ITEM DESCRIPTION QTY UNIT Unit Cost MTLS. COST Unit Labor LABOR COST AMOUNT
- -
I. GENERAL REQUIREMENTS - -
1 General Paragraph - -
a. Mobilization/Demobilization (905M2) 1.00 lot - 80.00 80.00 72,400.00
b. Permits, Licenses, Fees & taxes 1.00 lot - -
2 Construction Facilities - -
a. Temporary Facilities - -
1. Field office / warehouse 1.00 lot - - 40,000.00
2. Electric Consumption (9MONTHS) 1.00 lot - 7,000.00 7,000.00 63,000.00
3. Water Consumption (9MONTHS) 1.00 lot - 5,000.00 5,000.00 45,000.00
b. Equipment and tools 1.00 lot - - 50,000.00
d. Safety Requirements (60LM) 1.00 lot - - 18,000.00
e. All necessary material testings 1.00 lot - - 15,000.00
f. Preparation of As-Built Plan 1.00 lot - - 90,000.00
- -
TOTAL AMOUNT - GENERAL REQUIREMENTS
- -
II. SITE WORKS - -
1 Excavation Works 270.00 m3 - 500.00 135,000.00 135,000.00
2 Backfilling Works & compaction 200.00 m3 - 150.00 30,000.00 30,000.00
3 Filling materials 185.00 m3 125 23,125.00 100.00 18,500.00 41,625.00
4 Gravel Bedding 70.00 m3 1300 91,000.00 300.00 21,000.00 112,000.00
5 Soil Poisoning 700.00 m2 50 35,000.00 20.00 14,000.00 49,000.00
6 Trimming of soil 538.00 m2 - 60.00 32,280.00 32,280.00
- - -
TOTAL AMOUNT - SITE WORKS
- - -
III. CONCRETE WORKS - - -
1 Column Footings, Wall Footing, & Elevator - - -
Concrete, 3000psi @ 28days 42.00 m3 - - -
Formworks 126.00 m2 - - -
Rebars grade 40 2,579.00 kg - - -
Tie Wires 154.00 kg - - -
- - -
2 Footing Tie Beam - - -
Concrete, 3000psi @ 28days 13.50 m3 - - -
Formworks 122.00 m2 - - -
Rebars grade 40 2,970.00 kg - - -
Tie Wires 145.00 kg - - -
- - -
- - -
3 Column - - -
Concrete, 3000psi @ 28days 35.00 m3 - - -
Formworks 427.00 m2 - - -
Rebars grade 40 9,176.00 kgs - - -
Tie Wires 350.00 kgs - - -
- - -
4 Beams - - -
Concrete, 3000psi @ 28days 42.00 m3 - - -
Formworks 384.00 m2 - - -
Rebars grade 40 9,770.00 kgs - - -
Tie Wires 145.00 kgs - - -
- - -
5 Suspended slab - - -
Concrete, 3000psi @ 28days 54.00 m3 - - -
Rebars grade 40 5,890.00 kgs - - -
Tie Wires 118.00 kgs - - -
STEEL DECKING 358.00 m2 - - -
Formworks 88.00 m2 - - -
- - -
6 Concrete Gutter - - -
Concrete, 3000psi @ 28days 6.70 m3 - - -
Formworks 113.00 m2 - - -
Rebars grade 40 1,392.00 kgs - - -
Tie Wires 58.00 kgs - - -
- - -
7 Slab on Fill - - -
Concrete, 2500psi @ 28days 80.00 m3 - - -
Rebars grade 33 3,481.00 kg - - -
Tie Wires 52.00 kg - - -
ITEM DESCRIPTION QTY UNIT Unit Cost MTLS. COST Unit Labor LABOR COST AMOUNT
TOTAL AMOUNT - CONCRETE WORKS
- - -
IV. SCAFFOLDING WORKS 1.00 lot - - -
- - -
TOTAL AMOUNT - SCAFFOLDING WORKS
- - -
V. MASONRY WORKS - - -
a. CHB 4" Laying, 350psi 51.33 sq.m2 - - -
T&B m2 - - -
b. CHB 6" Laying, 350psi 1,159.00 sq.m2 - - -
Left, Right, Rear Side & Front Elevation m2 - - -
c Plastering 2,420.00 sq.m2 - - -
d Concrete Topping 797.00 sq.m2 - - -
e Waterproofing works 86.00 sq.m2 - - -
- - -
TOTAL AMOUNT - MASONRY WORKS
- - -
VI. STRUCTURAL WORKS - - -
a Steel Trusses - - -
Rafter (8w x 18#/1 x 12mts) 8.00 pcs - - -
Purlins (2.2mm x 2' x 6' x 6mts Cee Purlins) 84.00 pcs - - -
Hor. Strut (6w x 10 x 6mts) 19.00 pcs - - -
SagRod (12mm x 6mts Plain Round Bar) 37.00 pcs - - -
16mmØ x 6mts Plain Round Bar 16.00 pcs - - -
16mmØ xTurn Buckle 12.00 pcs - - -
10mm x 250mm x 250mm Base Plate 24.00 pcs - - -
12mm x 200mm Angchor Bolt 96.00 pcs - - -
6mm x 4' x 8' MS Plate 1.00 pc - - -
4.5mm x 2 x 2 x 6 Angle Bar 1.00 pc - - -
Welding Rod 20kg 4.00 box - - -
Welding Rod Ordinary 40.00 kg - - -
M-Gas 2.00 Tanks - - -
Oxygen 14.00 Tanks - - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
d Miscellaneous materials 1.00 lot - - -
such as oxygen, LPG, welding rod, grinding disc, cutting disc - - -
TOTAL AMOUNT - ROOF FRAMING WORKS
- - -
VII. ROOFING WORKS - - -
a. Roofing - - -
Prepainted Rib Type Panel 0.40mm thk 400.00 l.m - - -
complete with bended accss and insulation and other consumables - - -
- - -
- - -
TOTAL AMOUNT - ROOFING WORKS
- - -
VIII. 2 sets - T&B - - -
a Tileworks - - -
- 30cm x 30cm floor tiles 7.38 m2 - - -
- 20cm x 30cm wall tiles (5layers only) 12.87 m2 - - -
b PVC Door 60cm x 210 with inside lock 3.00 sets - - -
- - -
TOTAL AMOUNT
- - -
- - -
IX. DOORS - - -
a Steel Door - - -
1 Rool UP door - - -
D1 (4mts x 4mts) 1.00 set
D1.1 (1.95mts x 4mts) 1.00 set
D1.2 (3mts x 3mts) 20.00 sets
D1.3 (2mts x 3mts) 18.00 sets
b Metal Door
D2 (1.1mts x 2.15mts) 1.00 set
D2.1 (1mts x 2.15mts) Fire Exit Door 3.00 sets - - -
D2.2 (0.8mts x 2.15mts) 1.00 set
c Wood Door
D4 (0.9mts x 2.15mts) 2.00 sets
ITEM DESCRIPTION QTY UNIT Unit Cost MTLS. COST Unit Labor LABOR COST AMOUNT
d Alluminum Door - - -
D5 (1.9mts x 2.65mts) 1.00 set - - -
e Locksets (Henry Brand) 51.00 pcs - - -
TOTAL AMOUNT - DOORS
- - -
X. WINDOWS - - -
steel casement windows w/ 1/8 clear glass, with enamel paint - - -
a Alluminum Awning windows (2.65mts x 0.70mts) 4.00 sets - - -
b Alluminum Sliding windows (2.00mts x 1.30mts) 1.00 set - - -
TOTAL AMOUNT - WINDOWS
- - -
XI PAINTING WORKS - - -
a Doors - - -
set - - -
set - - -
b Metal Works, enamel paint - - -
- - -
- - -
- - -
c WALLS - - -
1 Semi Gloss paint Finish - - -
- Exterior /Interior m2 - - -
d CEILING - - -
- Flat Latex - - -
- - -
e Miscellaneous materials lot - - -
such as rugs, paint brush, sandpapers, newspaper - - -
- - -
TOTAL AMOUNT - PAINTING WORKS
- - -
XII. METAL WORKS - - -
a Steel Stair and Railing - - -
a.1 - - -
- - -
- - -
TOTAL AMOUNT - METAL WORKS
- - -
XIII. PLUMBING WORKS - - -
Supply and installation of all necessary piping, and fittings - - -
a. Drainage System 1.00 lot - - -
b. Sanitary Line & Vent 1.00 lot - - -
- - -
- - -
c. Plumbing Fixtures (Pozzi or any approved equivalent) - - -
- Common T&B - - -
Package watercloset with lavatory set - - -
- Miscellaneous such as angle valve, flexible hose, teplon 1.00 lot - - -
d. Pipe hangers and support 1.00 lot - - -
e. Cold Water Line 1.00 lot - - -
f. Testing & Commissioning 1.00 lot - - -
TOTAL AMOUNT - PLUMBING WORKS
- - -
XIV. ELECTRICAL WORKS - - -
a Power and Lighting - Roughing-In (Pipes and fittings) 1.00 lot - - -
b Boxes and enclosures 1.00 lot - - -
c Wires & Cables 1.00 lot - - -
d Wiring Devices 1.00 lot - - -
e. Panelboards & CB 1.00 lot - - -
f Telephone System 1.00 lot - - -
g CCTV System (Roughing-Ins /wiring Only) 1.00 lot - - -
h Electrical Fixtures (Installation Only) 1.00 lot - - -
i Testing & Commissioning 1.00 lot - - -
- - -
TOTAL AMOUNT - ELECTRICAL WORKS

GRAND TOTAL (Vat Excluded)