FCI GROUP
Date:19th Oct,2019
Sl No. What/Problems Who/Responsible
Layout plan is not planned considering critical to machine set up IE & Planning
22
Some style suddenly stopped due to accessories shortage and
Planning
23 plan again without preparation
During preset operator training is not done properly which Technical
24 caused machine problem again during feeding
Machine breakdown is made an issue if target is not achieving
Production
25 with some other reason
Not consider machine availability During planning need to consider the availability of
machines
Last moment machine requirement
come Machine requirement has to come well in advance
Rented machines quality is poor Need to avaoid rented machines
Final layout paper is not correctly ready
Final layout paper has to be ready on time
Space shortage Need to make space
Mindset problem Production need to take initiative to use preset
machines
Mindset problem Production need to take initiative to use preset
machines
Need to make machine requirement considering
Machine requirement is not made
considering actual scenery actual scenery
Layout Paper is not made correctly Layout paper has to make correctly considering
actual situation
Layout Paper is not made correctly Layout paper has to make correctly considering
actual situation
Production plan is not accurate Need to make layout considering available space
inside line
Space shortage Need to make plan to make space
Need to identify the regular required parts and make
Not consider spare parts availability a list of minimum stock of spare parts
Not available Need to purchase
Not available Need to purchase
Plan vs Actual is varying
Actual Need to be closed with plan
BEPZA gate problem
Need to fix standard
Production plan is not as per machine During planning need to consider the availability of
availability machines
Not serviced properly
Need to service regular basis
ERP is not updated ERP need to be updated
Production plan is not as per machine During planning need to consider the availability of
availability machines
RM Shortage/Production difficulties Ensure at least one month frozen plan