NSRP II Q~ ~ ~
Contractor Doc. No.
Complex Project Nghi Son Refinery and Petrochemical S-000-1679-0001V
Limited Liability Company Rev.A
Nghi Son, Vietnam
I Page 1 of 5
for
INSULATION WORK
Document Class: Z
N D
I 02-JANR- 2 0
A
15 dGCS
CONS ORTIUM
Employer Doc. No.
NSRP Complex Project Rev. A
CONTENTS
1. ITP
ITP No. 9000-101 Inspection and Test Plan for INSULATION WORK
Abbreviation:
H: Subcontractor is not allowed to proceed with the test/inspection unless a written release is issued
by the Employer and/or Contractor. Subcontractor shall submit inspection notification to
Contractor.
W: Subcontractor can proceed with the test/inspection when Employer and/or Contractor’s inspector
is not present at the notified time. Subcontractor shall submit inspection notification to
Contractor.
IW: Subcontractor is requested to notify Contractor of the initial inspection date/time. Subcontractor
can proceed with the test/inspection when Employer and/or Contractor’s inspector is not present
at the notified time. Subsequent test/inspection will not be witnessed unless any deficiencies are
found at the initial inspection.
S: Subcontractor is not requested to notify Contractor. Employer and/or Contractor’s inspector will
monitor manufacturing conditions, workmanship and test/inspection during his visit or periodical
inspection.
R: Subcontractor is not requested to notify Contractor. Subcontractor shall perform the required
test/inspection and provide relevant documents such as certificate, report and Quality Control
record. This documents shall be submitted to Contractor’s inspector for review.
I: Subcontractor shall be responsible for undertaking the inspection or test and generating the
appropriate report and record.
2. ATTACHMENT
2.1 Quality Control Report/Record
Form No. QCR-9000-101 INSPECTION REPORT FOR INSULATION WORK
D R A
N
I 02-JAN - 2 0 15
Employer Doc. No.
NSRP Complex Project Rev. A
Approved Drawing
and
1.1) Verify the Material / Size / S-000-1390-0001V
Quantity & Physical Properties 9000-101
Para 4.0.2 As per Drawing I W R
1.2) Check the Damage
S-000-1390-0002V
Para 4.1.2
3 INSULATION
3.1.) Pre-Insulation
Approved Drawing
a) Check the completion of
welding, Hydro test & Specification
D R A
N
I 02-JAN - 2 0 15
Employer Doc. No.
NSRP Complex Project Rev. A
D R A
N
I 02-JAN - 2 0 15
Doc.No. S-000-1679-0001V Rev.A
Type of Jacket :
st nd
Insulation thickness of each layer : 1 ( mm) / 2 ( mm) / Outer ( mm)
st
1.1 layer Anti-abrasive coating applied (only for Cellular Glass)
2. Securement as specified
COMMENT:
SIGNATURE
SUBCONTRACTOR CONTRACTOR EMPLOYER
D R A
N
I 02-JAN - 2 0 15