RnA Power Industrial Sdn Bhd

Daily Work Progress Report - Preshutdown Activity

Project No. : P-102 Date : 16 July 2017 Sunday


Project Title : 415 MCC UPGRADE PROJECT (ASU2 TA2017) Report No. : Day-1
Location : UK Client : Petronas Gas Berhad

No. of M.hrs M.hrs M.hrs


Manpower Weather
Man. Today Prev. Acc.
Project Manager 1 8 0 8
Project Engineer 1 8 0 8 12
11 1
Electrical Engineer 1 8 0 8
Project Controller 1 8 0 8 10 2
Site Engineer 1 8 0 8
Safety Executive 1 8 0 8 9 3 FINE
Safety Supervisor 1 8 0 8
Supervisor 1 8 0 8 4 RAIN
8
Work Leader 1 8 0 8
Technician 2 0 0 0 7 5 DRIZZLING
T&C Engineer (RA) 1 0 0 0 6
T&C Technician (RA) 1 0 0 0
VSR Comeca 2 0 0 0
Driver 1 0 0 0 Working Hours
0800 - 1700
Total 16 72 0 72

Wgth. Qty Qty Qty Qty %


Progress Status Equipment/Machinery Unit Qty
(%) Total Today Prev. Acc. complete
Site Activities Hand tools no 0
1. Mobilize & Preparation 0.40 1 Lot 20% 0% 20% 20% Inspection Tools no 0
2. Gemstart 5 New drawer delivery 0.20 27 nos. 0 0 0 0% Tritton no 1
3. Site verification ASU2 MCC data 0.10 36 nos. 0 0 0 0% Walkie-talkie no 0
4. Timer replacement 0.10 10 nos 0 0 0 0%
5. New drawer Calibration 0.20 27 nos. 0 0 0 0%

Total 1.0 Overall Progress 8%


Today Activities (Sunday 16/2017)
1. Manpower mobilize to site, safety induction conducted at MTC
2.Work pack preparation and approval
3. Preparation for permit to work

OVERAL ACTUAL PROGRESS: 8%


OVERAL PLANPROGRESS: 8%

Tomorrow Activities (Monday 17/7/2017)


1. Preparation work, tools and equipment inspection
2. Apply permit to work (vehicle entry, testing and calibration at sub 1, MCC site verification at sub3 )
3. Preparation for receiving of 27 nos. new drawer
4. remove exisitng timer at redundant MCC ASU1 at Sub3

Site Issue
1. Nil

Prepared by : MOHD AZRUL RAIS Checked/ Verified by : M SALIM M IBRAHIM