a).- Excavacion m3
Descripcion B H L f N PARCIAL TOTAL UND
Baden L= 8.00 m 14.40 m3
Excavacion para Estructura 4.50 1.000 8.00 0.40 14.40
m).- Junta
Descripcion B H L f N PARCIAL TOTAL UND
Baden L= 8.00 m 18.00 ml
Transversal 1.00 4.50 1.00 4.00 18.00
MAMPOSTERIA TIPO 02
DATOS: DESCRIPCION Und Nº L A H Cant ST TOTAL
1
L1= 0 60
0.60 1
H1= 08
0.85 Limpieza de Terreno 2
M2 2 0
2.70
L2= 0.60 H2= 0.3 Mamposteria 1 2.70 1.00 2.70
L3= 0.30 H3= 0.8 Trazo y Replanteo M2 2.70
L4= 1.20 H4= 0.3 Mamposteria 1 2.70 1.00 2.70
L5= 0.30 H5= 0.2 Excavacion M3 0.81
L6= 0.30 H6= 0.65 Mamposteria 1 Area= 2.70 0.20 0.54
L7= 1.10 H7= 0.20 Uña 1 0.60 0.45 1.00 0.27
L8= 1.00 H8= 0.6 Eliminacion M3 esponj 0.97
b= 1.00 Volumen Excavado 1 Vol= 0.81 1.20 0.97
L= 2.70 Solado M3 0.21
s= 0.10 Mamposteria 1 1.00 1.00 0.10 0.10
es= 0.15 1 1.10 1.00 0.10 0.11
Mamposteria con Concreto f'cM3 1.56
Mamposteria 1 1.20 1.00 0.20 0.24
1 0.65 1.00 0.20 0.13
1 1.70 2.70 0.20 0.92
Uña 1 0.60 0.45 1.00 0.27
Concreto f'c=210 Kg/cm2 M3 0.40
Sardinel sobre Mamp 2 1.20 0.30 0.15 0.11
2 1.15 0.30 0.15 0.10
2 0.30 1.20 0.15 0.11
2 0.85 0.30 0.15 0.08
Encofrado M2 5.28
Sardinel sobre Mamp 2 1.20 0.30 2 1.44
2 1.15 0.30 2 1.38
2 0.30 1.20 2 1.44
2 0.85 0.30 2 1.02
METRADO DE MAMPOSTERIA
MAMPOSTERIA TIPO 03
DATOS: DESCRIPCION Und Nº L A H Cant ST TOTAL
L1= 0.60 H1= 1.70 Limpieza de Terreno M2 4.05
L2= 0.90 H2= 0.3 Mamposteria 1 4.05 1.00 4.05
L3= 0.75 H3= 0.8 Trazo y Replanteo M2 4.05
L4= 0.30 H4= 0.3 Mamposteria 1 4.05 1.00 4.05
L5= 1.50 H5= 0.2 Excavacion M3 1.08
L6= 0.30 H6= 0.65 Mamposteria 1 Area= 4.05 0.20 0.81
L7= 0.30 H7= 0.60 Uña 1 0.60 0.45 1.00 0.27
L8= 1.10 Eliminacion M3 esponj 1.30
L9= 1.05 Volumen Excavado 1 Vol= 1.08 1.20 1.30
L10= 1.30 Solado M3 0.35
b= 1.00 Mamposteria 1 1.30 1.00 0.10 0.13
L= 4.05 1 1.05 1.00 0.10 0.11
s= 0.10 1 1.10 1.00 0.10 0.11
es= 0.15 Mamposteria con Concreto f'cM3 1.42
Mamposteria 1 1.50 1.00 0.20 0.30
1 0.85 1.00 0.20 0.17
1 1.05 1.00 0.20 0.21
1 0.85 1.00 0.20 0.17
1 1.50 1.00 0.20 0.30
Uña 1 0.60 0.45 1.00 0.27
Concreto f'c=210 Kg/cm2 M3 1.04
Sardinel sobre Mamp 2 Area= 3.45 0.15 1.04
Encofrado M2 13 80
13.80
Sardinel sobre Mamp 2 Area= 3.45 2 13.80
MAMPOSTERIA TIPO 04
DATOS: DESCRIPCION Und Nº L A H Cant ST TOTAL
L1= 0.50 H1= 3.40 Limpieza de Terreno M2 6.00
L2= 1.00 H2= 0.3 Mamposteria 1 6.00 1.00 6.00
L3= 0.70 H3= 0.8 Trazo y Replanteo M2 6.00
L4= 0.30 H4= 0.3 Mamposteria 1 6.00 1.00 6.00
L5= 1.50 H5= 0.2 Excavacion M3 1.44
L6= 0.30 H6= 0.65 Mamposteria 1 Area= 6.00 0.20 1.20
L7= 0.30 H7= 0.60 Uña 1 0.60 0.40 1.00 0.24
L8= 1.10 Eliminacion M3 esponj 1.73
L9= 1.00 Volumen Excavado 1 Vol= 1.44 1.20 1.73
L10= 1.30 Solado M3 0.54
b= 1.00 Mamposteria 1 1.30 1.00 0.10 0.13
L= 6.00 3 1.00 1.00 0.10 0.30
s= 0.10 1 1.10 1.00 0.10 0.11
es= 0.15 Mamposteria con Concreto f'cM3 2.12
Mamposteria 1 1.50 1.00 0.20 0.30
4 0.85 1.00 0.20 0.68
3 1.00 1.00 0.20 0.60
1 1.50 1.00 0.20 0.30
Uña 1 0.60 0.40 1.00 0.24
Concreto f'c=210 Kg/cm2 M3 1.62
Sardinel sobre Mamp 2 Area= 5.40 0.15 1.62
Encofrado M2 21.60
Sardinel sobre Mamp 2 Area= 5.40 2 21.60
METRADO DE MAMPOSTERIA
MAMPOSTERIA TIPO 05
DATOS: DESCRIPCION Und Nº L A H Cant ST TOTAL
L1= 0.50 H1= 4.25 Limpieza de Terreno M2 7.00
L2= 1.00 H2= 0.3 Mamposteria 1 7.00 1.00 7.00
L3= 0.70 H3= 0.8 Trazo y Replanteo M2 7.00
L4= 0.30 H4= 0.3 Mamposteria 1 7.00 1.00 7.00
L5= 1.50 H5= 0.2 Excavacion M3 1.64
L6= 0.30 H6= 0.65 Mamposteria 1 Area= 7.00 0.20 1.40
L7= 0.30 H7= 0.60 Uña 1 0.60 0.40 1.00 0.24
L8= 1.10 Eliminacion M3 esponj 1.97
L9= 1.00 Volumen Excavado 1 Vol= 1.64 1.20 1.97
L10= 1.30 Solado M3 0.64
b= 1.00 Mamposteria 1 1.30 1.00 0.10 0.13
L= 7.00 4 1.00 1.00 0.10 0.40
s= 0.10 1 1.10 1.00 0.10 0.11
es= 0.15 Mamposteria con Concreto f'cM3 2.49
Mamposteria 1 1.50 1.00 0.20 0.30
5 0.85 1.00 0.20 0.85
4 1.00 1.00 0.20 0.80
1 1.50 1.00 0.20 0.30
Uña 1 0.60 0.40 1.00 0.24
Concreto f'c=210 Kg/cm2 M3 1.95
Sardinel sobre Mamp 2 Area= 6.50 0.15 1.95
Encofrado M2 26.00
Sardinel sobre Mamp 2 Area=
Area 6 50
6.50 2 26 00
26.00
Estudio Definitivo del Proyecto : "CONSTRUCCIÓN Y MEJORAMIENTO DE LA CARRETERA PROGRESO SAN ANTONIO-ORTIZ ARRIETA-LONYA
GRANDE (KM 00+000 A KM 42+220)"
METRADO DE BADENES
Encauzamiento Excavacion Excavacion Concreto
Manposteria Manposteria Limpieza Trazo Relleno Eliminacion Encofrado Juntas Emboquillado
PROGRESIVA ESTRUCTURA Largo m2 C/ Equipo Manual f'c=210
Entrada Salida (2) (3) (6) (7) (9) (10) (11)
(1) (4) (5) (8)
N°
01 02+645.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
02 02+912.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.02 7.20 24.09 11.35 27.28 18.00 2.06
03 04+039.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.02 10.80 24.09 11.35 27.28 18.00 2.06
04 05+767.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.02 7.20 24.09 11.35 27.28 18.00 2.06
05 07+036.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.25 7.20 25.00 11.40 26.80 18.00 1.00
06 07+112.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
07 09+855.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
08 10+043.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
09 10+245 0
10+245.0 BADEN 8 00
8.00 1 1 42 60
42.60 42 60
42.60 42 60
42.60 14 58
14.58 6 249
6.249 7 20
7.20 25 00
25.00 11 40
11.40 26 80
26.80 18 00
18.00 1 00
1.00
10 12+869.0 BADEN 8.00 1 2 42.60 42.60 42.60 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
11 13+155.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
12 13+179.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
13 18+524.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
14 20+717.0 BADEN 8.00 1 2 43.35 43.35 43.35 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
15 23+120.0 BADEN 8.00 1 3 42.00 42.00 42.00 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
16 25+030.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
17 25+240.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
18 25+739.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
19 26+052.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
20 27+065.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
21 27+343.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
22 27+643.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
23 28+073.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
24 28+160.0 BADEN 8.00 1 3 43.35 43.35 43.35 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
25 28+680.0 BADEN 8.00 1 3 43.35 43.35 43.35 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
26 29+122.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
Estudio Definitivo del Proyecto : "CONSTRUCCIÓN Y MEJORAMIENTO DE LA CARRETERA PROGRESO SAN ANTONIO-ORTIZ ARRIETA-LONYA
GRANDE (KM 00+000 A KM 42+220)"
METRADO DE BADENES
Encauzamiento Excavacion Excavacion Concreto
Manposteria Manposteria Limpieza Trazo Relleno Eliminacion Encofrado Juntas Emboquillado
PROGRESIVA ESTRUCTURA Largo m2 C/ Equipo Manual f'c=210
Entrada Salida (2) (3) (6) (7) (9) (10) (11)
(1) (4) (5) (8)
N°
27 29+192.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
28 29+380.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
29 29+760.0 BADEN 8.00 1 3 42.00 42.00 42.00 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
30 30+651.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
31 31+280.0 BADEN 8.00 1 3 43.35 43.35 43.35 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
32 31+679.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
33 31+742.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
34 32+135.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
35 32+398 0
32+398.0 BADEN 12 00
12.00 1 2 60 00
60.00 60 00
60.00 60 00
60.00 14 05
14.05 6 0225
6.0225 10 80
10.80 24 09
24.09 11 35
11.35 27 28
27.28 18 00
18.00 2 06
2.06
36 32+454.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
37 32+649.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
38 33+009.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
39 33+538.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
40 34+519.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
41 34+691.0 BADEN 8.00 1 3 43.35 43.35 43.35 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
42 34+988.0 BADEN 8.00 1 1 42.60 42.60 42.60 14.58 6.249 7.20 25.00 11.40 26.80 18.00 1.00
43 35+503.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
44 35+705.0 BADEN 8.00 1 3 43.35 43.35 43.35 14.24 6.1035 7.20 24.41 11.99 35.80 18.00 1.92
45 36+928.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
46 37+379.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
47 38+043.0 BADEN 15.00 1 5 74.10 74.10 74.10 14.58 6.249 13.50 25.00 11.40 26.80 18.00 1.00
48 39+821.0 BADEN 8.00 1 2 42.00 42.00 42.00 14.05 6.0225 7.20 24.09 11.35 27.28 18.00 2.06
49 40+352.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
50 41+258.0 BADEN 12.00 1 2 60.00 60.00 60.00 14.05 6.0225 10.80 24.09 11.35 27.28 18.00 2.06
TOTAL 447.00 2,326.20 2,326.20 2,326.20 709.23 303.96 405.90 1,215.83 572.31 1,418.84 900.00 91.35