Progress Status Equipment/Machinery Unit Qty (%) Total Today Prev. Acc. complete Site Activities Hand tools no 0 1. Mobilize & Preparation 0.40 1 Lot 20% 0% 20% 20% Inspection Tools no 0 2. Gemstart 5 New drawer delivery 0.20 27 nos. 0 0 0 0% Tritton no 1 3. Site verification ASU2 MCC data 0.10 36 nos. 0 0 0 0% Walkie-talkie no 0 4. Timer replacement 0.10 10 nos 0 0 0 0% 5. New drawer Calibration 0.20 27 nos. 0 0 0 0%
Total 1.0 Overall Progress 8%
Today Activities (Sunday 16/2017) 1. Manpower mobilize to site, safety induction conducted at MTC 2.Work pack preparation and approval 3. Preparation for permit to work
OVERAL ACTUAL PROGRESS: 8%
OVERAL PLANPROGRESS: 8%
Tomorrow Activities (Monday 17/7/2017)
1. Preparation work, tools and equipment inspection 2. Apply permit to work (vehicle entry, testing and calibration at sub 1, MCC site verification at sub3 ) 3. Preparation for receiving of 27 nos. new drawer 4. remove exisitng timer at redundant MCC ASU1 at Sub3
Site Issue 1. Nil
Prepared by : MOHD AZRUL RAIS Checked/ Verified by : M SALIM M IBRAHIM