Beruflich Dokumente
Kultur Dokumente
Activity Immediate Predecessor/s Time (weeks) Step 1: Build the Network Diagram
A - 6 6
B - 8 A
C A,B 10
D C 5 10
E C 6 Start C
F D,E 14
G E 13 8
H F,G 7 B
Forward Pass
Se = maximum Fe of Predecessor/s or 0 if none
Fe = Se + t
A Se = 0 Fe =
B Se = 0 Fe =
C Se = 6&8 8 Fe =
D Se = 18 18 Fe =
E Se = 18 18 Fe =
F Se = 23 & 24 24 Fe =
G Se = 24 24 Fe =
H Se = 37 & 38 38 Fe =
Backward Pass
Late Finish FL = minimum SL of successir/s or maximum Fe if none
Late Start SL = FL - t
SLACK = LF - FE
A 8 6 2 Relax
B 8 8 0
C 18 18 0
D 24 23 1 Relax
E 24 24 0
F 38 38 0
G 38 37 1 Relax
H 45 45 0
5
D
14
F
6 7
E H
13
G
Early Finish, Fe
0+6 6
0+8 8
8 + 10 18
18 + 5 23
18 +6 24
24 + 14 38
24 + 13 37
38 + 7 45
LATE START, SL
45-7 38
38-13 25
38-14 24
24-6 18
24-5 19
18-10 8
8-8 0
8-6 2
EXAMPLE 2
Immediate Normal Crash
Activity Time (Days) Crash Cost
Predecessor/s Cost Duration
A - 5 100 4 200
B - 4 120 3 150
C A 12 400 8 1000
D B 8 300 6 700
E B 10 200 8 300
F C 7 400 5 900
G D, E, f 4 300 3 400
1820
A C F
Start
D G
A 1 100
G 1 100
C 1 150
25 days 2170
A-->c-->f-->g
A 0 5 C 5 17
5 0 5 12 5 17 F 17 24
0 0 0 0 7 17 24
=5 + 12+ 7+ 4 = 28 0 0
D 4 12
8 16 24
12 12
B 0 4 G 24 28
4 10 14 4 24 28
10 10 0 0
E 4 14
10 14 24
10 10
Most Pessimisti
Optimistic
Probable c
Immediate
Activity a m b t σ^2
Predecessor/s
A - 10 15 26 16 7.11 A 0 16
B - 8 10 18 11 2.78 16 0 16
C A,B 4 5 6 5 0.11 0
D - 10 12 14 12 0.44
E D 1 2 3 2 0.11
F D 1 3 11 4 2.78 B 0 11
G C, E 1 2 3 2 0.11 11 5 16
H F, G 1 2 3 2 0.11
I F 3 4 5 4 0.11
J H, I 1 2 3 2 0.11
D 0 12
Q1 Develop a project network and determine expected project completion 12 5 17
Q2 What is the probability that project completion time will meet
the 30-week deadline?
t = (a + 4m + b) / 6
σ^2 = ((b - a) / 6)^2
I 16 20
4 21 25