Sie sind auf Seite 1von 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/281280573

Composite steel-concrete cable-stayed bridges: Developments


and future trends

Conference Paper · September 2013

CITATION READS

1 1,864

2 authors:

José J. Oliveira Pedro António J. Reis


University of Lisbon GRID International Consulting Engineers
38 PUBLICATIONS   89 CITATIONS    34 PUBLICATIONS   114 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

GBT Numerical Model for bridge analysis View project

All content following this page was uploaded by José J. Oliveira Pedro on 27 August 2015.

The user has requested enhancement of the downloaded file.


Research and Applications in Structural Engineering, Mechanics and Computation – Zingoni (Ed.)
© 2013 Taylor & Francis Group, London, ISBN 978-1-138-00061-2

Composite steel-concrete cable-stayed bridges: Developments


and future trends

J.J. Oliveira Pedro


Technical University of Lisbon, Civil Engineer – GRID, Consulting Engineers, Portugal

A.J. Reis
Technical University of Lisbon, Technical Director – GRID, Consulting Engineers, Portugal

ABSTRACT: Composite cable-stayed bridges are elegant and efficient solutions. Today, they are the most
adopted solution for 400–600 m span range. Design developments of composite cable-stayed decks are resumed.
Particular reference is made to medium-span road and railroad composite decks and to truss decks. Slenderness
of the decks, material quantities of stays cables and decks are referred to. Future trends of composite cable-
stayed bridges are at last discussed. Particular reference is made to the prospective developments in the field of
structural materials, cables, and bridge concepts.

1 DESIGN DEVELOPMENTS floor-beams provided support for a slender and lighter


slab. Deck slenderness, defined as the length/depth
Cable-stayed structures are elegant and efficient solu- ratio of the main span, has been very much increased.
tions for bridges. In the last fifty years the range of Modern designs adopt thin and lighter decks, induc-
these bridges has been steadily increasing and today ing savings in the deck, cables, piers and foundations.
they are the mostly adopted solution for medium and Field bolted splices provided fast and simple con-
long-spans, reaching 1000–1200 m spans. nections between almost identical modules, ensuring
The increase on span required lighter and more maximum repetition of pre-fabricated deck compo-
resistant deck cross-sections. Steel decks adopting nents and construction procedures.3 These concepts
box-girder cross-sections made by orthotropic pan- have been applied to the majority of composite cable-
els are suitable for very long spans. For cable-stayed stayed bridges with main-spans exceeding 200 m, built
bridges with spans up to 600 m, and possibly to 700 m, over the last twenty years by the balanced cantilever
composite steel-concrete decks may be considered as construction method.
the most efficient and competitive solution, as con-
firmed by the variety of composite steel-concrete
decks built in the last years (Fig. 1).1,2,3,4

1.1 Design of long-span roadway bridges


Modern long-span composite decks adopted a simple
deck (Fig. 2). Reducing the space between stay-cables,
slender lateral main girders directly suspended by
closely spaced cables, were feasible. Closely spaced

Figure 2. Typical composite cable-stayed decks: a) steel


section detail and b) concrete slab executed with precast
Figure 1. Composite cable-stayed span length evolution.6 panels.5

729
Figure 3. Deck slenderness (main-span length/deck depth)
vs. main-span length, for composite cable-stayed bridges.6

Figure 5. Cables steel weight ratio per square meter of


the deck vs. a) main-span length; b) equivalent main-span
length.6

for steel, composite and concrete cable-stayed decks


Figure 4. a) Deck steel weight ratio and b) deck self-weight (Fig. 5a);
ratio, per square meter of the deck, vs. main-span length.6 • Plotting in the same graphic the steel weight of the
stays per deck square meter, for the composite cable-
The study of the main features of road and railway stayed bridges, results are quite dispersed;
composite cable-stayed bridges built all over the world • Railroad decks present always stay’s weight ratio
led to some significant conclusions.6 With respect to much higher than the values recorded for road decks,
the deck slenderness (Fig. 3): due to greater deck dead and live loads;
• For roadway girder decks, values grow up from 75 to • Assuming a equivalent main-span length for road
225 with the increasing on span length; slenderness bridges with an asymmetrical single tower equal
tends to be approximately constant for spans over to twice the real main-span length (Fig. 5b) stay’s
500 m long; steel weight ratios per deck square meter are much
• Out of this range, the four-girder deck of the Ting better fit;
Kau Bridge has a very high slenderness of 271. • A quadratic trend-line is almost over the average
• Slenderness of railway decks is much lower, with line proposed for composite decks with long spans
typical values below 50, due to deformability in the stay-cables catalogues7 (Fig 5b).
restrictions imposed by functional requirements.
1.2 Design of medium-span roadway bridges
With respect to the deck self-weight:
For spans up to 250 m, cable-stayed bridges compete
• The structural steel weight ratio per square meter of with box-girder bridges and arch bridges, and they
the deck is between 125 kg/m2 and 300 kg/m2 , with are rarely economical for these spans lengths. How-
an average value of 213 kg/m2 (Fig. 4a); ever, a cable-stayed bridge with slender deck may be
• The average deck self-weight ratio per square meter desirable in an urban environment for aesthetics or due
of the deck is 850 kg/m2 (considering the weight of to difficulties of positioning the deck supports. These
the structural steel and of the concrete slab), and typ- aspects may favour the cable-stayed solution, not only
ical values are between 700 kg/m2 and 1000 kg/m2 in the transposition of rivers and canals, but also on
(Fig. 4b). very wide road and railways. Other factors supporting
With respect to the stay-cables steel weight: a cable-stayed solution are: 1) aesthetic due to trans-
parency of the structure, resulting from the reduction
• steel weight ratio of the stays per square meter of the on the number of piers and increased slenderness of
deck increases with the main-span length, accord- the deck, and 2) reduction the traffic constraints during
ing with the boundaries of stay-cables catalogues7 the execution.

730
Figure 6. Seyssel Bridge, France.10 .
Figure 7. Arena Viaduct, Spain.11 .

For medium-spans the usual symmetric cable-


stayed layout with a three-span straight deck and two
towers, is not very often the best solution. Asymmet-
ric solutions with a single tower or with a curved
deck may be more appropriate to overcome local and
environment constraints.8
Design of medium-span composite cable-stayed
bridges has allowed simple deck solutions erected by
fast construction methods, like decks composed by two
plate girders lateral suspended. The concrete slab on
the top is still supported by closed spaced floor-beams,
like the Saint-Maurice Bridge (Switzerland, 1986) and
the Seyssel Bridge (France, 1987, Fig. 6). Built in the
end of the eighties, these two bridges have a struc-
tural asymmetric layout. The first bridge consisting of
two decks located at the exit of tunnels, with the tow-
ers built over the tunnels and suspending 99 m long
spans, with two planes of three stays, 24 m apart at the
deck level.9 The second bridge has a more classical Figure 8. Alzette River Bridge, Luxemburg.12 .
configuration, with a single tower suspending a 115 m
long main-span and three side spans of 35.2 m, with bridges incremental launching or erection by cranes
two plans of nine stays at each side.10 and temporary supports has been used, as in the
Decks with lateral suspension have nevertheless a Seyssel and Alzette River Bridges; the steel decks were
major drawback, due to the visual impact of two plans launched using temporary supports, and the slabs were
of stays. The axial suspension of the deck improves casted-in-place using mobile formworks supported on
aesthetics but requires a deck with higher torsional the steel structures.
rigidity, namely a box-girder cross-section. The Arena A special reference should also be made to sev-
Viaduct11 (Spain, 1993, Fig. 7), with five 105 m inner eral medium-span cable-stayed bridges built by the
spans, and the Alzette River Bridge12 (Luxembourg, incremental launching method in Finland, as the Täh-
1994, Fig. 8), with two side spans 130 m long, are tiniemi and Utsjoki Bridges, with main-spans of 165 m
good examples of medium-span cable-stayed bridges 155 m. The same method was used in the particular
in an in-plan curved road alignment, with an axial asymmetric Kemijoki Bridge (Fig. 9) with a compos-
suspension. ite box-girder deck with inclined struts supporting the
The Arena cable-stayed deck was built using an cantilevers, and a 126 m main-span suspended by two
unusual method. Each span was fully executed on the axial plans of stays.13
ground, including concreting the slab, and raised up
to a height of 30 m by lifting deck segments of around
1.3 Design of composite cable-stayed truss decks
2600 tons. Each span was then welded to the previous
one. Only after erecting all the deck, the steel masts The design of cable-stayed bridges with composite
were put in place and the six axial stays were installed truss decks allows superstructures to be lighter than
on each side of the masts.11 traditional prestressed concrete box-girders and less
Balanced cantilever construction method leads nor- deformable than steel or composite plate girder decks.
mally to longer construction time. For medium-span By anchoring the stays at the top slab level, the

731
Figure 9. Kemijoki Bridge, Finland.13 .

Figure 11. Øresund Bridge, Sweden/Denmark.15

recently in the Mercosur Bridge, over the Orinoco


River (Venezuela, 2011).
The 490 m span Øresund Bridge,15 adopted a deck
with two vertical steel trusses, with a concrete slab on
the top for the roadway. At the bottom level, a contin-
uous orthotropic steel deck supports two ballast boxes
for high-speed lines. The construction used deck steel
segments pre-fabricated in Spain and transported by
ship to Sweden, where the slab was pre-casted. Han-
dling operations of these elements, 120 m to 140 m
long, and weighting up to 6200 tons, were carried out
with a crane mounted on a barge. Deck segments
Figure 10. Karnali Bridge, Nepal.14 were placed on temporary supports and welded. Later,
the stays were installed and temporary supports were
removed to new positions.16
stays horizontal compression component is transmit- The 360 m long span Mercosur railroad Bridge17
ted directly to the slab, since the truss girders are adopted also a composite steel-concrete Warren truss
relatively flexible in the longitudinal direction com- girder deck, with 10 m between truss joints, and upper
pared to the axial rigidity of the slab. This feature of and lower cross-beams 3.33 m apart. However, unlike
the deck is actually important for a composite deck, the other examples, axial suspension was adopted, with
since it reduces the effects of shrinkage and creep two planes of stay-cables 0.80 m apart, and the deck
of the concrete slab, as in the longitudinal direction steel framing of the side spans were erected by incre-
each lattice girder acts as a “harmonium”, allowing mental launching. Afterwards, the concrete slab was
the deformations and reducing internal forces due to casted in place and stays were installed and tensioned.
time dependent effects. The 120 m steel central part of the main-span, weight-
Karnali Bridge 14 (Nepal, 1993, Fig. 10) was the ing 2400 tons, was then lifted from a barge by four
first cable-stayed road bridge with a composite truss strand jacks located on the existing cantilevers. The
deck. This outstanding structure has a 325 m lateral main-span slab was finally poured in several steps.17
span, suspended by a single tower (deck slenderness These two decks are relatively deep, with steel struc-
approximately 100). To reduce deck deformability two tures 10.2 m and 11.6 m height, which correspond to
lattices Warren girders 3 m deep were adopted.14 slenderness of only 48 and 28. Additionally, the self-
For rail and railroad bridges, a stiff deck is needed weight and structural steel of these decks are higher
to ensure train’s operation requirements. Truss girder than the values for double plate girder road composite
decks are widely adopted in suspension bridges and decks (Fig. 4a).
in some cable-stayed bridges. In particular, composite But, all these bridges adopted longitudinal trusses
steel-concrete truss decks combine high stiffness with with vertical diagonals. Three-dimensional tubular
relative low weight, using the concrete slabs to pro- diagonals can also be used, as it was first done in
vide the proper circulation platforms. Composite truss the Europa Bridge18 (Portugal, 2004, Fig. 12). This
decks were adopted in the Øresund Bridge (between highway deck, with a 186 m long main-span, is axially
Sweden and Denmark, 2000, Fig. 11), and more suspended by two plans of stays fixed to a single mast

732
The use of steel grades S420 and S460 has much
increased in recent years. New steels allow the design
of steel girders, floor-beams and stay anchors more
compact and with thinner plates. However, the use of
these steels has no significant advantage for fatigue
resistance. The recent introduction of even higher steel
grades in bridge construction, such as the S690 and
S700, may be explored in the future.20

2.2 In the field of cables


Cables made of CFRP have been proposed to reduce
weight and diameter, as they combine very high
resistance with a self-weight lower than steel. How-
ever, their time dependant behaviour is still not well
Figure 12. Europa Bridge, Portugal.18 . known, axial deformability is much higher, and CFRP
stay-cables are costly compared to steel stays.
Cable forces in service are usually limited to 45%
located on the left bank of the river. The mast inclined of its ultimate guaranteed resistant strength (FGUT).
8◦ towards the side spans is retained by two layers Few solid justifications have been given to continue
of backstays externally anchored to the transition pier using this limit, imposed to prevent the negative con-
blocks. The specificity of this composite deck truss, sequences of the fatigue stresses, and the local bending
with steel tube diagonals, comes not only from the steel stresses in the anchorage of the first large-diameter
elements joints to the concrete slabs, but also from stay-cables. For a characteristic combination of loads,
shear deformability and effects of local concentrated the Eurocode 3, part 1-11 allows cable forces up to 50%
bending moments introduced on the slab at the joints. of FGUT, if vibration damping devices are adopted
The deck is a 3D composite truss 4.2 m deep and 30 m at anchorages. In addition, during cables installation,
wide, made of high strength steel tubes with joints the first strands may have installed forces up to 60%
spaced at 3.75 m, and two concrete slabs prestressed FGUT, provided after stressing the remaining strands
in the transversal and longitudinal directions. of a cable work in the limit of 55% FGUT.
Steel plates enclosed by reinforced concrete were The assessment of stay-cable fatigue stresses needs
used at the upper truss nodes. These plates not only also to be carried out for the service conditions (con-
transfer the vertical forces from the slabs, but also sidering both the axial stresses and the bending stresses
balance the forces between the diagonal tubes that con- near the anchorages, due to angular deviations caused
verge on the node, and transmit the horizontal forces to by catenary effects, wind forces and erection imper-
the concrete slabs. On the lower node between 3.75 m fections). The French recommendations21 propose a
long segments, two “teeth” plates were used, perfectly simple method valid for road bridges, limiting the
matched to each other, to ensure the direct transmis- cables axial stress variation to 70 MPa for the passage
sion of vertical and horizontal internal forces. The of the fatigue vehicle LM3 of the Eurocode 1-Part 2.
bridge deck was designed to be executed with pre-
cast segments with the pre-casting yard located on the 2.3 In the field of design
left bank, and the precast segments (3.75 m length),
weighing up to 150 tons, transported in the river by In the field of design of composite steel-concrete
a barge, were lifted vertically to the deck. After deck cable-stayed bridges several new solutions have been
assembling and longitudinal prestressing applied, the recorded over the years, in some cases only with
overhangs of the deck slab were cast in-place and a architectural aspects, but in other cases technically
second phase of transversal pre-stressing was applied. innovative. Both types of developments are important,
since the public interest in cable-stayed bridges is, to
a large extent, also a result of its high aesthetics qual-
ity. The recent Boyne and Suir River Bridges (Ireland,
2 FUTURE TRENDS
2003 and 2009), Sirhowy River Bridge (Wales, 2005),
Berliner Bridge (Germany, 2005), Alcide de Gasperi
2.1 In the field of materials
Bridge (Italy, 2005) and Korabelny Bridge (Russia,
The use of precast slab panels with concrete strengths 2011), are good examples of medium-span compos-
up to 70 to 100 MPa is gradually increasing for very ite cable-stayed bridges, following these principles.
long-span composite cable-stayed bridges. To reduce New bridges of the same type, such as the Signature
weight ribbed slab sections between floor-beams have Bridge (India, 2014), are under construction or being
been recently adopted.1 Lightweight aggregate con- designed.
crete (LWAC) was also used in at least one composite In the field of rail and railroad decks, compos-
cable-stayed deck. The Grenland Bridge (Norway, ite solutions can also play an important role. In the
1996) adopted slabs of LWAC in the 305 m long future, this is certainly an area of composite cable-
main-span.19 stayed bridge developments, as shown by the recent

733
Present and Future. IABSE Conf. Proc, Malmö,
p. 352–361.
[3] Taylor, P. 1994. Composite cable-stayed bridges.
Intern. Conf. AIPC-FIP Proc. Vol.1. Deauville, p.185–
198.
[4] Pedro, J.J.O.; Reis, A.J. 2010. Nonlinear analysis of
composite steel-concrete cable-stayed bridges. Engi-
neering Structures 32 (2010), p.2702–2716.
[5] Hague,S.T. 2003. Steel/concrete composite design for
long span bridges. TRB 2003 annual meeting.
[6] Pedro,J.J.O. 2007. Structural analysis of composite
cable-stayed bridges. Ph. D Thesis. Technical Univer-
sity of Lisbon (in Portuguese), 426 p.
[7] Freyssinet, 1994-1999. Stay-cables Catalogue. Septem-
ber 1999 and May 1994.
[8] Reis, A. et al. 1999. Cable-Stayed Bridges for Urban
Spaces. Cable-Stayed Bridges: Past, Present and
Future. IABSE Conf. Proc., Malmö, p.106–115.
[9] SZS, 1987. Ponts sur le Rhône à Saint Maurice.
Construire en Acier, N˚10.
[10] Virlogeux,M. et al. 1985. Projet et Construction du
Pont de Seyssel. Bulletin de Ponts Métalliques, N˚ 12,
Figure 13. Preview of the Third Tagus River Crossing p.73–96.
Bridge, in Lisbon.22,23 . [11] Arenas, J.; Pantaleón, M. 1992. Puentes mixtos atiran-
tados. Puentes mixtos: Estado actual de su tecnología
y análisis - Comunicaciones y Mesas Redondas de las
Primeras Jornadas Intern. Barcelona.
[12] Biwer, R. et al. 1994. Cable-stayed bridge uponAlzette.
Intern. Conf. AIPC-FIP Proc.Vol.1. Deauville, p.413–
420.
[13] Vähäaho, J. et al. 1996. The Cable-stayed bridges in the
Finnish lake and river landscape. IABSE 15th Congress
Report. Copenhagen, p.171–177.
[14] Arzoumanidis, S.; Kunihiro, M. 1994. The Carnali
River Bridge. Intern. Conf. AIPC-FIP Proc. Vol.1.
Deauville, p.395–404.
[15] ASO Group, 1999. The Øresund Bridge. May 1999,
39p.
[16] Sörensen, L.T.; Thorsen, N.E. 1999. The Øresund
Bridge, Erection of the Cable-Stayed Span. Cable-
Stayed Bridges: Past, Present and Future. IABSE Conf.
Proc. p.465–475.
[17] Humpf,K.; Schiele, I. 2009. Puente Mercosur – Truss
Girder Bridge across the Orinoco. IABSE Conf. Proc.
Bangkok.
[18] Reis,A.; Pedro,J.J.O. 2004. The Europe Bridge in
Portugal: concept and structural design. ELSEVIER
Journal of Constructional Steel Research n◦ 60,
p.363–372.
[19] Fergestad, S.; Jordet, E. 2000. The economic potential
Figure 14. Preview of the Femern Belt Bridge, between of LWAC in 4 different major bridges. Proc.2nd Intern.
Germany and Denmark.24 . Symp. Structural Lightweight Aggregate Concrete.
Kristiansand, Norway, p. 355–364.
studies for the Third Tagus River Crossing Bridge in [20] IABSE, 2005. Use and Application if High-
Lisbon22,23 (Fig. 13), as well for the bridge connecting Performance Steels for Steel Structures. IABSE Struc-
the Fehmern Belt 24 between Germany and Denmark tural Engineering Documents, n◦ 8. 152p.
[21] SETRA, 2001. Haubans. Recommandations de la
(Fig. 14).
commission interministérielle de la précontrainte.
198p.
REFERENCES [22] GRID, SA, 2009. Third Tagus River Crossing: Main
Bridge – Base Case Design (in Portuguese).
[1] Taylor, P. 2001. What are the limiting criteria governing [23] Reis, A.J. 2008. Composite bridges: Options and
the maximum span of composite cable-stayed bridges? design issues. Proc. 7th Intern. Conf. Steel Bridges,
State of the Art in Technology and Analysis – Proc. p.I-3–I-28.
3rd Intern. Meeting on Composite Bridges, Madrid, [24] Femern Sund Baelt 2010. Fehmarnbelt Link – Techni-
p.43–54. cal Solution: Cable-Stayed Bridge. www.fehmarnlink.
[2] Svensson, H. 1999. The Development of Compos- com/uk, accessed in 15-11-2010.
ite Cable-Stayed Bridges. Cable-Stayed Bridges: Past,

734

View publication stats

Das könnte Ihnen auch gefallen