Beruflich Dokumente
Kultur Dokumente
H I GH L IG H T S
• Concluded three aspects characteristics of the VAC system in the subway station.
• Analyzed the problems existing in the operation of the subway station’s VAC system.
• Proposed seven energy-saving strategies for the VAC system in the subway station.
• After optimization, the VAC system can save energy more than 30%.
A R T I C LE I N FO A B S T R A C T
Keywords: Subway systems are rapidly developing, and their energy consumption is considerably growing. The ventilation
Energy consumption and air conditioning system in the subway station is the key energy-consuming system. It consumes a large
Energy audit amount of energy every day to provide a comfortable environment for passengers, and it has therefore received
Energy-saving potential increasingly more attention from researchers worldwide. In this work, the variation law of the ventilation and air
VAC system
conditioning system of a subway station is analyzed from three aspects (energy consumption, load, and tem-
Subway station
perature) based on field test data, and the problems existing in the operation and management of the system are
analyzed. For example, the results show that the total load of fresh air in the station was as high as 34–37%, and
about 30 min was required to adjust the indoor temperature to a stable state. In addition, three general models
and seven energy-saving strategies are put forward, and their energy saving potentials are estimated. After
optimization, the ventilation and air conditioning system is found to reduce energy consumption by more than
30%. Not only are common problems that exist in the actual operation of the subway station ventilation and air
conditioning system found in this research, but valuable measured data is also provided for the theoretical
research of the thermal environment of the subway and the design of environmental control systems.
⁎
Corresponding author at: Guangzhou Institute of Energy Conversion, Chinese Academy of Sciences, Guangzhou 510640, PR China.
E-mail address: tangzh@ms.giec.ac.cn (Z. Tang).
https://doi.org/10.1016/j.applthermaleng.2020.115555
Received 24 November 2019; Received in revised form 25 May 2020; Accepted 1 June 2020
Available online 08 June 2020
1359-4311/ © 2020 Elsevier Ltd. All rights reserved.
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
is very significant to analyze the energy consumption and load char- optimize a VAC energy management system by minimizing its monthly
acteristics of the VAC systems in subway stations, and to propose en- energy consumption [13]. The energy consumption of air conditioning
ergy saving suggestions. systems in Beijing subway stations has been explored; however, only
Many studies have been conducted to reduce the energy consump- the COP, SCOP, and EER of the VAC systems in ten subway stations
tion of subway systems and provide passengers with a comfortable and were analyzed, and the reason for the high energy consumption of the
healthy environment. Energy consumption trends and energy units for VAC system was not pointed out by the researchers [14]. Energy con-
subway stations have been investigated in South Korean cities and sumption signatures of the VAC system in Beijing were investigated by
Barcelona [7,8]. Based on survey data and Energy Plus software si- deploying environment monitoring sensors and smart meters [15];
mulation output data, a statistical model was proposed for developing however, the load of the VAC system was defined only as the quantity of
the Energy Use Intensity benchmark for subway stations [9]. An in- heat imported from outdoor environments and passengers into the
teresting approach was developed to predict the energy consumption of subway station in one time unit. Such an estimate is not sufficiently
railway stations, wherein a multilayered perceptron method was accurate, and it is therefore difficult to be used to determine the reasons
adopted to mimic the nonlinear correlation between energy consump- for the high energy consumption of the VAC system. The energy con-
tion, the spatial design of the station, and meteorological factors [10]. sumption and load characteristics of the VAC system in the public area
The electricity consumption of subway stations in different climate of a subway station have been investigated, but the study regarded the
zones in China was revealed to provide references for understanding the hourly equipment load as stable, and did not measure or calculate the
energy consumption level, as well as for establishing energy con- complex load of the equipment area [16]. It is therefore evident that a
sumption standards for subway stations [11]. However, none of these thorough investigation of the VAC systems of subway stations remains
studies have specifically analyzed the energy consumption of the VAC lacking.
system in subway stations. A modular structured simulation model was Furthermore, energy demand and energy-saving strategies in un-
presented for computing the energy consumption of the VAC system of derground stations are directly influenced by climatic characteristics
a light rail vehicle [12]. A robust evolutionary algorithm was used to [8]. VAC systems account for the largest proportion of the energy
2
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
consumed in subway stations in China [17], whereas lighting sub- the station hall, and the underground second floor is the platform. The
systems were revealed to be a significant energy consumer in a subway main building area of the station is 7918 m2, the area of the access
station in Barcelona, responsible for 37% of the total consumption passages is 2260 m2, and the area of the air passage and the wind pa-
[8,18]. In temperate climate regions, such as Beijing, piston wind is a vilion is 1405 m2. Thus, the total covered area is 11,583 m2.
good means of reducing air conditioning use, but it is limited in hot Furthermore, the area that requires refrigeration by the VAC system is
climate zones, especially in areas with high passenger flow [19]. The 3855 m2. As shown in Fig. 1, the station is divided into the equipment
heat of the train brake can be used to improve the station temperature management room (EMR) and public place (PS). The A and B terminals
in severely cold northern regions [20], but it has a pernicious effect on of the PS (including station hall and platform) are the EMRs. There are
the thermal comfort of stations in hot climate zones, and accordingly 3 access passages in the station, two of which are respectively con-
increases the energy consumption of VAC systems [19]. Humid sub- nected to the east and west sides of the station hall. Each access passage
tropical regions have humid and hot weather, and the energy con- has two entrances. The third access passage, which is arranged at the A
sumption in subway stations in such areas is considerably higher than terminal of the station hall, is an emergency entrance. Additionally,
those in northern China [11]. Furthermore, the energy-saving poten- four groups of wind pavilions are respectively set at the A and B
tials and strategies differ substantially from those in other climatic re- terminals of the station hall.
gions. The EMR is composed of a strong electricity room (SER), weak
Detailed field studies, environmental monitoring, heat dissipation electricity room (WER), comprehensive management room (CMR), and
detection, and power log processing were conducted in this work to other electromechanical room (OER). The equipment in the SER in-
investigate the characteristics of power consumption, load and tem- cludes switch cabinets, transformers, and switch boxes, etc. The
perature in subway VAC systems, and energy-saving strategies are ac- equipment in WER includes electrical control systems for the VAC
cordingly identified. Guangzhou, which is in southern China, has humid system, communication devices, signaling appliances, and civil com-
and hot weather, and a long air conditioner refrigeration time. munication devices, etc. The CMR is composed of a comprehensive/
Therefore, one typical station in the Guangzhou Metro was selected as station control, the station master’s office, platform operation, lockers,
the research object in the present study. and meeting rooms, etc. The OER includes a wastewater pump, gas
In this work, the characteristics of the VAC system in a subway cylinder, ventilation equipment, and fire pump rooms, etc. The electric
station were analyzed from three aspects: researching the monthly/ equipment in the PS includes advertising boards, elevators, lamps, gate
daily/hourly energy consumption of the VAC system and the proportion machines, ticket-selling machines, self-service equipment, and pas-
of the subsystems’ energy consumption, and then analyzing the change senger information display systems, etc.
trend of the VAC system’s energy consumption; analyzing the propor- Temperature and humidity sensors were installed about 1 m away
tion of various loads and their changing rules; studying the hysteresis of from the fresh air inlets to measure the outdoor temperatures and hu-
the VAC system in the subway station via temperature monitoring, and midity, respectively. Illustrations of the temperature and humidity
researching the influence of the outdoor temperature on the indoor sensors installed in the hall and the platform are presented in Fig. 1, and
temperature of the subway station. Finally, this research indicates the the data was recorded once every 5 or 6 s. Wind speed sensors were
problems existing in the operation and management of the VAC systems arranged in each entrance of the station to obtain the air rate in the
of subway stations, and proposes seven energy-saving strategies. entrances. The sensors were installed in the relatively flat part of the
Compared to the existing work, this study presents not only a passageways, located in the middle of the channel section and about
comprehensive field study of subway station VAC power consumption, 20 cm from the ceiling of the passageway, and the data was recorded
load signatures and temperature characteristics, but also actual opera- once every second. According to the field test of a European subway
tion problems and corresponding energy-saving recommendations. station, no significant variation in air speed exists at different positions
Additionally, valuable measurement data for the theoretical study of of a cross-section; thus, any measurement across the section could be
the thermal environment of the subway and the design of the en- considered as representative of the cross-sectional average air speed
vironmental control system have been accumulated. Furthermore, this along the corridor [22]. The power consumption of different compo-
paper addresses a very important topic of metro energy-saving in nents of the VAC system and other equipment in the station was mea-
humid, subtropical climates, and provides a significant reference for the sured in real time by embedded power meters, and the data was re-
development of future metropolitan cities in Malaysia, India, the corded once every 15 min. The temperature and humidity of fresh air
Philippines, and others. and the supply/return air were recorded using an automatic tempera-
ture and humidity recorder. The measuring points were located at the
2. Methodologies fresh air inlets, supply air inlets, and return air outlets in each area, and
the data was recorded once every minute. An intelligent wind speed
2.1. Selection of the case study recorder was used to measure the fresh air and return air volume in
each area. Data was recorded once every minute and continuously for
Guangzhou is located in the subtropical zone, and its weather is 3 days. The surface temperature of each room and the equipment in the
both humid and hot. The Guangzhou Metro is the third-largest urban EMR was measured using a thermal imager. It was measured once every
rail transit system in mainland China, and is one of the 14 members of 2 h and continuously for 2 days. The inner surface of the enclosure
the Community of Metros. Its total mileage is 391.6 km with 206 sta- structure and the surface area of the equipment were measured. The
tions. Since July 24, 2018, the daily average passenger flow has been details of the measurement techniques and instruments are exhibited in
predicted to be 8,200,000, with a daily maximum passenger flow of Table 2.
10,025,700 [21]. One typical station in the Guangzhou Metro was se-
lected as the research object in this study. The representative station, Table 1
which opened in 2005, is on the Guangzhou Metro Line 4. An analysis Selection of a typical station (underground non-transfer station).
of the number of annual passengers and the main physical character- Mean Lower quartile Upper quartile Station
ization parameters was conducted. The analysis revealed a station with
4
typical values, which are listed in Table 1. Daily passengers (10 ) 3.27 1.13 8.42 3.61
Hall floor area (m2) 1450 1230 2304 1400
Platform floor area (m2) 750 620 1480 690
2.2. Space structure of the study object
Number of layers 2 2 2 2
Number of entrances 4 2 5 4
It has an island-type platform with 4 entrances. The ground floor is
3
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
A C
A/B/C Entrance
D Emergency Entrance
SEM
Air distribution
Wind speed sensors
Temperature and humidity sensors
The calculation equations of subway station design mainly includes QC, equi = Cequi Qequi (9)
enthalpy equation and energy equation. The equations are expressed as
QC, fan = Cequi Qfan (10)
follows [23,24]:
h = 1.01tair + d (2500 + 1.84tair ) [23] (1) QC, others
= Vsup ρair (hindoor , air − h sup) − (QC, fre + QC, PHE + QC, person + QC, lig
QC, sta
+ QC, equi + QC, PSD + QC, fans ) (11)
= QC, fre + QC , PHE + QC , person + QC , lig + QC, equi + QC, PSD + QC, fans
+ QC, others λair Nu
(2) Qequi,1 = Aequi (tequi − tindoor , air )
lequi (12)
d = 0.622φPs /(P − φPs ) (3)
Qequi,2 = α int Aint (tint − tair ) (13)
QC, fre = ρair Vfre (houtdoor , air − hindoor , air ) (4) 4 4
Aequi (εequi σTequi − εint σTint )
Qequi,3 = A
QC, PHE = ρair Vunor , inlet (houtdoor , air − hindoor , air ) (5) 1 equi 1
+ A ( ε − 1)
εequi int int (14)
QC, person = (Cperson qs + ql ) nψτ /60 [24] (6) where Eq. (1) is the enthalpy conservation equation, and Eq. (2) is the
Table 2
Details of the measurement techniques and instruments.
Item Analytical methods and instruments
Air temperature and humidity sensors SHT-30; measurement range of humidity: 0–100% RH; measurement range of temperature: −40–125 °C; precision:
temperature ± 0.3 °C, humidity ± 3%.
Power consumption sensors NEMU-QR-4001 electrical information acquisition unit; precision: ± 0.5%.
Surface temperature sensors AR862A+; measurement range: −50–900 °C; precision: ± 1.5 °C.
Wind speed sensors in entrances NZ100SX anemometer; measurement range: 0–30 m/s; precision: ± 3%.
Wind speed sensors for fresh air and return air VS110 anemometer; measurement range: 0.5–50 m/s; precision: ± 0.5%.
4
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
250000 30
Electricity consumption
energy conservation equation. Eqs. (4)–(17) are the calculation equa-
tions of heat sources in the station. d is the humidity ratio of air, φ is the
Temperature (oC)
200000 25
relative humidity of the environment, P is the atmospheric pressure
150000
(kWh)
(Pa), Ps is the saturated vapor pressure of vapor (Pa); QC,fre is the 20
100000
cooling load formed by mechanical fresh air; QC,PHE is the cooling load
50000 15
formed by the permeation of heat due to the inlet air of the entrances;
QC,person is the cooling load formed by the heat dissipation of the human 0 10
body; QC,lig is the cooling load formed by the heat dissipation of the 1 2 3 4 5 6 7 8 9 10 11 12
Months
lighting; QC,PSD is the cooling load formed by heat transfer of the
HVAC Outdoor temperature
platform screen door; QC,equi is the cooling load formed by the heat
dissipation of the device; QC,fan is the cooling load formed by the heat Fig. 2. Influences of monthly passenger flow on monthly electricity consump-
dissipation of the fans; QC,otheris the cooling load due to the heat pe- tion of the station.
netrating from the tunnel into the platform, the heat transfer of the
enclosure structure, and other unknown heat sources, it can be de- 3.1. Energy consumption in the VAC system
termined from the difference between the supply load of the air con-
ditioner and the aforementioned loads. The heat dissipation of eleva- The monthly electricity consumption of the VAC system increased
tors, escalators, brakes, and fans is the difference between their actual with the increase of outdoor temperature (Fig. 2). According to the
power consumption and effective work [25]. The heat dissipation of Spearman’s correlation coefficient (rho) [31], which was calculated by
billboards, passenger information display system (PIDS), shops, self- Stata/MP software (version 14.0, StataCorp, College Station, TX), the
service equipment, data center communication equipment, etc. is esti- monthly electricity consumption had a very strong correlation with the
mated according to the actual power consumption [16,25].The heat outdoor temperature (rho = 0.9632). The unit area electricity con-
dissipation of indoor equipment is mainly formed by the following sumption of the VAC system in the air conditioning area was 370.23
three processes: first, convective heat exchange between the equipment kWh/(m2·year) (51.68 and 318.55 kWh during the NACTs and ACTs,
and indoor air is Qequi,1 , second, radiation heat exchange between the respectively). The unit area electricity consumption of the VAC system
equipment and the enclosure structure is Qequi,3, third, convection heat in the covered area ranged from 3.2 to 20.3 kW/(m2·month), which was
transfer between the inner surface of the enclosure structure and the air 2.5–7.0 kW/(m2·month) greater for humid and hot weather than that
is Qequi,2 [26]. Therefore, the distribution room, switch cabinet room, determined in a previous study [11]. The electricity consumption of the
high-voltage control room, rectifier transformer room, follow-up sub- VAC system in July was the highest, and was approximately 6.4 times
station, and other rooms obtain the heat dissipation of the equipment greater than that in February.
through the test method. The heat of convection heat transfer between During NACTs, the major electricity consumption included that by
the equipment and air is calculated by the Eq. (12), in natural con- the air handling units (AHUs) in the PS and EMR, and that by the fans in
vection, Nussle number (Nu) = Cn (Ge · Pr) n,where Cn and n are the PS and EMR. As presented in Fig. 3, the daily electricity con-
constant [27].In forced convection, the wall temperature is assumed to sumption of the VAC system during the NACTs was nearly uniformly
be isothermal [28], than the Nu is calculated according to different distributed (approximately 1286–1438 kWh/day). The electricity con-
values of Reynolds number Re and Prandtl number Pr, When the sumption of the AHUs and fans in the EMR were not volatile throughout
Re < 5 × 105and 0.5 < Pr < 15, Nu = 0.664Re1/2Pr1/3, When the the day, but the electricity consumption of the AHUs and fans in the PS
5 × 105 < Re < 107and 0.6 < Pr < 60, Nu=(0.037Re0.8-871) Pr1/ presented significant peak and valley fluctuations during the operation
3
,The convective heat exchange between the inner surface of the en- and outage periods. The error bars are the standard deviations of ten
closure and the air is calculated by the Eq. (13). where the value of αint discontinuous weeks, which were between 0 and 8.96 kWh. Further-
is 3.9 × 10−3 kW/(m2∙°C) [29]. The amount of radiant heat exchange more, the average standard deviation of the fans’ electricity consump-
between the equipment and the inner surface of the enclosure is cal- tion in the PS was 0.35 kWh, that of the AHUs’ electricity consumption
culated is calculated by the Eq. (14) [30], where the values of εequi and in the PS was 0.75 kWh, that of the AHUs’ electricity consumption in
εint are 0.65 and 0.85, respectively. the EMR was 0.54 kWh, and that of the fans’ electricity consumption in
the EMR was 0.36 kWh. As shown in Table 4, the electricity con-
sumption of the AHUs in the PS was the maximum, accounting for 36%
2.5. Evaluation indices of the total electricity consumption, followed by that of the AHUs in the
EMR (31%), fans in the PS (18%), and fans in the EMR (15%).
To assess the accuracy of models, statistical analysis measures, According to the daily electricity consumption data of the VAC
namely, the mean absolute percentage error (MAPE) and root-mean- system during the ACTs (Fig. 4), the daily electricity consumed by the
square error (RMSE), are used. ventilation subsystem fluctuated slightly (1187–1619 kWh/day).
However, the daily electricity consumed by the water subsystem in-
1 N
RMSE =
N
∑i =1 (yi − ypi )2 , (18)
creased with the outdoor temperature. This was due to the following.
30
Electricity consumption (kWh)
MAPE =
1
∑i =1
N ⎛⎜ |ypi − yi | × 100 ⎞⎟, 25
N ⎝ yi ⎠ (19) 20
15
where yi is the observed value, and ypi is the estimated value.
10
5
3. Results and discussion 0
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Hours
The energy consumption, load and temperature characteristics, and
Fans in PS AHUs in PS AHUs in EMR Fans in EMR
energy-saving potentials for the VAC system in the station were in-
vestigated. Fig. 3. Electricity consumption of the VAC system during the NACTs.
5
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
Table 4
Proportion of the electricity consumption during NATCs and ATCs.
Items During NATCs (air subsystem) During ATCs (water subsystem)
AHUs in PS AHUs in EMR Fans in PS Fans in EMR Chillers Chiller pumps Cooling pumps Cooling tower
Proportion (%) 36 31 18 15 77 11 9 3
6000
5000 30 respectively. However, the station load was relatively stable between
4000 8:00 and 18:00 (the maximum load was 855 kW, the minimum load was
(kWh)
25 769 kW, and the difference is 86 kW). According to the data in Fig. 7,
3000
the cooling load of the subway station equipment accounted for the
2000 20 largest proportion (34% in the operation period, 37% in the whole day),
1000 followed by the fresh air load (22% in the operation period, 21% in the
0 15 whole day) and PHE load (15% in the operation period, 13% in the
1-Apr 16-Apr 1-May 16-May 31-May 15-Jun 30-Jun
whole day). Other loads accounted for 11%, and the lighting load ac-
Days
counted for 10%. Because this station is a non-conversion station, the
Water subsystem Ventilation subsystem Outdoor temperature
proportion of personnel load was very small, only accounting for 3%.
Fig. 4. Influence of the daily outdoor temperature on the daily electricity Although the cooling load of the equipment was very large, it was
consumption of the VAC system (the measurement error of the power was ± difficult to change the heat dissipation of the equipment. Therefore, it is
0.5%). recommended to reduce the air conditioning load from the mechanical
fresh air load, PHE, lighting load, and other loads.
First, the mechanical fresh air loads and the permeation heat of en- As shown in Fig. 8, the cold load of the equipment fluctuated sig-
trances (PHE) increased with the outdoor temperature. Second, as the nificantly during the operation and outage periods (the data indicates
outdoor temperature increased, the air conditioning areas in the EMRs that the outage period was only 67.6% of the operating period).
were broadened. From the data in Fig. 5, it can be seen that the air However, the equipment load fluctuated little between 0:00–5:00 and
conditioning system in the SER was also sometimes running when the 7:00–22:00, from 163 to 167 kW and from 246 to 281 kW, respectively.
outdoor temperature was low, and that the refrigeration in the SER There are two reasons for the change of equipment load: (1) the ele-
exhibited strong subjectivity. The Spearman’s correlation coefficient vator, automatic ticket machine, and other equipment in the PS were
between the electricity consumption of the water subsystem and the closed or stopped during the outage period; (2) in the operation and
outdoor temperature was only 0.8518. outage periods, the thermal load of the power supply rooms in the
The electricity consumption of the chiller pumps, cooling pumps, station with hybrid traction and a step-down substation presented ob-
and cooling tower varied with the change of the chillers’ consumption vious fluctuation, and the average heat load during the outage period
(Fig. 5). The relational expression between the chiller’s electricity was only 38.9% that of the operation period (Fig. 9). Therefore, a VAC
consumption x and the water subsystem’s electricity consumption y was system with variable frequency is recommended for use in the PS and
fitted with the use of Curve Expert 1.3 software [32]. Because the power supply rooms. However, the thermal load fluctuation of the
standard deviation (S) [33] and correlation coefficient (r) [34] of the communication and signal rooms was relatively stable (Figs. 9 and 10);
binomial fitting (S = 3.69; r = 0.9988) were close to those of the tri- this was considered as a stable load, and a VAC system with constant
nomial and four-term fittings (S is 3.63 and 3.57; r is 0.9989 and frequency can be employed.
0.9989), binomial fitting was adopted in this paper (Eq. (20)). As shown The minimum mechanical fresh air volume in the PS of the station
in Table 4, the electricity consumption of the chillers was the max- was determined according to the average air leakage of the PSD, and
imum, accounting for 77% of that of the water system, followed by that the minimum mechanical fresh air volume in the EMR was about 10%
of the chiller pumps (11%), cooling pumps (9%), and cooling towers of the air supply volume. Therefore, the minimum fresh air volume
(3%). Thus, improving the energy efficiency of the chiller is significant presented obvious peak and valley changes from the outage period to
to the reduction of the electricity consumption of AVC systems. The the operation period, but was basically stable during either period
portion of electricity consumed by the pumps was 15% lower than that (Table 5). The mechanical fresh air load mainly changed with the
found in a previous study [15]. The reason for this was that the pumps change of temperature and humidity outside of the station (Fig. 11).
were jointly shut down when the refrigerator was turned off. Although it is the goal to maintain “positive pressure” in the station by
keeping the mechanical fresh air equal to the air leakage of the PSD,
y = - 3.6082 + 6.9351 × 10 - 1x + 3.0673 × 10 - 4x2 (20) according to the test, the instantaneous air leakage of the PSD was very
large when the train stops, and there was inevitably a “negative
Electricity consumption of
Electricity consumption of
40 300
and cooling pump (kWh)
For the calculated cooling load, the power consumption, tempera- 250
30
chiller (kWh)
ture, humidity, passenger flow, superficial area, and air volume were all 200
measured, and the heat transfer coefficient, surface emissivity, power 20 150
coefficient, etc., were estimated from the heat transfer theory or em- 100
10
pirical values. 50
As presented in Fig. 6, the total cooling load of the station was quite 0 0
0:00 8:00 16:00 0:00 8:00 16:00 0:00 8:00 16:00
different during the operation and outage periods; the average load Hours
during the operation period was 737 kW, and that of the outage period Chiller Cooling tower Chiller pump Cooling pump
was 287 kW. Thus, the average load of the operation period was 2.57
times that of the outage period. In addition, there was a large fluctua- Fig. 5. Electricity consumption of the water subsystem (the measurement error
tion in the station load between 6:00–8:00 and 18:00–23:00, and the of the power was ± 0.5%).
6
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
40 transfer of the PSD and other cooling loads, presented obvious peak and
PHE load
13% 3% 3.4. Establishment of general models
hourly average air leakage volume was fitted with the hourly passenger
200 flow and train departure density, and the fitting relationship is given by
150 Eq. (21). Table 6 lists the coefficients of the fitting relationships. Fig. 17
demonstrates that the nonlinear fitting effect of the hourly average air
100
leakage volume of the entrances is relatively good (RMSE = 1225.86,
50 MAPE = 5.22%, maximum relative error = 14.79%).
0
0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 (p1 + p2 ∗ n + p3 ∗ n2 + p4 ∗ n3 + p5 ∗ m + p6 ∗ m2)
Vunor , inlet =
Hours (1 + p7 ∗ n + p8 ∗ m + p9 ∗ m2)
Equipment load
(21)
Fig. 8. The trend chart of the equipment’s hourly cooling load in the subway
station.
3.4.2. Prediction of the daily electricity consumption of the VAC system
pressure” in the station. Thus, a large amount of fresh air entered the Subway stations have the same rules of passenger flow on working
station through the entrances (Fig. 12), which increased the fresh air days and rest days, as well as similar characteristics of the daily average
load (PHE, as shown in Fig. 11). air leakage volume of the screen door and the mechanical fresh air
Fig. 13 shows that the cooling loads formed by lighting heat dis- volume and load (except for the mechanical fresh air load and exit-
sipation, fan cooling, and body heat dissipation, as well as the heat entrance infiltration load). The daily power consumption of air con-
ditioning can be predicted according to the daily temperatures inside
7
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
Night Day
Fig. 9. Comparison of the equipment thermal load during the outage and operation periods in the subway station.
8
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
250 36
25,435 ± 1013
23:00 30
100 28
26
30,657 ± 319
30,608 ± 92
50
24
0 22
10:00
22:00
31,692 ± 345
Fig. 11. Hourly change trend of mechanical fresh air load and PHE.
21:00
9:00
according to the average air leakage of the PSD with the purpose of
maintaining “positive pressure” in the subway station. However, this is
30,693 ± 266
30,439 ± 250
not always the case. As presented in Fig. 12, when the PSD is open, a
large amount of fresh air enters the station through the entrances, thus
20:00
not to determine the mechanical fresh air volume by the air leakage of
the PSD, but to adjust the frequency of the fresh air fans via CO2
31,913 ± 135
30,916 ± 387
monitoring to reduce the fresh air volume and the power consumption
of the VAC system. Li et al. pointed out that most subway stations in
19:00
China no longer require mechanical fresh air [41], and that the halt of
7:00
mechanical fresh air could increase the outdoor air intake through the
entrances by about 24–30% [42]; therefore, the penetrating heat load at
30,776 ± 356
31,844 ± 182
the entrances will increase by this amount. In terms of the case study
station, when the PS mechanical fresh air is turned off, the energy
consumption by the VAC system can be reduced by at least 9.0% per
18:00
6:00
day.
31,005 ± 399
cording to the analysis in Section 3.2, the thermal loads of the SER
5:00
fluctuate, as does the load in the PS. Therefore, it is suggested that the
AHUs should be adjusted according to the conditions of minimum fresh
30,805 ± 329
air, full fresh air, and full ventilation. Under the condition of minimum
8774 ± 69
fresh air, when the return air temperature is lower than the set tem-
16:00
perature, the frequency of the AHUs should be reduced, and vice versa.
4:00
Under the full fresh air and full ventilation conditions, when the
average temperature in the WER, CMR, and PS is lower than the set
32,167 ± 331
versa. For the SER, it is suggested to adjust the frequency of the AHUs
by comparing the return air temperature with the set temperature. As
15:00
3:00
supply system will not be analyzed due to the length restrictions of this
8883 ± 61
paper. However, the target temperature of the SER was fixed, the heat
14:00
outage and operating periods, and the average heat load during the
outage period was only 38.9% that during the operating period; thus,
30,888 ± 254
7808 ± 125
h, accounting for 52% of the total air supply of the EMR. The average
1:00
power consumptions of the AHUs and fans of the EMR were 18 kW and
8 kW, respectively. Assuming that the air supply of the SER relies on the
31,868 ± 200
heat dissipation capacity of the equipment from 0:00 to 5:00, then the
7396 ± 86
Fresh Volume
Time
Time
9
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
60 27
Air volume (m3/s)
Temperature (oC)
40 26
25
20
24
0
23
19:00 19:04 19:08 19:12 19:16 19:20 19:25 19:29
-20 22
Seconds 1 31 61 91 121 151 181 211 241 271 301 331 361 391 421 451 481
Hours
Fig. 12. Curve of air intake at the entrances caused by air leakage from the Platform temperature Station hall temperature
platform to the tunnel (the measurement error of the air volume was ± 3%).
Fig. 15. Hourly temperature change curves of the platform and station hall (the
standard deviations of the 11 monitoring values in the station hall were be-
35
25
60 20 29.5
15
Temperature (oC)
40 24.5
10
20 5
19.5
0 0 14.5
0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00
Hours 9.5
Monday Thuesday Wednesday Thursday Friday Saturday Sunday
Lighting load Heat transfer of PSD Load of fans Hours
Others Personal load Temperature Outdoor temperature Indoor temperature
Fig. 13. Hourly trend chart of cooling load caused by lighting cooling, fan Fig. 16. Average temperature change curves of the station hall and platform in
cooling, and human body cooling, as well as the heat transfer of the PSD and the non-air conditioning season (the standard deviations of the 18 monitoring
other cooling loads. values in the PS were between 0 and 0.43 °C).
continuous supply of fresh air during the ACTs was thus unnecessary. Table 6
Fresh air may be made available, but only for a short time during staff Coefficients of the nonlinear fitting relations.
inspections. The average fresh air volume of the SER and WER was Equations 21 22 23
about 7040 m3/h; the fresh air volume from 0:00 to 5:00 accounted for
86% of the total fresh air volume, and that during the period of 6:00 to p1 104240.73 −140441428.70 11415.66
p2 9225.78 1354785.40 103.83
23:00 accounted for 22.8%. Therefore, the energy consumption by the
p3 3.23 −104322.28 −6.68
VAC system could be reduced by about 7.7% if the fresh air of the SER p4 0.00 3993.80 0.21
and WER was not made available. p5 −300771.04 −76.01 0.00
p6 −31568.32 0.58 0.00
p7 1.18 21470558.63 −21004.41
3.5.6. Regulation of the SER refrigeration conditions p8 −57.25 −1294509.77 14603.17
p9 −1.22 34664.55 −5052.67
The refrigeration in the SER was arbitrary. Sometimes, supplying
p10 – −347.86 870.21
the cooling capacity for the SER was unnecessary because the ventila- p11 – – −59.68
tion could maintain the temperature below 36 °C. The thermal load of
the equipment and lighting in the SER was 128 kW. Given that the SER
was unattended throughout the year, humidity load could be ignored. However, the actual refrigerating hours in the SER amounted to 108 h
The air supply for the SER was 42,130 m3/h, and the temperature and (Table 7). Thus, the SER could reduce thermal load by approximately
humidity in this room should be maintained below 36 °C and 60%, 6272 kW, and the energy consumption by the VAC system could be
respectively, i.e., the enthalpy value should be < 94.632 kJ/kg. Thus, reduced by 1.7%.
when the enthalpy value of the outdoor air was < 83.69 kJ/kg, the
temperature in the SER could reach control requirements through 3.5.7. Establishment of intelligent control platform
ventilation. The number of hours during which the outdoor air specific It is suggested to build an intelligent data platform to realize the
enthalpy value was greater than 83.69 kJ/kg in May was 59 h (Fig. 21). real-time analysis and dynamic adjustment control of VAC system
27.5
Temperature (oC)
26.5
25.5
24.5
23.5
5:36:14 5:44:46 5:53:19 6:01:51 6:10:24 6:18:56 6:27:29 6:36:01 6:44:33 6:53:06
Seconds
3-May 12-May 21-May
Fig. 14. Temperature change curve in the station hall (the standard deviations of the 11 monitoring values in the station hall were between 0.02 and 0.12 °C).
10
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
25000 16 100
Hourly average air leakage
MAPE (%)
15000 10 60
8
10000 40
6
5000 4 20
2
0
0 0 1 41 81 121 161 201 241 281 321 361 401 441 481 521
1 3 5 7 9 11 13 15 17
Hours Hours
Specific enthalpy of outdoor air Designed specific enthalpy
Observed value Calculated value MAPE
Fig. 21. Hourly specific enthalpy in May.
Fig. 17. Observed and calculated values of the hourly average air leakage vo-
lume.
The strategies proposed in Sections 3.5.1, 3.5.2 and 3.5.7 must be
implemented based on the monitoring platform, so they may be im-
7000 14
Electricity consumption
MAPE (%)
(kWh/d)
4000 8 the equipment in the SER should be detected and estimated, and its air
3000 6 supply and refrigeration conditions should be adjusted and regulated
2000 4 accordingly.
1000 2
0 0 4. Conclusions
1 5 9 13 17 21 25 29 33 37 41 45 49
Days
In this paper, the characteristics of a subway station ventilation and
Observed value Calculated value MAPE air conditioning system were analyzed based on field measurement data
from the three aspects of power consumption, load, and temperature.
Fig. 18. Observed and calculated values of the daily electricity consumption of
the air conditioning system.
Additionally, the problems existing in the operation and management
of a subway station ventilation and air conditioning system were ex-
amined. (1) The ventilation and air conditioning system used the
30 8
average air leakage of the platform screen door to determine the
Indoor temperature (oC)
7
25 6
minimum mechanical fresh air volume, which not only cannot maintain
the “positive pressure” in the station, but also greatly increases the fresh
MAPE (%)
5
20 4 air load and power consumption. It was found that the total load of
3 fresh air in the station was as high as 34–37% (operation period: fresh
15 2 air load 22%, permeation heat of entrances 15%; all-day: fresh air load
1 21%, permeation heat of entrances 13%). (2) The ventilation capacity
10 0 of the ventilation and air conditioning system in the subway station was
1 11 21 31 41 51 61 71 81 91 101 111 121
stable year-round, but it was found that the thermal load of some rooms
Hours exhibited obvious peak and valley variation during the operation and
Observed value Calculated value MAPE outage periods, and that the actual ventilation capacity and thermal
Fig. 19. Observed and calculated values of the indoor temperature during load were not matched. (3) The temperature in the subway station was
NACTs. generally lower than the design temperature, which can be controlled
by load or power consumption prediction and the frequency of the
28 adjustment of air handling units. (4) The ventilation and air con-
Temperature (oC)
11
H. Yin, et al. Applied Thermal Engineering 178 (2020) 115555
Table 7
Refrigeration hours of the SER in May.
Date May 8 May 15 May 26 May 27 May 28 May 29 May 30 May 31
conducting cost. [19] Z. Yue, X. Li, Research on airflow and energy performance in PBD, PSD and PBD-
PSD-combined environment control systems in subway, Sustain. Cities Soc. 42
(2018) 434–443.
Declaration of Competing Interest [20] J. Ma, X. Zhang, A. Li, B. Deng, W. Lv, Y. Guo, W. Zhang, L. Huang, Analyses of the
improvement of subway station thermal environment in northern severe cold re-
gions, Buid. Environ. 143 (2018) 579–590.
The authors declare that they have no known competing financial [21] Statistical analysis on passenger flows of Guangzhou metro. https://www.ditietu.
interests or personal relationships that could have appeared to influ- com/p/1825 (on 29 December 2018).
ence the work reported in this paper. [22] C.D. Perna, A. Carbonari, R. Ansuini, M. Casals, Empirical approach for real-time
estimation of air flow rates in a subway station, Tunn. Undergr. Sp. Tech. 42 (2014)
25–39.
Acknowledgment [23] Ch. Xie, C. Li, W. Shi, Discussion of the air supply calculation of metro hall &
platform air-conditioning system, Refrigeration 29 (2010) 58–61.
[24] J. Luo, Study on Operation Strategy of Energy-saving in Ventilation and Air con-
The authors would like to thank the Guangdong Science and
ditioning system of Metro (Master's Thesis), Guangzhou University, China, 2015.
Technology Department for their sponsorship (2017A020216006). [25] China Electronics Engineering Design Institute, Air Conditioning Design Manual
[M], third ed.,China Building Industry Press, Beijing, 2017, pp. 214–217
References (Chapter 2).
[26] Sh. Fang, M. Xia, J. Zheng, Practical measurement of air-conditioning load in
subway station equipment room, Urban Mass Transit 10 (2018) 112–115.
[1] L. Yang, B. He, M. Ye, The application of solar technologies in building energy [27] (America) D.R. Pitts, L.E. Sissom, Schaum’s outline of theory and problems of heat
efficiency: BISE design in solar-powered residential buildings, Technol. Soc. 38 transfer [M], second ed., Sh. Ge, Z. Chen, translation, Science Press, Beijing, 2002,
(2014) 111–118. pp. 180 (Charpter 8).
[2] S. Pan, F. Pei, Y. Wei, H. Wang, J. Liu, X. Zhang, G. Li, Y. Gu, Design and experi- [28] S. Yang, W. Tao, Heat Transfer [M], forth ed., Higher Education Press, Beijing,
mental study of a novel air conditioning system using evaporative condenser at a 2006, pp. 212–217 (Chapter 5).
subway station in Beijing, China, Sustain. Cities Soc. 43 (2018) 550–562. [29] Ministry of Housing and Urban-Rural Development of the People's Republic of
[3] B. He, D. Zhao, J. Zhu, A. Darko, Zh. Gou, Promoting and implementing urban China, Design Code for heating ventilation and air conditioning of civil buildings
sustainability in China: an integration of sustainable initiatives at different urban (GB 50736-2012) [S], China Building Industry Press, China, 2012.
scales, Habitat Int. 82 (2018) 83–93. [30] X. Zhang, Fundamental of Thermo-technology [M], third ed., Higher Education
[4] China Association of Subways, Annul statistics and analysis of urban railway system Press, Beijing, 2015, pp. 324 (Charpter 11).
in 2018. http://www.199it.com/wp-content/uploads/2019/04/1554732757- [31] G.F. Frate, L. Ferrari, U. Desideri, F. Sorbi, N. Bosi, M. Lazzari, Energy and economic
2603-0407.jpg (on 30 March 2019). savings through a plant supervised management in large-scale commercial activ-
[5] National Energy Administration, The total electricity consumption increased by 8. ities, Appl. Therm. Eng. 141 (2018) 269–279.
5% in 2018. http://www.nea.gov.cn/2019-01/18/c_137754978.htm (on 18 [32] J.L. Gómez, A. Bódalo, E. Gómez, A.M. Hidalgo, M. Gómez, M.D. Murcia,
January 2019). Experimental behaviour and design model of a fluidized bed reactor with im-
[6] H. Yin, H. Guo, Z. Tang, J. Yu, H. Lu, Conventional and advanced exergy analyses of mobilized peroxidase for phenol removal, Chem. Eng. J. 127 (2007) 47–57.
an air-conditioning system in a subway station, Int. J. Exergy 29 (2019) 236–262. [33] G.-Y. Ye, K.-J. Xu, W.-K. Wu, Standard deviation based acoustic emission signal
[7] W. Hong, S. Kim, A study on the energy consumption unit of subway stations in analysis for detecting valve internal leakage, Sensor. Actuat. A – Phys. 283 (2018)
Korea, Buid. Environ. 39 (2004) 1497–1503. 340–347.
[8] M. Casals, M. Gangolells, N. Forcada, M. Macarulla, A. Giretti, A breakdown of [34] M. Korun, T. Petrovič, B. Vodenik, B. Zorko, Empirical determination of the cor-
energy consumption in an underground station, Buid. Environ. 78 (2014) 89–97. relation coefficient between the number of counts in a peak in a gamma-ray spec-
[9] J. Ahn, S. Cho, D.H. Chung, Development of a statistical analysis model to bench- trum and the number of counts in the continuum where the peak is superimposed,
mark the energy use intensity of subway stations, Appl. Energy 179 (2016) Appl. Radiat. Isotopes 158 (2020) 109063.
488–496. [35] Zh. Shi, Design and Construction of Subway [M], Shaanxi Science and Technology
[10] P.C.M. Leung, E.W.M. Lee, Estimation of electrical power consumption in subway Press, 1997, pp. 406 (Charpter 5).
station design by intelligent approach, Appl. Energy 101 (2013) 634–643. [36] X. Li, Y. Wang, Simulation study on air leakage of platform screen doors in subway
[11] B. Guan, X. Liu, T. Zhang, J. Xia, Energy consumption of subway stations in China: stations, Sustain. Cities Soc. 43 (2018) 350–356.
Data and influencing factors, Sustain. Cities Soc. 43 (2018) 451–461. [37] Y. Zhang, The Variable Air Volume Analysis of the Subway Air Conditioning Based
[12] C. Dullinger, W. Struckl, M. Kozek, A modular thermal simulation tool for com- on the Relative Warmth Index (RWI) (Master's Thesis), Xi'an University of Science
puting energy consumption of HVAC units in rail vehicles, Appl. Therm. Eng. 78 and Technology, China, 2011.
(2015) 616–629. [38] L. Fan, L. Feng, On design temperature of metro system by using relaitve warmth
[13] K.F. Fong, V.I. Hanby, T.T. Chow, System optimization for HVAC energy manage- index, Urban Mass Transit 1 (2002) 50–52.
ment using the robust evolutionary algorithm, Appl. Therm. Eng. 29 (2009) [39] G. Liu, J. Zhu, Reliminary discussion on design parameter inside of room for air
2327–2334. conditioning in summer season at Shenzhen subway, J. Railway Eng. Soc. 2 (2002)
[14] S. Pan, H. Wang, F. Pei, L. Yang, X. Zhang, An investigation on energy consumption 110–113.
of air conditioning system in Beijing subway stations, Energy Procedia 142 (2017) [40] Zh. Yang, L. Yu, F. Ma, M. Shao, Hourly optimization of the energy saving control
2568–2573. strategy in subway ventilation and air conditioning system, J. Tianjin Univ. 45
[15] Y. Wang, H. Feng, X. Xi, Monitoring and autonomous control of Beijing Subway (2012) 599–603.
HVAC system for energy sustainability, Energy Sustain. Dev. 39 (2017) 1–12. [41] Y. Wang, X. Li, Unorganized ventilation in subway stations with Platform Screen
[16] J. Li, Subway Station Air-Conditioning Load Caculation Method Research Base on Doors, Buid. Environ. 125 (2017) 556–564.
Field Measurement (Master's Thesis), Tsinghua University, China, 2009. [42] B. Guan, T. Zhang, X. Liu, Performance investigation of outdoor air supply and
[17] M. Lu, T. He, X. Pei, Z. Chen, Analysis of the electricity consumption and the water indoor environment related to energy consumption in two subway stations, Sustain.
consumption of Beijing subway, J. Beijing Jiaotong Univ. 35 (2011) 136–144. Cities Soc. 41 (2018) 513–524.
[18] M. Casals, M. Gangolells, N. Forcada, M. Macarualla, Reducing lighting electricity
use in underground metro stations, Energ. Convers. Manage. 119 (2016) 130–141.
12