Employer

Consultants

Contractor

Document Category:
Method Statement
Contract No.: RA-240
Project Title:
Construction, Completion and maintenance of Roads and Interchanges of the existing part of
the 7th Ring Road
Doc. No.
Procedure Title:

‫ ﺳﯾد‬a7
Demolition of Existing Bridge
ROAD#40
S RA240-MS1-BRG-MS-020

Revision No.: Rev. 0

‫ﻣﻊ‬
lm
E3
‫دﯾ‬
‫ﺎب‬

REVISION HISTORY

CONTRACTOR-SHC
Date Revision History ENGINEER Status of
Rev. No. Prepared by Approved by Approval
First Submission following
0 10/05/2018 Elsayed Diab award of Contract

1
CONTENTS

1.0 Purpose

2.0 Scope

3.0 Definitions

4.0
‫ ﺳﯾد‬a7
S
References

5.0 ‫ﻣﻊ‬ Equipment and Tools


lm

6.0 Safety
E3

7.0 Prior Activities


‫دﯾ‬

8.0 Procedures
‫ﺎب‬

9.0 Responsibilities

2
1.0 Purpose

1.1 To ensure that the Demolition of Existing Bridges activities are executed safely and
in accordance with the contract requirements and that all quality assurance/ control
activities are conducted in a systematic manner, works are inspected and
conformance is verified and documented.

2.0 Scope of Work

2.1 This procedure is applicable to the following works associated with the Project
titled, Construction, Completion and maintenance of Roads and Interchanges of the
existing part of the 7th Ring Road –RA240 Project to comply with the contract
specification and other applicable standards.

2.2 This method statement outlines the procedures to be followed in Demolition of

‫ ﺳﯾد‬a7
Existing Bridge at locations shown on Contract drawings and as directed by the
Engineer. (Bridge Existing in Road #40).

3.0 Definitions
S
3.1
3.2
GS
SHC ‫ﻣﻊ‬
MPW General Specifications for Kuwait Roads & Highways
SINOHYDRO
lm

3.3 HSE Health, Safety & Environmental


3.4 PPE Personal Protective Equipment
3.5 AFC Approved for Construction
3.6 WIR Work Inspection Request
E3

3.7 PM Project Manager


3.8 DPM Deputy Project Manager
3.9 SE Site Engineer
‫دﯾ‬

3.10 LS Land Surveyor


3.11 QA/QC Quality Assurance/Quality Control
3.12 ME Material Engineer
‫ﺎب‬

4.0 References

4.1 Project Specifications


4.2 MPW General Specifications 2012
4.3 Drawings : Document III Volume 3 & AFC Drawings
4.4 BOQ : DIVISION 02 Item 02 41 01
4.5 All Related Approved Method Statements

5.0 Equipment and Tools

5.1 9 Unit Machines of Jack Hammers. (Caterpillar Model-230&235&330&335)


3
5.2 2 Half Lorry (Toyota)
5.3 4 Unit of Bucket Machines. (Caterpillar Model-230&235&330&335)
5.4 2 Units of Loaders. (Caterpillar 950&960)
5.5 12 Units of Dumping Trucks. (Different Models)
5.6 2 Units of Oxygen Bottles (Re-Filled).
5.7 6 Units of Fire Extinguisher Bottles.
5.8 1 Unit of Ambulance
5.9 1 Unit of Asphalt Brushing Cleaning Machine
5.10 1 Unit of CRUSHER Caterpillar Machine (35 Meter Arm Length), Photo
Attached.

6.0 Safety

6.1 We understand that the health and safety of every employee as well as that of any
Person who is directly or indirectly connected with the project is of utmost

6.2

6.3
importance.

working in site.
‫ ﺳﯾد‬a7
We are committed to provide the best safety equipment to all our employees

All persons involved shall be given fire extinguisher and water barrel for the
S
activities concerned, no work will be allowed unless all safety precautions have been

6.4
taken.
‫ﻣﻊ‬
Ambulance Car will be available in case of unexpected accident happen during
Demolishing.
lm

6.5 Disposal of all materials will be done in an environmentally friendly manner so the
minimal damage is caused to the environment.
E3

7.0 Prior Activities


‫دﯾ‬

7.1 Ensure that all related documents are the latest AFC revision.
‫ﺎب‬

8.0 Procedure

8.1 Photo attached with all related work mentioned on it and explanation of the
procedure as follows:

A. Sand layer of 60 cm will be spread all over the Asphalt road under the bridge area
to protect the asphalt from any concrete pieces falling from the demolished
bridge.

B. 1 Unit Machine of CRUSHER Caterpillar of 35 meter arm length will start to


demolish the existing side Cantilever barriers on the longitude line to avoid
any damage to the new constructed pier heads, after providing the required
protection to the piers.

C. 3 Unit machines of Jack Hammers are available as stand by and will be placed
on the ground level, as indicated on the photo attached, and also will help
in demolishing the concrete after the bridge collapsed on the street.

4
D. 4 Unit machines of Jack Hammers on each side on top of the bridge level above
abutment A &B will Start to demolish the deck slab at the support point of the
deck on the abutment and the deck slab will be collapsed and fall down on the
street.

E. Please note that as per the drawings of the existing bridge post tension steel
strands is expected to be available in the pre-cast units and therefore all require
safety precaution is considered during demolishing the bridge. (No labors or
human will be available during demolishing process, only operators of
machine will be available).

 After complete removal of the bridge, other group will start to take out all
steel bars and strands from concrete and start to isolate them and all salvage
steel bars will be stacked in the containers or half lorry in order to be
removed from site.

‫ ﺳﯾد‬a7
 All debris shall be disposed of and removed to the dumping area approved
from Kuwait Municipality.

 10 to 15 units of dumping trucks with 2 units of loaders and 4 unit of bucket


S
machines will be used to put all the salvage material on the trucks which

‫ﻣﻊ‬
will transfer it to the dumping area.

F. Side Slopes backfilling around the abutment will not be removed during the
lm

demolishing of the bridge and it will be removed later after opening ROAD #40 for
traffic.

 Demolishing of retaining wall will start after complete removal of backfilling


E3

behind the existing abutment and demolishing will continue till the removal
of foundation and new backfilling material will be used to backfill the space
under the demolished retaining wall as per MPW Specs.
‫دﯾ‬

G. All middle supported columns (Piers), will be removed till foundation and layers of
‫ﺎب‬

backfilling material will be used to backfill the empty area as per MPW specification.

 All spreading sand on the asphalt road will be removed properly and to be
cleaned by road cleaning asphalt machine and all the salvage material will
be removed also and street will be opened according to MOI Permit.

9.0 Responsibilities

9.1 The Project Manager and Deputy Project Manager will coordinate with Site Engineer
to ensure that the necessary resources to implement the approved Method Statement,
HSE plan have been allocated to the task.

9.2 The Site Engineer (SE) will ensure that the site preparation activities are conducted according
to the approved Method Statement, and HSE plan.

9.2.1 Ensure all necessary approvals are obtained prior to start the work.
9.2.2 Convey all technical data to civil foreman and to ensure that the foreman
understood the activities to be executed.
5
9.2.3 Arrange & ensure the required manpower to execute the work.
9.2.4 Ensure safe working procedures are followed in accordance with the site safety
plan.
9.2.5 Prepare the necessary Work Inspection Request (WIR's) to arrange the consultant
Engineer for inspections.
9.2.6 Organize the work in a safe manner to ensure that safety and protective
equipment are being properly utilized.

9.3 The Material Engineer (ME) will ensure that the materials being used are in accordance with
the Project Specifications and approved Material Submittals. He will be in charged with the
field laboratory and will undertake the necessary tests as required for the project with the
assistance from Laboratory Technicians.

9.4 Quality Control Engineer


9.4.1 Review all documents and test reports.
9.4.2 Ensure that all other discipline activities that must be inspected within the

‫ ﺳﯾد‬a7
concrete casting works have been inspected and ready for operating safely.
9.4.3 Organize and allocate inspection works.
9.4.4 Perform pre inspection to determine acceptability prior to inspections.
9.4.5 Co-ordinate with the consultant inspectors.
S
9.5 Foreman
9.5.1
‫ﻣﻊ‬
Conduct the toolbox meetings and briefing for his crew workers the potential
hazards and precautionary measures to be taken during the casting process.
lm

9.5.2 Ensure that certified fire extinguishers are deployed at site in the right location.
9.5.3 Ensure that all engaged personnel have right PPE and all equipment are
experienced enough to execute the work.
9.5.4 Control the workmanship quality by directing and instructing his crew workers
E3

and during the work execution.


9.5.5 Responsible for proper execution of the formwork levels and dimensions as per
approved drawings.
‫دﯾ‬

9.5.6 Ensure that, all the tools & equipment are available at site to execute the different
activities.
‫ﺎب‬

9.6 Safety Officer

The Safety Officer shall be responsible for safe execution of work activities in
compliance with the approved HSE plan & project HSE requirements.
9.6.1 Ensure that all HSE requirements are applied and implemented according to the
MPW requirements while executing the works.
9.6.2 Ensure that recommendations of workplace precautions are followed up strictly.
9.6.3 Stop any/or all works in case of specified recommendations/ observations are not
applied by the construction team.
9.6.4 Inspect & ensure that all engaged personnel have got correct PPE and all
equipment’s are perfect and certified to execute the works.

6
F G
All middle supported existing columns (Piers) will be removed till
Side Slopes backfilling around the abutment will not be
foundation and layers of backfilling material will be used to backfill
removed during the demolishing of the bridge and
the empty Holes as per MPW Specification.
it will be removed later after opening ROAD #40
for the cars. B
1 Unit Machine of CRUSHER Caterpillar of 35 meter
D Arm Length will start to demolish the existing side
4 Unit Machines of Jack Hammers on each side on top of the

‫ ﺳﯾد‬a7
Cantilever barriers on the longitude line to avoid any
bridge level above abutment A &B will start to demolish the damage to the new Constructed Pier heads , after
deck slab at the support point of the deck on the abutment providing the required protection to the piers.

S
and the deck slab will be collapsed and fall down on the street.

‫ﻣﻊ‬
lm
A
Sand layer of 60 cm will be spread all over the Asphalt

E3
road under the bridge area to protect the Asphalt from
any concrete pieces falling from the demolished bridge.

‫دﯾ‬
C ‫ﺎب‬
3 Unit Machines of Jack Hammers are available as stand
by and will be placed On the Ground level as indicated
on the Photo attached and also will help in demolishing
the Concrete after the bridge collapsed on the street.
Project : RA/240 Document No.: Revision No.:

RA240-HSE-RA-016 Rev.0
Construction, completion and maintenance of
Roads and Interchanges of the existing part of Work to be done: Demolishion of the existing Bridge Located on ROAD #40 Date: 10-May-18
7th Ring Road

Activity:Demolishing
RISK
SEVERITY PROBABILIT RESIDUA
HAZARD Y LEVEL
RATIN PRECAUTIONS TO BE TAKEN ACTION BY
LEVEL L RISK
G
work area shall be isolated from public traffic by means of hard barrication

all personnel shall wear mandatory HI-VIZ vest


all construction equipment on site shall be provided with reverse alarm and flashing lights to alert
workers struck by equipment 3 2 6 9 STE/SO/CM
everybody of it presence
qualified banks man shall be made available on site

all personell shall be trained in safe work practice during detour works

install required warning signs to alert public of ongoing road activity

‫ ﺳﯾد‬a7
vehicular accident on
1 2 2 ensure all work area is enclosed and provided with hard barrication 3 STE/SO/CM
adjuscent road
install warning lights

ensure that cool and substantial amount of clean drinking water is provided to workers at all times

provide shaded rest area for workers at site.


excessive heat 4 3 12 9 CM / SE / STE
training shall be provided to all workers on ways to avoid heat related diseases
S no work shall be conducted under direct sunlight during summer months between 11 am to 4 pm

‫ﻣﻊ‬
all dirt road in the project shall be regularly water sprayed

dump[ truck carrying sand loads in public roads shall be adequately covered
excessive dust 3 3 9 6 STE/SO
workers shall be provided with adequate type dust mask
‫ ﺎ ب‬lm
all personnel shall be trained in precautionary measures to be taken during sand storm.

all equipments shall be fitted with silencers to avoid causing excessive noise

excessive noise 3 3 9 activities creating load noises near residensial areas shall be planned in order to minimise the impact 6 STE/SO/CM
to the community.

provide proper ear protection (ear plugs and muffs) to workers


E3

ensure all work area is well lighted

provide flashing arrows and flashing lights on all traffic barricades as needed.
working at night 3 3 9 6 CM / STE / SO
all workers shall wear high reflective apparel when working at night.
‫دﯾ‬

all personnel shall be trained in the precautionary measures to be taken when working at night

all lifting equipments must be 3rd party certified


all lifting equipments must be inspected regularly and prior to use
unsafe lifting operation 1 1 1 safe lifting procedure must be observed
1 STE/SO/CM
never overload any lifting device/equipment

ensure that all protective guards are properly installed


use of unsafe
2 2 4 use only appropriate tools for the job 3 STE/SO/CM
powertools
workers will be trained in the power tools that they will use
Legend : - PM - Project Manager / DPM - Deputy PM / CM - Construction Manager / SE - Safety Engineer / STE - Site Engineer / SO - Safety Officer