MONITORING REPORT FORM (CDM-MR) *

Version 01 - in effect as of: 28/09/2010

CONTENTS

A. General description of the project activity


A.1. Brief description of the project activity
A.2. Project participants
A.3. Location of the project activity
A.4. Technical description of the project
A.5. Title, reference and version of the baseline and monitoring methodology applied to
the project activity
A.6. Registration date of the project activity
A.7. Crediting period of the project activity and related information
A.8. Name of responsible person(s)/entity(ies)

B. Implementation of the project activity


B.1. Implementation status of the project activity
B.2. Revision of the monitoring plan
B.3. Request for deviation applied to this monitoring period
B.4. Notification or request of approval of changes

C. Description of the monitoring system

D. Data and parameters monitored


D.1. Data and parameters used to calculate baseline emissions
D.2. Data and parameters used to calculate project emissions
D.3. Data and parameters used to calculate leakage emissions
D.4. Other relevant data and parameters

E. Emission reductions calculation


E.1. Baseline emissions calculation
E.2. Project emissions calculation
E.3. Leakage calculation
E.4. Emission reductions calculation
E.5. Comparison of actual emission reductions with estimates in the registered CDM-PDD
E.6. Remarks on difference from estimated value

* as contained within the document entitled "Guidelines for completing the monitoring report form (CDM-MR)”
(EB 54 meeting report, annex 34).
MONITORING REPORT
Version 02 date: 08/11/2010

Yunnan Dali Zhemoshan Wind Power Project


CDM registration reference number: 3058
Monitoring period Number: 01
Monitoring period Dates: 29/04/2010 – 30/09/2010

SECTION A. General description of project activity

A.1. Brief description of the project activity:


>>
The project is located within Yongjian Town, Weishan Village, Taiyi County, Dali City,
Yunnan Province, People’s Republic of China. The project involves the wind power
installation of a total capacity of 30.75MW. Therefore, it’s expected to generate
approximately 60,687MWh per year which are sold to the Yunnan Power Grid, an integral
part of the South China Power Grid.

The project helps reduce GHG emissions generated from the high-growth, coal-dominated
power generation. And also, it contributes to sustainable development in the region by
reducing pollution, creating employment opportunities, promoting the local tourism industry
and improving the living standard of local people. At a larger scale, the project assists China
in stimulating and accelerating the commercialization of grid-connected renewable energy
technologies and markets.

The Project commenced construction in June 2008 and put into operation in December 2008.
The expected technical lifetime of the Project is 21years as stated in the registered PDD.

This Monitoring Report is for the 1st phrase of monitoring period, which is from
29/04/2010-30/09/2010. The total emission reduction achieved in this monitoring period is
24,745 tCO2e.

A.2. Project Participants


>>

Name of Party involved Private and/or public entity(ies) Kindly indicate if the Party
project participants involved wishes to be
considered as project
participant (Yes/No)
People’s Republic of China Sinohydro 14th Bureau Dali
No
(host) Juneng Investment Co. Ltd
Netherlands Rabobank International No

A.3. Location of the project activity:


>>
The project is located within Yongjian Town, Weishan Village, Taiyi County, Dali City,
Yunnan Province, People’s Republic of China. The geographical coordinates of the project
are east longitude of 100°10'27.7'' and north latitude of 25°32'52.9''

A.4. Technical description of the project:


>>
The project involves the installation of 41 wind turbines with each capacity of 750 kW, and
totals up an installation capacity of 30.75MW. The wind turbines are supplied by the biggest
Chinese wind turbine manufacturer, Goldwind Science & Technology Ltd. The technology
employed is advanced domestic made wind turbine in China.

An 110kV project station set up at the site, which connects the proposed project to the 110kV
Dafengba Substation and then connects to the Dali 110 kV New Seven-Five Substation, and
the power produced in the wind farm can be transmitted to the Yunnan Provincial Power Grid,
which is an integral part of the South China Power Grid.

A. 5. Title, reference and version of the baseline and monitoring methodology applied
to the project activity:
>>
Approved consolidated baseline methodology ACM0002: “Consolidated baseline methodology
for grid-connected electricity generation from renewable sources” (Version 10 dated 28 May 2009,
Sectoral Scope 01).
Reference:
http://cdm.unfccc.int/methodologies/PAmethodologies/approved.html

A. 6. Registration date of the project activity:


>>
The project was registered on 29/04/2010.

A. 7. Crediting period of the project activity and related information (start date and
choice of crediting period):

After the project was registered on 29/04/2010, the crediting period of the project was set
from 29/04/2010 to 28/04/2017 (Renewable).

A. 8. Name of responsible person(s)/entity(ies):


>>
Name of person/entity completing the monitoring report:
Ms. Lin, Wei / Mr. Guan, Yisong
Easy Carbon Consultancy Co., Ltd.
13-801, Jianwai SOHO, 39 Dongsanhuan Zhonglu, Chaoyang District, Beijing 100022, P. R.
China
Phone/fax: +86 10 58697044/59000064
Email: tonilin@easy-carbon.com / gyisong@easy-carbon.com

Easy Carbon Consultancy Co., Ltd is not Project Participant.

SECTION B. Implementation of the project activity

B.1. Implementation status of the project activity


>>
The wind turbine generator units were put into operation from 17/12/2008. The monitoring
plan was implemented in compliance with the registered PDD. And there was no significant
malfunction or any emergency overhaul times, downtimes of equipment, exchange of
equipment reported during this monitoring period from 29/04/2010 to 30/09/2010. The
project implementation follows monitoring plan in the PDD and in line with methodology
applied.

B. 2. Revision of the monitoring plan


>>
The monitoring plan of the project as described in the registered CDM-PDD was not revised.

B. 3. Request for deviation applied to this monitoring period


>>

There is no deviation request proposed for the current monitoring period.

B. 4. Notification or request of approval of changes


>>
There is no request of approval of changes from the project activity as described in the
registered CDM-PDD.

SECTION C. Description of the monitoring system


>>
In accordance with the Monitoring Methodology ACM0002,Ver 10, the key data that must be
monitored ex-post for the specific crediting period (since the emission factor has been
calculated ex ante), are:

1. EGfacility,y - Quantity of net electricity generation exported by the project to the Grid in year
y.
2. EGexport,y - Electricity supplied to the Grid by the project during year y.
3. EGimport,y - Electricity purchased from the grid by the proposed project during year y

The monitoring system is specified as below:

1. Monitoring procedures

Electricity purchased from the grid by the project (EGimport,y) is subtracted from electricity
supplied to the grid by the project (EGexport,y) to obtain net electricity supplied to the grid
(EGfacility, y).

Electricity supplied to and purchased from the grid was monitored and recorded by the main
meter installed at the project substation. Due to the regulation of the local Grid Company, the
monthly cut-off time for electricity supplied to the grid is at 24:00 on the last day in every
month. However, the monthly cut-off time for electricity purchased from the grid is at 24:00
on the 15th day in every month.

Electricity supplied to the grid is continuously measured. The readings of the meter were daily
read and recorded. Sales receipts are issued based on these readings. Therefore, the electricity
supplied to the grid from 29/04/2010 to 30/09/2010 was well measured and recorded.

The electricity supplied to the grid by the project during the period from 29/04/2010 to
30/09/2010 from meter readings and sales receipt are confirmed by the grid company, which
has been supplied to DOE for verifying.

Electricity purchased from the grid is continuously measured. The readings of the meter were
daily read and recorded. Sales receipts are issued based on these readings. Therefore, the
electricity purchased from the grid from 29/04/2010 to 30/09/2010 was well measured and
recorded.

The meters installed by the monitoring system of the project during this crediting period have
an accuracy of 0.2s. The meters measure the electricity supply on a continuous basis. The
electricity supplied to the grid on continuously basis and records and reports the daily and
monthly total supply.

The main meter and the backup meter are calibrated by Electric Power Research Institute of
Yunnan Electric Power Test and Research Institute (Group) Co., Ltd. (Certificate No.:
CNAS L3356) annually according to Chinese national calibration standard. The entity is an
authorized entities to implement electricity meters calibration.

The location of the main meter (M1) and back-up meter (M2) are at Zhemoshan Substation on the
project site are as the following chart.
2. Monitoring structure and responsibility of personnel

The owner of the proposed project used the registered PDD as guideline in monitoring of the
project emission reduction performance and adhered to the guidelines set out in this monitoring
plan to ensure that the monitoring is credible, transparent and conservative.

The responsibilities of the project staff are as follow:

General Manager: To be responsible for supervising the whole monitoring procedure.


CDM Project Manager: To be responsible for data management and compiling monitoring report.
Operational and monitoring manager: To be responsible for collecting data and do internal audit.
Financial chief: To be responsible for collection of sales receipts.
Technical chief: To be responsible for preparing operational reports of the project activity,
recording the daily operation of the wind farm, including operating periods, equipment defects,
etc.
All the above staffs are qualified to do the work after training.
General Manager

CDM Project Manager

Operational and Financial Chief Technical Chief


Monitoring Manager of the
plant

3. Emergency Procedure:

In case metering equipment is damaged and no reliable readings can be recorded the project
entity will estimate net supply by the proposed project activity according to the following
procedure:
1. In case of that the main meter (M1) is out of service, the back-up meter (M2) will be
used as monitoring of the electricity supplied to the Grid and electricity purchased from the
Grid.
2. In case both main meter and back up meter are damaged: The project entity and the grid
company will jointly calculate a conservative estimate of power exported to the grid. A
statement will be prepared indicating
► the background to the damage to metering equipment
► the assumptions used to estimate net supply to the grid for the days for which no record
could be recorded
► the estimation of power exported to the grid. The statement will be signed by both a
representative of the project entity as well as a representative of the grid company.

If any error is detected, the party owning the meter shall repair, recalibrate or replace the
meter giving the other party sufficient notice to allow a representative to attend during any
corrective activity.

SECTION D. Data and parameters

D.1. Data and parameters determined at registration and not monitored during the
monitoring period, including default values and factors

Data / Parameter: EFy


Data unit: tCO2/MWh
Description: Combined emission factor.
Source of data: Baseline Emission Factors for Power Grids in China, sourced from
China
Energy Statistical Yearbook, China Electric Power Yearbook and
2006 IPCC
Guidelines for National Greenhouse Gas Inventories
Value: 0.9660
Indicate what the data The data is used for the baseline emission calculation.
are used for (Baseline/
Project/ Leakage
emission calculations)
Additional comment: The baselines emission factor was determined ex ante and will be
used throughout the first crediting period.

D.2. Data and parameters monitored

Data / Parameter: EGfacility,y


Data unit: MWh
Description: Quantity of net electricity generation exported by the project to the
Grid in year y.
Measured /Calculated Calculated through continuously measured parameters (EGexport,y and
/Default: EGimport,y) and monthly recording
Source of data: The net electricity exported to the Grid by the proposed project will be
calculated through electricity exported by the project to the grid
(EGexport,y) minus electricity imported from the Grid (EGimport,y) at the
project substation.
Value(s) of monitored 25,616.560
parameter:
Indicate what the data Baseline emission calculation
are used for (Baseline/
Project/Leakage
emission calculations)
Monitoring equipment
(type, accuracy class, Main meter (M1) Backup meter (M2)
serial number, Meter Type MK6E、3*57.7V、 MK6E、3*57.7V、
calibration frequency, 3*1(6)A 3*1(6)A
date of last calibration, Accuracy 0.2s 0.2s
validity) class
Serial No. 280206196 280206195
Calibration annually annually
frequency
Calibration 07/10/2009; 07/10/2009;
Validity 07/10/2009-06/10/2010 07/10/2009-06/10/2010
07/06/2010-06/06/2011 07/06/2010-06/06/2011
Measuring/Recording Continuously measurement and monthly recording
frequency:
Calculation method (if Not applicable
applicable)
QA/QC procedures to The electricity supplied to and imported from the grid by the Project
be applied: is monitored and recorded by the meter M1 installed at the project
substation. The project operator is responsible for recording this set
of data. Data will be archived for 2 years following the end of the
last crediting period by means of electronic and paper backup.
Receipts from electricity sales are obtained for double check. The
calibration frequency is once a year.

Data / Parameter: EGexport,y


Data unit: MWh
Description: Electricity supplied to the Grid by the project during year y
Measured /Calculated Directly measured at the 110kV project substation
/Default:
Source of data: Reading of meter M1 at the project substation
Value(s) of monitored 25,685.200
parameter:
Indicate what the data Baseline emission calculation
are used for (Baseline/
Project/Leakage
emission calculations)
Monitoring equipment
(type, accuracy class, Main meter (M1) Backup meter (M2)
serial number, Meter Type MK6E、3*57.7V、 MK6E、3*57.7V、
calibration frequency, 3*1(6)A 3*1(6)A
date of last calibration, Accuracy 0.2s 0.2s
validity) class
Serial No. 280206196 280206195
Calibration annually annually
frequency
Calibration 07/10/2009; 07/10/2009;
date 07/06/2010 07/06/2010
Validity 07/10/2009-06/10/2010 07/10/2009-06/10/2010
07/06/2010-06/06/2011 07/06/2010-06/06/2011
Measuring/Recording Continuously measurement and monthly recording
frequency:
Calculation method (if Not applicable
applicable)
QA/QC procedures to The electricity supplied to the grid by the Project are monitored and
be applied: recorded by the meter M1 installed at the project substation. The
project operator is responsible for recording this set of data. Data
will be archived for 2 years following the end of the last crediting
period by means of electronic and paper backup. Receipts from
electricity sales are obtained for double check. The calibration
frequency is once a year.

Data / Parameter: EGimport,y


Data unit: MWh
Description: Electricity purchased from the Grid by the project during year y
Measured /Calculated Directly measured at the 110kV project substation
/Default:
Source of data: Reading of meter M1 at the project substation
Value(s) of monitored 68.640
parameter:
Indicate what the data Baseline emission calculation
are used for (Baseline/
Project/Leakage
emission calculations)
Monitoring equipment
(type, accuracy class, Main meter (M1) Backup meter (M2)
serial number, Meter Type MK6E、3*57.7V、 MK6E、3*57.7V、
calibration frequency, 3*1(6)A 3*1(6)A
date of last calibration, Accuracy 0.2s 0.2s
validity) class
Serial No. 280206196 280206195
Calibration annually annually
frequency
Calibration 07/10/2009; 07/10/2009;
date 07/06/2010 07/06/2010
Validity 07/10/2009-06/10/2010 07/10/2009-06/10/2010
07/10/2009-06/06/2011 07/10/2009-06/06/2011
Measuring/Recording Continuously measurement and monthly recording
frequency:
Calculation method (if Not applicable
applicable)
QA/QC procedures to The electricity imported from the grid by the Project are monitored
be applied: and recorded by the meter M1 installed at the project substation. The
project operator is responsible for recording this set of data. Data
will be archived for 2 years following the end of the last crediting
period by means of electronic and paper backup. Receipts from
electricity sales are obtained for double check. The calibration
frequency is once a year.
SECTION E. Emission reductions calculation

E.1. Baseline emissions calculation


>>
The baseline emission BEy (tCO2) during the monitoring period results from:

BEy =EGfacility, y × EFgrid,CM,y


Where

EGfacility,y — Quantity of net electricity generation supplied by the project plant/unit to the grid
in year y (MWh/yr)
EFgrid,CM,y — Combined margin CO2 emission factor for the project electricity system in year y
calculated using the latest version of the “Tool to calculate the emission factor for
an electricity system”.

The net electricity supplied to the grid via the main power lines measured by the meter M1
installed at the project substation was aggregated on designated time in every month
(normally the last day of each month), as in the below table. All the relative metered readings
and sales receipts were submitted to the DOE for verifying.

Net Electricity supplied to the SCPG by the Project

Monitoring period Electricity Supplied to Electricity


the Grid (MWh) imported Net electricity
Monitoring result after from the supplied to the grid
being double checked grid1 (MWh)
with sales receipts (MWh)
From To A B C=A-B
29/04/2010 30/04/2010 336.600 1.320 335.280
01/05/2010 31/05/2010 8,158.920 1.320 8,157.600
01/06/2010 30/06/2010 7,168.920 3.960 7,164.960
01/07/2010 31/07/2010 4,812.720 17.160 4,795.560
01/08/2010 31/08/2010 2,444.640 27.720 2,416.920
01/09/2010 30/09/2010 2,763.400 17.160 2,746.240
Total 25,685.200 68.640 25,616.560

According to the registered PDD, the Emission factor of the grid is determined ex-ante; the

1
The monthly cut-off time for electricity purchased from the grid is at 24:00 on the 15th day in every
month. The project entity and the grid company jointly calculated electricity imported from the grid at
24:00 on the last day in every month based on the reading of meter M1. And the data have been
confirmed by both of two parties.
ex-ante determined emission factor is 0.9660 tCO2e/MWh.

BEy =EGfacility, y × EFgrid,CM,y = 25,616.560 MWh*0.9660 tCO2e/MWh = 24,745 tCO2e.

E. 2. Project emissions calculation


>>

According to ACM0002 (Version 10), no Project Emissions is to be counted by the Project.

Hence, PEy=0

E. 3. Leakage calculation

According to ACM0002 (Version 10), the main indirect emissions potentially giving rise to
leakage in the context of electric sector projects result from power plant construction, fuel
handling (mining, processing, and transportation) and land inundation (for hydroelectric
projects). The project developer does not need to consider such indirect emissions when
applying the methodology. Project activities using this baseline methodology shall not claim
any credit for the project on account of reducing these emissions below the level of the
baseline scenario. The leakage from the project is zero.

Ly=0

E. 4. Emission reductions calculation / table


>>
Total baseline emissions: BEy= 24,745 tCO2e.
Total project emissions: PEy = 0
Total leakage: Ly-=0
Total emission reductions: ERy= BEy -PEy -Ly = BEy -0-0= 24,745 tCO2e.
Emission reductions generated in the monitoring period (29/04/2010 – 30/09/2010):
24,745tCO2e.

E. 5. Comparison of actual emission reductions with estimates in the CDM-PDD


>>
According to the registered PDD, the emission reductions of the project are estimated to be
58,623 tCO2e per annum. This monitoring period from 29/04/2010 to 30/09/2010 has 155
days.

As a result, the estimated emission reductions during the monitoring period are
58,623 tCO2 / 365 * 155 = 24,894 tCO2

Comparison of actual electricity generated in the monitoring report with the estimated in the
registered PDD is as following:
Item Values applied in ex-ante Actual values reached
calculation of the registered during the monitoring
CDM-PDD period
Electricity generations 25,771 25,616.560
(MWh)
Emission Factor 0.966 0.966
(tCO2e/MWh)

So,the comparison of actual emission reduction in the monitoring report with the estimated
in the registered PDD:
Item Values applied in ex-ante Actual values reached
calculation of the registered during the monitoring
CDM-PDD period
Emission reductions 24,894 24,745
(tCO2e)

E..6. Remarks on difference from estimated value in the PDD


>>
The comparison shows that the actual emission reduction is lower than the expectation in the
registered PDD. The reason for the difference is mainly because of wind resource during the
monitoring period from 29th April to 30th September is smaller than the average value in the
whole year. Therefore, the emission reduction of the project during this monitoring period
was less than estimated value in the PDD.