be visually inspected for de-
fects prior to lowering the pipe in the ditch. Insulating
862
EXTERNAL CORROSION CONTROL type coatings on mains and transmission lines shall be
862.1 New Installations inspected for holidays by the most appropriate method.
Coating defects or damage that may impair effective
862.11 Buried Steel Facilities corrosion control shall be repaired before installing the
862.111 General. All new transmission pipelines, pipe in the ditch.
compressor station piping, distribution mains, service (e) In addition to the provisions of paras. 841.222,
81
841.252, and 841.253, care shall be exercised in han- and operation of the pipeline by means of suitable de-
dling, storage, and installation to prevent damage to sign for bonding, shielding, or grounding techniques;
the coating, including measures such as the following. (b) the possibility of lightning or fault currents
(1) Minimize handling of coated pipe. Use equip- inducing voltages sufficient to puncture pipe coatings
ment least likely to damage the coating, e.g., belts or or pipe;
cradles instead of cables. (c) possible adverse effects on cathodic protec-
(2) Use padded skids where appropriate. tion, communications, or other electronic facilities;
(3) Stack or store pipe in a manner that minimizes (d) the corrosive effects of high voltage direct
damage to coating. current (HVDC) power systems.
(3) further information whichmaybeobtained
862.113 Cathodic Protection Requirements. Un-
from NACE RP-01-77 and EPRI EL-3106.
less it can be demonstrated by tests or experience that
cathodic protection is not needed, all buried or sub- 862.115 Electrical Connections and Monitoring
merged facilities with insulating type coatings, except Points
facilitiesinstalled for a limitedservicelife, shall be (a) Except for offshore, sufficient test points should
cathodically protected as soon as feasible following in- be installed to demonstrate the effectiveness of corro-
stallation; except that minor replacements or exten- sion control or the need for cathodic protection. (See
sions shall be protected as covered by para. 862.212. Chapter VI11 for special considerations for offshore
Facilities installed for a limited service lifeneed not pipelines.)
be cathodically protected if it can be demonstrated (6) Special attention shall be given to the manner of
that the facility will not experience corrosion that will installation of electrical leads used for corrosion con-
cause it to be harmful to the public or environment. trol or testing to avoid harmful stress concentration at
Cathodic protection systems shall be designed to pro- the point of attachment to the pipe. Acceptable meth-
tect the buried or submerged system in its entirety. A ods include, but are not limited to:
facility is considered to be cathodically protected ( I ) electrical leads attached directly on the pipe or
when it meets one or more of the criteria established by the thermit welding process, usingcopper oxide and
in Appendix K. aluminum powder. The size of the thermit welding
862.114 Electrical Isolation charge shall not exceed a 15 g cartridge.
(a) All coatedtransmission and distribution systems (2) attachment of electrical leads directly to the
shall be electrically isolatedat all interconnections with pipe by the use of soft soldersor other materials which
foreign systems including customer’s fuel lines, except do not involve temperatures exceeding those for soft
where underground metallic structures are electrically solders.
interconnected and cathodically protected as a unit. (c) All pipe that is barred for electrical lead connec-
Steel pipelines shall be electrically isolated from cast tions and all bared electrical lead wires shall be pro-
iron, ductile iron, or nonferrous metal pipelines and tected by electrical insulating material compatible with
components. Electrical tests shall be madeof transmis- existing coating.
sion and distribution systems to locate unintentional 862.116 Electrical Interference
contacts with other metallic structures. If such contacts (a) Impressed current cathodic protection systems
exist, they shall be corrected. See para. 841.143 for shall be designed,installed, and operated so as to mini-
clearance requirements. mize adverse effects on existing metallic structures.
(b) Where a gas pipeline parallels overhead electric (b) Field tests shall be conducted to determine the
transmission lines, consideration shall be given to: adverse electrical interference from foreign structures,
(1) investigating the necessity of protecting in- including DC electrical facilities. The effects shall be
sulating joints in the pipeline against induced voltages mitigated by such means as control bonds, supplemen-
resulting from ground faults and lightning. Such pro- tary cathodic protection, protective coatings, and in-
tection can be obtained by connecting buried galvanic sulating devices.
anodes to the pipe near the insulatingjoints or by brid-
ging the pipeline insulator with a spark gap, or both, or 862.117 Casings. The useof metalliccasings
by other effective means. should be avoided insofar as possible from a corrosion
(2) making a study in collaboration with the elec- control standpoint. However, it is recognized that in-
tric company, taking the following factors into consid- stallation of metallic casings is frequently required or
eration and applying remedial measures as appropriate: desirable to facilitate construction, as an economical
(a) the need to mitigate induced AC voltages or method of protecting existingpipelines, to provide
their effects on personnel safety during construction structural protection from heavy or impact loads, or
82
83
termining the Remaining Strength of Corroded Pipe- ings that are part of the underground system shall be
lines. maintained as necessary to ensure effectiveness of ca-
862.214 Cathodic Protection Criteria thodic protection. Electrical measurementsand inspec-
(a) A facility is considered to be cathodically pro- tions shall be made as necessary to provide timely evi-
tected when it meets oneor more of the criteria estab- dence of shorts that would adversely affect cathodic
lished in Appendix K. protection. If evidence of shorts between the carrier
(6) It is not intended that cathodic protection be pipe and casing is found that renders cathodic protec-
limited to these criteria if it can be demonstrated by tion of the pipeline or main ineffective, or if evidence
other means that adequate control of corrosion has of corrosion of the carrier pipe inside the casing is
been achieved. found, remedial measuresshall be taken as necessary to
correct the condition or minimize corrosion insidethe
862.215 Electrical Interference casing.
(a) Adverse electrical interference from or to for-
eign structures as determined byfield tests shall be 862.22 Buried Cast Iron, Wrought Iron, and Ductile
mitigated. Iron
(b) Facilitiesformitigatingelectricalinterference 862.221 Evaluation. The recordsavailable as a
shall be periodically monitored. result of leakage surveysand normal maintenancework
862.216 Examination When Exposed in accordance withparas. 852.2 and 852.6 shall be
(a) Wheneveraburiedfacilityisexposed during routinely reviewed to determine pipe conditions. Ap-
normal maintenance or construction activities, a visual propriate corrective measures shall be taken in accord-
inspection shallbe made of the coating condition and/ ance with para. 862.222 if such review reveals that a
or the metal surface, if exposed. condition whichmay affect publicand employee safety
(b) The extent of any corrosion shallbe evaluated in exists. Pipe size,operating pressure, terrain, recent un-
accordance with para. 862.213. derground construction, and proximity and number of
other underground facilities and buildings, as well as
862.217 Operation and Maintenance of Cathodic pipe condition, shall be considered in determining the
Protection System presence of such a condition.
(a) Inspections shall be made as required to main-
tain continuous and effective operation of the cathodic 862.222 Corrective Measures. The magnitude of
protection system. the problem willdictate the corrective measures which
(6) Electrical tests shall be made periodicallyto de- shallbeconsidered.Theymayinclude, but are not
termine that the piping system is protected in accord- limited to:
ance with the applicable criteria. (a) pipe repair;
(c) The type, frequency,and location of inspections (6) pipe replacement;
and tests shallbe adequate to establish with reasonable (c) pipe reinforcement or support, or both;
accuracy the degree of protection providedon the pip- (d) pressure reduction.
ing system. Frequencyshould be determined by consid-
eration of, but not limited to, the following: 862.223 Installation of Electrical Connections
(1) condition of pipe; (a) Electrical connections may be attached directly
(2) method of cathodic protection; onto the cast or ductile iron pipe by the thermit welding
(3) corrosiveness of the environment; process using copper oxide and aluminum powder. The
(4) probability of loss or interruption of protec- size of the thermit welding charge shall not exceed a32
tion; g cartridge.
(5) operating experience,includinginspections (b) All pipe that is baredfor test lead connections
and leak investigations; and all bared test lead wires shall be protected by elec-
(6) design life of the cathodic protection installa- trical insulating material compatible with existing coat-
tion; ing.
(7) public or employee safety. 862.224 Electrical Interference
(d) Where the tests or surveysindicate that adequate (a) If an impressed current type cathodic protection
protection does not exist, appropriate corrective mea- system is used, the anodes shall be located so as to
sure shall be taken. mitigate adverse effect on existingunderground metal-
862.218 Casings. Electrical isolation of cathodi- lic structures.
cally protected pipelinesand mains from metallic cas- (b) Adverseelectricalinterferencefromforeign
84
structures as determined byfield tests shall be miti- for the protection of the facility from the corrosive
gated. media involved, basedon the type of coating and meth-
ods of application;
862.23 Requirements for Cast Iron and Ductile Iron (2) applied coatings shall be inspected in accord-
Piping Facilities ExposedtoAtmosphere. Above- ance with established specifications or accepted prac-
ground cast iron and ductile iron pipe shall be suitably tice;
protected in areas where severe atmospheric corrosion (3) when coated pipe or other components are
may occur. joined by welding or other methods which leave the
862.24 Other Metallic Materials. When a nonfer- parent metal exposed, provision shall be made to pre-
rous metal or ferrous alloy component is found to have vent joint corrosion, such as cleaning and recoating or
corroded to the point where public or employee safety the continuing use of a suitable inhibitor;
may be affected, it shall be reconditioned in accordance (4) if pigs or spheres are to be used, the types of
with para. 862.13 or replaced. The replacement shall coating and pitting tools used should be evaluated and
meet one of the following criteria: chosen to prevent damage to the internal coating.
(a) it shall be constructed with other materials or (b) When a corrosion inhibitor is to be used as an
geometry, or both, designed for the remaining life of the additive to the gas streams:
parent facility; or (1) the equipment for the holding, transfer, and
(b) it shall be cathodically or otherwise protected. injection of the inhibitor into the stream shall be in-
cluded in the design;
862.25 Atmospheric Corrosion.Facilities exposed to (2) the operation of the injection program should
the atmosphere shall be periodically inspected for indi- be a part of the planning;
cation of surface corrosion. Where corrosion is taking (3) sufficient test coupon holders or other moni-
place to the extent that public or employee safety may toring equipment shall be provided to allow for con-
be affected,the facility shall be reconditioned in accord- tinued program evaluations;
ance with para. 862.12 or replaced. Special considera- (4) the corrosion inhibitor selected shall be of a
tion shall be given to surfaces near the ground line. type that will not cause deterioration of any compo-
nents of the piping system.
(c) When a pipeline pigging system is planned:
( I ) scraper traps for the insertion and removal of
863
INTERNAL
CORROSION
CONTROL pigs or spheres, or both, shall be provided;
General
863.1 (2) sections of pipeline to be traversed by pigs or
spheres shall be designed to prevent damage to pigs,
When corrosive gas istransported, provision shall be spheres, pipes, or fittings during operations;
made to protect the piping system from detrimental (3) piping for pigs or spheres shall be designed to
corrosion. Gas containing free water under the condi- guide the tool and the materials they propel effectively
tions at which it will be transported shall be assumed and safely;
to be corrosive, unless proven to be noncorrosive by (4) provision shall be made for effective accumu-
recognized tests or experience. lation and handling of liquid and solid materials
removed from the pipeline by pigs or spheres.
(d) When corrosion coupons, corrosion probes,
863.2 New Installations
and/or test spools are to be used:
When designing a new or replacement pipeline sys- (1) corrosion coupons, probes, or test spools shall
tem, or additions or modifications to existing systems, be installed where practical at locations where the
measures shall be considered to prevent or inhibit iuter- greatest potential for internal corrosion exists;
nal corrosion, or both. To preserve the integrity and (2) corrosion coupons, probes and test spools
efficiency of a pipeline in which it is known or antici- must be designed to permit passage of pigs or spheres
pated that corrosive gas willbe transported, the follow- when installed in sections traversed thereby.
ing factors should be included in the design and con- (e) When gasis to be treated to reduce itscor-
struction, either separately or in combination. rosivity:
(a) When internal coating is to be used to protect a ( I ) separators or dehydration equipment, or both,
piping system: may be installed;
(1) the coating shall meet the quality specifica- (2) equipment for theremoval of other deleterious
tions and the minimum dry film thickness established material from the gas should be considered.
85
03 The material of the pipe and other equipment (3) Add fittings for removal of water from low
exposed to the gas stream must resist internal corro- spots, or reposition piping to reduce sump capacities.
sion; therefore: (4) Under some circumstances, application of a
(1) materials selected for pipe and fittings shall suitable internal coating may be effective.
be compatiblewith the components of the gas, the (c) Internal corrosion control measuresshallbe
liquidscarried by the gas, and witheach other. A evaluated by an inspection and monitoring program,
source of informationonmaterialsperformance in including but not limited to, the following.
corrosive environments is the Corrosion Datu Survey, (1) The inhibitor and the inhibitor injection sys-
published by the National Association of Corrosion tem should be periodically checked.
Engineers. (2) Corrosioncoupons and testspools shall be
(2) where plastic, nonferrous, or alloy steel pipe removed and evaluated at periodic intervals.
and components are used to prevent or control internal (3) Corrosion probesshould be checked manually
corrosion, such materials shall have been determined to at intervals, or continuously or intermittently moni-
beeffective under the conditionsencountered [see tored or recorded, or both, to evaluate control of pipe-
paras.842.611(b)and849.611(b)forlimitationson line internal corrosion.
copper]; (4) A record of the internal condition of the pipe,
(3) erosion-corrosioneffectsfromhigh-velocity of leaks and repairs from corrosion,and of gas, liquids,
particles at probable pointsof turbulence and impinge- or solids quantities and corrosivity shouldbe kept and
ment should be minimized by use of erosion resistant used as a basis for changes in the pigging schedule,
materials, added wall thickness, designor flow config- inhibitor program, or gas treatment facility.
uration, and size or dimensions of the pipe and fittings. (5) When pipe is uncovered,or on exposed piping
where internal corrosion may be anticipated, pipe wall
thickness measurement or monitoring will help evalu-
863.3 Existing
Installations
ate internal corrosion.
A pipeline internal corrosion control program shall (6) Whereinspections,observation, or record
include, but not be limited to, the following. analysis indicates internal corrosion is taking place to
(a) The establishment and evaluation of a program an extent that maybe detrimental to public or em-
for the detection, prevention, or mitigation of detri- ployee safety, that portion of the system shall be re-
mental internal corrosion should include the following. paired or reconditioned, andappropriate steps takento
(1) Pipeline leakand repair records should be re- mitigate the internal corrosion.
viewed for indication of the effects of internal corro-
sion.
(2) When any part of a pipeline is removed and
the internal surfaceisaccessible for inspection,it
should be visually examined and evaluated for internal 864 PIPELINES IN ARCTIC
corrosion. ENVIRONMENTS
(3) If evidence of internal corrosion is discovered,
864.1 General
the gas shall be analyzed to determine the types and
concentrations of any corrosive agents. Special consideration must be given to the corrosion
(4) Liquids or solids removed fromthe pipeline by control requirements of buriedpipelines and other
pigging, draining, or cleanup should be analyzed as facilities installed in arctic environments, particularly
necessary for determining the presence of corrosive ma- in permafrost regions. For pipelinesin contact with
terials and evidence of corrosion products. frozen earth, the corrosion rate is reduced because of
(6) Where it is determinedthat internal corrosion is the extremely high resistivity of the soil and low ion
taking placethat could affect public or employee safety, mobility, but does not reach zero. Significant corrosion
one or more of the following protective or corrective can occur, however, in unfrozen inclusions, discontinu-
measures shall be used to control detrimental internal ous permafrost, or thaw areas such as those that may
corrosion. occur in the vicinity of rivers, lakes, springs,or pipeline
(1) An effective corrosion inhibitor shall be ap- sections where the pipe surface temperature is above
plied in a manner and quantity to protect all affected the freezing point of the environment. Cathodic protec-
portions of the piping systems. tion in localized thaw areas may be more difficult due
(2) Remove corrosive agentsby recognized meth- to the shielding of cathodic protection currents by the
ods, such as acid gas or dehydration treating plants. surrounding frozen soil. Other detrimental effects can
86
be caused by seasonal thaws which increase biological anode backfill material should be increased to reduce
and bacteriological activity in the nonpermafrost areas the effective resistance between the anode and the sur-
or in the “active layer” above underlying permafrost. rounding earth.
Pipeline facilities installed in arctic environments (d) Impressed current facilities utilizing distributed
shall be coated and cathodically protected in the same or deep anode ground beds should be used to protect
manner as pipelinesin temperate locations, and the buried station facilities and pilings where used to sup-
same consideration shall be given to the need for pro- port aboveground plant facilities. The pilings and any
tection from internal and atmospheric corrosion, ex- other adjacent underground metallic facilities must be
cept as specifically provided in this section. electrically interconnected to prevent detrimental in-
terference.
87
erated ionic or molecular activity. Elevated tempera- temperatures and are not stable. Appropriate mitiga-
tures typically occur downstream of compressor sta- tion and monitoring measures are given in para. 863.
tions or in gathering systems.
865.2 External
Coating
Requirements 866 STRESS CORROSION
AND OTHER
PHENOMENA
Selection of coatings shall take into account the par-
ticular requirements for pipeline facilities in high tem- Environmentallyinduced and other corrosion-re-
perature service. These include resistance to damage lated phenomena, including stress corrosion cracking,
from soil or secondary stresses, compatibility with any corrosion fatigue, hydrogen stress cracking, andhydro-
applied cathodic protection, and particularly resistance gen embrittlement havebeenidentified as causes of
to thermal degradation. In rocky environments,the use pipeline failure. Considerable knowledge and data have
of a protective outer wrap, select backfill,or other suit- been acquiredand assembled on these phenomena,and
able measures shallbe considered to minimize physical research is continuing as to their causes and prevention.
damage. Operating companies should be alert for evidence of
such phenomena during allpipeinspections and at
other such opportunities. Whereevidence of such a
865.3
Cathodic
Protection
Facilities condition is found, an investigative program shall be
865.31 Criteria. Criteria for cathodic protection initiated and remedialmeasurestaken as necessary.
shall be the same as for normal temperature service, Any such evidenceshould be given consideration in all
except that recognition shouldbe given to the effects of pipelinefailureinvestigations. Operating companies
decreased resistivity and increased cathodic protection should avail themselves of current technology on the
current requirements in elevated temperature service subject or consult with knowledgeable experts,or both.
on anyIR component of the pipe-to-soil potential mea- This paragraph mustbelimited to general state-
surement. Possible depolarization effects due to high ments rather than specificlimitsinregard to stress
temperature operation shall also be considered. corrosion. Stress corrosion is currently the subject of
investigative research programs and more specificdata
865.32GalvanicAnodes. Considerationshallbe will certainly be availableto the pipeline designer and
given to the impact on the performance of close gal- operating company in the future. In the interim, this
vanic anodes (especially braceletor ribbon type) subject Code suggeststhat the user referto the current state of
to elevated temperatures due to their proximity to a hot the art. Cathodic protection current levels, quality of
pipeline. Higher temperatures tend to increase boththe pipe surface preparation and coating, operating tem-
current output and rate of degradation of most anode peratures, stress levels, and soil conditions shall be con-
materials.Some anode materialsmaybecome more sidered in pipeline design and operations.
noble than steel at temperatures above 140°F in certain
electrolytes. Zinc anodescontaining aluminum are also
susceptible to intergranular corrosion above 120°F.
RECORDS
867
(a) Records indicating cathodically protected pip-
865.4
Internal
Corrosion
Control
ing, cathodic protection facilities,and other structures
When gas or a mixture of gas and liquids or solids affected by or affecting the cathodic protection system
known or anticipated to be .corrosive istransported at shall be maintained by the operating company.
elevated temperatures, special consideration shall be (b) Records of tests,surveys,inspectionresults,
given to the identification and mitigation of possible leaks, etc., necessary for evaluatingthe effectiveness of
internal corrosion.Suchmeasures are necessarybe- corrosion control measures, shall be maintained and
cause corrosion reaction rates increase with elevated retained for as long as the piping remains in service.
88
CHAPTER VI1
MISCELLANEOUS
MISCELLANEOUS
870 soluble in water to a greater extent than 2% parts of
odorant to 100 parts of water by weight.
ODORIZATION
871 (6) The products of combustion from the odorant
871.1 shall be nontoxic to humans breathing air containing
the products of combustion and shall not be corrosive
Any gas distributed to customers through gas mains or harmful to the materials with which such products
or service lines or used for domestic purposes in com-
of combustion would ordinarily come in contact.
pressor plants, which does not naturally possess a dis-
(c) The combination of the odorant and the natural
tinctive odor tothe extent that its presence in the atmo- odor of the gas shall provide a distinctive odor so that
sphere is readily detectable at all gas concentrations of
when gas is present in air at the concentration of as
one-fifth of the lower explosive limit and above, shall
much as 1% by volume, the odor is readily detectable
have an odorant added to it to make it so detectable.
by a person with a normal sense of smell.
871.11 Odorization is not required for:
(a) gas in underground or other storage;
(b) gas used for further processing or use where the 871.4
odorant would serve no useful purpose as a warning For all odorizers, except small wick-type or bypass-
agent or would be a detriment to the process; type, or similar odorizers serving individual customers
(c) gas used in lease or field operations. or small distribution systems, each operating company
871.12 If gas is delivered for use primarily in one of shall maintain records containing the following items:
the above exempted activities or facilities and is also (a) the type of odorant introduced into the gas;
used in one of those activities for space heating, refrig- (b) the amount of odorant injected per million cubic
eration, water heating, cooking, andother domestic feet.
uses, or if such gas is used for furnishing heat or air
conditioning for office or living quarters, the gas shall
871.5
be odorized.
Odorant concentration tests shall be conducted by
each operating company of the gas supplied through its
871.2 facilities which requires odorization. Test points shall
be remotely located from the odorizing equipment so as
Each
operating company shall use odorization
to provide data representative of gas at all points of the
equipment designed for the type and injection rate of
system.
odorant being used.
871.3
872
LIQUEFIED
PETROLEUM GAS (LPG)
Each operating company shall use anodorant in SYSTEMS
accordance with the following requirements.
872.1
(a) The odorant when blended with gas in the speci-
fied amount shall not be deleterious to humans or to the Liquefied petroleum gases generally include butane,
materials present in the gas system and shall not be propane, and mixtures of the two that can be stored as
89
liquids under moderate pressures(approximately 80 in underground vaults, except in cases where suitable
psig to 250 psig) at ambient temperatures. provisions for forced ventilation are made.
(6) Special care is required in the location of relief
valve discharge vents releasingLPG tothe atmosphere
872.2
to prevent accumulation of the heavy gasesat or below
This Code is concerned only with certain safety as- ground level. Likewise, special precautions are neces-
pects of liquefied petroleum gases when they are vapo- sary for adequate ventilation whereexcavations are
rized and used as gaseous fuels. made for the repair of leaks in an underground LPG
distribution system.
872.3
All of the requirements of ANSI/NFPA 58 and 873 PIPELINES ON PRIVATE
ANSVNFPA 59 and of this Code concerning design, RIGHT-OF-WAY OF ELECTRIC
construction, and operation and maintenance of piping TRANSMISSION LINES
facilities shall apply to piping systemshandling butane,
propane, or mixtures of these gases. Where gas pipelines parallel overhead electric trans-
mission lines on the same right-of-way, the company
operating the pipelines shall take the following precau-
872.4SpecialSafetyRequirementsforLPG tions.
Systems
872.41 Odorization. Liquefied petroleum gases are 873.1
usually nontoxic, but for safety, when distributed for
consumer use or used as fuel ina place of employment, Employ blowdown connections that will direct the
shall be odorized. Criteria for odorization are given in gas away from the electric conductors.
'
para. 87 1.
872.42 Ventilation 873.2
(a) All liquefied petroleum gases are heavier than Install a bonding conductor across points where the
air; hence, structures aboveground for housing regula- main is to be separated and maintain this connection
tors, meters, etc., shall have open vents near the floor while the pipeline is separated. The current carrying
level. Such equipment shall not be installed in pits or capacity of the bonding conductor should be at least
one-half of the capacity of the overhead line conduc-
'Refer to ANSI/NFPA 58 and ANSVNFPA 59. tors. [See also para. 862.114@).]
90
CHAPTER VI11
OFFSHORE GAS TRANSMISSION
91
hyperbaric weld- a weld performed at ambient hydro- return interval - average time interval between suc-
static pressure in a submerged chamber from which the cessive events ofdesignwavebeing equalled or ex-
water has been removed from the surfaces to be welded ceeded
ofshore- the area beyond the line of ordinary high soil liquefaction - a soil condition, typically caused by
water along that portion of the coast that is in direct dynamic cyclic loading (e.g., earthquake, waves) where
contact with the open seas and beyond the line marking the effective shear stresses in the soil are reduced to
the seaward limit of inland coastal waters zero, and the soil exhibits the properties of a liquid
-
offshore pipeline riser the vertical or near vertical splash zone- the area of the pipeline riser or other
portion of an offshore pipeline between the platform pipeline components which is intermittently wet and
piping and the pipeline at orbelow the seabed, includ- dry due to wave and tidal action
ing a length of pipe of at least five pipe diameters weight coating- any coating attached to the pipeline
beyond the bottom elbow, bend, or fitting. Due to the for the purpose of increasing the pipeline specific grav-
wide variety of configurations, the exact location of ity
transition between pipeline, pipelineriser, and platform
piping must be selected on a case-by-case basis.
offshorepipeline system - all components of a pipeline A810
MATERIALS AND EQUIPMENT
installed offshore for the purpose of transporting gas Materials and equipment for offshore pipeline sys-
other than production facility piping. Tanker or barge tems shall conform to the requirements of paras. 810
loading hoses are not considered part of the offshore and A81 1 through A8 16.
pipeline system.
offshore platform - any man-made fixed or perma-
nently anchored structure or artificial island located A811 QUALIFICATION OF MATERIALS
offshore AND EQUIPMENT
pipe collapse - flattening deformation of the pipe re- Materials and equipment shall conform to themeth-
sulting in loss of cross-sectional strength and circular
ods of qualification as specified inpara. 8 1 1, except that
shape, which is caused byexcessive external hydro-
“unidentified” pipe, plastic pipe, plastic pipe with non-
static pressure acting alone
metallic reinforcement, cast iron pipe, and ductile iron
platform piping pipe shall not be used for transporting natural gas.
fa) On offshore platforms where hydrocarbons are
produced, platform piping consists of all the gas
transmission piping, appurtenances, and components MARKING
A812
that are between the production facility and the off-
shore pipeline riser(s). This includes any gas compres- Marking of all offshorepipeline system materials
sors and piping that are not a part of the production shall conform to para. 812.
facility.
(b) On offshore platforms where hydrocarbons
arenot produced, platform piping consists of all A813
MATERIAL SPECIFICATIONS
the gas transmission piping, compressors, appurte- A813.1
nances, and components between the offshore pipeline
risers. Materials used in offshore pipelinesystems shall con-
Due toa wide variety of configurations, the exact loca- form to the provision of para. 813 as expanded or ex-
tion of the transition between the offshore pipeline ri- cepted below.
ser(s), the platform piping, and the production facility (a) Concrete weight coating materials (cement, ag-
shall be selected on a case-by-case basis. gregate, reinforcing steel) shall meet or exceed the re-
quirements of applicable ASTM standards.
propagating buckle- a buckle which progresses rap- (6) Flexible pipe shall be manufactured from mate-
idly along a pipeline caused by the effect of external rials meeting the requirements of applicable ASTM or
hydrostatic pressure on a previously formed buckle, ASME standards.
local collapse, or other cross-sectional deformation
pull tube - a conduit attachedto an offshore platform
through which a riser can be installed A813.2
puff-tuberiser- riser pipe or pipes installed through In addition to the requirements contained in refer-
a pull tube enced standards, certain other requirements may be
92
considered for pipe and other components used off- dures, andwelding qualifications shall be in accordance
shore, depending on water depth, water temperature, with the provisions of Chapter I1 of this Code with
internal pressure, product composition, product tem- application of the special provisions of this Chapter.
perature, installation method and/orother loading This Chapterdoes not apply to thewelding of the seam
conditions. Thus, consideration may include one or in the manufacture of pipe and other manufactured
more of the following: appurtenances.
(a) wall thickness tolerance
(b) outside diameter tolerance A821.2
Welding
Processes
(e) out-of-roundness
(d) maximum and minimum yield and tensile The welding may be done by any process or combi-
strengths nation of processes which produce welds that meet the
cfl maximum carbon equivalent procedure qualification requirements of this Code and
(g) fracture toughness can be inspected by conventional means.
(h) hardness
(i) pipe mill hydrostatic testing and other mechani- A821.3 Requirements
cal testing.
(a) Prior to atmospheric welding of any pipe, piping
components, or related equipment, Welding Procedure
Specificationsshall be written and the procedure quali-
A814MATERIALS FOR USEIN COLD
fied. The approved procedure shall include all of the
CLIMATES
applicable details listed in API Standard 1104.
Materials for use in offshorepipeline systems in cold (b) Prior to hyperbaric welding of any pipe, piping
environments shall conform to para. 814 unless other- components, or related equipment, Welding Procedure
wise stated herein. Specificationsshall be written and the procedure quali-
fied. The approved procedure shall include all of the
applicable details listed in API Standard 1104 and
A815 EQUIPMENT SPECIFICATIONS ANSI/AWS D3.6.
(e) Each welder or welding operator shall be quali-
Specificationsfor offshore pipeline system equipment
fied for the established procedure before performing
shall conform to para. 815 unless otherwise stated
any welding on any pipe, piping component, or related
herein.
equipment installed in accordance with this Code.
(d) Welding Procedure Qualifications, as well as
welder or welding operator qualifications, are valid
A814 TRANSPORTATION OF LINE PIPE
only within the specified limits of the welding proce-
Transportation of line pipe shall conform to para. dure. If changes are made in certain details, called
816 and to the applicable provisions of API RP 5LW. “essential variables” or “essential changes,” additional
Additionally, transportation by truck or otherroad qualification is required. API Standard 1 1 0 4 essential
vehicles shall be performed in sucha manner as to variables shall take precedence in matters not affected
avoid damage to the pipe. Provisions shall be made to by the underwater environment, andANSI/AWS
protect the pipeline corrosion coating, end bevel, and D3.6 shall govern those essential changes related to the
weight coating from damage. underwater welding environment and working condi-
tions.
A820
WELDING OFFSHORE PIPELINES
A822
PREPARATION FOR
WELDING
GENERAL
A821
End preparation for welding shall be in accordance
A821.1
Scope with the requirements of para. 822.
This section concerns the welding of carbon steel
materials which are usedin a pipeline in the offshore A823 QUALIFICATION OF PROCEDURES
environment. It covers buttand filletwelds in pipe,
AND WELDERS
valves, flanges, fittings, etc., including connections to
apparatus or equipment. The weldingcoveredmaybe Qualification of procedures and welders shall be in
performed under atmospheric or hyperbaric condi- accordance with the requirements of para. 823, except
tions. The requirements for welding,welding proce- paras. 823.1 and 823.2 do not apply offshore.
93
(a) Welding procedures and welders performing at- welds on offshore pipelines shall be nondestructively
mospheric welding under this section shall be qualified inspected, if practical, but in no case shall less than
under API Standard 1104, except that for applications 90% of such welds be inspected. The inspection shall
in which design, materials, fabrication, inspection, and cover 100% of the length of such inspected welds.
testing are in accordance with BPV Code, Section VIII,
welding procedures and welders shall bequalified A826.12 Standardof Acceptability. All welds which
under BPV Code, Section IX. are inspected must meet the standards of acceptability
of API Standard 1104 or BPV Code, Section VIII, as
(6) Welding procedures and welders performing hy-
perbaric welding under this section shall be qualified in appropriate for the service of the weld, or be appropri-
ately repaired and reinspected or removed.
accordance with the testing provisions of API Standard
1104 as supplemented by ANSI/AWS D3.6, Specifica- A826.13 Alternative Flaw Acceptance Limits. For
tion for Underwater Welding for Type “ 0 ’ Welds. girth welds on a pipeline, alternative flaw acceptance
limits may be established based upon fracture mechan-
A823.3 WelderRequalificationRequirements ics analyses and fitness-for-purpose criteria as de-
scribed in API Standard 1104. Such alternative accept-
Welder requalification shall be in accordance with ance standards shall be supported by appropriate stress
para. 823.3. analyses, supplementary welding procedure test re-
quirements, and nondestructive examinations beyond
the minimum requirements specified herein. The accu-
A824 PREHEATING
racy of the nondestructive techniques for flaw depth
Preheating provisions shall bein accordance with measurement shall be verified by sufficient data to es-
para. 824. tablish probabilities for the proposed inspection error
allowance.
94
method. Care should be exercised in any new applica- A841 DESIGN CONSIDERATIONS
tion of existing designs to insure suitability for the in-
A841.1
Design
Conditions
tended service.
A number of physical parameters, henceforth re-
ferred to as design conditions, govern design of the
A832 EXPANSION AND FLEXIBILITY offshore pipeline system so that it meets installation,
operation, andother post-installation requirements.
Unburied subsea pipeline systems, including plat- Some of the factors which may influence the safety and
form piping, shall conform to therequirements of para. reliability of an offshore pipeline and riser include:
832. Thermal expansion and contraction calculations (a) waves
shall consider the temperaturedifferential between ma- (6) current
terial temperature duringoperations and material tem- (c) marine soils
perature during installation. (d) wind
(e) ice
IJ’I seismic activity
A834 SUPPORTS AND ANCHORAGE FOR (g) platform motion
EXPOSED PIPING (h) temperature
Supports andanchorage for platform piping and ris- (i) pressure
ers shall conform to the requirements of para. 834, 0) water depth
except thatnoattachmentotherthan an encircling (k) support settlement
member shall be welded directly to the pipeline (see (I) accidental loads
para. A842.27). (m) commercial shipping
(n) fishing/shrimping activities
The design of offshore pipelines is often controlled by
A835
ANCHORAGE FOR BURIED PIPING installation considerations ratherthan by operating
load conditions.
Buried subsea pipelines shall conform to therequire-
ments of 835. Thermal expansion and contraction cal-
culations shall consider the effectsof fully saturated A841.2InstallationDesignConsiderations
backfill material on soil restraint. The design of an offshore pipeline system suitable for
When a submerged pipeline is to be laid across a safe installation and the development of offshore pipe-
known fault zone, or in an earthquake-pronearea line construction procedures shall be based on consid-
where new faults are a possibility, consideration shall eration of the parameters listed in paras. A841.21
be givento theneed for flexibility in the pipeline system through A841.25: These parameters shall be consid-
and its components to minimize the possibility of dam- ered to the extent that they are significant to the pro-
age due to seismic activity. posed system and applicable to the method of installa-
The requirements of para. 835.51 for header and tion being considered.
branch connections are not applicable to offshore sub-
merged piping systems. An appropriate means of pre- A841.21 Weight.The effect ofpipe or pipeline assem-
venting undue stresses at offshore submerged piping bly weights (in airand submerged) on installation
connections is to provide adequate flexibility at branch stresses and strains shall be considered. Variability due
connections on the seabed. to weight coating manufacturing tolerances and water
absorption shall also be considered.
A841.22 Profile.Variations in water depth along the
A840 DESIGN, INSTALLATION, AND pipeline route shall be considered. The effect of tides
TESTING shall be included for locations where such variations
A840.1
General Provisions are a significant fraction of the water depth. Bottom
slope, obstructions, or irregularities which affect instal-
The design, installation, and testing of offshore gas lation stresses shall be considered.
transmission systems (including pipelines, risers, com-
pressor stations, and their appurtenances) shall be in A841.23EnvironmentLoads. Local environmental
accordance with the provisions of the following sec- forces including those induced by wind, wave, currents,
tions. ice, seismicactivity, and other naturalphenomenon are
95
96
91
2 [(
sL- h)2 + S2lH I F3S
practical. When doing so is impractical, the totalresult-
ant stresses shall be less than the allowable limits in
para. A842.22, and such that fatigue failure should not
where result during the design life of the pipeline.
S, = maximum longitudinal stress, psi (positive ten- A842.26DesignAgainstFracture. Materials used
sile or negative compressive) for pipelines transporting gas or gas-liquid mixtures
s h = hoop stress, psi
under high pressure should have reasonably high resist-
F3 = combined stress design factor from Table ance to propagating fractures at thedesign conditions,
A842.22 or other methods shall be used to limit the extent of a
S = specified minimum yield strength, psi fracture.
S, = tangential shear stress, psi
Alternatively, the Maximum Distortional Energy A842.27Design of ClampsandSupports. Clamps
Theory (Von Mises combined stress) may be used for andsupports shall be designed suchthat a smooth
limiting longitudinal stress values. Accordingly, the transfer of loads is made from the pipeline or riser to
longitudinal stress should not exceed values given by thesupportingstructure without highly localized
stresses due to stress concentrations. When members
are to be weldedto thepipe they shall fully encircle the
pipe and be welded to the pipe by a full encirclement
A842.23 Alternate Design for Strain. In situations weld. The support shall be attached to the encircling
where the pipeline experiences a predictable noncyclic member and not the pipe.
displacement of its support (e.g., fault movement along All weldsto the pipe shall be nondestructively tested.
the pipeline route or differential subsidence along the Clamps and supports shall be designed in accordance
line) or pipe sag before support contact, the longitudi- with the requirements of API RP 2A, Section 3.
nal and combined stress limits need not be used as a Clamp and support design shall consider the corro-
criterion for safety against excessive yielding, so long as sive effects ofmoisture retaining gaps and crevices and
the consequences of yielding are not detrimental to the galvanically dissimilar metals.
integrity of the pipeline. The permissible maximum A842.28 Designof Connectorsand Flanges. Connec-
longitudinal strain depends upon the ductility of the tors and flanges shall be such that smooth transfer of
material, anypreviously experienced plastic strain, and loads is made without high localized stresses or exces-
the buckling behavior of the pipe. Where plastic strains sive deformation of the attached pipe.
areanticipated,the pipe eccentricity, pipe out-of- Connectors and flanges shall have a level of safety
roundness, and theability of the weld to undergo such against failure by yielding and failure by fatigue which
strains without detrimental effect should be considered. is comparable to that of the attached pipeline or riser.
Similarly, the same criteria may be applied to the pipe
duringconstruction (e.g., pull-tube or bending shoe A842.29 Designof Structural Pipeline Riser Protec-
risers). tors. Where pipeline risers are installed in locations
subject to impact from marine traffic, protective devices
A842.24 Design Against Buckling and Ovalization. shall be installed in the zone subject to damage to pro-
Avoidance of buckling of the pipeline and riser during tect the pipe and coating.
operation shall be considered in design. Modes of buck-
ling which may be possible include: A842.30 Design and Protection of Special Assem-
(a) local buckling of the pipe wall blies. Design of connections and special assemblies,
(b) propagation buckling following local buckling such as subsea tie-in assemblies, expansion loops, sea-
(c) column buckling bed riser connections, and subsea pipeline manifolds,
98
shall consider the additional forces and effects imposed ever is smaller. Portions of the pipeline system to be
by a subsea environment. Such additional considera- trenched shall be designed for wave and current condi-
tions include design storm currents and potential for tions based on prudent assessment of the period of pipe
seabed movement in soft sediments, soil liquefaction, exposure. The most unfavorable expected combination
increased potential corrosion, thermal expansion and of wave and current conditions shall be used. Maxi-
contraction, and stress due to installation procedures. mum wave and maximum current conditions do not
In areas of active fishing, protective measures may be necessarily occur simultaneously. The most unfavor-
appropriate for connections and special assemblies. able condition selection shall consider the timing of
occurrence of the wave and currentdirection and mag-
A842.31 Design of Flexible Pipe. Due toits compos-
nitude.
ite makeup, the mechanical behavior of flexible pipe is
significantly different from steel pipe.Flexible pipe may
be usedfor offshore pipelines if calculations and/or test A843.2 Stability Against Waves andCurrents
results verify that the pipe can safely withstand load-
A843.21 Submerged Weight. The submerged weight
ings considered in paras. A841.32 through A841.33. In
of the pipe may be designed (such as by weight coating)
the selection of flexible pipe, consideration should be
to resist or limit movement to acceptable values. Hy-
given to its permeable nature. The possibility of implo-
drodynamic forces shall be based on the wave and cur-
sion under the combined conditions of high pressure,
rent values for the design storm condition for the spe-
high temperature,and very rapid depressurization
cific location.
should be investigated where such conditions may be
Wave andcurrent directionality and concurrency
expected.
shall be considered.
A843.22 Bottom Soils. The pipe-soil interaction fac-
A843 ON-BOTTOM STABILITY tors that are used shall be representative of the bottom
conditions at the site.
Pipeline design for lateral and vertical stability is
governed by seafloor bathymetry, soil characteristics, A843.23 Trenching. The pipeline and its appurte-
and by hydrodynamic, seismic, and soil behavior events nances may betrenched below bottom gradeto provide
having a significant probability of occurrence during stability. The pipeline must be designed for wave and
the life ofthe system. Design conditions to consider are current stability prior to trenching. However, such sta-
provided in following subsections. bility need only be based on environmental conditions
The pipeline system shall be designed to prevent ho- expected during the period of pipe exposure.
rizontal and vertical movements, or shall be designed
A843.24 Backfilling. Backfilling or other protective
so that any movements willbe limited to values not
coverings, when necessary, shall be accomplished by
causing design strength to be exceeded(see para.
using such materials and procedures so as to preclude
A842). Typical factors to be considered in the stability
damage to the pipeline and coatings.
design include:
(a) wave and current forces A843.25 Anchoring. Anchoring maybeused in-
(6) scour and resultant spanning stead of or in conjunction with submerged weight to
(c) liquefaction maintain stability. The anchors shall bedesigned to
(dl slope failure withstand lateral and vertical loads expected from
Stability may be obtained by such means as, but not the design storm condition. Anchors shall be spaced
limited to: pipe submerged weight; trenching of pipe so as to prevent excessive stresses in the pipe sections
below grade; anchoring. between anchors. The anchoring system and adjacent
When calculating hydrodynamic forces, the fact that pipe shall be designed to prevent scour and resultant
wave forces vary spatially along the length of the pipe- spanning from overstressing the pipe. The effect of
line may be taken into account. anchors on thecathodic protection system shall be
considered.
A843.1 Design Storm Conditions
A843.3 Shore Approaches
Design wave and current conditions for portions of
a pipeline which will not be trenched shall be based Pipe in the shore approach zone shall be trenched or
upon a storm having a minimum return interval of no bored to the depth necessary to prevent scouring, span-
less than five times the design life or 100 years, which- ning, or stability problems which affect integrity and
99
safe operation of the pipeline duringitsanticipated A844.21 Enclosures. All enclosures located on an
service life. Seasonal variation in the near shore thick- offshore platform shall be constructed of noncornbusti-
ness of seafloor sediments and shoreline erosion over ble or limited combustible material as defined inNFPA
the pipeline service life shall be considered. 220, Chapter 2, Section 2-6 and Section 2-3. Design of
enclosures on offshore platformsshall consider the
loading conditions defined in para. A841.3.
A843.4 Slope
Failure
The pipeline shall be designed for slope failure in A844.22 Exits. A minimum of two exits shall be
zones of known or anticipated occurrence, such as provided for each operating level of a compressor
mudslide zones andareas of seismic slumping. The building. Any elevated walkway, including engine cat-
design exposure period shall be no less than the ex- walks more than 10 ft above the deck, shall also be
pected life of the pipline. If it is not practical to design provided with two exits. The maximum distance from
the pipeline system to survive the event, the pipeline any point within the compressor building to an exit
shall be designed for controlled breakaway with check shall not exceed 75 ft. Enclosure exits shall be unob-
valving to prevent blowdown of the pipeline. structed andlocated so as toprovide a convenient route
of escape and shall provide continuous unobstructed
passage to a place of safety. Exit doorslocated on exte-
A843.5 Soil Liquefaction rior walls shall swing outward and shall be equipped
Design for the effects of liquefaction shall be per- with latches which can be readily opened from the
formed for areasof known or expected occurrence. Soil inside without a key.
liquefaction normally results from cyclic wave over-
pressures or seismic loading of susceptible soils. The A844.3 Electrical
Facilities
bulk specific gravity of the pipeline shall be designed or
alternative methods shall be selected to ensure both All electrical equipment and wiring installed on off-
horizontal and vertical stability. shore compression platforms shall conform to the re-
Seismic design conditions used to predict the occur- quirements of NFPA 70, if commercially available
rence of bottom liquefaction or slope failure shall have equipment permits.
the same recurrence interval as used for the operating Electrical installations in offshore hazardous loca-
design strength calculations for the pipeline. Occur- tions as defined inNFPA 70 Chapter 5, Article 500 and
rence ofsoil liquefaction due to wave overpressures which are to remain in operation during compressor
shall be based on a storm return interval of no less than station emergency shutdown as provided in para.
five times the designlife or 100 years, whichever is A844.431 shall be designed to conform to NFPA 70,
smaller. for Class I, Division I requirements.
The guidelines of API-RP-14F should be considered
in electrical facility design.
A844 COMPRESSOR STATIONS
A844.1 General
Information A844.4 CompressorStationEquipment
The requirements of this section recognize the A844.41 Gas Treating Facilities
unique design conditions and space limitations imposed A844.411 Liquid Removal. Unless otherwise
when designing offshore compression facilities and statedall provisions of para. 843.411 shall apply to
therefore relate only to offshore compression facilities. offshore facilities.
All other provisions of para. 843 are applicable to off-
shore compression facilities. A844.412 Liquid Removal Equipment,Unless oth-
It is the further intent of this section to make the erwise stated allprovisions of para. 843.412 shall apply
designer aware of personnel safety during the design to offshore facilities.
and operation of offshore compression facilities. A844.42 Fire Protection. Unless otherwise stated all
provisions of para. 843.42 shall apply to offshore facili-
A844.2 LocationofCompressor Facilities ties.
gency shutdown system that will block out thegas going A845 CONTROL AND LIMITING OF GAS
to and from the compressor station. Operation of the PRESSURE
emergency shutdown system shall cause the shutdown
All applicable provisions of para. 845 apply unless
of all gas compression equipment and all gas fired equip-
otherwise stated.
ment, and shall de-energize the electrical facilities in the
compressor building, except those that provide emer-
gency lighting for personnel protection and those that
VALVES
A846
are necessary for protection of equipment. The emer-
gency shutdown system shall be operable from a mini- Offshore transmission lines shall be equipped with
mum of two locations on each deck level, Le., should an valves or other components to shut off the flow of gas
offshore platform facility have more than one clearly to an offshore platform in an emergency.
defined deck, each deck shall have a minimum of two Block valves shall be accessible and protected from
shutdown locations. Blowdown piping shall extend to a damage and tampering. If a blowdownvalve is in-
location where the discharge of gas is not likely to create volved, it shall be located where the gas can be blown
a hazard to the platform facilities. Consideration should to the atmosphere without undue hazard.
be givento potential entrained liquids, prevailing winds, Blowdown valvesshall be provided so that each sec-
and location of crew quarters if part of the platform tion of pipeline between main line valves can be blown
facility. Under conditions of heavy liquid entrainment down. The sizes and capacity of the connections for
and poor prevailing wind conditions, a separate struc- blowing down the line shall be such that under emer-
ture for a blowdown facility shall be considered. gency conditions the section of line can be blowndown
as rapidly as is practicable.
A844.432 Engine Overspeed Stops. Unless other-
wise stated all provisions of para. 843.432 shall apply
to offshore facilities. A847 TESTING
A844.44PressureLimitingRequirements for Off- A847.1
General
Provisions
shore Compression Facilities. Unless otherwise stated,
All offshore pipelines shall be tested after installation
the provisions of paras. 843.441 and 843.442 shall
and prior to operation within the provisions of this
apply to offshore facilities.
section.
A844.444 Venting. Pressure relief valves shall be
vented to atmosphere such that no hazard is created. A847.2
Test Pressure
Vent lines, common headers, and platform blowdown
lines shall have sufficient capacity so that they will not The installed pipeline system shall be hydrostatically
interfere with the performance of the relief device. tested to at least 1.25 times the maximum allowable
operating pressure. Offshore platform piping and off-
A844.45 Fuel Gas Control. Unless otherwise stated, shore pipeline risers must be tested to at least 1.4 times
the provisions of para. 843.45 shall apply to offshore the maximum allowable operating pressure either
facilities. before or after installation. Prefabricated portions of
platform piping that have been pretested to 1.4 times
A844.46 Cooling andLubricationFailures. Unless the maximum allowable operating pressure need not be
otherwise stated, the provisions of para. 843.46 shall tested after installation if all items are tied in by connec-
apply to offshore facilities. tors, flanges, or welds which have been radiograph-
ically inspected.
A844.5
Explosion
Prevention
Unless otherwise stated,the provisions of paras. A847.3
Test Medium
843.471 and 843.472 shall apply to offshore facilities. The test medium for all offshore pipelines willbe
water. Additives to mitigate the effects of corrosion,
biofouling, and freezing should be considered. Such
A844.6CompressorStationPiping
additives should be suitable for the methods of disposal
Unless otherwise stated the provisions of paras. of the test medium.
843.51, 843.52, 843.53, 843.54, 843.55, 843.56, and In arctic areas where freezing of water is a hazard,
843.57 shall apply to offshore facilities. the use ofair, inert gas, or glycol is allowable. Platform
101
gas and compression piping may be tested with inert A850 OPERATING AND MAINTENANCE
gas. PROCEDURES AFFECTING THE
SAFETY OF GAS TRANSMISSION
FACILITIES
A847.4 Test Procedure A850.1
The hydrostatic pressure test shall be conducted in All provisionsof para. 850.1 shall apply unlessother-
accordance with a specified procedure which shall, at wise stated.
a minimum, provide for the following:
(a) Performance of the test after installation and
before initial operation of the pipeline system exceptas A850.2
Basic
Requirements
provided in para. A847.2. All provisionsof para. 850.2 shall apply unlessother-
(b) Whenever practical, prefabricated pretested por- wise stated.
tions of offshore pipeline risers should be included in
the pipeline system hydrostatic test.
(c) Maintenance of the test and recording of results A850.3EssentialFeatures of theOperating and
on pipelineand assemblies for a minimum of 8 continu- Maintenance Plan
ous hr ator above the specified pressure. Allvariations
The plan prescribed in para. 850.2(a) shall include:
in test pressure shall be accounted for. Test duration of
(a) detailed plans and instructions foremployees
prefabricated piping may be 2 hr.
covering operating and maintenance procedures for gas
(d) If, during the hold time, a rupture or hazardous
facilities during normal operations and repairs;
leak occurs, the test is invalid and testing shall recom-
(b) itemsrecommended for inclusionin the plan
mence after repairs have been made.
forspecificclasses of facilitieswhich are given in
paras. A851.2, A851.3, A851.4, A851.5, A851.6, and
A861.2;
A847.5
Records (c) plans to give particular attention to those por-
The operating company shall maintain in its file, for tions of the facilities presenting the greatest hazard to
the useful life ofeach pipeline,records showing the type the public and environment in the event of an emer-
of test fluid, the test procedure, the test pressure, and gency or because of construction or extraordinary
the duration of the test. maintenance requirements;
(d) provisions for periodicinspectionsalong the
route of existing pipelines.
A847.6
Tie-ins
It is recognized that it may not be possibleto hydro- A850.4EssentialFeatures of the Emergency Plan
statically test the tie-in between twotest sections. Pres- A850.41 Written Emergency Procedures. All provi-
sure testing of tie-in welds may be exemptedtheiftie-in sions of para. 850.41 shall apply unless otherwise
weld is inspected by radiographic and/or other applica- stated.
ble NDT methods.
A850.42 Training Program. All provisions of para.
850.42 shall apply unless otherwise stated.
A847.7TestingforBuckles A850.43 Liaison. Each operating company shall es-
tablish and maintain liaisonwithavailableoffshore
Testing for buckles, dents, and other diameter re-
firefighting entities (public and or privately owned)
strictions shall be performed after installation. Testing
which might be designated for any particular offshore
shall be accomplished by passing a deformation detec-
area.
tion device through the pipeline section, or by other
methods capable of detecting a change in pipe diame- A850.44 Fducational Program. An educational pro-
ter. Pipe having excessive deformation which affects gram shall be established to enable producers and the
the serviceability of the pipeline facilities shall be re- general public operating in the offshore area to recog-
paired or replaced. consideration should also be given nize and report a gas emergency to the appropriate
to repairing excessive ovality which mayinterfere with officials. The educational program called forunder this
pigging operation or internal inspection. section should be tailored to the type of pipeline opera-
102
tion and theenvironment traversed by the pipeline and by the company, and any other factors affecting the
should be conducted in each language that is significant safety and operation of the pipeline. These inspections
in the community served. Operators of transmission should be made as often as necessary to maintain the
systems should communicate their programs to people, integrity of the pipeline. Records of these inspections
contractors, or others that usually work in the offshore shall be maintained for the life of the facility.
area of concern. The programs of operators in the same
area shouldbe coordinated to properly direct reports of
emergencies and to avoid inconsistencies. A851.3
Leakage
Survey
All provisions of para. 85 1.3 shall apply unless other-
A850.5PipelineFailureInvestigation wise stated.
103
104
105
A862.5
Electrical
Isolation shall be repaired or replaced and corrosion control
measures applied or augmented.
Underwater pipeline systems shall be electrically iso-
lated from other metallic structures so that cathodic
protection can be effective. An exception can be made A863.3
Inspection
when both the foreign structure and the pipeline are
When a pipeline is lifted above water for mainte-
designed to be protected as a unit. Other general con-
nance or repair purposes, the operating company shall
siderations include:
visually inspect for evidence of coating deterioration,
(a) Tie-Ins. Isolation from foreign pipelines at tie-
external corrosion, and where possible, the condition of
ins maybe made by the installation of insulation
any exposed anode. If excessive corrosion is present,
flanges, unions or other insulating devices. When mak-
remedial action shall be taken as necessary.
ing a tie-in of a coated line to a bare line, the two lines
If repairs are made below water, inspection for evi-
shall be electrically isolated.
dence of external corrosion or coating deterioration
(b) Foreign Pipeline Crossings. When crossing a for-
shall be made and necessary corrective action shall be
eign pipeline, care shallbe exercised to assure adequate
taken to maintain the corrosion protection of the pipe-
separation between the two lines so that the possibility
line.
for electrical interference is minimized.
(c) Pipeline Riser Support andSecondary Piping.
When installing riser piping at platforms, supporting A863.4
Electrical
Isolation
devices such as clamps and pipe supports shall isolate
Periodic tests shall be made to assure that electrical
the piping from the structure. Insulating devices shall
isolation from foreign pipelines or other structures re-
be installed where electrical isolation of a portion of the
mains complete. Some indications of electrical interfer-
piping system from production piping, tanks, and other
ence are: changes in pipe to electrolyte potential,
facilities isnecessary to facilitate application of ca-
changes in current magnitude or direction, localized
thodic protection. Electrical interference between elec-
pitting, and coating breakdown. When new foreign
trically isolated structures shall be minimized. Wiring
pipelines are laid in the vicinity of existing lines, inspec-
and piping connections to an isolated pipeline shall also
tions shall be made to assure electrical isolation in ac-
have insulation between the pipeline and the platform.
cordance with para. 862.1 14. If electrical isolation can-
Tests shall be made to assure adequate isolation and
not be attained, measures shall be taken to minimize
appropriate action shall be taken to ensure such isola-
electrical interference. Particular note should be made
tion when necessary.
to check and maintain electrical isolation from the plat-
form unless the system was specifically designed to be
A862.6
Test
Connections jointly protected.
All provisions of para. 862.1 15 shall apply unless
otherwise stated. Test leads shall be installed so that A863.6
Atmospheric
Corrosion
they are mechanically secure, electrically conductive,
and accessible for testing. It is considered impractical Detailed inspections shall be made periodically of all
to locate test leads in deep or open water. Test leads piping for atmospheric corrosion. This inspection shall
installations are usually limited to platforms and the include those areas most susceptible to corrosion such
pipeline entrance to the shore. as flanges, flange bolts, areas under pipe straps, areas
where pipe is in contact with supports, and otherplaces
where moisture collects. Where atmospheric corrosion
A863 CORROSION CONTROL ON is found, prompt corrective action shall be taken. Cor-
EXISTING INSTALLATIONS rective action shall consist of painting, replacement of
components as necessary, or other action deemed ap-
A863.1
General propriate by the operating company.
The operating company must rely on monitoring,
investigation, inspections, and corrective action to con-
trol corrosion. Such activities shall be performed at A864 INTERNAL CORROSION CONTROL
periodic intervals sufficient to assure that adequate cor-
A864.1 General
rosion control is maintained. Where it is determined
that corrosion is taking place to the extent that it may The design and maintenance of offshore pipeline
be detrimental to public or employee safety, the facility facilities that may carry natural gas containing carbon
106
dioxide, chlorides, hydrogen sulfide, organic acids, sol- control measures. Tests or investigations shall be per-
ids or precipitates, sulphur bearing compounds, oxy- formed at intervals sufficient to assure the maintenance
gen, or free water require special consideration for the of adequate corrosion control. If the pipe is opened, the
control of internal corrosion. Other general require- interior surface of the pipe shall be inspected for evi-
ments are prescribed in para. 863. dence of corrosion.
Where inspections or monitoring results indicate de-
trimental internal corrosion is taking place, appropri-
A864.2 Control Requirements ate remedial action shall be taken.
A program shall be established for the detection,
prevention, and/or mitigation of internal corrosion. A864.4 Records
Where determined to be necessary, means which may
be employed to mitigate internal corrosion include de- A864.41 Records showing cathodically protected
hydration, the use of inhibitors, provision for pigging, piping, cathodic protection facilities, internal corrosion
the application of an internalcoating, or a combination control measures, and other structures affecting or af-
of these. The type and concentration of materials antic- fected by the pipeline or piping facility shall be main-
ipated to be transported will determinethecontrol tained by the operating company.
method or methods to be used. A864.42 Records of tests, surveys, monitoring and
inspection results, leaks, etc., necessary for evaluating
the effectiveness of applied external or internal corro-
A864.3 Monitoring
sion control measures shall be maintained, and be re-
A monitoring program shall be established to peri- tained for as long as the pipeline facility remains in
odically evaluate the effectiveness of applied corrosion service.
107
APPENDIX A
REFERENCES'
Standards incorporated in thisCode by reference, and the names and addressesof the sponsoring organizations, are shownin thisAppendix.
It is not practicalt o refer t o a specific edition of each standard throughout the Code text; instead, the specific edition reference dates are shown
here. Appendix A will be revised at intervals as needed, and issued in Addenda to this Code. An asterisk (*I is used to indicate those standards
that have been accepted as American National Standards by the American National Standards Institute (ANSI).
AGA
ASME Codes and Publications ASTM Specifications
"A21.14-89 (Cont'd) (Cont'd)
"A21.52-82
"2223.1-88 8316-1984 A 671-85
A 672-81 (R-88)
"831.1-1989 & Addenda
API Standards "831.2-1968 B 88-88a
"831.3-1987 & Addenda
5L, 37th Edition, 1988 "831.4-1989 & Addenda D 696-79 (R-88)
6A, 16th Edition, 1989
6D, 19th Edition, 1988 836.10M-1985 D 2513-88b
D 2517-81 (R-87)
1104, 17th Edition, 1988 "Boiler andPressureVesselCode, D 2837-88
Section VIII, 1989 & Addenda,
RP2A, 19th Edition, 1991 Section IX, 1989 & Addenda E 380-89a
RP 5L1, 3rd Edition, 1972
RP 5LW, 1st Edition, 1990 S1-1, Ninth Edition, 1982
AWS Standards
109
*lo-1988
SP-6-1985 RP-01-69 (1983) "30-1987
SP-25-1983 (R1983) RP-02-75 (1975) "58-1989
SP-44-1990 RP-06-75 (1988) "59-1989
SP-70-1984 RP-01-77 (1983) "70-1990
SP-71-1984
SP-75-1988 Corrosion Data Survey"220-1985
(1974)
SP-78-1987 [Note (211
NOTES:
(1) These specification editions may be immediately applied to materials purchased for use under this Code, and shall be applied t o all materials
purchased 12 months or later after the date ofissuance of an addenda containing revised references. A component or pipe conforming to
an earlier approved material specification edition purchased by the user prior to the date of issuance of an addenda containing revised
references may beused, provided the component or pipe is inspected anddetermined t o be satisfactory for theservice intended by the user.
(2) Discontinued; no longer in print.
110
APPENDIX B
LIST OF NUMBERS AND SUBJECTS OF THOSE
STANDARDS AND SPECIFICATIONS WHICH
APPEAR IN APPENDIX A
A 53 Pipe,
Steel, Black and Hot-Dipped, Zinc-Coated B 88 Seamless Copper Water Tube
Welded and Seamless
D 696 Test for Coefficient of Linear Thermal Expansion of
A 105 Forgings, Carbon Steel, for Piping Components Plastics
A 106 Seamless Carbon Steel Pipe for High-Temperature
Service D 2513 Thermoplastic Gas Pressure Pipe, Tubing, and Fit-
A 120 Pipe, Steel, Black and Hot-Dipped Zinc-Coated (Gal- tings
vanized) Welded and Seamless for Ordinary Use D 2517 Reinforced Epoxy Resin Gas PressurePipe and Fit-
A 134 Electric-Fusion (Arc)-Welded Steel Plate Pipe (Sizes tings
16 in. and Over) D 2037 Hydrostatic Design Basis for Thermoplastic Pipe Ma-
A 135 Electric-Resistance-Welded Steel Pipe terials, Obtaining
A 139 Electric-Fusion (Arc)-Welded Steel Plate Pipe (Sizes
4 in. and Over) E 380 Metric Practice
A 193 Alloy-Steel and Stainless Steel Bolting Materials for
High-Temperature Service
A 194 Carbon and Alloy Steel Nuts for Bolts for High-Pres- API
sure and High-Temperature Service
5L Line Pipe
A 211 Spiral-Welded Steel or Iron Pipe
6A Wellhead Equipment
6D Pipeline Valves
A 307 Carbon Steel Externally Threaded Standard Fasten-
ers
1104 Standard for Welding Pipelines and Related Facilities
A 320 Alloy Steel BoltingMaterialsforLow-Temperature
Service
RP 2A Recommended Practice for Planing, Designing and
A 333 Seamless and Welded Steel Pipe for Low-Tempera-
Constructing Fixed Offshore Platforms
ture Service
RP 5 L 1 Recommended Practice for Railroad Transportation
A 354 Quenchedand Tempered Alloy Steel Bolts, Studs, and
of Line Pipe
Other Externally Threaded Fasteners
RP 5L5 Recommended Practice for Marine Transportation of
A 372 Carbon and Alloy Steel Forgings for Thin-Walled
Line Pipe
Pressure Vessels
RP 5L6 Recommended Practice forTransportationof Line
A 381 Metal-Arc-Welded Steel Pipe for Use With High-
Pipe on Inland Waterways
Pressure Transmission Systems
A 395 Ferritic Ductile Iron Pressure-Retaining Castings for
Use a t Elevated Temperatures
N FPA
A 449 Quenched and Tempered Steel Bolts and Studs
10 Portable Fire Extinguishers
30 Flammable and Combustible Liquids Code
A 671 Electric-Fusion-Welded Steel Pipe for Atmospheric
and Lower Temperatures
A 672 Electric-Fusion-Welded Steel Pipe for High-pressure
Service at Moderate Temperatures
111
58 Liquefied Petroleum Gases, Storage and Handling 816.24 Bronze Pipe Flanges and Flanged Fittings
59 Liquefied Petroleum Gases at Utility Gas Plants
70 National Electrical Code 816.33 Small Manually Operated Metallic Gas Valves in Gas
Distribution SystemsWhose Maximum Allowable
220 Types of Building Construction Operating Pressure DoesNot Exceed 60 psig or 125
Psig
816.34 Steel Valves (Flanged and Buttwelding End)
MSS 816.38 Large Manually Operated Metallic Gas Valves in Gas
Distribution Systems,Whose Maximum Allowable
S P-6 Standard Finishes for Contact Faces of Pipe Flanges Operating Pressure Does Not Exceed 125 psig (8.6
and Connecting End Flanges of Valves and Fittings bar, gage)
SP-25 Standard Marking System for Valves, Fittings, 816.40 Manually Operated Thermoplastic Gas Shut-Offs and
Flanges,andUnions Valves in Gas Distribution Systems
SP-44 Steel Pipe Line Flanges
SP-70 Cast Iron Gate Valves, Flanged and Threaded Ends 816.42 Ductile Iron Pipe Flanges and Flanged Fittings
SP-71 Cast Iron Swing Check Valves, Flanged and Threaded
Ends 818.2.1 SquareandHex Bolts andScrews, Including Askew
SP-75 Specification for High Test Wrought Welding Fittings Head Bolts, HexCapScrews, and Lag Screws
SP-78 Cast Iron Plug Valves 818.2.2 SquareandHex Nuts
112
APPENDIX C
LIST OF NUMBERS AND SUBJECTS OF THOSE
STANDARDS AND SPECIFICATIONS WHICH DO
NOT APPEAR IN THE CODE OR APPENDIX A BUT
MAY BE OF INFORMATIONAL BENEFIT
A 6 Rolled Steel Plates, Shapes, Sheet Piling, and Bars for A 350 Forgings, Carbon and Low-Alloy Steel
Requiring
Structural Use Notch Toughness Testing for Piping Components
A 20 Steel Plates for Pressure Vessels A 377 Cast Iron and Ductile Iron Pressure Pipe
A 29 Steel Bars, Carbon and Alloy, Hot-Rolled and Cold-
Finished A 420 Piping Fittings of WroughtCarbonSteel and Alloy
A 36 Structural Steel Steel for Low-Temperature Service
A 47 Malleable Iron Castings A 441 High-Strength Low-Alloy Structural Manganese Va-
A 48 Gray Iron Castings nadium Steel
A 442 Pressure Vessel Plates, Carbon Steel, Improved Tran-
A 125 Heat-Treated Steel Helical Springs sition Properties
A 126 Gray Iron Castings for Valves, Flanges and Pipe Fit- A 487 Steel Castings Suitable for Pressure Service
tings
A 155 Electric-Fusion Welded Steel Pipe for High-pressure A 502 Steel Structural Rivets
Service A 515 Pressure Vessel Plates, Carbon Steel for Intermediate
A 181 Forgings, Carbon Steel for General Purpose Piping and Higher Temperature Service
A 182 Forgedor Rolled AlloySteel Pipe Flanges, Forged A 516 Pressure Vessel Plates, Carbon Steel, for Moderate-
Fittings, and Valves and Parts for High-Tempera- and Lower-Temperature Service
ture Service A 539 Electric-Resistance-Welded Coiled SteelTubing for
A 197 CuDola Malleable Iron Gas and Fuel Oil Lines
A 575 Merchant Quality Hot Rolled Carbon Steel Bars
A 216 Carbon-Steel Castings Suitable for Fusion Welding A 576 Steel Bars, Carbon, Hot Rolled, Special Quality
for High-Temperature Service
A 217 Martensitic Stainless Steel and Alloy Steel Castings A 691 Carbon and Alloy Steel Pipe, Electric-Fusion-Welded
for Pressure-Containing PartsSuitablefor High- for High-pressure Service a t High Temperatures
Temperature Service A 694 Forgings, Carbon andAlloySteel for Pipe Flanges,
A 225 Pressure Vessel Plates, Alloy Steel, Manganese-Va- Fittings, Valves and Parts forHigh-pressure Trans-
nadium mission Service
A 234 Piping Fittings of Wrought Carbon Steel and Alloy
Steel for Moderate and Elevated Temperatures B 21 Naval Brass Rod, Bar, and Shapes
A 242 High-Strength Low Alloy Structural Steel B 42 Seamless Copper Pipe, Standard Sizes
A 283 Low and Intermediate Tensile Strength Carbon Steel B 43 Seamless Red Brass Pipe
Plates, Shapes, and Bars B 61 Steam or Valve Bronze Castings
A 285 Pressure Vessel Plates, Carbon Steel, Low- and Inter-
mediate-Tensile Strength
113
B 62 Composition Bronze or Ounce Metal Castings 5LE Specification for Polyethylene Line Pipe
B 68 Seamless Copper Tube, Bright Annealed 5LP Specification for Thermoplastic Line Pipe
B 75 Seamless Copper Tube 5LR Specification for Reinforced Thermosetting Resin
Line Pipe
B 249 Wrought Copper and Copper-Alloy Rod, Bar, and
Shapes RP 5L4 Recommended Practice for CareandUse of Rein-
B 251 General Requirements for Wrought Seamless Copper forced Thermosetting Resin Line Pipe
and Copper-Alloy Tube (Metric) RP 1107 RecommendedPipeline Maintenance Welding Prac-
tices
8 584 Copper Alloy Sand Castings for General Applications
Mss
ASM E
SP-55 Quality Standard for Steel Castings-Visual Method
81.20.3 Dryseal Pipe Threads SP-61 Pressure Testing of Steel Valves
816.14 Ferrous Pipe Plugs, Bushings, and Locknuts With Pipe MR-01-75 Sulfide Stress Cracking Resistant MetallicMaterial
Threads for Oil Field Equipment
816.15 Cast Bronze Threaded Fittings
816.18 Cast Copper Alloy Solder Joint Pressure Fittings
N FPA
616.22 Wrought Copper and Copper Alloy Solder-Joint Pres-
sure Fittings 59A Liquefied Natural Gas, Production, Storage, and Han-
816.25 Buttwelding Ends dling of
NOTE:
(1) Obsolete, see API 5L.
114
APPENDIX D
See para. 84 1.1.
SPECIFIED MINIMUM YIELD STRENGTH FOR STEEL PIPE
COMMONLY USED IN PIPING SYSTEMS
Type
Spec. No. Grade [Note (1)l SMYS, psi
ASTM A 53 BW 25,000
115
GENERALNOTE:
This Table is not complete. For the minimum specified yield strength of other grades and grades in other
approved specifications, refer to the particular specification.
NOTES:
(1) Abbreviations: BW - furnace butt-welded; ERW - electric resistance welded; S - seamless; FW -
flash welded; EFW - electric fusion welded; DSA - double submerged-arc welded.
(21 Intermediate grades are available in API 5L.
(3) See applicable plate specification for SMYS.
long-Term HydrostaticStrength Values for Thermoplastic Pipes Covered byASTM D 2513. The valuesapply
only to materials and pipes meeting all the requirements of the basic materials and ASTM D 2513. They
are based on engineering test data obtained in accordance with ASTM D 1599 and analyzed in accordance
with ASTM D 2837. A list of commercial compounds meeting these requirements is published yearly by the
Plastic Pipe Institute.
PB 2110 2000
PE 3406 1250
PE 3306 1250
PE 2306 1250
PE 3408 1600
Long-Term Hydrostatic Strength for Reinforced Thermosetting Pipes Covered byASTM D 251 7 is 11,000
psi. The values apply only t o materials and pipes meeting all the requirements of the basic materials and
ASTM D 2517. They are based on engineering test data obtained in accordance with ASTM D 1599 and
analyzed in accordance with ASTM D 2837.
116
APPENDIX E
FLEXIBILITY AND STRESS INTENSIFICATION
FACTORS
TABLE E l
FLEXIBILITY FACTOR k AND STRESS INTENSIFICATION FACTOR i
Stress Intensification
Factor [Notes ( l ) ,(211
Flexibility Flexibility
Factor Outplene lnplane Cheracteristic
Description k a ii h Sketch
i
Welding elbow
[Notes (1). (3)-(6)1 -
1.65 -
0.75 -
0.9
h h 2/3 h 2/3
or pipe bend
R1 = bend
radius
Closely spaced
miter bend -
1.52
h 5/6
-
0.9
[Notes (1). (3).(411 h 2/3
s < r2 ( 1 + tan 0)
117
TABLE E l (CONT'D)
FLEXIBILITY FACTOR k AND STRESS INTENSIFICATION FACTOR i
Stress Intensification
Factor [Notes (1). (211
Flexibility Flexibility
Factor Outplane lnplane Characteristic
Description k i0 ii h Sketch
Welding tee
[Notes (1). (3). (e)]
per ANSI B 16.9 with 1
ro 2 d/8
rc 2 1.57
Reinforced fabricated
[Notes (1). (3). (7).(811
1
tee with pad or
saddle
Pad ' Saddle -
Unreinforced
[Notes (1). (3). (811 1 -
h0.9
2/3 314 io + 1/4
fabricated tee
Extruded
[Notes (1). (311
welding tee 1
ro 2 0.05d
rc < 1.5 P
Welded-in
[Notes (1). (3). (8)l
contour insert
ro 2 d/8
rc 2 1.5T
1
,0.9
- 2/3
3/4 io -k 1/4 4.4
7
-
'2 w:
118
TABLE E l (CONT'D)
FLEXIBILITY FACTOR k AND STRESS INTENSIFICATION FACTOR i
Stress Intensificetion
Factor [Notes (1). (211
Flexibility Flexibility
Characteristic
lnplaneOutplaneFactor
Description k a i. h Sketch
-
Branch
[Notes (11, (3).(8). (911
welded-on fitting 1 -
0.9 -
0.9
3.3 -
7
h 2/3 h 2/3 '2
(integrally
reinforced)
Stress
Flexibility Intensification
Description Factor k Factor i
119
TABLE E l (CONT'D)
FLEXIBILITY FACTOR k AND STRESS INTENSIFICATION FACTOR i
Characteristic h
Chart A
1.oo
0.75
F
0
:
c
8
LC
0.50
L
b
0.375 1 End flanged c1 = h"6
120
TABLE El (CONT'D)
NOTES:
(1) The flexlbillty factor k In the Table apples to bendlng In any plane The flexlblllty factors k and stress lntenslflcatlon factors ishall not beleSS than
unlty. factors for torslonequal unlty. Both factors applyover the effectwe arc length (shown byheavy center llnes In thesketches) for curved and
miter bends, and t o the tntersectlon polnt for tees.
(2) A slngle lntenslflcatlon factor equal t o 0 9/h2/3 may be used for both i, and j 0 If deslred.
(3) The values of k and I can be read dlrectly from Chart A above. by enterlng with the characterlstlc h computed from the formulas glven above.
Nomenclature
- IS as follows:
T = for elbows and mlter bends, the nommal wall thlckness of the flttlng
= for tees, the nomlnal wall thlckness of the matching plpe
T, = the crotch thlckness of tees
,t = pad or saddle thlckness
8 = one-half angle between adjacent mlter axes
r2 = mean radlus of matchlng pipe
R, = bend radlus of weldlng elbow or plpe bend
ro = see Appendlx F
s = mlter spaclng at center hne
d = outside diameter of branch
D = outslde diameter of run
(4) Where flanges are attached t o one or both ends, the values of k and I In the Table shall be corrected by the factors C,,whlch can be read dlrectly
from Chart B. entering wlth the computed h
(5) The designer IS cautloned that cast butt welded flttlngsmay have conslderably heavler walls than that of the plpe wlth whlch they are used. Large
errors may be Introduced unless the effect of these greater thlcknesses IS consldered
(z)
(6)In large diameter thin-wall elbows and bends. pressure can signlficantly affect the magnitudes of k and 1. TO correct values from the Table.
[
dlvlde k by. 1 + 6(%) (+)
7/3
(2)] 1/3
[
dlvlde I by: 1 + 3.25($) (+) 2'5
where
P = Internal pressure
E, = room temperature modulus of elasticity
(7) When t, > 1 'h use h = 4 r/r2
(8) For branch connections In the range of 0 5 < d/D < 1 0, multlply the calculated value by 1 5 t o compensate for posslble nonconservatlve
out-of-plane stress lntenslflcatlon factors.
(9) The deslgner must be satlsfled that this fabrlcatlon has a pressure ratlng equlvalent to stralght plpe.
(10) Factors shown apply to bendmg. Flexlblllty factor for torson equals 0.9.
121
APPENDIX F
See para. 83 1.6.
123
Limits of
GENERAL NOTE:
reinforcement
Sketch to show method
of establishing To when
the taper encroaches
on the crotch radius.
FIG. F2
Corrosion allowance
FIG. F1
GENERAL NOTE:
Sketch is drawn for
condition where
K = 1 .OO.
FIG. F3
1Reinforcement
GENERAL NOTE:
Sketch is drawn for
condition where
K = 1.OO.
FIG. F4
124
L = smaller of 2-112 H
or 2-112 B + M
It! Al- I h I
125
PD 650 x 24
t=-- - Effective A’2 = 0.295 X -
35?000 - 0.22 in.’
2SFET 2 x 46,000 x 0.60 x 1 . 0 0 x 1.00 46,000
= 0.283 in.
Required area
650 x 8.625
tb = Area (15.50 - 8.62) x 0.25 = 1.72 in.2
2 x 35,000 x 0.60 x 1.00 x 1.00
= 0.133 in. Fillet welds (assuming two ‘/4 in. welds each side):
126
= 15.376 in.
16 + 12.3 = 29 in. (rounded to the next higher whole
number)
Reinforcement Required
Use plate 29 in. long:
AR = dt = 15.376 X 0.283 = 4.35 in.2
A3 = 0.312 X (29 - 16) = 4.05 in.2
Reinforcement Provided
Two '/4 in. welds to outlet:
A , = (H - t) d = 0.029 x 15.376 = 0.44 in.2
2 X 0.25 X 0.25 X 0.50 = 0.06 in.?+
Effective Area in Outlet
= 2.5 x 0.312 + 0.312 = 1.09 in. The use of end welds is optional. See Fig. 13.
127
8.625 in.
FIG. F6
16 in.
I
I
I
30.752 in. -71
1
1
FIG. F7
128
APPENDIX G
TEST OF WELDERS WHO ARE LIMITED TO WORK
ON LINES OPERATING AT HOOP STRESSES OF
LESS THAN 20% OF THE SPECIFIED MINIMUM
YIELD STRENGTH
See para. 823.1 1.
(a) An initial test shall qualify a welder for work. junction of the fitting and run pipe shows incomplete
Thereafter, his work shall be checked either by requa- fusion, overlap, or poor penetration.
lification at 1 year intervals or by cutting out and test- & I the periodic checking of welders who work
For
ing production work at least every 6 months. on small service lines only(2 in. or smaller in diameter),
(b) The test may be made on pipe of any diameter the following special field test may be employed. This
12 in. or smaller. The test weld shall be made with the test should not be used as a substitute for the original
pipe in a horizontal fixed position so that the test weld qualifying test.
includes at least one section of overhead position weld- Two sample welds made by the welder under test
ing. should be taken from steel service line. Each sample
(c) The beveling, root opening, andother details should be cut 8 in. long with the weld located ap-
must conform tothe procedure specification under proximately in the center. One sample shall have the
which the welder is qualified. ends flattened andthe entire joint subjected to the
(dl The test weld shall be cut into four coupons tensile strength test. Failure must bein the parent
and subjected to the root bend test. If as a result of metal and not adjacent to or in the weld metal to be
this test, a crack develops in the weld material or be- acceptable. The second sample shall be centered in
tween the weld and base metal more than YE in. long the guided bend testing machine and bent to the con-
in any direction, this shall be cause for rejection. tour of the die for a distance of 2 in. on each side of
Cracks occurring on the corner of the specimen during the weld. The sample to be acceptable must show no
testing shall not be considered. If not more than one breaks or cracks after removal from the bending ma-
coupon is rejected, the weld is to be considered as ac- chine.
ceptable. When a tensile strength testing machine is not availa-
(e) Welders who are to make welded service line ble, two bend test samples will be acceptable in lieu of
connections to mains should be required to satisfac- one tension and one bending test.
torily pass the following tests. (g) Tests for Copper Joints. Personnel who are to
(1) Weld a service line connection fitting to a pipe work on copper piping should pass the following test
section having the same diameter as a typical main. satisfactorily.
This weld should be made in the same position as this A brazed or soldered copper bell joint should be
type of weld is made in the field. made on any size of copper pipe used, with the axis of
(2) The weld should be tested by attempting to the pipe stationary in the horizontal position. The joint
break the fitting off the runpipe by any available means so welded is to be sawed open longitudinally at the top
(knocking it off). of the pipe (the top being the uppermost point on the
A sample shall be rejected if the broken weld at the circumference at time joint is brazed). The jointshould
129
be spread apart for examination. The bell end of the surfaces. At least 50% of the length at the top of the
joint must be completely bonded. The spigot end of the joint must be joined.
joint must give evidence that the brazing alloy has (h) Records shall be kept of the original tests and all
reached at least 75% of the totalarea of the telescoped subsequent tests conducted on thework of each welder.
130
APPENDIX H
FLATTENING TEST FOR PIPE
See para. 8 11.253(b).
(a) The flattening test shall be made on standard than three-fourths of the original outside diameter for
weight and extra strong pipe over NPS 2. It shall not buttweld, or two-thirds the outside diameter for lap
be required for double extra strong pipe. weld and electric-resistance weld, and no cracks or
(6) For lap-welded and butt-welded pipe, the test breaks in the metal elsewhere than in the weld shall
section shall be 4 in. to 6 in. in length, and the weld occur until the distance between the plates is less than
shall be located 45 deg. from theline of direction of the shown below. For seamless pipe, no breaks or cracks in
applied force. the metal shall occur until the distance between the
(c) For electric-resistance-welded pipe, bothcrop plates is less then that shown below:
ends from each length of pipe shall be flattened between
parallel plates with the weld at the point of maximum Type of Pipe Distance Between Plates H
Buttwelded 60% of outside diameter
bending until the opposite walls of the pipe meet. No Lap welded '/3 the outside diameter
opening in the weld shall take place until the distance Electric-resistance welded, b'3 the outside diameter
between the plates is lessthan two-thirdsof the original Grades A and B
outside diameter of the pipe. No cracks or breaks in the Seamless, Grades To the distance H developed
metal elsewhere than in the weld shall occur until the A and B by the following formula:
distance between the plates is lessthan one-thirdof the
original outside diameter of the pipe, but in no case less
than five times the thickness of the pipe wall. Evidence
of lamination or burnt material shall not develop dur- where
ing the entire flattening process, and the weld shall not H = distance between flatten-
show injurious defects. ing plates, in.
t = nominal wall thickness of
(d) For seamless pipe the test section shall not be pipe, in.
less than 2'12 in. in length. e = deformation per unit
(e) The test shall consist of flattening a section of length (constant for a
pipe between parallel plates until the opposite walls given grade of steel, 0.09
meet. For welded pipe, no opening in the weld shall for Grade A and 0.07 for
Grade B)
take place until the distance between the plates is less
131
APPENDIX I
GENERAL NOTES:
(a) When a welding saddle is used, it shall be inserted over this type of connection.
(b) W1 = 36/8, but not less than 1/4 in.
(c) N = 1/16 in. min., 1/8 in. max., unless back welded or backing strip is used.
FIG. I1 WELDING DETAILS FOR OPENINGS WITHOUT REINFORCEMENT OTHER THAN THAT I N HEADER AND
BRANCH WALLS
133
Pad
Saddle
GENERAL NOTES:
(a) All welds to have equal leg dimensions, and a minimum throat = 0.707 X leg dimension.
(b) If M is thicker than H, the reinforcing member shall be tapered down to the header wall thickness.
(c) Provide holein reinforcement to reveal leakage in buried welds and to provide venting during
welding and heat treatment [See para 83 1.4 1 (h)]
134
-7-----
These longitudinal
-il
'I
'
may
welds be 'I
located anywhere II
Ice II
GENERAL NOTE:
GENERAL NOTE:
provide hole in reinforcement to reveal
Since fluid pressure is exerted
on bothsides of pipe metal under tee, leakage in buriedwelds and t o provide
venting during welding and heat
the pipe metal does not provide
treatment [see para. 8 3 1 4 1 H I
reinforcement.
Not required for tee type.
lee Type
Sleeve Type
Optional weld
4
Sleeve and Saddle Type Saddle Type
135
.9 n
.
U
hl
z
W
LL
0
136
EXPLANATORY NOTES (2) Where the nominal internal offset is more than
3/32 in. and there is no access to the inside of the pipe
General
for welding, the transition must be made by a taper cut
(a) The sketches in Fig. I 5 illustrate acceptable on the inside end of the thicker section. See sketch (b).
preparations for joining pipe ends by butt welding for The taper angle shall not be steeper than 30 deg. nor
materials having unequal wall thicknesses and/or with less than 14 deg.
unequal strengths (minimum specified yield strength). (3) Where the nominal internal offset is more than
(b) The thickness of the sections to be joined beyond 3/32 in. but does not exceed one-half the thinnersection,
the joint design area shall comply with the design re- and there is access to theinside of the pipe for welding,
quirements of this Code. the transition may be made with a tapered weld as
(c) When the minimum specified yield strengths of shown in sketch (c). The land on the thicker section
the sections to be joined are unequal, the deposited must be equal to the offset plus the land on abutting
weld metal shall have mechanical properties at least section.
equal to those of the section having the higher strength. (4) Where the nominal internal offset ismore than
(d) The transition between ends of unequal thick- one-half the thinner section and there is access to the
ness may be accomplished by taper or welding as illus- inside of the pipe for welding, the transition may be
trated or by means of a prefabricated transition ring. made with a taper cut on the inside end of the thicker
(e) Sharp notches or grooves at theedge of the weld section as shown in sketch (b), or by a combination
where it joins a slanted surface shall be avoided. taper weld to one-half the thinner section and a taper
U, For joining unequal thicknesses of equal spe- cut from that point as shown in sketch (d).
cified yield strengths, the rules given herein apply, ex-
cept there is no minimum angle limit to the taper.
(g) The maximum thickness f D for design purposes
shall not be greater than 1.5t. External Diameters Unequal
(a) Where the external offset does not exceed one-
half the thinner section, the transition may be made by
Internal
Diameters
Unequal welding as shown by sketch (e), provided the angle of
rise of the weld surface does not exceed 30 deg. and
(a) For Piping to operate at hoop stresses ofless both beveledges are properly fused.
than 20% ofspecified minimum yield strength, if the (6) Where there is an external offset exceeding one-
nominal wall thicknesses of the adjoining ends do not half the thinner section, that portion of the offset Over
vary more than 9'8 in., no special treatment is necessary %t shall be tapered as shown in sketch (f).
provided adequate penetration and bond is accom-
plished in welding. If the offset is greater than x/! in.,
the following paragraphs will apply.
(b) For stress Levels 20% or-More ofthe Spec$ed Internal and External Diameters Unequal
Minimum Yield Strenpth -
(1) If the nominal wall thicknesses of the adjoin- Where there is both an internal and anexternal offset,
ing ends do not vary more than 3/32 in., no special the joint design shall be a combination of sketches (a)
treatment is necessary, provided full penetration and through (f), i.e., sketch (g). Particular attention must be
bond is accomplished in welding. See sketch (a). paid to proper alignment under these conditions.
137
t
+
t
t
‘D
c 3 0 deg. max.
30deg. rnax. \
(d, 14 deg. min. (1:4)
Internal Offset
3 0 deg. max.
[Note (111
(e) (f)
External Offset
30 deg. max.
14deg. min. (1:4)
(9) Combination
138
U U
t
4t
0.707t
(c) FrontWeld
Back
and (dl
Weld
Back
and
Face
I
Not less
than t
I c min. = 1-1/4t,
h - l / l S in.
but not less than 5/32 in.
7 Nominal
t pipe
wall
thickness
139
and Material
Forged Rolled Steel ASTM A 106
Drilling Template
Outside
th Inside Outside Nominal
Pipe Diameter Thickness Diameter of Hub of Hub of and Length of Bolt Each,
Size A T B L E Bolts of Bolts Circle Ib
6 11 -
9
16
6.72 11 7 16
9 8 f x 2f 91 13
8 13i - 8.72 11 911. 8 f x 2: llf 18
16 10
16
-
11 10.88 11 12
lb
12 ;x 2 1 141 26
19 12
I6
-
11
16
12.88 11 14; 1217 ;x 21 42
21 14 14.14 11 15; 12
4 1 x 2; 18: 44
16 23; 3
4
16.16 11 18 16 1 x 2f 21: 58
18 25 4
18.18 11 19; 16 1; x 3 22: 59
20 27; 4
20.20 :1 22 20 If x 3 25 69
22 29f 1 22.22 12 24: 20 11 x7631 271
4 2
48 59i 44 1; x 4; 56 426
50 61: 44 124
x 424 58: 451
52 64 44 If x 44 6Of 477
54 66i 44 11 x 42 62: 504
4 4
NOTE:
(1) Flat faced: designed for use with full face gasket or asbestos sheet gasket extending to the bolt holes.
140
TT\ I
11
plant
processing plant
r
LNG baseload plant
covered by NFPA 59A
GENERAL NOTE: Facilities and piping indicatedby solid lines are within the scope
of ASME 831.8,
-
Legend
Main line (pipeline) transmission line
Gathering pipelines
-0-o- Gas flow lines
Separation and/or processing plant
Gas well with separator
Gas well without separator or processing plant
Production platform
Compressor station
141
Onshore P
Pipe or bottle
type holder
7
See Fig. 110
GENERAL NOTE: Facilities and piping indicated by solid lines are within the scope of ASME B31.8.
-
Legend
Main
line
pipelines
Gathering
(pipeline)
transmission line Gas well without separator or processing plant
station
compressor
-0 -0- station
GasMeter
flow lines
?E: Separation and/or processing plant A Overpressure protection device for pipelines and mains
*Ld-
7
CT Gas well
with separator
142
High-pressure High-pressure
LNG or LPG peak shaving plant distribution system distribution system
\r '..
(above 60 psi) (60 psi
or less)
See
Fig. I9
Holder
filling
' regulator
See
Fig. I9
GENERAL NOTE: Facilities and piping indicated by solid lines are within the scope of ASME 831.8.
Legend
Compressor station
Meter station
143
APPENDIX J
Extracted partially from ASME SI-1.
COMMONLYUSEDCONVERSIONFACTORS
(For others, see ASTM E 380.)
145
GENERAL NOTE:
The factors are written as a number greater than one and less than ten withsix or less decimal places. The
number is followed by the letter E (for exponent), a plus or minus symbol, and two digits which indicate to
what power of ten by which the number must be multiplied t o obtain the correct value.
For example,
1.745 329
E-02 is 1.745 x lo-' or 0.017
329 453 29
NOTE:
(1) Relationships that are exact in terms of the base units.
Other Units or
Quantity Unit' Symbo Limitations
146
Other Units or
Quantity Unit1 Symbol Limitations
Mechanics
Heat
147
Other Units or
Quantity Unit1 Symbol Limitations
NOTES:
(1) Conversion factors between SI units and U.S. customary are given in ASTM E 380.
(2) Preferred use for temperature and temperature interval is degrees Celsius (“0, except for thermody-
namic and cryogenic work where kelvins may be more suitable. For temperature interval, 1 K = 1°C
exactly.
148
APPENDIX K
CRITERIA FOR CATHODIC PROTECTION
Reprinted with permission from the National Association of Corrosion Engineers' NACE Standard RP-01-69, Section 6. Asterisk (*)
denotes word change from NACF. text.
6.2.4 Voltage measurements on pipelines are to be made with the 6.3.1.5 A net protective current from the electrolyte into the
reference electrode located on the electrolyte surface as closeas structure surface as measured by an earth current technique applied
feasible to the structure surface being investigated. Consideration at predetermined current discharge (anodic) points of the structure.
shall begiven to voltage (IR) drops other than those across the
structure-electrolyte boundary, the presence of dissimilar metals, and
the influence of other structures for valid interpretation of voltage 6.3.2 Aluminum Structures
measurements.* 6.3.2.1 A minimum negative (cathodic) voltage shift of 150
millivolts, produced by the application of protective current. The
6.2.5 No one criterion for evaluating the effectivenessof cathodic voltage shift is measured between the structure surface and a satu-
protection has proven to be satisfactory for all conditions. Often a rated coppercopper sulfate reference electrode contacting the elec-
combination of criteria is needed for a single structure. trolyte. See precautionary notes in 6.3.2.3 and 6.3.2.4.
6.3.2.2 A minimum negative (cathodic) polarization voltage
6.3 Criteria shift of 100 millivolts, measured between the structure surface and
a saturated copper-copper sulfate reference electrode contacting the
6.3.1 Steel and Cast Iron Structures electrolyte. This polarization voltage shift is to be determined by
6.3.1.1 A negative (cathodic) voltageof at least 0.85 volt as interrupting the protective currentand measuring polarization
measured between thestructure surface and a saturated copper- decay. When the current is initially interrupted, an immediate volt-
copper sulfate reference electrode contacting the electrolyte. Deter- age shift will occur. The voltage reading after the immediate shift
mination of this voltage is to be made with the protective current shall be used as the base reading from which to measure polarization
applied. decay. See precautionary notes in 6.3.2.3 and 6.3.2.4.
149
6.3.2.3 PRECAUTIONARYNOTE - ExcessiveVoltages: 6.3.2.3 and 6.3.2.4), they should be electrically isolated with insulat-
Notwithstanding the alternative minimum criteria in 6.3.2.1 and ing flanges or the equivalent.
6.3.2.2, aluminum, if cathodically protected at voltages in excess of
1.20 volts measured between the structure surface and a saturated
copper-copper sulfate reference electrode contacting the electrolyte
6.4 Alternative Reference Electrodes
and compensated for the voltage (IR) drops other thanthose across
the structure-electrolyte boundary, may suffer corrosion resulting 6.4.1 Other standard reference electrodes may be substituted for
from the buildup of alkali on the metal surface. A voltage in excess the saturated copper-copper sulfate reference electrodes. Two com-
of 1.20 volts should not be used unless previous test results indicate monly used electrodes are listed below along with their voltage equiv-
no appreciable corrosion will occur in the particular environment. alent to -0.85 volt referred to saturatedcopper-copper sulfate refer-
ence electrode:
6.3.2.4 PRECAUTIONARY NOTE - Alkaline Soil Condi-
tions: Since aluminum maysuffer from corrosion under high pH 6.4.1.1 Saturated KC1 calomel reference electrode: -0.78 volt.
conditions and since application of cathodic protection tends to in-
6.4.1.2 Silver-silver chloride reference electrode usedinsea
crease the pH at the metal surface, careful investigation or testing
water: -0.80 volt.
should be made before applying cathodic protection to stop pitting
attack on aluminum structures in environments with a natural pH in 6.4.2 In addition to these standard reference electrodes, an alterna-
excess of 8.0. tive metallic material or structure may be used in place of the satu-
rated copper-copper sulfate reference electrode if the stability of its
6.3.3 Copper Structures electrode potential is assured and if its voltage equivalent referred to
6.3.3.1 A minimum negative (cathodic) polarization voltage a saturated copper-copper sulfate reference electrode is established.
shift of 100 millivolts measured between the structure surface and
saturated copper-copper sulfate reference electrode in the electrolyte.
This polarization voltage shift is to be determined by interrupting the
protective current and measuring the polarization decay. When the 6.5 Special Considerations
current is initially interrupted, immediate voltage shift will occur. 6.5.1 Specialcases, such asstraycurrentsandstray electrical
The voltage reading after the immediate shift shall be used as the base gradients, may exist which require the use of criteria different from
reading from which to measure polarization decay. those listed above. Measurements of current loss and gain on the
structure and current tracing in the electrolyte have been useful in
6.3.4 Dissimilar Metal Structure such cases.
6.3.4.1 A negative (cathodic) voltage, between all structure sur-
faces and a saturated copper-copper sulfate reference electrode con- 6.5.2 Abnormal conditions sometimes exist where protection is
tacting the electrolyte, equal to that required for the most anodic ineffective or only partially effective. Such conditions may include
metal should be maintained. If amphoteric structures are involved elevated temperatures, disbonded coatings, shielding, bacterial at-
that could be damaged by high alkalinity (see precautionary notes in tack, and unusual contaminants in the electrolyte.
150
APPENDIX L
DETERMINATION OF REMAINING STRENGTH OF
CORRODED PIPE
-
(For background information, see ANSI/ASME B31G, Manual for Determining the Remaining Strength of Corroded Pipelines.)
A = 0.893 L A 6 i
where FIG. L1
D = nominal O.D. of the pipe, in.
( )
(d) For values of A less than or equal to 4.0,
151
APPENDIX M
GAS LEAKAGE CONTROL CRITERIA
See para. 852.2.
153
practical, at no more than 2 in. above the ground sur- (2) Procedure. Allvisual indications should be
face. In areas where the pipingis under pavement, evaluatedusing a combustible gas indicator (CGI).
samplings should also be at curb line@),available Personnel performing these surveys should have good
ground surface openings (such as manholes, catch ba- allround visibility of the area being surveyed and their
sins, sewer, power, and telephone duct openings, fire speed of travel should be determined by taking into
and traffic signal boxes, or cracks in the pavement or consideration the following:
sidewalk), or other interfaces where the venting of gas (a) system layout
is likely to occur. Sampling should be adjacent to the (b) amount and type of vegetation
exposed piping. (c) visibility conditions (such as lighting, re-
(3) Utilization. The use of this survey method flected light, distortions, terrain, or obstructions)
may be limited by adverse conditions (such as excessive (3) Utilization
wind, excessive soil moisture, or surface sealing by ice (a) This survey method should be limited to
or water). areas where adequate vegetation growth is firmly estab-
The survey should be conducted at speeds slow lished.
enough to allow an adequate sample to be continuously (b) This survey should not be conducted under
obtained by placement of equipment intakes over the the following conditions:
most logical venting locations, giving consideration to (I) soil moisture content abnormally high
the location of gas facilitiesand any adverse conditions (2) vegetation dormant
which might exist. (3) vegetation in an accelerated growth pe-
(6) Subsurface Gas Detection Survey riod, such as in early spring
(1) Definition. The sampling of the subsurface at- (c) Other acceptable survey methods should be
mosphere with a combustible gas indicator (CGI) or used for locations within a vegetationsurvey area
other device capable of detecting 0.5% gas inair at the where vegetation is not adequate to indicate the pres-
sample point. ence of leakage.
(2) Procedure. The survey should be conducted by (d) Pressure Drop Test
performing tests with a CGI in a series of available (I) DeJinition. A test to determine if an isolated
openings(confinedspaces and small substructures) segment of pipeline loses pressure due to leakage.
and/or bar holes over, or adjacent to, the gas facility. (2) Procedure. Facilitiesselectedfor pressure
The location of the gas facility and its proximity to drop tests should first be isolated and then tested. The
buildings and other structures should be considered in following criteria should be considered in determining
the spacing of the samplepoints.Sampling points test parameters.
should be as close as possible to themain or pipeline, and (a) Test Pressure. A test conducted on existing
never further than 15 ft laterally from the facility. Along facilities solely for the purpose of detecting leakage
the route of the main or pipeline, samplingpoints should should be performed at a pressure at least equal to the
be placed at twice the distance between the pipeline and operating pressure.
the nearestbuildingwall, or at 30 ft, whichever is (b) Test Medium. The test medium used must
shorter, but, in no case need the spacing be lessthan 10 comply with the requirements of para. 841.3.
ft. The sampling pattern should include sample points (c) TestDuration. The duration of the test
adjacent to service taps, street intersections, and known should beof sufficient length to detect leakage. The
branch connections as well as sampling points over or following should be considered inthe determination of
adjacent to buried service lines at the building wall. the duration:
(3) Utilization (1) volume under test
(a) Good judgment should beused to deter- (2) time requiredfor the testmedium to
mine when availableopenings (such as manholes, become temperature stabilized
vaults, or valve boxes) are sufficient to provide an ade- (3) sensitivity of the test instrument
quate survey. When necessary, additional sample (3) Utilization. Pressure drop tests should be used
points (bar holes) should be made. only to establish the presence or absence of a leak on
(b) Sampling points should be of sufficient a specifically isolated segmentof a pipeline. Normally,
depth to sample directly within the subsurface or sub- this type of test will not providea leak location. There-
structure atmosphere. fore, facilities on which leakage is indicated may re-
(c) VegetationSurvey quire further evaluation by another detection method
( I ) Definition. Visual observations made to detect in order that the leak may be located, evaluated, and
abnormal or unusual indications in vegetation. graded.
154
155
probable hazard to persons or property, and requires which could have contributed to the leakage. Gas may
immediate repair or continuous action until the condi- also migrate and vent alonga trench provided forother
tions are no longer hazardous. facilities.
(b) Grade 2 is a leak that is recognized as being (d) Place evenly spaced bar or test holes over the
nonhazardous at the time of detection, but requires suspected leaking gas line and trace the gas to its source
scheduled repair based on probable future hazard. by identifying the test holes with the highest readings.
(c) Grade 3 is a leak that is nonhazardous at the All bar holes should be of equal depth and diameter
time of detection and can be reasonably expected to and down to the pipe depth where necessary in order
remain nonhazardous. to obtain consistent and worthwhile readings. All CGI
readings should be taken at an equal depth. Only the
highest sustained readings should be utilized.
M5.3 Leak Classification andAction Criteria (e) High readings are found frequently in more than
Criteria for leak classification and leakage control one adjacent bar hole and additional techniques are
are provided in Tables M5.3A, M5.3B, and M5.3C. necessary to determine which reading is closest to the
The examples of leak conditions provided inthe Tables probable source. Many of the bar hole readings will
are presented as guidelines and are not exclusive. The normally decline over a period of time, but it may be
judgment of the company personnel at the scene is of desirable to dissipate excess gas fromthe underground
primary importance in determining the grade assigned locations to hasten this process. Evaluation methods
to a leak. should be used with caution to avoid the distorting of
the venting patterns.
# Once the underground leakage has been iden-
M5.4 Reevaluation of a Leak tified, additional holes and deeperholes should be
When a leak is to be reevaluated (seeAction Criteria probe&to bracket the area more closely. For example,
in Tables M5.3B and M5.3C), it should be classified test holes may be spaced 6 ft apart initially. The 6 ft
using the same criteria as when the leak was first dis- spacing between the two highest test holes might then
be probed with additional test holes with spacing as
covered.
close as 12 in.
(g) Additional tests include taking CGI readings
at the top of a bar hole or using a manometer or
M6 PINPOINTING bubble forming solution to determine which bar hole
M6.1 Scope has the greatest positive flow. Other indications are:
dust particles blowing from the bar holes, the sound
Pinpointing is a systematic process of tracing a de- of gas coming from the bar hole, or the feel of gas
tected gas leakto its source. Use ofthe following proce- flow on a sensitiveskinsurface. On occasion, sun-
dures as appropriate should prevent unnecessary exca- light defraction can be observed as the gas vents to
vation, whichis more time consuming than pinpointing the atmosphere.
a leak. (h) When gas is found in an underground conduit,
tests at available openings may be used to isolate the
source in addition to the techniques previously men-
M6.2 Procedure
tioned. Many timesthe leak is found at the intersection
{a) Determine the migration of gas by establishing of the foreign conduit and a gas line, and particular
the outer boundaries of the indications. This will define attention should be given to these locations.
the area in which the leak will normally be located. (i)When the pattern of the CGI readings has stabil-
These tests should be made with a CGI without ex- ized, the bar hole with the highest reading will usually
pending excessive effort providing sample points. pinpoint the gas leak.
(b) Locate all gas linesto narrow the area of search, (j) When and where piping has been exposed, test
giving particular attention to the location ofvalves, withbubble-forming solution particularly to locate
fittings, tees, and stubs. Connections have a relatively smaller leaks.
high probability of leakage. Caution should be exer-
cised to prevent damage to other underground struc-
M6.3 Precautions
tures during barring or excavating.
(c) Identify foreign facilities in the area of search, (a) Unusual situations, which are unlikely but possi-
Look forevidence of recent construction activities ble, may complicate these techniques on some occa-
156
sions. For example, multiple leakage, which givescon- thus, give substantially higher readings. Gas detected
fusing data, can occur. To eliminate this potential com- in sewer systems should be considered as migrating gas
plication, the area should be rechecked after repairs are leakage until proven otherwise by test and/or analysis.
completed. Gas may form pockets occasionally and (6) When pinpointing leakage where the gasis
give a strong indication until the cavity in which the heavier than air(LP gas) the gas will normally stay low
pocket has formed has been vented. Foreign gases, such near the pipe level, but may flow downhill. LP gases
as gas from decomposed material, occasionally may be usually do not diffuse rapidly or migrate widely in the
encountered. This presence is characterized by fairly soil so the leak isgenerally close to theindication. If the
constant CGI readings between 15% and 30% of gas gas is venting into a duct or sewer system, it can travel
in airthroughoutan area. Landfill areas could, considerable distances.
157
i
TABLE M4
TYPE AND GENERAL USAGE1
l- T T
Instrument Ty - -
- tnsitivi
.ewer Level Upper Sensitivi -
Levc
Sampling Sample
Surface Survey Subsurface Survey
-- -
'PM2 16 LEL b Gas
-
> Ga! Method Flow Rate
... Thermal conductivity 5,000 50 2.5 ... ... 00 iand aspirated ...
( % Gas)
1
Infrared detector 1
1,000 2 0.1 Pump 2-5 liters/min
- 50,000 100 -
5
I
NOTES
(1) The PPM, percent LEL, and percent gas values shown are for methane concentrations. Where other gases (such as liquefied petroleum gas
or manufactured gas) are involved, appropriate adjustment should be made to be commensurate with the criteria of these procedures.
(2) PPM: parts per million.
(3) When the maximum concentration detectable is exceeded, the needle of the instrument meter will drop t o zero or below.
(4) Upper sensitivity level varies with different models.
158
TABLE M5.3A
LEAK CLASSIFICATION AND ACTION CRITERIA - GRADE 1
NOTE:
(1) The prompt action in some instances may require one or more of the following:
implementation of company emergency plan (see para. 850.4);
evacuating premises;
blocking off an area;
rerouting traffic;
eliminating sources of ignition;
venting the area;
stopping the flow of gas by closing valves or other means;
notifying police and fire departments.
159
TABLE M5.3B
LEAK CLASSIFICATION AND ACTION CRITERIA - GRADE 2
Grade Definition Action Criteria Examples
160
TABLE M5.3C
LEAK CLASSIFICATION AND ACTION CRITERIA - GRADE 3
161
APPENDIX N
RECOMMENDED PRACTICE FOR HYDROSTATIC
TESTING OF PIPELINES IN PLACE
163
and check the test section for leakage. Repair any sured volume) per increment of pressure rise that was
major leaks that are found. required during the straight-line part of the pressure-
(3) Afterthe hold time period, pressurize at a volume plot before any deviation occurs.
uniform rate, to the test pressure. Monitor fordeviation (2) the pressure shall not exceed the pressure oc-
from a straight line by use of pressure-volume plots curring when the number of pump strokes (measured
(logs or automatic plotter). volume) takenafter deviation from the straight-line
(4) When the test pressure is reached and stabl- part of the pressure-volume plot, times the volume per
ized from pressuring operations, a hold period may stroke, is equal to 0.002 times the test section fill vol-
commence. During this period, test medium may be ume at atmospheric pressure. This represents theaver-
added as required to maintain the minimum test pres- age behavior of the test section. Individual pipe lengths
sure. may experience greater or smaller expansion based on
their respective mechanical properties.
(a) Pressure-Volume Plot Methods. If monitoring If during the hold period, leakage is indicated, the
deviation from a straight line with graphical plots, an pressure may be reduced while locating the leak. After
accurate plot of pressure versus the volume of water the leak is repaired, a new hold period must be started
pumped into the line may be made either by hand or at full test pressure.
automatic plotter. To make a hand plot, thepump
strokes are counted to determine volume and plotted N7.0 RECORDS
against pressure readings. The plot should be started at
a pressure low enough to accurately establish the The operating company shall maintain in its file for
straight-line portion of the pressure-volume plot. The the useful life of each pipeline and main, recordsshow-
points should be plotted frequently enough so that devi- ing the following:
ation from thestraight-line portion can be detected (a) test medium;
readily. The deviation from the straight line is the start (b) test pressure;
of the nonlinear portion of the pressurevolume plot (c) test duration;
and indicates that the elastic limit of some of the pipe (dl test date;
within the section has been reached. (e) pressure recording chart and pressure log;
(b) Yield for unidentified or used pipe [as limited by cf3 pressure versus volume plot (if applicable);
para. 841.1 12(a) and allowed under paras. 8 11.l(f) and (g) pressure at high and low elevations;
817.13(h)] is determined by using the pressure at the (h) elevation at point test pressure measured;
highest elevation within a test section, at which the (i) person(s) conducting test, operator, and testing
number of pump strokes(measured volume) per incre- contractor, if utilized;
ment of pressure rise becomes twice the number of fj) environmental factors (ambient temperature,
pumpstrokes (measured volume) per increment of raining, snowing, windy, etc.);
pressure rise that was required during the straight-line (k) manufacturer (pipe, valves, etc.);
part of the pressure-volume plot before any deviation (1) pipe specifications (SMYS, diameter, wall thick-
occurs. ness, etc.);
(c) For control of maximum test pressure when ex- (m) clear identification of what is included in each
ceeding 100% SMYS within a test section, one of the test section;
following measures may be used: (n) description of any leaks or failures and their dis-
( I ) the pressure at whieh the number of pump position.
strokes (measured volume) per increment of pressure The above records shall be reviewed to assure that the
rise becomes twice the number of pump strokes (mea- requirements of this Code have been met.
164
APPENDIX 0
PREPARATION OF TECHNICAL INQUIRIES TO THE
ASME CODE FOR PRESSURE PIPING, B31
165
INDEX
For Index of Definitions. see para. 806.
A Clearance
underground
other
between
and mains
Accessibility of vaults .......................... 847.2 structures
of plastic piping ............................ 842.38
Air piping system ............................ 843.53
of steel piping ............................ 841.143
Air receivers ................................ 843.535
climates,
Cold
materials for use in .................814
Anchorage for buried piping ...................... 835
corrosion control in ............................ 864
Arcburns .................................. 841.244
Cold-springing
elimination of ............................. 841.245
definition of .............................. 805.151
Arctic environment .............................. 864
of piping .................................. 832.37
Combustible materials. storage of. in
B compressor stations ......................... 853.15
Backfilling Compressor stations ............................. 843
steel pipe ................................. 841.253 construction of building ..................... 843.12
plastic pipe ............................ . 8 42.431(b) design of ................................... 843.1
Bends. elbows. and miters ..................... 841.23 electrical facilities ........................... 843.2
Bends in plastic piping ........................ 842.44 equipment .................................. 843.4
Bottle-tight facilities. control of pressure in . . . . . . .845.21 cooling and lubrication failures . . . . . . . . . . . . . 843.46
Branch connection. welded emergency shutdown facilities . . . . . . . . . . . . .843.43 1
reinforcement of .................... Fig . F5. App. F engine overspeed stops . . . . . . . . . . . . . . . . . . .843.432
rules for reinforcement of. examples . . . . . . . . . . APP. F explosion prevention ...................... 843.47
Branchesinplasticpiping ..................... 842.44 fire protection ............................ 843.42
Buildings intended for human occupancy .......... 840.2 fuelgas control .......................... 843.45
Buried piping. anchorage for ...................... 835 gas treating facilities ...................... 843.41
at bends . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2 liquid removal .......................... 843.4 1 1
forces on pipe joints ......................... 835.4 liquid removal equipment . . . . . . . . . . . . . . . . .843.412
general information .......................... 835.1 mufflers ................................ 843.47 1
interconnection of underground lines . . . . . . . . . . .835.6 pressure limiting requirements . . . . . . . . . . . . . .843.44
restraint due to soil friction . . . . . . . . . . . . . . . . . . .835.3 safety devices ............................ 843.43
supports for buried piping .................... 835.5 ventilations of building . . . . . . . . . . . . . . . . . . .843.472
exits ...................................... 843.13
fenced areas ............................... 843.14
C
location of building ......................... 843.11
Casing. insertion in. piping ..................................... 843.5
of plastic piping ........................... 842.432 air piping system ......................... 843.53
of steelpiping ............................ 841.144 air receivers ............................ 843.535
Cast iron service lines . . . . . . . . . . . . . . . . . . . . . . . . . . 849.3 fuel gas piping ........................... 843.52
connections to mains ........................ 849.32 gas piping ............................... 843.5 1
use of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 849.3 1 testing of ............................. 843.5 13
Class location. change in ......................... 854 hydraulic piping .......................... 843.57
description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 840.2 identification of valves and piping . . . . . . . . . . 843.514
167
168
169
170
171
172
173
174
T
Test requirements for pipelines . . . . . . . . . . . . . . . . . . 841.3
at less than 30% of yield ........ 841.33, Table 841.33
at 30% or more of yield . . . . . . 841.32, Table 841.322(f) W
Testing repairs ................................ 85 1.4
Wall thickness
Tests of welders ............................. APP. G
Thermoplastic design. limitations of . . . . . . . . . . . . . 842.32 nominal .................................. 804.222
Thermoplastic pipe. wall thickness and standard ductile iron. determination of . . . . . . . . . . . . . . . . 842.21 1
dimension ratio .................... .Table 842.32(c) Water piping ................................ 843.55
Thermosetting plastic design. limitations of . . . . . . . 842.33 Welders. qualifications for ........................ 823
Thermosetting plastic pipe. diameter Welding ....................................... 820
and wall thickness . . . . . . . . . . . . . . . . . ..Table 842.33(c) butt welds. preparation for .................... 822.1
Transmission facilities. abandoning of . . . . . . . . . . . . . 851.8 fillet welds. preparation for .................... 822.2
Transportation of line pipe ........................ 8 16 general information ............................ 821
inspection and tests
piping systems with stress less than 20% of yield
strength ................................ 826.1
U piping systems with stress 20% or more of yield
strength ................................ 826.2
Uprating ..................................... 845.6
on bottle type holders .................... . 8 4 4 .41(c)
preheating .................................... 824
preparation for ................................ 822
qualification of procedures and welders . . . . . . . . . . .823
V
piping systems with stress less than 20% of yield
Valves strength ................................ 823.1
cast iron ............................... .83 1.1 l(c) piping systems with 20% or more of yield
ductile iron ............................. .83 1 . 1 l(b) strength ................................ 823.2
in compressor stations . . . . . . . . . . . . .831.1 Ita), 843.51 1 records, qualification ......................... 823.4
in copper mains ........................... 842.6 12 requalification requirements for welders . . . . . . . . .823.3
in copper service lines . . . . . . . . . . . . . . . . . . . . . . 849.6 12 variables requiring separate qualification . . . . . . . 823.23
location of welders .................................... 823
distribution system ....................... 846.22 seal welds. preparation ....................... 822.3
service line .............................. 849.13 special components fabricated by. . . . . . . . . . . . . . 83 1.35
transmission . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 846.21 standards of acceptability ..................... 821.4
175
Y
Yield strength. specified minimum. for
steel and iron pipe ......................... APP. D
176
NOTE:
(1) USAS B31.2-1968 waswithdrawn as an American National Standard on February 18, 1988. ASME will
continue to make available USAS B31.2-1968 as a historical document for a period of time.