Address
To,
Consultant Name
Address: 21, B wing, Manik plaza, ZP Marg, Chembur, Mumbai.
Tel/Mobile No: 9423003268
Material VAT Reg. No: N.A
Email ID-abccontra@gmail.com
Service Tax No: AFTSF 4526F/SD002
PAN: AFT4526F
Subject: RCC work for HIVIYA villa at, Sahakar Nagar, Pune
With reference to your quotation dated 21/01/20 , & discussions we had with you, we are
placed to award you the work order RCC work of Sub structure & Super Structure for HIVIYA Villa
Project, Sahakar nagar, Pune
The detailed terms & conditions of the work order are as follows:
2. SCOPE OF WORK:
The contract shall mean the construction, completion and maintenance during defects liability period,
provisions of all labour for shuttering, lifting, cutting and tying of reinforcement, concreting as per
specified grade, all the shuttering materials, tools and machinery as mentioned herein.
4. QUANTITY VARIATION:
If due to any reasons, this area changes as per the actual executed work on site, then the revised actual
area shall be considered for the final payable amount calculation. The change in the area shall be
jointly certified by the contractor and our site in charge.
5. PAYABLE AMOUNT:
The rate agreed for the completion of the work as mentioned in the scope of the work is Rs. ___- per
slab area as per annexure I. As per this rate, the total amount of this contract comes out to
Rs.1,50,87,160/-(In words Rs One crore fifty lac fifty eight seven thousand one hundred and sixty
only)
6. TIME OF COMPLETION:
Time is the essence of the contract. The entire work in your scope shall be completed in all respects
and handed over to us before the targeted date of completion. Contractor shall adhere to the schedule
fixed by the site in charge to suit the site conditions. It shall be the contractor’s responsibility to
jointly workout the detailed program along with the site in charge so as to complete the work within
the time period.
Slab cycle for typical floors shall be of 18 days including all holidays.
9. TERMS OF PAYMENTS:
a. No mobilization advance shall be paid to contractor.
b. Contractor shall submit his R.A bill after each payment stage along with abstract /measurements on
the company’s standard format.
c. 5% retention shall be deducted from each R.A bill 50% of this retention amount shall be released
after completion of LMR & OHWT. OHWT and rest 50% shall be released after successful
completion of defects liability period of 6 months from the completion of LMR & OHWT.
d. Payment of R.A bills will be made be to contractor within 15 days on submission of technically &
commercially correct invoice to our project manager. Contractor shall get the R.A bills scrutinized
and certified at site from the site in charge.
e. Debit notes , if any , shall be attached along with each R.A Bill duly signed by site in charge and
accepted by the contractor .Decision of director / project manager /site in charge will be considered as
final in case of discrepancies.
f. Applicable TDS will be deducted from each payable amount and TDS certificate for the same will
be handed over to the contractor at the financial year end.g. Service tax shall be paid extra on each
RA bill (Service tax registration shall be provided to claim service tax)
9. PAYMENT STAGES:
The payment stages of the contractor shall be per attached annexure II.
If any accident occurs at site due to negligence of the above mentioned safety norms, the contractor
will be solely responsible for all the consequences arising out of the above and the client is abso9lved
of any claims/Compensation if any payable by the contractor to his workman.
Company/client shall be indemnified for any theft, damages, accident for the plant & machinery.
Entire responsibility of safety, storage of machinery; consumables etc. shall be with the contractor
after the issue of material.
Equipment’s:
Sr. No. Plant/Machinery Quantity Unit
1 Mixer 1 Nos
2 Platform 1 Nos
3 Material lift (Hoist) 1 Nos
4 Electric Vibrator 3 Nos
5 Vibrator needle Dia 20 mm 1 Nos
a) If the contractor fails within three day notice from the developers to proceed diligently with the
work to his satisfaction and at all times in such a manner as will not in the developers opinion ,
prejudice the completion of the whole or any portion of the work under the principal contract in
accordance therewith.
b) If the contractor refuses / delays or fails within three days’ notice to rectify any defective
workmanship to the developer’s satisfaction.
c) If the contractor fails to complete and deliver any work or portion of the work by the time or times
specified in the work schedule or by such extended time or times as may be allowed by the developers
in writing.
d) If the contractor fails to withdraw /replace immediately, at developers instructions any one or more
of the employees to whom developer objects o whose presence on the works may not be good to
maintain healthy working environment on site.
e) If the contractor sublets whole or part to this work without developers written prior approval.
f) If the contractor fails within three days’ notice from developer to take action on any of the
obligations on the part of the contract herein contained.
g) If the contractor fails to mobilize sufficient man power, machineries etc. affecting quality and
progress of work. Company shall engage another agency to complete the work at contractors risk and
cost. I accept this Work order along with the annexure/s