Contract Manager
APPROVED 06.12.2018
Ivan Nikolić M.Sc.C.E
Content
No. Title Page
111 Subject and purpose 5
112 Project Targets 5
Cost 5
Contractual Dates 5
Quality 5
Work Safety 5
Environment 5
Client Relationship 5
121 Project Description 6
131 Scope of Works and Services 7
141 Contractual Dates 8
211 INTEGRAL INZENJERING Project organization 9
212 Project Organisation Chart 10
Structure of the Project Organisation 10
213 Job Descriptions 10
Contract Manager 10
Chief Engineer 11
Pavement and Material Engineer 12
Traffic Safety Engineer 12
Bridge Engineer 13
Surveying Engineer 13
Quality control Manager 14
214 Meeting Concept and Reporting Schedule 15
Objective 15
Concept 15
216 Project Principles 16
Health and Safety 16
Target 16
Principles 16
Addictive Drugs 16
Target 16
Principles 16
Employees 16
221 Document Management 17
Internal/ External correspondence 17
External correspondence 17
Incoming external correspondence: 17
Outgoing external correspondence 18
Internal correspondence 18
Data Security and Back-up 18
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
3
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Archiving 19
Hard format data archiving (paper format) 19
Soft format data archiving (electronic format) 19
231 Office Organisation / Mail / Telephone 20
Objective 20
General 20
Address List 20
Internal Telephone List 20
Telephone 20
Mail 20
Incoming: 20
Outgoing: 21
Fax 21
Incoming: 21
Outgoing: 21
E-mail 22
Incoming 22
Outgoing 22
Office Supplies 22
Office Inventory 22
241 Working Hours 22
Objective 22
Principles 22
Working Time Regulations 22
Business Hours 23
Public Holidays 23
251 Health and Safety Plan 23
252 Environmental protection Plan 23
253 Internal / External Audits 24
Purpose 24
Definitions 24
Responsibilities 24
Process 24
Audit Planning 24
Independence of Auditors 24
Qualification of Auditors 24
Performance of Audits 25
Audit Report 25
Follow-up Audits 25
Relevant Documents 26
Records 26
254 Control of Non-conformities 27
Purpose 27
Definitions 27
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
4
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Non-conformity 27
Classification of Non-conformities: 27
Responsibilities 27
Process 28
Evaluation of Non-conformities 28
Non-conformity Report 28
Marking of Non-conformities 28
Employer’s Concessional Acceptance 29
Relevant Documents 29
Records 29
255 Preventive and Corrective Action 30
Purpose 30
Definitions and responsibilities 30
Measures for Detection and Prevention of Non-conformities 30
Process 30
List of Non-conformities 30
Workgroup 31
Investigation of General Significance 31
Responsibility of the Quality Manager 31
Schedule of Activities 31
Relevant Documents 31
Records 31
256 Management Review 31
311 Choosing the Suppliers 33
312 Planning the Procurement 33
313 Procurement of Material and Equipment 34
314 Material and Equipment Approvals 34
315 Subcontractors Management 35
321 Workmanship and Delivery of required Programmes to the
Engineer 36
322 Observance of the Method Statement 37
323 Responsibility for Execution of the Works 38
331 Examination of Executed Works 39
332 Taking-over of Executed Works 40
333 Requesting for Taking over of the Works 41
334 Technical Inspection and Taking-over Certificate 42
4 FORMS AND TEMPLATES 43
5 Tabular overview TSQCP 46
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
5
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Cost
• Keeping to the budget.
Contractual Dates
• Completion and handing-over of the Project within the contractually agreed time frame.
• Following and respecting the Program of works
Quality
• Completion of the Project to the contractually agreed standard and with Serbian Laws
and standards.
Work Safety
• „Zero-Accident-Policy “
Environment
• Use of environmentally friendly materials, plant and equipment,
• Avoiding disturbances of residents.
• According to the EMP monitoring plans
Client Relationship
• Performance of the Project as reference project for future contracts and/or new
technologies,
• Strengthen the relationship with the „Employer ““
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
6
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
In the framework of the Road Rehabilitation and Safety Project (RRSP), a part of the state road
IA 3 in the length of L = 21.805 km is envisaged. The section intended for construction is the
section of the highway in the full profile from the border crossing with the Republic of Croatia
(Batrovci) (outside the border crossing point) to Kuzmin 1 (highway) (frame station km 22 +
218), where the design solution should not cover the zone of toll ramps Šid at km 7 + 085.
The complete section of the route is located in a plain region with a small number of cross-
sectional flows, which opened the possibility for the application of very comfortable elements of
the route, which is full in its length on the embankment. On the section there is a significant
watertight crossing, that is the bridge over the Bosut River, at km 5 + 660. The embankment of
the road, is mostly in very good condition. Its altitude varies along the route of about 2.0
meters, up to a height of up to 10.0 meters in the zone of naval ramps around the bridge over
the Bosut River and in the Adaševci area. On the route there is one end station for toll
collection, as well as one denivelated intersection - the Adaševci interchange
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
7
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Consequences / Liquidated
Date Description
Damages / Penalties
15.08.2018. Commencement Date
14.11.2019. Completion Date 0.10 % of the value / day to
maximum of 10% of the final
Contract Price
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
9
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
• Integral Inzenjering PLC from Laktasi, established back in 1989, is a leading company
within the Integral Grupa. Integral Inzenjering Company is a giant and leader on the
markets of Republic of Srpska, Bosnia and Herzegovina and Montenegro in Civil
Engineering and Water Engineering sectors, in which the company does its business
successfully for years; constructing remarkable structures and objects of general social
and economic interest. Behind us, there are kilometres and kilometres of roads and
highways, airport runaways, water supplying systems, railways, bridges, viaducts,
tunnels, and objects of special purpose and importance like; airports, helipads, Olympic
and recreational swimming pools, border crossings, hydro-power plants, water factories
and other hydro-technical facilities and sanitary landfills. Being very proud on our
results and satisfaction of our clients, partners and community as a whole, we present
our representative infrastructural projects and objects, and top-class human and
material-technical resources making it all possible.
• The core business of Integral Inzenjering assumes all sorts of works in construction
business (including building construction; in association with Integra Inzenjering ltd);
including preparation of project documentation and feasibility studies, design,
consulting, engineering, and the very construction of demanding and complex
structures.
• Led by the team of experienced engineers and equipped with the most up to date
equipment, following and implementing the latest achievement in science and
technology, Integral Inzenjering PLC is capable of successful completion of any given
project.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
10
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Contract Manager
Reports to: Engineer, Employer and Integral Inzenjering Top Management
Duties: ➢ Is in charge of managing all activities of the Contractor under the
contract and responsible for communication and correspondence with
the Engineer
➢ Is Contractor’s Representative for the purpose of the Contract,
➢ Liaison with the Engineer, attend manage meetings concern all
contract matters and obligations by the Contractor, contract
administration and quality assurance,
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
11
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Chief Engineer
Reports to: The Contract Manager
Duties: ➢ responsible for the organization, performance and control of the
Works on the Site
➢ perform works according to the Main Design on the basis of which
the construction approval was issued, and in accordance with
regulations, standards, technical norms and quality norms that are
applicable for the particular kind of works, installations and
equipment.
➢ organize the Site to enable access to the location, undisturbed
traffic, and protection of the environment during the whole period of
construction
➢ secure the safety of the structure, persons on the Site, and
surroundings (adjacent objects and traffic facilities)
➢ provide evidence on the quality of the performed works and built-in
materials, installations and equipment.
➢ keep a construction log book and inspection book
➢ provide measurements and surveying of movements of the soil and
objects on it during construction.
➢ secure the objects and the surroundings in case that the works are
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
12
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
interrupted.
➢ make sure that the Main Design and all the construction
documentation are available on the Site.
➢ be obliged for all other site activities specified by laws and the
Contract
Bridge Engineer
Reports to: The Contract Manager
Duties: ➢ responsible for the organization, performance and control of the
Bridges repair Works on the Site
➢ organize, supervise and coordinate the following activities:
➢ perform Bridge repair works according to the Final design on the
basis of which the construction approval was issued, and in
accordance with regulations, standards, technical norms and quality
norms that are applicable for the particular kind of works,
installations and equipment,
➢ provide evidence on the quality of the performed Bridge repair
works and built-in materials, installations and equipment,
➢ provide measurements and surveying of movements of the soil and
objects on it during construction.
Surveying Engineer
Reports to: Chief Engineer
Duties: ➢ Planning and conducting an engineering survey of the selected
roads building site structures and civil works including a
Topographic survey and recording all site-related details.
➢ providing guidance and direction to field crew(s) and surveying
technicians;
➢ Formulate a topographic survey of project sites using TOTAL
STATIONS Geodetic GPS Stations equipment and monitoring
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
14
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Objective
• Provision of adequate flow and state of information through co-ordinated regular
minuted meetings on all levels of the Project.
• Minimisation of effort to establish regular reports to the Project Partners by
implementing a co-ordinated Reporting Schedule.
Concept
Continuing minutes of meeting including responsibilities and deadlines for tasks are prepared
for each meeting listed in the Meeting Schedule. Open items from previous sessions are
carried on in the current minutes of meeting and the status of these open items is recorded.
Meetings are recorded by the chairman of the meeting.
The minuted results of the meetings are incorporated into the relevant higher- and lower-level
meetings.
A permanent co-ordinated agenda (see Reporting Schedule) ensures that the relevant results
from the Design-/ Construction meetings are reported to the higher Project levels. The agenda
will be sent out to the participants minimum two days in advance.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
16
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Target
• Zero Accidents.
Principles
• Each Project team member is aware of his responsibility for Health and Safety on the
Project and acts accordingly.
• Compulsory situational use of Personal Protective Equipment is enforced.
Addictive Drugs
Target
• Maintain and promote Project team members’ health.
Principles
• The project office is a smoke-free zone.
• Working under influence of alcohol or addictive drugs is strictly prohibited.
• Drinking alcohol and smoking is strictly prohibited in the Project official cars.
Employees
• We respect human rights and cultural differences.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
17
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
All the documents are registered, distributed and archived by the Secretary.
Only current revisions of the aforementioned documents are available electronically.
External correspondence
Original incoming external correspondence and copies of outgoing external correspondence
with original confirmation of receipt are registered with a consecutive internal reference
number.
Original external correspondence is filed in the Central Correspondence File after registration
with the internal reference number, distribution and scanning to the database.
The original documents are stored in thick ring binders in sequence of the increasing internal
reference number. In order to simplify searching each binder consists of 50 documents and the
reference numbers of the first and last included documents are marked on a label inserted in
the spine pocket of the binder.
Project team members have access to the documents at any time according to rights given.
Internal correspondence
Internal correspondence crucial for the project should be written down in form of Internal
Memorandum and registered.
Archiving
Objective
Communication optimisation via correct office organisation
General
Address List
The Project Central Address Database is updated by the responsible secretary on a regular
basis. It is available to all Project team members in the Project group database.
All Project team members inform the responsible secretary about new companies´ and
persons´ addresses to be added, as well as about all changes.
Telephone
During office hours the central telephone line is always attended.
External incoming phone calls should be answered with:
- the name of the Project Organisation
- the last name of the person who answers.
In absence phone calls will be forwarded to the secretary or to own mobile phone. Person
forwarding phone calls should give prior information. The secretary will take note of each
incoming call, indicating the caller (company, name), telephone number and date and time of
call, and will forward this information to the absent person as soon as possible.
All phone calls received during absence will be answered as soon as possible.
The telephone instruction manual is made available to the Project team members and is
located on the server in the Office Administration folder.
Incoming:
All incoming mail is received in the secretariat. The secretary opens all envelopes, except for
those marked “Private”, “Confidential”, or with the name written above the Project
Organisation’s name.
Private mail will be deposited on the recipient’s tray.
All registered mail cards will be confirmed by the secretary with the signature, date and the
Project Organisation stamp, copied and the original returned to the mailman.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
21
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
All external incoming correspondence with a request for confirmation will be legibly signed by
the secretary on a copy of the cover sheet, stamped with the date stamp and returned to the
sender.
The correspondence received after 17:00h or Fridays after 12:30h will be stamped with the
date of the following working day.
The original UNSTAMPED correspondence will be forwarded to the Document Controller for
further processing.
Outgoing:
All official outgoing correspondence will be prepared in accordance with the Document Control
Procedure and the Directive for Signing on the valid Project Organisation’s letter form and
registered with the reference number prior to sending.
All outgoing external correspondence should be deposited for sending in the secretariat before
17:00h or Fridays before 12:30h in sufficient copies for all recipients plus one full copy for the
Document Controller.
The sender is responsible for obtaining a confirmation of receipt with a legible signature and
date from each recipient (if by hand - on the enclosed copy of the cover sheet, if by mail – on
the registered mail card).
Confirmations are attached at the end of the full copy of the document and deposited at the
Document Controller for further processing.
Fax
Incoming:
All incoming faxes are received to a central fax machine at the Document Controller and
processed accordingly to the distribution procedure.
Faxes received after 17:00h or Fridays after 12:30h will be treated as received on the following
working day.
In case of an urgently awaited fax, the Document Controller shall be notified in order to deliver
the document for information to the recipient before processing or to process without delay for
action.
Private faxes, legibly marked as “PRIVATE” and bearing the name of the recipient, will not be
registered, but deposited on the recipient’s tray.
Outgoing:
Official outgoing faxes will be prepared in accordance with the Document Control Procedure
and the Directive for Signing on the valid Project Organisation telefax form and registered with
the reference number prior sending.
Faxes will be sent from the secretariat’s fax machine. The confirmation of transmittal will be
attached at the end of the original document, stapled and deposited at the Document Controller
for further processing.
The person sending the telefax is obliged to make sure that all pages of the fax were
transmitted correctly.
In case a fax cannot be transmitted, the secretary / person sending the fax will notify the
author.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
22
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Incoming
Official incoming e-mails will be forwarded for registration to the Document Controller.
When absent, the “Out of Office” function shall be activated, indicating the return date and the
replacing person to be contacted in urgent matters with telephone number and e-mail address.
The mailbox will be cleaned and archived on a regular basis.
Outgoing
All official outgoing e-mails will be prepared in accordance with the Document Control
Procedure and registered prior to sending.
As other types of correspondence, e-mails should have a meaningful subject.
Recipients for action should be addressed in the “To:” field, recipients for information in the
“CC:” field.
The Signature should include the full name, position, Project Organisation name and telephone
number if needed.
Office Supplies
Office supplies will be stored in a main storage room and distributed by the responsible
secretary. Each person taking supplies from the storage room will note the description and
quantity of taken goods in the office supplies book, together with his/her name.
The secretary will be informed if any specific office supplies should be ordered and will check
the stock on a weekly basis. Office supplies will be ordered after approving by the Commercial
Manager.
Each delivery of supplies will be checked and signed off by the secretary and the delivery note/
invoice will be deposited with the Commercial Manager.
Office Inventory
The Project Organisation provides all Project team members with the necessary work
infrastructure (i.e. office furniture, PC, etc.)
The office inventory will be used with care and maintained on a regular basis.
The Commercial Manager is responsible for acquisition of office inventory after having obtained
approval from the Contract Manager.
Objective
Clear regulation of working hours and vacations
Principles
• Within the scope of operational requirements and legal regulations Project Management
determines beginning and end of working hours and duration of lunch-break for all
Project team members.
• These Working Time Regulations are valid for all Project team members, including part-
time employees.
• If work load requires/ allows, the weekly working time may be increased/ decreased for
individual Project team members. The team member and his superior confer about
working time deviations and their settlement. The team member’s superior is
responsible for controlling these deviations and achieving a balanced working hour’s
account. The monthly payment of the team member’s salary is based on the 40-hour
week.
• Vacation, short breaks, bridging days, etc. shall be applied for from Project
Management by Leave Request. The Leave Request shall be submitted generally 10
working days in advance and shall indicate the requesting Project team member’s
substitute.
• „Out-of-office“(site visits, lunch, vacation, etc.) shall be reported to the reception. The
receptionist keeps a register showing “Who”, “Where”, “Since when”, “Until when”.
Business Hours
• “Business hours” primarily relates to the team which must be available for internal and
external clients during the defined times. Each Project team member is required to
ensure his own availability within the team accordingly.
• If the business hours do not fulfil the internal and/or external client’s requirements,
Project Management may determine specific business hours. Presence during these
specific business hours may be achieved through staggered working hours within the
team.
• Travel time during the short- and long weeks does not count as working time.
• A holder of a position and his substitute may not take short breaks at the same time, but
shall co-ordinate in order to take short breaks in alternation.
• Short breaks shall be planned in good time and shall be recorded in the calendar as
“Out-of-office”.
Public Holidays
• Applicable Public Holidays are those of the country of the Project.
Given separately.
Given separately.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
24
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Purpose
This Procedure describes the process of planning and execution of Internal and External Audits
including Follow-up Audits.
Definitions
For the purpose of this Procedure, the term “Internal Audit” shall mean all audits performed by
the Project organisation on the Project organisation and/or sub-contractors’ and suppliers’
organisations.
For the purpose of this Procedure, the term “External Audit” shall mean all audits performed by
third parties, including the certifying organisation and the Employer, on the Project organisation
and/or sub-contractors’ and suppliers’ organisations.
Responsibilities
See chapter “Process”
Process
Audit Planning
The Quality Manager establishes the Annual Audit Plan to assure that every process described
in the Project Management Plan is reviewed at least once a year. During execution of works,
the individual Sections are also subject to annual Internal Audits. After authorisation of the
Annual Audit Plan by the Management Representative, the Quality Manager distributes the
Annual Audit Plan for information to the Heads of Departments.
For each individual Internal Audit, the Quality Manager establishes an Audit Schedule in order
to assure that all relevant processes described in the Project Management Plan are reviewed.
At least three weeks before the planned Internal Audit, the Quality Manager sends out the
Audit Schedule to the audited function with a copy for information to the Management
Representative.
Independence of Auditors
The Management Representative assures that only adequately trained personnel perform
Internal Audits.
In order to assure objectivity of the Audits, Auditors only audit functions for which they bear no
organisational responsibility.
Qualification of Auditors
Internal Auditors
➢ Quality Manager
➢ Appointment by the Contract Manager.
➢ Other Internal Auditors – proof of engagement in the establishment and/or maintenance
of the Project Management Plan.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
25
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
External Auditors
➢ Certificate by an accredited certifying body
➢ Selection and employment by Management Representative
Performance of Audits
Internal Audits
During Internal Audits, the processes described in the Project Management Plan are reviewed
in order to verify the following main objectives:
➢ Evaluation of suitability, adequacy and effectiveness of the measures described in the
Project Management Plan.
➢ Assessment of adequate documentation of all activities.
➢ Detection of organisational and/or other deficiencies, establishment of possible
improvements.
➢ Control of application and effectiveness of agreed Corrective and Preventive Actions.
External Audits
The External Auditor assesses if our documented Project Management Plan is in accordance
with ISO 9001:2000, if it is workable and adequate. He verifies if the Project Management Plan
is effective throughout the company.
Audit Report
Internal Audit Report
The Internal Auditor documents the results of Internal Audits in Internal Audit Reports. Non-
conformities with the requirements of the Project Management Plan are recorded in the Internal
Audit Report. The Internal Auditor distributes unabridged copies of the Internal Audit Report to
the audited functions for action and to the Contract Manager, the Quality Manager and/or the
Health and Safety and Environmental Manager for information.
Follow-up Audits
The heads of the audited functions verify the recorded Non-conformities and, in co-operation
with the Quality Manager and/or the Health and Safety Manager and/or the Environmental
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
26
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Manager, determine and establish adequate measures for improvement in order to avoid re-
occurrence of Non-conformities. After an agreed reasonable period of application, the
effectiveness of the measures for improvement is verified and documented during a Follow-up
Audit.
Relevant Documents
Annual Audit Plan
Audit Schedule
Checklist for Audit Planning
Records
Annual Audit Plan
Audit Schedule
Audit Reports
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
27
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Purpose
This Procedure describes the process of and determines the responsibilities for controlling
materialised Non-conformities.
Definitions
Non-conformity
The term “Non-conformity” describes deviations from
➢ The contractual agreements,
➢ Quality requirements and/or tolerances of applicable standards,
➢ Relevant valid regulations and guidelines.
Classification of Non-conformities:
Critical Non-conformity
➢ All Non-conformities which, if not corrected, will afflict
o The safety of those engaged in the construction and/or
o The structural properties of constructions and/or
o The overall performance of the project.
Major Non-conformity
➢ All significant Non-conformities, whether correctable or not, which
o Do not fulfil the contractually agreed requirements,
o Incur additional cost for correction (additional personnel, utilisation of additional
plant and equipment, additional subcontractors, etc.), but do not afflict the
condition of the finished works,
Secondary Non-conformity
➢ All Non-conformities, which are usually corrected during the normal sequence of works
and/or Non-conformities which will have no or only insignificant influence on the
performance of the finished works.
Responsibilities
See section “Process”
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
28
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Process
Evaluation of Non-conformities
Secondary Non-conformities are reported as Non-conformity Observation by the Contract
Manager. A copy of the report is given to the Quality Manager who informs the Contract
Manager. After closing of Non-conformity, the original is kept with the Quality Manager.
On detection of Critical Non-conformities, the Chief Engineer is responsible for stopping the
works on the respective structure immediately, securing the afflicted area and informing the
Employer and the Contract Manager.
Non-conformity Report
Critical Non-conformities and Major Non-conformities are reported to the Quality Manager with
a copy to the Contract Manager. The Non-conformity Report includes a description of the
detected Non-conformity and proposed Corrective Action.
The Quality Manager analyses the Non-conformities in order to detect systematic Non-
conformities.
Alternatively, Non-conformities may be recorded in Minutes of Site Meetings, Management
Board Meetings, Defects Lists, etc. provided the necessary information as required in the Non-
conformity Report is given. Copies of the alternative record are submitted to the Construction
Manager and the Quality Manager. In order to facilitate follow-up, the Quality Manager issues
Non-conformity Reports based on the alternative records, where necessary.
Employer’s complaints during Warranty Period may be analysed as a further means to detect
systematic Non-conformities.
The Non-conformity Report may also be used during risk assessment to describe potential
Non-conformities and the proposed Preventive Actions.
Marking of Non-conformities
The Contract Manager in co-operation with the Chief Engineer determines appropriate means
of marking materialised Non-conformities in construction, such as:
Relevant Documents
255 Corrective and Preventive Action
Records
Non-conformity Report
Non-conformity Observation
Minutes of Site Meetings
Minutes of Management Board Meetings
Defects Lists
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
30
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Purpose
This Procedure describes the initiation, execution and review of corrective- and preventive
actions.
Root causes for Non-conformities are investigated, systematically collected and analysed in
order to avoid re-occurrence of systematic Non-conformities and to prevent potential Non-
conformities.
Subcontractor’s / Supplier’s
Chief Engineer X
Performance
Process
List of Non-conformities
The Quality Manager records all submitted Non-conformity reports, defects lists, defects
notifications, warranty claims, etc. in the List of Non-conformities and analyses the Non-
conformities at least quarterly in order to detect systematic (similar) Non-conformities.
The analysis is distributed to Project Management and shall comprise the following:
• Accumulation of Non-conformities in defined areas and processes.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
31
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Workgroup
Project Management may nominate members of staff who, together with the Quality Manager,
form a workgroup in order to determine preventive and corrective actions to be taken. Upon
authorisation of the preventive and corrective actions, Project Management determines how
and when the suitability of the a. m. measures is evaluated.
Schedule of Activities
Following the quarterly analysis of the List of Non-conformities, the Quality Manager
incorporates the analysis into the Schedule of Activities. At least annually, the Quality Manager
prepares the Schedule of Activities together with a report on the performed corrective and
preventive actions to be presented to and discussed by the Management Board (Management
Review).
Relevant Documents
See above table
Records
as per referred relevant documents
Before commencement of realization of the Project, the Head of Commercial Section shall give
proposal to the Contract Manager on the basis of their list of Suppliers. The Contract Manager
shall make the choice of prospective Suppliers and submit names of suggested suppliers to
approval of the Engineer together with:
- data showing the fact that suggested Supplier has required regular production
capacity and can satisfy the needs of construction Programme as well as that
their availability had been provided;
- data on tests and investigations (Certificates of Compliance)
After signing of the Contract and Work Commencement, Contractor shall plan materials
procurement on the basis of the Time Schedules. This Plan shall define necessary monthly
quantities of materials and stocks, if necessary, i.e. procurement plan of certain items.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
34
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
During execution of the Works, on the basis of monthly plans for procurement of materials,
Technical Department of the Project shall by requisition submit defined quantities and required
quality of material to the Head of Commercial Section in Serbia.
On the basis of requisitions, plans for procurement of materials and list of Suppliers approved
by the Resident Engineer, Head of Commercial Section in Serbia shall organize procurement
of required materials, products and/or equipment.
Reception quantity control of supplied material, products and/or equipment shall be performed
by Foremen. Laboratory Technicians (Contractor’s or from Highway Institute) on the Site shall
perform Quality Estimation and sampling. Samples shall be delivered to the Site or Central
laboratory for testing.
Foremen are responsible for reception, storing, taking care and distribution of supplied material
at the Site.
Employer’s personnel has the right to check, control, measure and test materials, manufacture
and check up production progress of equipment and materials.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
35
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
If, during Works Execution comes out, that technical conditions for Execution of Works are
significantly different comparing to supposed technical conditions, Contract Manager shall
propose variation of Method Statement to the Resident Engineer’s approval.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
38
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
MPR shell be delivered every month within 7 days after the last day of the period.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
40
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
The Resident Engineer with his verification in the Site diary confirms taking-over of the Works.
On the basis of As Built Drawings for the Measurement Book made by the Foremen and Chief
Engineer, Planning Engineer prepares calculations in the Measurement Book. On the basis of
calculations, the Resident Engineer verifies the Measurement book confirming executed
Quantities of the Works.
Once a month, on the basis of the Works taken-over by the Resident Engineer, Planning
Section carries out the measurement of the Works. The measurement mentioned above shall
be shown in Certificates of Payment, made by Commercial and Financial Section in the
manner described in Contract documentation and after verification by the Chief Resident and
Engineer it is to be submitted to the Financial Department in order to refund the Works.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
41
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
The Contract Manager shall, after completion of all the Contracted Works and registration in
the Site diary, submit to the Chief Resident Engineer request for Taking-Over of the Works.
The Chief Resident Engineer shall, within 28 days after receiving the Request for Taking-Over
of the Work, issue plan for works which, perhaps, should be carried out before final Inspection.
The Contract Manager shall through the Technical Manager and Chief Engineer organize
execution of any minor outstanding works and removal of defects properly.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
42
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
Technical Acceptance shall be carried out by the Committee nominated by the respective
Ministry in such a manner regulated by the Law on Planning and Construction (Official Gazette
of the Republic of Serbia No 47/03). During such Inspection, the Employer shall be given all the
documentation regulated by the Contract.
If the Committee approves Issuance of the Certificate of Completion to the Contractor, the
Engineer shall issue mentioned Certificate. If this procedure has been refused, the Contract
Manager shall, through the Technical Manager and Chief Engineer, organize the Works
required and described in Committee’s report for obtaining of the Certificate and shall repeat
the procedure.
The Engineer may, at the sole discretion of the Employer, issue a ToC for any part of the
Permanent Works.
Heavy Maintenance (Upgrading) of the State Road IA 3
Border CRO/SER (Batrovci) – Kuzmin 1 (highway), RRSP - IA3BK
from km 0+554.86 to km 22+196.11 (left carriageway),
43
_ QAMS-18R4
from km 0+564.64 to km 22+229.16 (right carriageway)
The following item of the Permanent works has been completed / is ready for inspection and in in accordance with the Contract
(следећи радови су завршени / спремни за контролу по уговорним условима)
Attachment (Прилог ):
Received by:
Преузео: Engineer's Assistant
r Approved
(Прихваћен )
Comment (Напомена ):
r Approved with comments
(Прихваћен са коментаром ) r Not Approved
(Није прихваћен )
Date (Датум )
Engineer's Assistant
Signed by:
Потписао: Project Assistant
Approved by:
Одобрио: Chief Resident Engineer
Date, Signature Adressee Date, Signature on behalf of Contractor Date Signature on behalf of Employer’s
Representative
4.2.4 Trial section (for determination of all details for Report for Trial Section must be prepared in
construction tehnology) form of written report for each type of saphalt
mixture. 1
Minimum tree asphalt mixture samples from
continuous production
4.2.5 Quality control during construction works on
asphalt plant and on site
Bitumen emulsion at each 50t of supplied emulsion 2
Testing of bitumen
Complete Bitumen BIT 50/70 testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Basic Bitumen BIT 50/70 testing at each 25t of supplied bitumen 18
Testing of filler
Complete filler testing at each 200t of supplied filler 3
Basic filler testing at each 25t of supplied filler 18
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 3
Basic sand testing once for every day of asphalt production 3
Crushed stone aggregate fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 9
Basic crushed stone aggregate fraction testing once for every day of asphalt production
3
4.2.6 Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
the paver on the constuction site) at the 21
beginning of works and at each 500t and/or
minimum one per day
4.2.7 In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
asphalt mix is taken) at the beginning of works 21
and at each 500t and/or minimum one per day
4.4. Bituminous base course BNS22sA (AC22 Base) with bitumen BIT 50/70
1.4.2.2 Asphalt concrete AC22sA 3 17573.68 Quality Material Testing for preliminary asphalt One per each type and at every 12 months
m
State road + Access junctions d=10cm 4.4.1 mix desing and on every change og any of basic 2
+ Resting area d=10cm materials
4.4.2 Preliminary testing of asphalt mixture 2
Job Mix Formular on asfalt plant (Working Job Mix Formular must be prepared in form of
mixture) written report for each type of saphalt mixture.
4.4.3 Minimum tree asphalt mixture samples from 2
continuous production
Trial section (for determination of all details for Report for Trial Section must be prepared in
construction tehnology) form of written report for each type of saphalt
4.4.4 mixture. 1
Minimum tree asphalt mixture samples from
continuous production
4.4.5 Quality control during construction works on
asphalt plant and on site
Bitumen emulsion at each 50t of supplied emulsion 1
Testing of bitumen
Complete Bitumen BIT 50/70 testing at the beginning of works and at each 500t of
4
supplied emulsion bitumen
Basic Bitumen BIT 50/70 testing at each 25t of supplied bitumen 66
Testing of filler
Complete filler testing at each 200t of supplied filler 5
Basic filler testing at each 25t of supplied filler 40
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 4
Basic sand testing once for every day of asphalt production 9
Crushed stone aggregate fraction testing
Basic crushed stone aggregate fraction testing once for every day of asphalt production
25
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.4.6 the paver on the constuction site) at the 81
beginning of works and at each 500t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.4.7 asphalt mix is taken) at the beginning of works 9
and at each 500t and/or minimum one per day
1.4.2.3 Asphalt concrete AC22sA with PmB - m3 35,441.56 Quality Material Testing for preliminary asphalt One per each type and at every 12 months
4.4.1
State road mix desing and on every change og any of basic 2
4.10.1
materials
4.4.2 Preliminary testing of asphalt mixture 2
Job Mix Formular on asfalt plant (Working Job Mix Formular must be prepared in form of
mixture) written report for each type of saphalt mixture.
4.4.3 Minimum tree asphalt mixture samples from 2
continuous production
Trial section (for determination of all details for Report for Trial Section must be prepared in
construction tehnology) form of written report for each type of saphalt
4.4.4 mixture. 1
Minimum tree asphalt mixture samples from
continuous production
4.4.5 Quality control during construction works on
4.10.5 asphalt plant and on site
Bitumen emulsion at each 50t of supplied emulsion 1
Testing of bitumen
Complete PmB testing at the beginning of works and at each 500t of
6
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 132
Testing of filler
Complete filler testing at each 200t of supplied filler 26
Basic filler testing at each 25t of supplied filler 205
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 18
Basic sand testing once for every day of asphalt production 18
Crushed stone aggregate fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 51
Basic crushed stone aggregate fraction testing once for every day of asphalt production
51
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.4.6 the paver on the constuction site) at the 163
beginning of works and at each 500t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.4.7 asphalt mix is taken) at the beginning of works 175
and at each 500t and/or minimum one per day
4.7. Wearing Course - Asphalt concrete АВ11s (AC11 Surf) with polimer modified bitumen PmB 45/80-65
1.4.2.5 Asphalt concrete AC11 PmB –wearing m2 4.7.1 Quality Material Testing for preliminary asphalt One per each type and at every 12 months
course mix desing and on every change og any of basic 2
materials
4.7.2 Preliminary testing of asphalt mixture
Resting area, Access junctions d=4cm 3,910.90 2
Resting area, Access junctions d=5cm 6,236.07 4.7.3 Job Mix Formular on asfalt plant (Working Job Mix Formular must be prepared in form of
mixture) written report for each type of saphalt mixture.
Minimum tree asphalt mixture samples from 2
continuous production
Resting area, Access junctions d=5cm 6,236.07 RRSPIA3BK - Section border CRO/SER (BATROVCI)-KUZMIN 1 - Tabular overview TS/QCP - Asphalt
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 2
Basic crushed stone aggregate fraction testing once for every day of asphalt production
2
4.7.6 Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
the paver on the constuction site) at the 4
beginning of works and at each 350t and/or
minimum one per day
4.7.7 In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
asphalt mix is taken) at the beginning of works 4
and at each 500t and/or minimum one per day
5.1.11.2 Procurement and construction of m2 3,144.50 4.7.5 Quality control during construction works on
levelling asphalt course АC11 PmB on asphalt plant and on site
the bridge (to the end of parapet walls) Bitumen emulsion at each 50t of supplied emulsion 1
in single 5 cm thick layer. Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 1
Testing of filler
Complete filler testing at each 200t of supplied filler 1
Basic filler testing at each 25t of supplied filler 3
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 1
Basic sand testing once for every day of asphalt production 1
Crushed stone aggregate fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 1
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.7.6 the paver on the constuction site) at the 2
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.7.7 asphalt mix is taken) at the beginning of works 2
and at each 500t and/or minimum one per day
5.3.11.2 Procurement and construction of m2 817.00 4.7.5 Quality control during construction works on
levelling asphalt course АC11 PmB on asphalt plant and on site
the bridge (to the end of parapet walls) Bitumen emulsion at each 50t of supplied emulsion 1
in single 5 cm thick layer. Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 1
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.7.6 the paver on the constuction site) at the 4
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.7.7 asphalt mix is taken) at the beginning of works 1
and at each 500t and/or minimum one per day
5.5.11.2 Procurement and construction of m2 263.00 4.7.5 Quality control during construction works on
levelling asphalt course АC11 PmB on asphalt plant and on site
the bridge (to the end of parapet walls) Bitumen emulsion at each 50t of supplied emulsion 1
in single 5 cm thick layer. Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 1
Testing of filler
Complete filler testing at each 200t of supplied filler 1
Basic filler testing at each 25t of supplied filler 3
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 1
Basic sand testing once for every day of asphalt production 1
Crushed stone aggregate fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 1
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.7.6 the paver on the constuction site) at the 1
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.7.7 asphalt mix is taken) at the beginning of works 1
and at each 500t and/or minimum one per day
5.6.11.2 Procurement and construction of m2 250.00 4.7.5 Quality control during construction works on
levelling asphalt course АC11 PmB on asphalt plant and on site
the bridge (to the end of parapet walls) Bitumen emulsion at each 50t of supplied emulsion 1
in single 5 cm thick layer. Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 1
Testing of filler
Complete filler testing at each 200t of supplied filler 1
Basic filler testing at each 25t of supplied filler 3
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 1
Basic sand testing once for every day of asphalt production 1
Crushed stone aggregate fraction testing
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.7.6 the paver on the constuction site) at the 1
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.7.7 asphalt mix is taken) at the beginning of works 1
and at each 500t and/or minimum one per day
4.12 Wearing Course - Stone Mastic Asphalt SMA11S2 with Polymer Modified Bitumen PmB 45/80-65
1.4.2.4 Split mastic asphalt SMA11s 2 457,278.02 4.12.1 Quality Material Testing for preliminary asphalt One per each type and at every 12 months
m
State road mix desing and on every change og any of basic 2
materials
4.12.2 Preliminary testing of asphalt mixture 2
4.12.3 Job Mix Formular on asfalt plant (Working Job Mix Formular must be prepared in form of
mixture) written report for each type of saphalt mixture.
Minimum tree asphalt mixture samples from 2
continuous production
4.12.4 Trial section (for determination of all details for Report for Trial Section must be prepared in
construction tehnology) form of written report for each type of saphalt
mixture. 1
Minimum tree asphalt mixture samples from
continuous production
4.12.5 Quality control during construction works on
asphalt plant and on site
Bitumen emulsion at each 50t of supplied emulsion 1
Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
5
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 108
Testing of filler
Complete filler testing at each 200t of supplied filler 26
Basic filler testing at each 25t of supplied filler 204
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 5
Basic sand testing once for every day of asphalt production 5
Crushed stone aggregate fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 30
Basic crushed stone aggregate fraction testing once for every day of asphalt production
30
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.12.6 the paver on the constuction site) at the 131
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.12.7 asphalt mix is taken) at the beginning of works 131
and at each 500t and/or minimum one per day
5.1.11.1 Procurement and construction of m2 3144,5 4.12.5 Quality control during construction works on
asphalt wearing course SMA 11S2 on asphalt plant and on site
the bridge (to the end of parapet walls) Bitumen emulsion at each 50t of supplied emulsion 1
in single 4 cm thick layer Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 1
Testing of filler
Complete filler testing at each 200t of supplied filler 1
Basic filler testing at each 25t of supplied filler 1
Crushed sand fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 1
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.12.6 the paver on the constuction site) at the 2
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.12.7 asphalt mix is taken) at the beginning of works 2
and at each 500t and/or minimum one per day
5.3.11.1 Procurement and construction of m2 817.00 4.12.5 Quality control during construction works on
asphalt wearing course SMA 11S2 on asphalt plant and on site
the bridge (to the end of parapet walls) Bitumen emulsion at each 50t of supplied emulsion 1
in single 4 cm thick layer Testing of bitumen
Complete Bitumen PmB testing at the beginning of works and at each 500t of
1
supplied emulsion bitumen
Basic Bitumen testing at each 25t of supplied bitumen 1
Testing of filler
Complete filler testing at each 200t of supplied filler 1
Basic filler testing at each 25t of supplied filler 1
Crushed sand fraction testing
Complete sand testing at each 2000 m³ of supplied sand 1
Basic sand testing once for every day of asphalt production 1
Crushed stone aggregate fraction testing
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
testing aggregate fraction for each fraction 1
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.12.6 the paver on the constuction site) at the 1
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.12.7 asphalt mix is taken) at the beginning of works 1
and at each 500t and/or minimum one per day
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
1
testing aggregate fraction for each fraction
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Complete crushed stone aggregate fraction at each 1000 m³ of supplied crushed stone
1
testing aggregate fraction for each fraction
Basic crushed stone aggregate fraction testing once for every day of asphalt production
1
Quality control of produced hot mix asphalt on (specimen of hot mix saphalt shall be taken
construction site from non compacted hot asphalt mix behind
4.12.6 the paver on the constuction site) at the 1
beginning of works and at each 350t and/or
minimum one per day
In-Situ testing for the control of quality of (cores shall be taken from a finished layer at
placed layer the same place where a specimen of hot
4.12.7 asphalt mix is taken) at the beginning of works 1
and at each 500t and/or minimum one per day
5.2.5.1 Набавка материјала, израда оплате и m3 60.58 8.2.1 Претходна испитивања компонената за
5.3.5.1 уградња бетона претходно срушених справљање бетона
5.4.5.1 делова коловозне АБ плоче. 8.2.2 Пројекат бетона / Претходна испитивања
Карактеристике бетона: бетона
C35/45 (МБ40); водонепропустљивост
8.2.2.1 Испитивање претходне бетонске мешавине Пре почетка производње и при свакој
5cm; отпорност на мраз М150; отпорност
промени компонентних материјала током 1
на мраз и со: 25 циклуса,степен
производње
оштећења 0 - без љуштења.
8.2.2.2 Дозажа - потврда претходне бетонске
мешавине на фабрици бетона На почетку производње бетона 1
8. CONCRETE
8.2 Concrete Category В.II
5.1.5.1 Procurement of material, production of 3 345.81 8.2.1 Preliminary Testing og Components of
m
5.2.5.2 formwork and concreting pedestrian Concrete
5.3.5.2 paths and edge beams on the section 8.2.2 Concrete design / Preliminary Testing og
5.5.5.2 of superstructure as well as on a part Components Mixtures
5.6.5.1 of wing walls. 8.2.2.1 Preliminary Testing og Components Mixtures Before starting of the production, and for any
5.6.5.2 Concrete properties for pedestrian (Preliminarnary concrete mixture design) change of component material during the 1
paths and edge beams: production
C35/45 (МB40); water-tightness 5 cm; 8.2.2.2 Job Mix Formula (JMF) on Concrete plant for On start of concrete production
frost resistance М-150; frost and salt the needs of verification of Preliminary Testing 1
resistance: 25 cycles, damage degree og Components Mixtures
0 – no scaling. 8.2.3 Concrete Production Quality Control
8.2.3.1 Production Capability Testing of Concrete Basic testing at start, a report is vaild until a
1
plant major overhaul/repair of concrete plant
8.2.3.2 Regular Control of Components of Concrete
on Place of Production - Concrete plant
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making Every day
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done when it is
concrete, temperature ) concreted
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
For Determination of the depth of penetration 3 specimens from the same sample of the
of water under pressure fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 1000m³ for each type of
concrete
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
2000m³ for each type of concrete
5.2.5.1 Procurement of material, production of m3 60.58 8.2.1 Preliminary Testing og Components of
5.3.5.1 formwork and concreting earlier Concrete
5.4.5.1 demolished parts of RC deck 8.2.2 Concrete design / Preliminary Testing og
Concrete properties: Components Mixtures
C35/45 (МB40); water-tightness 5 cm; 8.2.2.1 Preliminary Testing og Components Mixtures Before starting of the production, and for any
frost resistance М-150; frost and salt (Preliminarnary concrete mixture design) change of component material during the 1
resistance: 25 cycles, damage degree production
0 – no scaling. 8.2.2.2 Job Mix Formula (JMF) on Concrete plant for On start of concrete production
The item of works includes also the needs of verification of Preliminary Testing 1
placing of styrodur on connection of og Components Mixtures
edge and sleeper beams. 8.2.3 Concrete Production Quality Control
8.2.3.1 Production Capability Testing of Concrete Basic testing at start, a report is vaild until a
1
plant major overhaul/repair of concrete plant
8.2.3.2 Regular Control of Components of Concrete
on Place of Production - Concrete plant
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making Every day
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done when it is
concrete, temperature ) concreted
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 5000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
5000m³ for each type of concrete
8.2.4. Concrete Quality Control on Site of placement
(Sampling of fresh concrete, Slamp test, Air
contentof fresh concrete, temperature )
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Every day
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making
when it is
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done
concreted
concrete, temperature )
Making and Curing of Test Speciment for
Strength Test and Special Properties of
Hardened Concrete on Place of Production
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
For Determination of the depth of penetration 3 specimens from the same sample of the
of water under pressure fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2500m³ for each type of
concrete
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 5000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
5000m³ for each type of concrete
8.2.4. Concrete Quality Control on Site of placement
(Sampling of fresh concrete, Slamp test, Air
contentof fresh concrete, temperature )
8.2.3.2 RRSPIA3BK - Section border CRO/SER (BATROVCI)-KUZMIN 1 - Tabular overview TS/QCP - Concrete
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Every day
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making
when it is
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done
concreted
concrete, temperature )
Making and Curing of Test Speciment for
Strength Test and Special Properties of
Hardened Concrete on Place of Production
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
For Determination of the depth of penetration 3 specimens from the same sample of the
of water under pressure fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2500m³ for each type of
concrete
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 5000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
5000m³ for each type of concrete
8.2.4. Concrete Quality Control on Site of placement
(Sampling of fresh concrete, Slamp test, Air
contentof fresh concrete, temperature )
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making Every day
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done when it is
concrete, temperature ) concreted
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
2000m³ for each type of concrete
5.5.5.3 Procurement of material, production of m3 128.73 8.2.1 Preliminary Testing og Components of
formwork and concreting new Concrete
approach slabs behind the abutments. 8.2.2 Concrete design / Preliminary Testing og
Concrete properties for new approach Components Mixtures
slab: 8.2.2.1 Preliminary Testing og Components Mixtures Before starting of the production, and for any
C25/30 (МБ30); water-tightness 5 cm; (Preliminarnary concrete mixture design) change of component material during the 1
frost resistance М-100; frost and salt production
resistance: 25 cycles, damage degree 8.2.2.2 Job Mix Formula (JMF) on Concrete plant for On start of concrete production
1 – poor scaling. the needs of verification of Preliminary Testing 1
og Components Mixtures
8.2.3 Concrete Production Quality Control
8.2.3.1 Production Capability Testing of Concrete Basic testing at start, a report is vaild until a
1
plant major overhaul/repair of concrete plant
8.2.3.2 Regular Control of Components of Concrete
on Place of Production - Concrete plant
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Every day
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making
when it is
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done
concreted
concrete, temperature )
Making and Curing of Test Speciment for
Strength Test and Special Properties of
Hardened Concrete on Place of Production
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
For Determination of the depth of penetration 3 specimens from the same sample of the
of water under pressure fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2500m³ for each type of
concrete
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 5000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
5000m³ for each type of concrete
8.2.4. Concrete Quality Control on Site of placement
(Sampling of fresh concrete, Slamp test, Air
contentof fresh concrete, temperature )
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
For Determination of the depth of penetration 3 specimens from the same sample of the
of water under pressure fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 1000m³ for each type of
concrete
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
2000m³ for each type of concrete
5.5.5.4 Procurement of material, production of m3 9.02 8.2.1 Preliminary Testing og Components of
5.5.5.6 formwork and concreting central Concrete
reservation on the section of 8.2.2 Concrete design / Preliminary Testing og
superstructure as well as on part of Components Mixtures
pier parapet walls.Concrete properties 8.2.2.1 Preliminary Testing og Components Mixtures Before starting of the production, and for any
for central reservation:C35/45 (МB40); (Preliminarnary concrete mixture design) change of component material during the 1
water-tightness 5 cm; frost resistance production
М-150; frost and salt resistance: 25 8.2.2.2 Job Mix Formula (JMF) on Concrete plant for On start of concrete production
cycles, damage degree 0 – no scaling. the needs of verification of Preliminary Testing 1
The item of works includes also og Components Mixtures
placing of styrodur on connection of 8.2.3 Concrete Production Quality Control
edge and sleeper beams. 8.2.3.1 Production Capability Testing of Concrete Basic testing at start, a report is vaild until a
1
plant major overhaul/repair of concrete plant
8.2.3.2 Regular Control of Components of Concrete
on Place of Production - Concrete plant
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Every day
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making
when it is
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done
concreted
concrete, temperature )
Making and Curing of Test Speciment for
Strength Test and Special Properties of
Hardened Concrete on Place of Production
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
For Determination of the depth of penetration 3 specimens from the same sample of the
of water under pressure fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 2500m³ for each type of
concrete
For Testing of concrete surface for resistence 3 specimens from the same sample of the
to frost and salt fresh concrete in the same time with making
of specimens for strength test. 1
1test at every 5000m³ for each type of
concrete
For Testing of concrete resistence to frost
15 specimens from the same sample of the
fresh concrete in the same time with making
1
of specimens for strength test. 1test at every
5000m³ for each type of concrete
8.2.4. Concrete Quality Control on Site of placement
(Sampling of fresh concrete, Slamp test, Air
contentof fresh concrete, temperature )
Concrete admixtures
every receved batch - delivery /every change
1
of cement / if storing longer than 6 months
8.2.3.3 Regular Control of Concrete on Place of For each type of concrete every day at the
Every day
Production - Concrete plant (Sampling of fresh beginning of the woring day, and when making
when it is
concrete, Slamp test, Air contentof fresh of specimens for strength tests shall be done
concreted
concrete, temperature )
Making and Curing of Test Speciment for
Strength Test and Special Properties of
Hardened Concrete on Place of Production
For Determination of compressive strength of 3 specimens (at 28 days age) for every day of
test specimens production for every concrete type on every
50m³ produced concrete Regular
qualiti control of achieved concrete strength Every day
grade - monthly report for each type of when it is
concrete. concreted
Proofing of achieved concrete strenght grade -
1 report every 3 months for each tupe of
concrete
8.2.4. Concrete Quality Control on Site of placement
(Sampling of fresh concrete, Slamp test, Air
contentof fresh concrete, temperature )
5.4.10.2 Премазивање бетонских површина у Комплетно испитивање у складу са на основу произвођачког сертификата о
5.5.10.2 додиру са земљом врућим битуменом - декларацијом производа усаглашености, за сваку врсту један
5.6.10.2 бетона парапета крајњег стуба С4 као и m2 184.00 сертификат 1
бетона крилних зидова, све до коте
ископа.
5.1.12.8 Израда заштитног полиуретанског Комплетно испитивање у складу са на основу произвођачког сертификата о
5.2.12.8 хидроизолационог абразивног премаза декларацијом производа усаглашености, за сваку врсту један
5.3.12.8 горње површине бетона пешачких стаза. 2 сертификат
m 1,255.52 1
5.4.12.8 Боју заштитног премаза одредити у
5.5.12.07. договору са Надзорним органом.
5.6.12.8.
ГРАНИТНИ ИВИЧЊАЦИ
Претходна испитивања гранитних ивичњака
5.1.12.4 Набавка, транспорт и уградња резаних Комплетно испитивање у складу са на основу произвођачког сертификата о
5.2.12.4 гранитних ивичњака 13/20cm. Ивичњаци декларацијом производа усаглашености, за сваку врсту један
5.3.12.4 се уграђују на распонском делу моста сертификат
5.4.12.4 између парапетних зидова. Позиција
5.5.12.4 радова обухвата израду подливке за
5.6.12.4 денивелацију испод ивичњака као и m' 1,024.60 1
заптивање спојница - фуга између
ивичњака, на споју ивичњака и пешачке
стазе и на споју асфалта и ивичњака
("DENSO" трака).
ЗАШТИТНА ОГРАДА
Претходна испитивања заштитне ограде
Заштитна ограда Комплетно испитивање у складу са на основу произвођачког сертификата о
декларацијом производа усаглашености, за сваку врсту један
сертификат
1
ЛЕЖИШТА
Претходна испитивања лежишта
Лежишта Комплетно испитивање у складу са на основу произвођачког сертификата о
декларацијом производа усаглашености, за сваку врсту један
сертификат
1
АНКЕРИ
Претходна испитивања анкера
Анкери Комплетно испитивање у складу са на основу произвођачког сертификата о
декларацијом производа усаглашености, за сваку врсту један
сертификат
1
ДИЛАТАЦИОНЕ СПОЈНИЦЕ
Претходна испитивања дилатационих спојница
Дилатационе спојнице Комплетно испитивање у складу са на основу произвођачког сертификата о
декларацијом производа усаглашености, за сваку врсту један
сертификат
1
САОБРАЋАЈНА СИГНАЛИЗАЦИЈА
Претходна испитивања саобраћајне сигнализације
Саобраћајна сигнализација Комплетно испитивање у складу са на основу произвођачког сертификата о
декларацијом производа усаглашености, за сваку врсту један
сертификат
1
СМЕРОКАЗИ
Претходна испитивања смероказа
Смерокази Комплетно испитивање у складу са на основу произвођачког сертификата о
декларацијом производа усаглашености, за сваку врсту један
сертификат
1
БЕТОН
Претходна испитивања бетона
Бетон Комплетно испитивање у складу са на основу произвођачког сертификата о Бетонска база
декларацијом производа усаглашености, за сваку врсту један
сертификат Дозаже
Цемент
Адитиви
5.7.3.4 Grid reinforcement Q503 Complete testingaccording to Product Quality shall be proven based on Producer
kg 749,08 specification certificate, for each type one Certificate 1
5.4.10.2 Coating concrete surfaces in contact Complete testingaccording to Product Quality shall be proven based on Producer
5.5.10.2 with soil with hot bitumen - concrete of specification certificate, for each type one Certificate
5.6.10.2 parapet of the abutment S4 as well as m2 184.00 1
concrete of wing walls, up to
excavation level.
5.1.12.8 Construction of protective Complete testingaccording to Product Quality shall be proven based on Producer
5.2.12.8 polyurethane waterproofing abrasive specification certificate, for each type one Certificate
5.3.12.8 coat of the top concrete surface on
5.4.12.8 pedestrian paths. Colour of the m2 1,255.52 1
5.5.12.07. protective coat shall be agreed with
5.6.12.8. the Supervisor.
GRAVITY EXPLORERS
Preliminary testing of gravity explorers
5.1.12.4 Procurement, transport and Complete testingaccording to Product Quality shall be proven based on Producer
5.2.12.4 installation of cut granite curbs 13/20 specification certificate, for each type one Certificate
5.3.12.4 cm. Curbs are installed on the
5.4.12.4 superstructure between parapet walls.
5.5.12.4 The item of works includes
5.6.12.4 construction of grout pad for m' 1,024.60 1
delevelling below the curbs as well as
sealing joints between curbs, on
connection of curbs and pedestrian
path and on connection of asphalt and
curbs ("DENSO" tape).
PROTECTIVE FENCE
Preliminary testing of protective fence
Protective fence Complete testingaccording to Product Quality shall be proven based on Producer
specification certificate, for each type one Certificate
1
BEARINGS
Preliminary testing of bearings
Bearings Complete testingaccording to Product Quality shall be proven based on Producer
specification certificate, for each type one Certificate
1
ANCHORS
Preliminary testing of anchors
Anchors Complete testingaccording to Product Quality shall be proven based on Producer
specification certificate, for each type one Certificate
1
EXPANSION JOINTS
Preliminary testing of expansion joints
Expansion joints Complete testingaccording to Product Quality shall be proven based on Producer
specification certificate, for each type one Certificate
1
TRAFFIC SIGNALIZATION
Preliminary testing of traffic signalization
Traffic signalization Complete testingaccording to Product Quality shall be proven based on Producer
specification certificate, for each type one Certificate
1
DELINEATORS
Preliminary testing of delineators
Delineators Complete testingaccording to Product Quality shall be proven based on Producer
specification certificate, for each type one Certificate
1
CONCRETE
Preliminary testing of concrete
Concrete Complete testingaccording to Product Quality shall be proven based on Producer Concrete base
specification certificate, for each type one Certificate
Dosage
Cement
Adittives