Sie sind auf Seite 1von 3

Why won’t the

concrete dry?
The benefits of well-cured concrete don’t apply to
floors that must reach a low moisture-vapor emission
rate before floor coverings are installed
BY BRUCE A. SUPRENANT AND WARD R. MALISCH

n September 1997, a general con- vapor at a rate of 51⁄2 to 6 pounds/1,000

I tractor placed a 5-inch-thick con-


crete floor directly on a vapor re-
tarder. The design water-cement
ratio was 0.54, and the contractor’s
crew added no water at the jobsite,
keeping the slump of the 3500-psi con-
crete at a nearly constant 4 inches to aid
square feet/24 hours. And the rate
hadn’t changed much in the past 2
months. Before the floor coating could
be applied, however, the emission rate
had to reach 3 lbs/1,000 sf/24 hrs.
We were stumped by the contractor’s
predicament. A reasonable water-ce-
in meeting flat- ment ratio, no wet granular layer be-
ness tolerances for neath the slab, excellent curing to bind
the steel-troweled capillary water in the hydrated cement
Relative moisture transport capacity surface. Because paste, and a long drying period should
35
the building have produced concrete that would
wasn’t enclosed quickly reach the desired moisture-
30 until December vapor emission rate. But it didn’t. Why?
and the fall
weather was par- How curing affects drying
25 ticularly rainy, the Because cement hydration immobi-
floor was continu- lizes some of the mixing water, well-
ously wet for cured concrete contains less free water
20
nearly 3 months. that must evaporate before floor cover-
After the building ings can be applied. But well-cured con-
15
was enclosed, it crete also has a disconnected void sys-
was heated from tem that slows the moisture-vapor
December emission rate. So drying well-cured con-
10 through March, crete requires removing a small amount
and air-condition- of water, but that water must exit the
ing units were concrete through a winding, constricted
5 turned on in June. path.
In September In poorly cured concrete, where the
1998, the contrac- duration of curing is short, the reverse is
1 3 57 26 days 3 12 months tor called us for true. Less cement hydrates, so there’s
Length of curing period advice: “Why more free water. But the void structure
won’t the concrete of this concrete is more likely to be in-
The rate at which concrete loses moisture depends on dry?” he asked. Al- terconnected, resulting in larger pores
how long the concrete cures. The longer the curing though placed a that allow a higher moisture-emission
duration, the slower the water loss. Based on this test year ago, with 9 rate.
data showing the rate at which concrete specimens lose months after Which curing condition is best if a
moisture, curing concrete for 3 to 7 days provides about building enclosure contractor needs to install moisture-sen-
the same rate of moisture loss, no curing about doubles in which to dry, sitive flooring as soon as possible? Re-
the rate, and curing for about 3 months decreases the the floor was still sults from several studies provide an an-
rate by about half.
emitting moisture swer to this question.
Table 1 Estimated drying time in days to reach 85% relative humidity weight-loss tests showing similar ef-
fects of moist-curing duration on
Water-cement ratio water loss (Ref. 4). The researchers
Duration of curing 0.50 0.60 0.70 placed mortar into metal pans to
produce 61⁄2 x12-inch specimens 2
1 day 66 112 184 inches thick. Some specimens were
4 weeks 92 157 258 left uncovered, and others were cov-
Note: Drying times are for 4-inch-thick concrete slabs drying from one side in a room at ered with wet burlap for 1, 2, or 3
50% RH and 70° F. The 85% RH is measured at a depth equal to 40% of the slab thick- days before being allowed to dry
ness. In the United States, moisture-vapor emission rates are measured instead of inter- from the top surface only in a room
nal RH. Research conducted in 1965 found that 4-inch-thick specimens cured for 7 days
and dried from one side at 73° F and 50% RH took 82, 117, and 130 days to reach 3 at 100° F and 32% RH. Table 2 shows
lbs/1,000 sf/24 hrs for water-cement ratios of 0.50, 0.60, and 0.70, respectively (Ref. 5). the percentage of original mixing
water remaining at ages up to 28
days. At 28 days, specimens that
More curing requires ing period, and as much as 15 times weren’t cured had lost 41% of the
longer drying as high as that for a 365-day curing initial mixing water while the speci-
Before moisture-sensitive floor period (Ref. 3). Hedenblad found a mens that received a 1- to 3-day
coverings can be installed, Swedish similar trend (see graph on page 29), burlap cure had lost only 19% or
specifications require the concrete’s showing that the ability of concrete less.
internal relative humidity (RH) to to lose moisture declines continu- Given the effect of prolonged cur-
reach 85% or 90%, depending on ously as the curing period lengthens. ing on drying time, what curing
the type of floor covering. Jackson and Kellerman conducted duration should specifiers require for
In one study, Hedenblad measured
the time required to reach specified
internal RH values at a depth equal Is no cure an option?
to 40% of the slab thickness (Ref. 1).
Based on that research, he developed Howard Kanare, principal inforce Kanare’s reservations about
a method for estimating drying time scientist and group manager for eliminating moist curing. Gonner-
using correction factors to account Construction Technology Labora- man found that air-cured concrete
for one- or two-sided drying and for tories, Skokie, Ill., tells of a con- specimens showed a nearly 50%
variations in slab thickness, curing struction project for which an un- increase in wear over similar speci-
conditions, and temperature and RH cured 4-inch-thick concrete slab mens moist cured for 2 days. To
during drying (Ref. 2). with a water-cement ratio of 0.50 assess surface strength, he placed
Table 1 shows calculated one- and a 4-inch slump achieved a a 1⁄2-inch-diameter steel ball on the
sided drying times for concretes with moisture-vapor emission rate of 4 surface of test specimens and
water-cement ratios of 0.50 to 0.70 lbs/1,000 sf/24 hrs in only 4 measured the force required to
and moist cured for either 1 day or 4 weeks. “The floor was built under produce a 1⁄4-inch-deep indenta-
weeks before drying began. Note a waterproof roof and was placed tion. The required forces were
that concrete with a water-cement directly on the vapor retarder,” 8,340 and 9,770 pounds for air-
ratio of 0.50 and cured for 1 day says Kanare, “so unreacted mix- dried and 2-day-moist-cured con-
would reach 85% RH in about 66 ing water was the only source of cretes, respectively. Concretes
days but would take about 92 days moisture-vapor emissions.” used in both tests were 3 months
to reach the same RH if it had been He believes the no-cure regi- old with 28-day compressive
moist cured for 4 weeks. For 0.70- men reduced the time needed to strengths ranging from 3500 to
water-cement-ratio concrete, the ex- achieve the desired moisture- 4500 psi.
tended curing increased the drying emission rate but worries that low For floors that will receive mois-
time more than 2 months. More strength at the concrete surface ture-sensitive floor coverings,
work by Hedenblad shows that could cause a flooring- Kanare recommends using plastic
when mature concrete is rewetted, it adhesive bond failure. “The sur- sheeting to cure the concrete for 3
takes even longer to dry (see “When face of such poorly cured con- days.
Year-Old Concrete Gets Wet”). crete, even when covered, also
These results aren’t surprising. In Reference
might deteriorate under wheel
a study of water-vapor conductivity H.F. Gonnerman, “Study of Methods
loads from heavily loaded gurneys of Curing Concrete,” Journal of the
through concrete and mortar, Wierig or carts,” says Kanare. American Concrete Institute, February
found that a 1-day wet curing period Results of laboratory studies re- 1930, p. 359.
resulted in vapor conductivity about
twice as high as that for a 3-day cur-
floors that will receive moisture-
sensitive coverings? When year-old concrete gets wet
Meeting schedules vs. If new concrete loses moisture water-cement ratio took 184 days
achieving quality more slowly the longer it cures, when cured for 1 day and 258
ACI 308-92, “Standard Practice for how long does it take mature con- days when cured for 4 weeks
Curing Concrete,” recommends a 7- crete to dry after it’s rewetted? To (Table 1).
day minimum curing period for find out, Hedenblad tested well- This confirms the experiences of
slabs on ground. Hedenblad’s data hydrated concrete specimens contractors who have had to re-
show that reducing the curing pe- more than a year old. After rewet- pair flooded basements. When a
riod from 7 days to 3 days doesn’t ting the mature concrete speci- basement floods, the mature con-
dramatically change the water-loss mens of different thicknesses and crete absorbs water and gives it up
rate, but reducing it to 1 day does. water-cement ratios were allowed at a much slower rate. Removal
Results from one project show that to dry at 50% relative humidity and replacement of a moisture-
no curing is another option for and 70° F. The internal RH was sensitive floor covering in a
speeding up drying (see “Is No Cure measured at a depth of 40% of flooded basement will probably
an Option?”). If the construction the thickness for one-sided drying require the use of a surface mois-
schedule requires floor-covering ap- and 20% of the thickness for two- ture barrier to limit the concrete’s
plication shortly after concrete sided drying. moisture-emission rate.
placement, reducing the curing pe- Rewetted mature concrete with
riod can help the contractor meet a water-cement ratio of 0.70 and Reference
that schedule. drying from one side took 515
Goran Hedenblad, “Drying Times for
However, most designers are reluc- days to reach 85% internal RH. To Concrete after Water Damage” (Eng-
tant to specify a 1-day cure or no reach the same RH level, newly lish Translation), The Swedish Council
cure because this would reduce sur- placed concretes with the same for Building Research, 1993.
face strength and abrasion resistance
and increase shrinkage cracking and
curling of the floor. Thus, the age- References September 1965, p. 482.
old tradeoffs between achieving 1. Goran Hedenblad, “Drying of Con- 4. F.H. Jackson and W.F. Kellerman,
quality and meeting construction struction Water in Concrete,” Swedish “Tests of Concrete Curing Materials,”
schedules must still be addressed. Council for Building Research, 1997, Journal of the American Concrete
We know one thing for sure. available from the Portland Cement As- Institute, June 1939, p. 481.
When floors will receive moisture- sociation, Skokie, Ill. 5. Bruce A. Suprenant, “Moisture
sensitive floor coverings, curing peri- 2. Goran Hedenblad, “Concrete Drying Movement Through Concrete Slabs,”
ods longer than 7 days are unlikely Time,” Concrete Technology Today, Concrete Construction, November
July 1998, Portland Cement Associa- 1997, pp. 879-885.
to produce quality benefits that will tion. Publication #C99G029
offset the adverse effects on the
3. Von H.-J. Wierig, “The Permeability Copyright© 1999, The Aberdeen Group
schedule. of Cement, Mortar and Concrete to a division of Hanley-Wood, Inc.
Water Vapor,” Zement Kalk Gips, All rights reserved

Table 2 Percent of water remaining in specimens

Duration of curing
Hrs Days
Type of curing 3 1 2 3 4 7 14 21 28
No curing 95 75 72 72 71 68 64 62 59
Burlap cure for 1 day 101 94 92 91 90 84 83 81
Burlap cure for 2 days 103 98 97 95 91 89 86
Burlap cure for 3 days 102 99 97 91 90 88

Note: Water remaining in specimens is shown as percent of original mixing water.


Specimens were 61⁄2 inches wide, 12 inches long, and 2 inches deep.

Das könnte Ihnen auch gefallen